PROJECT INFO
Project:
Proposed a primary school of four storey building comprising with 36
unit of classrooms, offices, library, labs, store and others facilities and
one storey building of canteen.
Location:
Above Lot 110012, Persiaran Lestari Perdana 5, Mukim Petaling, Daerah
Petaling, Selangor Darul Ehsan.
PROJECT DETAILS:
Client: S.J.K.(C) BUKIT SERDANG
Building purposes: Education
Type of project: Government
Gross floor area (GFA): 4717.07 m2
Contract Sum: RM 7,249,424.43
Date of commencement: 22th July 2013
Date of completion: 5th April 2014
LOCATION PLAN
KEY PLAN
SITE PLAN
Form 1
Form 1
Form 1
Gross Floor Area
Gross Floor Area (Ground Floor)
GFA (Ground Floor) = 1402.01 m2
Gross Floor Area (1st Floor)
GFA (First Floor) = 1105.02 m2
Gross Floor Area (2nd Floor)
GFA (Second Floor) = 1105.02 m2
Gross Floor Area (3rd Floor)
GFA (Third Floor) = 1105.02 m2
Total Gross Floor Area
TOTAL GROSS FLOOR AREA
= 1402.01 + 1105.02 + 1105.02 + 1105.02
= 4717.07 m2
NET FLOOR AREA
USABLE AREA
CIRCULATION AREA
ANCILLARY AREA
INTERNAL DIVISION
NET FLOOR AREA - GROUND FLOOR
NET FLOOR AREA - FIRST FLOOR
NET FLOOR AREA- SECOND FLOOR
NET FLOOR AREA - THIRD FLOOR
SUMMARY OF NET FLOOR AREA
TOTAL USABLE AREA = 2950.21m2
TOTAL CIRCULATION AREA = 506.75m2
TOTAL ANCILLARY AREA = 1066.51m2
TOTAL INTERNAL DIVISION = 193.60m2
FLOOR SPACE NOT
ENCLOSED
FLOOR SPACE NOT ENCLOSED - GROUND FLOOR
Floor Space Not Enclosed (Ground Floor) = 2448.79 m2
FLOOR SPACE NOT ENCLOSED - 1ST FLOOR
Floor Space Not Enclosed (First Floor) = 317.34 m2
FLOOR SPACE NOT ENCLOSED - 2ND FLOOR
Floor Space Not Enclosed (Second Floor) = 317.34 m2
FLOOR SPACE NOT ENCLOSED - 3RD FLOOR
Floor Space Not Enclosed (Third Floor) = 317.34 m2
SUMMARY OF FLOOR SPACE NOT ENCLOSED
TOTAL FLOOR SPACE NOT ENCLOSED
= 2448.79 + 317.34 + 317.34 +317.34
= 3400.81m2
Total Roof Area = 2871.64 m2
ROOF AREA
Form 1
Calculation
Form 2
Form 2
Calculation
Form 2
1A Piling
Total Cost of Piling: RM 131,922.60
Total Element Unit Quantity: 1,524 m
1B Work Below Lowest Floor Finish
Total cost of Work Below Lowest Floor Finish: RM 131,922.60
Total Element Unit Quantity: 1,402 m2
1B Work Below Lowest Floor Finish
(Reinforced concrete)
Total Reinforced Concrete: 326.69 m3
1B Work Below Lowest Floor Finish (Reinforcement)
Total Reinforcement:
24237.50 kg
1B Work Below Lowest Floor Finish (Formwork)
Total Formwork:
1379.50 m2
Form 2
2A Frame
Total cost of frame:
RM 883,940.85
Total Element Unit Quantity:
4,717 m2
2A Frame (Reinforced concrete)
Total Reinforced Concrete:
677.05 m3
2A Frame (Reinforcement)
Total Reinforcement:
110,167.00 kg
2A Frame (Formwork)
Total Formwork:
1,163 m2
2B Upper Floor
Dedeuction for formwork:
5,342 m2 - 223 m2 = 5,119 m2
Cost of formwork in Upper Floor:
5,119 m2 x RM 38.00 = RM 194,522.00
2B Upper Floor
Total Cost of Upper Floor:
RM 573,542.79
Total Element Unit Quantity:
3,315 m2
2B Upper Floor (Reinforced concrete)
Total Reinforced Concrete:
562.90 m3
2B Upper Floor (Reinforcement)
Total Reinforcement:
5,332.63 kg
2B Upper Floor (Formwork)
Total Formwork:
45,422 m2
2C Roof
2C Roof
2C Roof
Total Element Unit Rate of Roof:
2,741 m2 + 670 m2 = 3,411 m2
Total Cost of Roof:
RM 451,534.18
2C Roof (Reinforced concrete)
Total Reinforced Concrete:
22.30 m3
2C Roof (Reinforcement)
Total Reinforcement:
990.12 kg
2C Roof (Formwork)
Total Formwork: 223 m
2D Stairs
2D Stairs
Total Cost of External Walls:
RM 67,892.06
2D Stairs (Reinforced concrete)
Total Reinforced Concrete:
38.74 m3
2D Stairs (Reinforcement)
Total Reinforcement:
4518.00 kg
2D Stairs (Formwork)
Total Formwork:
319.77 m2
2E External Walls
Total Cost of External Walls:
RM 176,586.00
Total Element Unit Quantity:
3,931 m2
2F Windows and External Doors
2F Windows and External Doors
2F Windows and External Doors
Total Cost Of Windows and External Doors: RM 216,355.70
Total Element Unit Quantity: 1,495 m2
2G Internal Walls and Partitions
Total Cost of Internal Walls and
Partitions: RM 62,774.00
Total Element Unit Quantity:
1,646 m2
2H Internal Doors
2H Internal Doors
2H Internal Doors
Total Cost of Internal Doors: RM 31,140.05
Total Element Unit Quantity: 136 m2
Form 2
3A Internal Wall Finishes
3A Internal Wall Finishes
Total Cost of Internal Wall
Finishes: RM 299,237.00
Total Element Unit Quantity:
6,733 m2
3B Internal Floor Finishes
3B Internal Floor Finishes
Total cost of internal floor finishes:RM 112,050.50
Total Element Unit Quantity: 5,555 m2
3C Internal Ceiling Finishes
Total cost of internal ceiling
finishes: RM175,402.50
Total Element Unit Quantity:
7,538 m2
3D EXTERNAL FINISHES
3D1- EXTERNAL WALL FINISHES
Total Cost of External Wall
Finishes: RM142,300.00
3D EXTERNAL FINISHES
3D2- EXTERNAL FLOOR FINISHES
Total Cost of External Floor
Finishes: RM120,610.00
3D EXTERNAL FINISHES
3D3- EXTERNAL CEILING FINISHES
Total Cost of The External Ceiling
Finishes: RM 46,557.00
3D- EXTERNAL FINISHES
TOTAL COST OF EXTERNAL FINISHES
= RM 142,300.00 + RM 120,610.00 + RM 46,557.00
= RM 309,467.00
Form 2
4 FITTINGS AND FURNISHES
Total cost of fittings and
furnishes RM 10,000.00
Form 2
5A SANITARY APPLIANCES
Total Cost of Sanitary Appliances RM 93,425.00
Total Element Unit Quantity: 450 Nos
5B PLUMBING INSTALLATION
Total cost of plumbing
installation:
RM 360,000.00
5E ELECTRICAL INSTALLATION
Total cost of electrical
installation:
RM600,000.00
5F FIRE PROTECTION INSTALLATION
Total cost of fire installation:
RM 100,000.00
5K BUILDER’S PROFIT AND ATTENDANCE ON SERVICES
Total cost of builder’s profit and
attendance on services:
RM 31,800.00
Form 2
6A Site Work
6A Site Work
Total cost of site work:
RM 674,141.85
6B Drainage
Total Cost of Drainage: RM 572,299.50
6C External Service
Total Cost of External Service:
RM 129,926.00
6D Ancillary Buildings
Total Cost of Ancillary Buildings:
RM 27,000