BOYS HOSTEL FLOOR
S.No. Description of work No's L(in ft.) B(in ft.) D(in ft.) Quantity unit rate cost
1
V.R.C.C. 1:2:4 using 20mm HBG
metal and Fe 415 steel including all
(c) Columns
12X18 5 1.00 1.5 8.50 63.75
15X15 1 1.25 1.25 8.50 13.28
18X15 1 1.50 1.25 8.50 15.94
92.97 Cft 200 18594
(d ) Meta color Profile sheet roofing
Including Truss work 517.00 Sft 150 77550
SLAB for OHT
1 12.5 6.5 0.33 26.81 Cft 200 5362.5
(e) lintels/sunshades
W5 1 5.00 1.5 0.25 1.88
kw3 1 3 1.5 0.25 1.13
v3 1 3 1.5 0.25 1.13
v2 2 2 1.5 0.25 1.50
5.63 Cft 150 843.75
1
(f) Kitchen Platform 1 13.50 2.00 0.25 6.75 Cft 150 1012.5
(g) Lofts 1 13.50 2.00 0.25 6.75
1 4.50 7.50 0.25 8.44
15.19 Cft 150 2278.1
2 Supplying and fixing of teak wood
frames & Teak wood shutters,hard
ware fittings etc.
MAIN DOORS 1 3.50 7.00 24.50
24.50 Sft 929 22770
2a Supplying and fixing of Sal wood
frames & Block board shutters,hard
ware fittings etc.
D2.5 6 2.50 6.5 97.50
97.50 Sft 465 45307
3 Supplying and fixing of Sal wood
windows with double glazed glass
etc.
W2 1 2.00 4.50 9.00
W3 2 3.00 4.50 27.00
KW3 1 3.00 2.00 6.00
W5 1 5.00 4.50 22.50
64.50 Sft 250 16125
4 Supplying and fixing of ventilators
with frames hardware fittings etc.
V2 1 2.00 2.00 4.00
V3 2 3.00 2.00 12.00
68.50 Sft 250 17125
5 Superstructure in brick masonry
using first class brick in C.M 1:4 for
6" thk. Walls including all
1 81.75 0.5 8.50 347.44
347.44 Cft
Deductions
MD -1 3.5 0.5 7.00 -12.25
D2.5 -2 2.5 0.5 6.50 -16.25
W2 -1 2.00 0.5 4.50 -4.50
W3 -2 3.00 0.5 4.50 -13.50
KW3 -1 3.00 0.5 2.00 -3.00
W5 -1 5.00 0.5 4.50 -11.25
V2 -1 2.00 0.5 2.00 -2.00
V3 -2 3.00 0.5 2.00 -6.00
-68.75
Total 6" Brick masonary 278.69 Cft 155.76 43409
5A Superstructure in brick masonry
using first class brick in C.M 1:4 for
4.5" thk. Walls including all
1 37.00 0.375 8.50 117.94
1 4.00 0.375 8.50 12.75
130.69
Deductions
D2.5 -3 2.50 0.375 6.50 -18.28
-18.28
Total 4.5" Brick masonary 112.41 Cft 118.95 13370
S.No. Description of work No's L(in ft.) B(in ft.) D(in ft.) Quantity unit
6 Internal plastering of 12mm thk. To
the walls with sponge finishing
C.M.1:6 including all
Internal wall area 1 37.00 8.50 314.50
1 4.00 8.50 34.00
Deduction area
D2.5 -3 2.50 6.50 -48.75
299.75
Sofits area 44.96
Net Plaster area 344.71 Sft 20 6894.3
7 External plastering 12mm thk.to the
walls with sponge finishing C.M.1:6
including all
EXternal wall area 1 105.50 8.50 896.75
Deduction area
MD -1 3.50 7.00 -24.50
D2.5 -2 2.5 6.50 -32.50
W2 -1 2.00 4.50 -9.00
W3 -2 3.00 4.50 -27.00
KW3 -1 3.00 2.00 -6.00
W5 -1 5.00 4.50 -22.50
V2 -1 2.00 2.00 -4.00
V3 -2 3.00 2.00 -12.00
759.25
Sofits area 113.89
Net Plaster area 873.14 Sft 26 22721
8
Plastering 12mm thk.to the Ceiling
with sponge finishing C.M.1:6
including all
9
Distemper for inside plastering
including all 344.71 Sft 11 3844.4
9a
Distemper for ceiling plastering
including all
10 Weather Proof paint on external
walls including all 873.14 Sft 30 26194
11 Flooring with 3/4" thick Marble
stones in CM 1:6 and joint with white
cement including all.(for all rooms)
living 1 200.00
Multipurpose 1 66.00
Kitchen 1 68.00
334.00 Sft 250 83500
11a Flooring with antiskid tiles including
all.(for all toilets &utilities)
WC1 1 13.00
WC2 1 31.50
BATH 1 23.00
UTILITY 1 70.00
114.50 Sft 45 5152.5
12 Providing & dadoing in toilets using
ceramic tiles
WC1 1 14.50 6 87.00
WC2 1 14.75 6 88.50
BATH 1 21.75 6 130.50
UTILITY 1
Deductions -3 2.50 6 -45.00
Net Dadoing area 261.00 Sft 45 11745
12a
Providing & dadoing in kitchen
using ceramic tiles 1 13.5 2 27.00 Sft 45 1215
13 Skirting with 3/4" thick Marble
stones in CM 1:6 and joined with
cement including all
1 62.5 0.5 31.25
1 34.25 0.5 17.13
staircase 20 3.125 0.5 31.25
79.63 Sft 30 2388.8
14 M.S railings
balconies 1 39.5 4 158.00
staircase handrailing 1 20 3 60.00
218.00 Sft 209 45586
Boys Hostel Floor Total 472987
contingencies 15% 70948
Estimated Cost 543935
area 596
cost/sft 912.64
Same as insideside plastering area
Same as ceiling plastering area
Same as outside plastering area
Boys home shed estimation

More Related Content

Similar to Boys home shed estimation

Girls home estimation
Girls home estimationGirls home estimation
Girls home estimationkrkantamneni
 
Cost of breeder farm
Cost of breeder farmCost of breeder farm
Cost of breeder farmOmar Faruque
 
97170708 estimate-of-material-and-labor
97170708 estimate-of-material-and-labor97170708 estimate-of-material-and-labor
97170708 estimate-of-material-and-laborimaduddin91
 
Building Economics Preliminary Cost Appraisal
Building Economics Preliminary Cost Appraisal Building Economics Preliminary Cost Appraisal
Building Economics Preliminary Cost Appraisal ashleyyeap
 
28725680 qarghayi-anp-estimation
28725680 qarghayi-anp-estimation28725680 qarghayi-anp-estimation
28725680 qarghayi-anp-estimationimaduddin91
 
128249253 deped-estimate
128249253 deped-estimate128249253 deped-estimate
128249253 deped-estimateimaduddin91
 
91488667 estimation-of-building-house
91488667 estimation-of-building-house91488667 estimation-of-building-house
91488667 estimation-of-building-houseimaduddin91
 
Tender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdf
Tender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdfTender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdf
Tender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdfssuserd43de8
 
L. labour-charges-for-11k v-system-1
L. labour-charges-for-11k v-system-1L. labour-charges-for-11k v-system-1
L. labour-charges-for-11k v-system-1Ramesh Meti
 
Farm Survey Assignment, Avin Kharel (16, IAAS Lamjung Campus)..pdf
Farm Survey Assignment, Avin Kharel (16, IAAS Lamjung Campus)..pdfFarm Survey Assignment, Avin Kharel (16, IAAS Lamjung Campus)..pdf
Farm Survey Assignment, Avin Kharel (16, IAAS Lamjung Campus)..pdfAvin Kharel
 
Baf Shaheen College (B+12) ETABS Dynamic Analysis.pptx
Baf Shaheen College (B+12) ETABS Dynamic Analysis.pptxBaf Shaheen College (B+12) ETABS Dynamic Analysis.pptx
Baf Shaheen College (B+12) ETABS Dynamic Analysis.pptxDES Engineers Ltd
 
72747160 estimation
72747160 estimation72747160 estimation
72747160 estimationimaduddin91
 
Intro. to management lecture 06
Intro. to management lecture 06Intro. to management lecture 06
Intro. to management lecture 06Haitham Sharnouby
 
58517990 estimating-resi-building
58517990 estimating-resi-building58517990 estimating-resi-building
58517990 estimating-resi-buildingimaduddin91
 
Scheduling SLEX (FS)-InitialCPM
Scheduling SLEX (FS)-InitialCPMScheduling SLEX (FS)-InitialCPM
Scheduling SLEX (FS)-InitialCPMAllan Leyte
 

Similar to Boys home shed estimation (20)

Girls home estimation
Girls home estimationGirls home estimation
Girls home estimation
 
Construction Management Project
Construction Management ProjectConstruction Management Project
Construction Management Project
 
Cost of breeder farm
Cost of breeder farmCost of breeder farm
Cost of breeder farm
 
97170708 estimate-of-material-and-labor
97170708 estimate-of-material-and-labor97170708 estimate-of-material-and-labor
97170708 estimate-of-material-and-labor
 
GBI: Role of BS
GBI: Role of BSGBI: Role of BS
GBI: Role of BS
 
Building Economics Preliminary Cost Appraisal
Building Economics Preliminary Cost Appraisal Building Economics Preliminary Cost Appraisal
Building Economics Preliminary Cost Appraisal
 
28725680 qarghayi-anp-estimation
28725680 qarghayi-anp-estimation28725680 qarghayi-anp-estimation
28725680 qarghayi-anp-estimation
 
Rab
RabRab
Rab
 
128249253 deped-estimate
128249253 deped-estimate128249253 deped-estimate
128249253 deped-estimate
 
GP Report
GP ReportGP Report
GP Report
 
91488667 estimation-of-building-house
91488667 estimation-of-building-house91488667 estimation-of-building-house
91488667 estimation-of-building-house
 
Tender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdf
Tender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdfTender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdf
Tender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdf
 
L. labour-charges-for-11k v-system-1
L. labour-charges-for-11k v-system-1L. labour-charges-for-11k v-system-1
L. labour-charges-for-11k v-system-1
 
Farm Survey Assignment, Avin Kharel (16, IAAS Lamjung Campus)..pdf
Farm Survey Assignment, Avin Kharel (16, IAAS Lamjung Campus)..pdfFarm Survey Assignment, Avin Kharel (16, IAAS Lamjung Campus)..pdf
Farm Survey Assignment, Avin Kharel (16, IAAS Lamjung Campus)..pdf
 
Baf Shaheen College (B+12) ETABS Dynamic Analysis.pptx
Baf Shaheen College (B+12) ETABS Dynamic Analysis.pptxBaf Shaheen College (B+12) ETABS Dynamic Analysis.pptx
Baf Shaheen College (B+12) ETABS Dynamic Analysis.pptx
 
72747160 estimation
72747160 estimation72747160 estimation
72747160 estimation
 
RR Nagar
RR NagarRR Nagar
RR Nagar
 
Intro. to management lecture 06
Intro. to management lecture 06Intro. to management lecture 06
Intro. to management lecture 06
 
58517990 estimating-resi-building
58517990 estimating-resi-building58517990 estimating-resi-building
58517990 estimating-resi-building
 
Scheduling SLEX (FS)-InitialCPM
Scheduling SLEX (FS)-InitialCPMScheduling SLEX (FS)-InitialCPM
Scheduling SLEX (FS)-InitialCPM
 

Boys home shed estimation

  • 1. BOYS HOSTEL FLOOR S.No. Description of work No's L(in ft.) B(in ft.) D(in ft.) Quantity unit rate cost 1 V.R.C.C. 1:2:4 using 20mm HBG metal and Fe 415 steel including all (c) Columns 12X18 5 1.00 1.5 8.50 63.75 15X15 1 1.25 1.25 8.50 13.28 18X15 1 1.50 1.25 8.50 15.94 92.97 Cft 200 18594 (d ) Meta color Profile sheet roofing Including Truss work 517.00 Sft 150 77550 SLAB for OHT 1 12.5 6.5 0.33 26.81 Cft 200 5362.5 (e) lintels/sunshades W5 1 5.00 1.5 0.25 1.88 kw3 1 3 1.5 0.25 1.13 v3 1 3 1.5 0.25 1.13 v2 2 2 1.5 0.25 1.50 5.63 Cft 150 843.75 1 (f) Kitchen Platform 1 13.50 2.00 0.25 6.75 Cft 150 1012.5 (g) Lofts 1 13.50 2.00 0.25 6.75 1 4.50 7.50 0.25 8.44 15.19 Cft 150 2278.1 2 Supplying and fixing of teak wood frames & Teak wood shutters,hard ware fittings etc. MAIN DOORS 1 3.50 7.00 24.50 24.50 Sft 929 22770 2a Supplying and fixing of Sal wood frames & Block board shutters,hard ware fittings etc. D2.5 6 2.50 6.5 97.50 97.50 Sft 465 45307 3 Supplying and fixing of Sal wood windows with double glazed glass etc. W2 1 2.00 4.50 9.00 W3 2 3.00 4.50 27.00 KW3 1 3.00 2.00 6.00 W5 1 5.00 4.50 22.50 64.50 Sft 250 16125 4 Supplying and fixing of ventilators with frames hardware fittings etc. V2 1 2.00 2.00 4.00 V3 2 3.00 2.00 12.00 68.50 Sft 250 17125
  • 2. 5 Superstructure in brick masonry using first class brick in C.M 1:4 for 6" thk. Walls including all 1 81.75 0.5 8.50 347.44 347.44 Cft Deductions MD -1 3.5 0.5 7.00 -12.25 D2.5 -2 2.5 0.5 6.50 -16.25 W2 -1 2.00 0.5 4.50 -4.50 W3 -2 3.00 0.5 4.50 -13.50 KW3 -1 3.00 0.5 2.00 -3.00 W5 -1 5.00 0.5 4.50 -11.25 V2 -1 2.00 0.5 2.00 -2.00 V3 -2 3.00 0.5 2.00 -6.00 -68.75 Total 6" Brick masonary 278.69 Cft 155.76 43409 5A Superstructure in brick masonry using first class brick in C.M 1:4 for 4.5" thk. Walls including all 1 37.00 0.375 8.50 117.94 1 4.00 0.375 8.50 12.75 130.69 Deductions D2.5 -3 2.50 0.375 6.50 -18.28 -18.28 Total 4.5" Brick masonary 112.41 Cft 118.95 13370 S.No. Description of work No's L(in ft.) B(in ft.) D(in ft.) Quantity unit 6 Internal plastering of 12mm thk. To the walls with sponge finishing C.M.1:6 including all Internal wall area 1 37.00 8.50 314.50 1 4.00 8.50 34.00 Deduction area D2.5 -3 2.50 6.50 -48.75 299.75 Sofits area 44.96 Net Plaster area 344.71 Sft 20 6894.3 7 External plastering 12mm thk.to the walls with sponge finishing C.M.1:6 including all EXternal wall area 1 105.50 8.50 896.75 Deduction area MD -1 3.50 7.00 -24.50 D2.5 -2 2.5 6.50 -32.50 W2 -1 2.00 4.50 -9.00 W3 -2 3.00 4.50 -27.00 KW3 -1 3.00 2.00 -6.00 W5 -1 5.00 4.50 -22.50 V2 -1 2.00 2.00 -4.00 V3 -2 3.00 2.00 -12.00 759.25 Sofits area 113.89 Net Plaster area 873.14 Sft 26 22721
  • 3. 8 Plastering 12mm thk.to the Ceiling with sponge finishing C.M.1:6 including all 9 Distemper for inside plastering including all 344.71 Sft 11 3844.4 9a Distemper for ceiling plastering including all 10 Weather Proof paint on external walls including all 873.14 Sft 30 26194 11 Flooring with 3/4" thick Marble stones in CM 1:6 and joint with white cement including all.(for all rooms) living 1 200.00 Multipurpose 1 66.00 Kitchen 1 68.00 334.00 Sft 250 83500 11a Flooring with antiskid tiles including all.(for all toilets &utilities) WC1 1 13.00 WC2 1 31.50 BATH 1 23.00 UTILITY 1 70.00 114.50 Sft 45 5152.5 12 Providing & dadoing in toilets using ceramic tiles WC1 1 14.50 6 87.00 WC2 1 14.75 6 88.50 BATH 1 21.75 6 130.50 UTILITY 1 Deductions -3 2.50 6 -45.00 Net Dadoing area 261.00 Sft 45 11745 12a Providing & dadoing in kitchen using ceramic tiles 1 13.5 2 27.00 Sft 45 1215 13 Skirting with 3/4" thick Marble stones in CM 1:6 and joined with cement including all 1 62.5 0.5 31.25 1 34.25 0.5 17.13 staircase 20 3.125 0.5 31.25 79.63 Sft 30 2388.8 14 M.S railings balconies 1 39.5 4 158.00 staircase handrailing 1 20 3 60.00 218.00 Sft 209 45586 Boys Hostel Floor Total 472987 contingencies 15% 70948 Estimated Cost 543935 area 596 cost/sft 912.64 Same as insideside plastering area Same as ceiling plastering area Same as outside plastering area