1. BOYS HOSTEL FLOOR
S.No. Description of work No's L(in ft.) B(in ft.) D(in ft.) Quantity unit rate cost
1
V.R.C.C. 1:2:4 using 20mm HBG
metal and Fe 415 steel including all
(c) Columns
12X18 5 1.00 1.5 8.50 63.75
15X15 1 1.25 1.25 8.50 13.28
18X15 1 1.50 1.25 8.50 15.94
92.97 Cft 200 18594
(d ) Meta color Profile sheet roofing
Including Truss work 517.00 Sft 150 77550
SLAB for OHT
1 12.5 6.5 0.33 26.81 Cft 200 5362.5
(e) lintels/sunshades
W5 1 5.00 1.5 0.25 1.88
kw3 1 3 1.5 0.25 1.13
v3 1 3 1.5 0.25 1.13
v2 2 2 1.5 0.25 1.50
5.63 Cft 150 843.75
1
(f) Kitchen Platform 1 13.50 2.00 0.25 6.75 Cft 150 1012.5
(g) Lofts 1 13.50 2.00 0.25 6.75
1 4.50 7.50 0.25 8.44
15.19 Cft 150 2278.1
2 Supplying and fixing of teak wood
frames & Teak wood shutters,hard
ware fittings etc.
MAIN DOORS 1 3.50 7.00 24.50
24.50 Sft 929 22770
2a Supplying and fixing of Sal wood
frames & Block board shutters,hard
ware fittings etc.
D2.5 6 2.50 6.5 97.50
97.50 Sft 465 45307
3 Supplying and fixing of Sal wood
windows with double glazed glass
etc.
W2 1 2.00 4.50 9.00
W3 2 3.00 4.50 27.00
KW3 1 3.00 2.00 6.00
W5 1 5.00 4.50 22.50
64.50 Sft 250 16125
4 Supplying and fixing of ventilators
with frames hardware fittings etc.
V2 1 2.00 2.00 4.00
V3 2 3.00 2.00 12.00
68.50 Sft 250 17125
2. 5 Superstructure in brick masonry
using first class brick in C.M 1:4 for
6" thk. Walls including all
1 81.75 0.5 8.50 347.44
347.44 Cft
Deductions
MD -1 3.5 0.5 7.00 -12.25
D2.5 -2 2.5 0.5 6.50 -16.25
W2 -1 2.00 0.5 4.50 -4.50
W3 -2 3.00 0.5 4.50 -13.50
KW3 -1 3.00 0.5 2.00 -3.00
W5 -1 5.00 0.5 4.50 -11.25
V2 -1 2.00 0.5 2.00 -2.00
V3 -2 3.00 0.5 2.00 -6.00
-68.75
Total 6" Brick masonary 278.69 Cft 155.76 43409
5A Superstructure in brick masonry
using first class brick in C.M 1:4 for
4.5" thk. Walls including all
1 37.00 0.375 8.50 117.94
1 4.00 0.375 8.50 12.75
130.69
Deductions
D2.5 -3 2.50 0.375 6.50 -18.28
-18.28
Total 4.5" Brick masonary 112.41 Cft 118.95 13370
S.No. Description of work No's L(in ft.) B(in ft.) D(in ft.) Quantity unit
6 Internal plastering of 12mm thk. To
the walls with sponge finishing
C.M.1:6 including all
Internal wall area 1 37.00 8.50 314.50
1 4.00 8.50 34.00
Deduction area
D2.5 -3 2.50 6.50 -48.75
299.75
Sofits area 44.96
Net Plaster area 344.71 Sft 20 6894.3
7 External plastering 12mm thk.to the
walls with sponge finishing C.M.1:6
including all
EXternal wall area 1 105.50 8.50 896.75
Deduction area
MD -1 3.50 7.00 -24.50
D2.5 -2 2.5 6.50 -32.50
W2 -1 2.00 4.50 -9.00
W3 -2 3.00 4.50 -27.00
KW3 -1 3.00 2.00 -6.00
W5 -1 5.00 4.50 -22.50
V2 -1 2.00 2.00 -4.00
V3 -2 3.00 2.00 -12.00
759.25
Sofits area 113.89
Net Plaster area 873.14 Sft 26 22721
3. 8
Plastering 12mm thk.to the Ceiling
with sponge finishing C.M.1:6
including all
9
Distemper for inside plastering
including all 344.71 Sft 11 3844.4
9a
Distemper for ceiling plastering
including all
10 Weather Proof paint on external
walls including all 873.14 Sft 30 26194
11 Flooring with 3/4" thick Marble
stones in CM 1:6 and joint with white
cement including all.(for all rooms)
living 1 200.00
Multipurpose 1 66.00
Kitchen 1 68.00
334.00 Sft 250 83500
11a Flooring with antiskid tiles including
all.(for all toilets &utilities)
WC1 1 13.00
WC2 1 31.50
BATH 1 23.00
UTILITY 1 70.00
114.50 Sft 45 5152.5
12 Providing & dadoing in toilets using
ceramic tiles
WC1 1 14.50 6 87.00
WC2 1 14.75 6 88.50
BATH 1 21.75 6 130.50
UTILITY 1
Deductions -3 2.50 6 -45.00
Net Dadoing area 261.00 Sft 45 11745
12a
Providing & dadoing in kitchen
using ceramic tiles 1 13.5 2 27.00 Sft 45 1215
13 Skirting with 3/4" thick Marble
stones in CM 1:6 and joined with
cement including all
1 62.5 0.5 31.25
1 34.25 0.5 17.13
staircase 20 3.125 0.5 31.25
79.63 Sft 30 2388.8
14 M.S railings
balconies 1 39.5 4 158.00
staircase handrailing 1 20 3 60.00
218.00 Sft 209 45586
Boys Hostel Floor Total 472987
contingencies 15% 70948
Estimated Cost 543935
area 596
cost/sft 912.64