SlideShare a Scribd company logo
1 of 12
CROSSTOWN LRT
Chaplin-Avenue CLC
November 6, 2019
Chaplin Construction Updates
3
Chaplin Station Construction Update
Activity Location Approx. Date & Duration Impacts
Excavation Main Entrance
Underway through 2019; 6:00
a.m. – 11:00 p.m.
• Closure of the east sidewalk on Chaplin
Cres between Eglinton Ave and Spadina
Rd
• Closure of the north crosswalk
• Dump trucks
Excavation Tertiary Entrance
Underway until mid-November
2019; 6:00 a.m. – 11:00 p.m.
• Closure of the south sidewalk on
Eglinton Ave between Tertiary Entrance
and Chaplin Cres
• Dump trucks
Shallow Excavation
and Roof
Construction
South Station Box (south
side of Eglinton Ave
between Spadina Rd and
Russell Hill Rd)
Underway through February
2020
• Eglinton Ave and Chaplin Cres reduced to
one lane in each direction
• Dump trucks
Concrete Roof
Pours
Chaplin Cres and
Eglinton Ave West
Three (3) concrete pours to take
place in December 2019
Tentative dates:
• December 7, 2019
• December 14, 2019
Pours will take between 14-18
hours to complete
• At least one pour will require a full
closure intersection closure of Chaplin
Cres and Eglinton Ave will be required
between Spadina Rd and Russell Rd on
both Eglinton Ave and Chaplin Cres
• Overnight noise from concrete trucks and
pumps
4
Chaplin Station Construction Update
Activity Location Approx. Date & Duration Impacts
Deep Excavation
Tertiary Entrance
beneath the station roof
Mid-November 2019 through
2020; 6:00 a.m. – 11:00 p.m.
• Truck traffic in the Russell Hill-Chaplin
laneway
Concrete Works Tertiary Entrance
Periodic concrete pours
beginning mid-November 2019
• Noise from concrete truck and pumps
5
Current Construction Configuration
Through 2020
6
Construction Progress Photos
MAIN ENTRANCE EXCAVATION
SHALLOW EXCAVATION
Avenue Construction Updates
8
Avenue Station Construction Update
Activity Location
Approx. Date &
Duration
Impact
Mining Excavation
Between the Main and
Secondary Entrances
Completed as of
October 2019
• Overnight noise from drilling activity
• Road occupation on Eglinton Ave
Mining Excavation
East of the Secondary
Entrance between
Oriole Parkway and
Eastbourne Avenue
Ongoing through July
2020
• Overnight noise from drilling activity
• Road occupation on Eglinton Ave
Concrete Pours
Between Main and
Secondary Entrances
Periodically through
2019; beginning at 3
a.m. for approx. 16
hours
• Concrete pours in December are expected to
require southbound lane closures on Avenue Rd –
one lane in each direction will be maintained
• Concrete truck traffic
• Additional temporary road occupation on the
north side of Eglinton Ave west of Main Entrance
Dewatering Well
Maintenance
Eglinton Ave between
Braemar Ave and
Lascelles Blvd
Periodically through
2021; 9 a.m. – 4 p.m.
(Mon.-Fri.)
• Road occupancy around well
• Use of hydro-vac truck
Monitoring Work
Eglinton Ave between
Braemar Ave and
Lascelles Blvd
Periodically through
2021
• Short-term road occupancy
Installation of
Connection Bore
Holes
North side of Eglinton
Ave, west of Main
Entrance
Late November 2019 for
approx. one (1) week
• Short-term road occupancy
• Noise from drilling activity
Avenue Station – Mining Information
Avenue Station – Upcoming Works
• In late November 2019, two boreholes will be drilled to the west of the Main Entrance to
facilitate concrete delivery to cavern level
• Permanent works at the Main Entrance shaft has now started
– The work zone expanded to the west.
– A pump will be on the boulevard to the west of the main entrance for the duration of the permanent works.
– A temporary construction zone will be put in place periodically during concrete pours in the west bound curb lane.
1 Week for Borehole Drilling
Long term occupation on boulevard
Temporary occupation during pours
Current Traffic Configuration
Through September 2021
Avenue Station – Construction Progress Photos

More Related Content

What's hot

Cedarvale & Forest Hill Construction Liaison Committee - July 2018
Cedarvale & Forest Hill Construction Liaison Committee - July 2018Cedarvale & Forest Hill Construction Liaison Committee - July 2018
Cedarvale & Forest Hill Construction Liaison Committee - July 2018
Crosstown TO
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
Crosstown TO
 
Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018
Crosstown TO
 

What's hot (20)

Brentcliffe to Victoria Park - CLC construction update January 2021
Brentcliffe to Victoria Park - CLC construction update January 2021Brentcliffe to Victoria Park - CLC construction update January 2021
Brentcliffe to Victoria Park - CLC construction update January 2021
 
Eglinton & Mt pleasant CLC - November
Eglinton & Mt pleasant CLC - November Eglinton & Mt pleasant CLC - November
Eglinton & Mt pleasant CLC - November
 
Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021
 
Fairbank-Oakwood Construction Update - July 2021
Fairbank-Oakwood Construction Update - July 2021Fairbank-Oakwood Construction Update - July 2021
Fairbank-Oakwood Construction Update - July 2021
 
Cedarvale & Forest Hill Construction Liaison Committee - July 2018
Cedarvale & Forest Hill Construction Liaison Committee - July 2018Cedarvale & Forest Hill Construction Liaison Committee - July 2018
Cedarvale & Forest Hill Construction Liaison Committee - July 2018
 
Cedarvale & Forest Hill Construction Update (November 24, 2021)
Cedarvale & Forest Hill Construction Update (November 24, 2021)Cedarvale & Forest Hill Construction Update (November 24, 2021)
Cedarvale & Forest Hill Construction Update (November 24, 2021)
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
 
Western Works CLC - Construction Update: January 18, 2022
Western Works CLC - Construction Update: January 18, 2022Western Works CLC - Construction Update: January 18, 2022
Western Works CLC - Construction Update: January 18, 2022
 
Avenue & Chaplin CLC - Construction Update: January 5, 2022
Avenue & Chaplin CLC - Construction Update: January 5, 2022Avenue & Chaplin CLC - Construction Update: January 5, 2022
Avenue & Chaplin CLC - Construction Update: January 5, 2022
 
Brentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingBrentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC Meeting
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting
 
Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021
Brentcliffe to Victoria Park CLC Meeting -  Presentation - November 4, 2021 Brentcliffe to Victoria Park CLC Meeting -  Presentation - November 4, 2021
Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021
 
Cedarvale & Forest Hill Construction Update (July 30, 2021)
Cedarvale & Forest Hill Construction Update (July 30, 2021)Cedarvale & Forest Hill Construction Update (July 30, 2021)
Cedarvale & Forest Hill Construction Update (July 30, 2021)
 
Cedarvale & Forest Hill Construction Update (September 30, 2020)
Cedarvale & Forest Hill Construction Update (September 30, 2020)Cedarvale & Forest Hill Construction Update (September 30, 2020)
Cedarvale & Forest Hill Construction Update (September 30, 2020)
 
CLC: Leaside and Laird - Sept 13 2021
CLC: Leaside and Laird - Sept 13 2021 CLC: Leaside and Laird - Sept 13 2021
CLC: Leaside and Laird - Sept 13 2021
 
Avenue & Chaplin CLC - Construction Update: May 6, 2020
Avenue & Chaplin CLC - Construction Update: May 6, 2020Avenue & Chaplin CLC - Construction Update: May 6, 2020
Avenue & Chaplin CLC - Construction Update: May 6, 2020
 
Cedarvale & Forest Hill CLC - September 25, 2019
Cedarvale & Forest Hill CLC - September 25, 2019Cedarvale & Forest Hill CLC - September 25, 2019
Cedarvale & Forest Hill CLC - September 25, 2019
 
Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018
 
Fall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue StationsFall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue Stations
 

Similar to Chaplin & Avenue Construction Liaison Committee Meeting

Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2019
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2019Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2019
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2019
Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019
Crosstown TO
 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - July 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - July 2019Eglinton & Mount Pleasant Construction Liaison Committee Meeting - July 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - July 2019
Crosstown TO
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
Crosstown TO
 
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Crosstown TO
 
Eglinton & Mount Pleasant Construction Liaison Committee - Sep 2019
Eglinton & Mount Pleasant Construction Liaison Committee - Sep 2019Eglinton & Mount Pleasant Construction Liaison Committee - Sep 2019
Eglinton & Mount Pleasant Construction Liaison Committee - Sep 2019
Crosstown TO
 
Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018
Crosstown TO
 
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Crosstown TO
 
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - Nov 2019
Pharmacy to Kennedy Construction Liaison Committee Meeting - Nov 2019Pharmacy to Kennedy Construction Liaison Committee Meeting - Nov 2019
Pharmacy to Kennedy Construction Liaison Committee Meeting - Nov 2019
Crosstown TO
 

Similar to Chaplin & Avenue Construction Liaison Committee Meeting (20)

Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2019
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2019Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2019
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2019
 
CLC pharmacy to Kennedy (Nov24)
CLC pharmacy to Kennedy (Nov24)CLC pharmacy to Kennedy (Nov24)
CLC pharmacy to Kennedy (Nov24)
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019
 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - July 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - July 2019Eglinton & Mount Pleasant Construction Liaison Committee Meeting - July 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - July 2019
 
Cedarvale-Forest Hill CLC Presentation - November 27 2019
Cedarvale-Forest Hill CLC Presentation - November 27 2019Cedarvale-Forest Hill CLC Presentation - November 27 2019
Cedarvale-Forest Hill CLC Presentation - November 27 2019
 
Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
 
Pharmacy kennedy clc meeting -january 29 2019
Pharmacy kennedy clc meeting -january 29 2019Pharmacy kennedy clc meeting -january 29 2019
Pharmacy kennedy clc meeting -january 29 2019
 
Eglinton & Mount Pleasant Construction Liaison Committee - Sep 2019
Eglinton & Mount Pleasant Construction Liaison Committee - Sep 2019Eglinton & Mount Pleasant Construction Liaison Committee - Sep 2019
Eglinton & Mount Pleasant Construction Liaison Committee - Sep 2019
 
Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018
 
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
 
Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020
 
Cedarvale- Forest Hill Construction Update (July 29, 2020)
Cedarvale- Forest Hill Construction Update (July 29, 2020)Cedarvale- Forest Hill Construction Update (July 29, 2020)
Cedarvale- Forest Hill Construction Update (July 29, 2020)
 
Pharmacy kennedy clc meeting- april 30, 2019
Pharmacy kennedy clc meeting- april 30, 2019Pharmacy kennedy clc meeting- april 30, 2019
Pharmacy kennedy clc meeting- april 30, 2019
 
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - Nov 2019
Pharmacy to Kennedy Construction Liaison Committee Meeting - Nov 2019Pharmacy to Kennedy Construction Liaison Committee Meeting - Nov 2019
Pharmacy to Kennedy Construction Liaison Committee Meeting - Nov 2019
 

More from Crosstown TO

More from Crosstown TO (20)

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
 

Recently uploaded

Securing the Future | Public Good App House
Securing the Future | Public Good App HouseSecuring the Future | Public Good App House
Securing the Future | Public Good App House
TechSoup
 

Recently uploaded (20)

Securing the Future | Public Good App House
Securing the Future | Public Good App HouseSecuring the Future | Public Good App House
Securing the Future | Public Good App House
 
Introduction to The Guidelines for the Long-term Sustainability of Outer Spac...
Introduction to The Guidelines for the Long-term Sustainability of Outer Spac...Introduction to The Guidelines for the Long-term Sustainability of Outer Spac...
Introduction to The Guidelines for the Long-term Sustainability of Outer Spac...
 
PPT Item # 9 2ndQTR Financial & Inv. Report
PPT Item # 9 2ndQTR Financial & Inv. ReportPPT Item # 9 2ndQTR Financial & Inv. Report
PPT Item # 9 2ndQTR Financial & Inv. Report
 
World Wildlife Crime Report 2024 - Introduction
World Wildlife Crime Report 2024 - IntroductionWorld Wildlife Crime Report 2024 - Introduction
World Wildlife Crime Report 2024 - Introduction
 
“Bee engaged with Youth”. World Bee Day 2024; May. 20th.
“Bee engaged with Youth”. World Bee Day 2024; May. 20th.“Bee engaged with Youth”. World Bee Day 2024; May. 20th.
“Bee engaged with Youth”. World Bee Day 2024; May. 20th.
 
How to Save a Place: Get the Word Out Far And Wide
How to Save a Place: Get the Word Out Far And WideHow to Save a Place: Get the Word Out Far And Wide
How to Save a Place: Get the Word Out Far And Wide
 
2024: The FAR - Federal Acquisition Regulations, Part 34
2024: The FAR - Federal Acquisition Regulations, Part 342024: The FAR - Federal Acquisition Regulations, Part 34
2024: The FAR - Federal Acquisition Regulations, Part 34
 
Our nurses, our future. The economic power of care.
Our nurses, our future. The economic power of care.Our nurses, our future. The economic power of care.
Our nurses, our future. The economic power of care.
 
Item ## 4a -- April 29, 2024 CCM Minutes
Item ## 4a -- April 29, 2024 CCM MinutesItem ## 4a -- April 29, 2024 CCM Minutes
Item ## 4a -- April 29, 2024 CCM Minutes
 
EDI Executive Education MasterClass- 15thMay 2024 (updated).pdf
EDI Executive Education MasterClass- 15thMay 2024 (updated).pdfEDI Executive Education MasterClass- 15thMay 2024 (updated).pdf
EDI Executive Education MasterClass- 15thMay 2024 (updated).pdf
 
OECD Green Talks LIVE | Diving deeper: the evolving landscape for assessing w...
OECD Green Talks LIVE | Diving deeper: the evolving landscape for assessing w...OECD Green Talks LIVE | Diving deeper: the evolving landscape for assessing w...
OECD Green Talks LIVE | Diving deeper: the evolving landscape for assessing w...
 
Electric Vehicle infrastructure planning in Rural Planning Organizations
Electric Vehicle infrastructure planning in Rural Planning OrganizationsElectric Vehicle infrastructure planning in Rural Planning Organizations
Electric Vehicle infrastructure planning in Rural Planning Organizations
 
Topical Guide for RID 3830 Public Image Training Series.ppsx
Topical Guide for RID 3830 Public Image Training Series.ppsxTopical Guide for RID 3830 Public Image Training Series.ppsx
Topical Guide for RID 3830 Public Image Training Series.ppsx
 
Ian Bremmer's message for those graduating in toxic times.pdf
Ian Bremmer's message for those graduating in toxic times.pdfIan Bremmer's message for those graduating in toxic times.pdf
Ian Bremmer's message for those graduating in toxic times.pdf
 
2024: The FAR - Federal Acquisition Regulations, Part 33
2024: The FAR - Federal Acquisition Regulations, Part 332024: The FAR - Federal Acquisition Regulations, Part 33
2024: The FAR - Federal Acquisition Regulations, Part 33
 
Nitrogen filled high expansion foam in open Containers
Nitrogen filled high expansion foam in open ContainersNitrogen filled high expansion foam in open Containers
Nitrogen filled high expansion foam in open Containers
 
PPT Item # 7&8 6900 Broadway P&Z Case # 438
PPT Item # 7&8 6900 Broadway P&Z Case # 438PPT Item # 7&8 6900 Broadway P&Z Case # 438
PPT Item # 7&8 6900 Broadway P&Z Case # 438
 
Value, protect, respect and invest in our nuses for a sustainable future for ...
Value, protect, respect and invest in our nuses for a sustainable future for ...Value, protect, respect and invest in our nuses for a sustainable future for ...
Value, protect, respect and invest in our nuses for a sustainable future for ...
 
Characterizing wildlife trafficking and associated crime.
Characterizing wildlife trafficking and associated crime.Characterizing wildlife trafficking and associated crime.
Characterizing wildlife trafficking and associated crime.
 
Building a better Britain: How cities like Bradford can help to end economic ...
Building a better Britain: How cities like Bradford can help to end economic ...Building a better Britain: How cities like Bradford can help to end economic ...
Building a better Britain: How cities like Bradford can help to end economic ...
 

Chaplin & Avenue Construction Liaison Committee Meeting

  • 3. 3 Chaplin Station Construction Update Activity Location Approx. Date & Duration Impacts Excavation Main Entrance Underway through 2019; 6:00 a.m. – 11:00 p.m. • Closure of the east sidewalk on Chaplin Cres between Eglinton Ave and Spadina Rd • Closure of the north crosswalk • Dump trucks Excavation Tertiary Entrance Underway until mid-November 2019; 6:00 a.m. – 11:00 p.m. • Closure of the south sidewalk on Eglinton Ave between Tertiary Entrance and Chaplin Cres • Dump trucks Shallow Excavation and Roof Construction South Station Box (south side of Eglinton Ave between Spadina Rd and Russell Hill Rd) Underway through February 2020 • Eglinton Ave and Chaplin Cres reduced to one lane in each direction • Dump trucks Concrete Roof Pours Chaplin Cres and Eglinton Ave West Three (3) concrete pours to take place in December 2019 Tentative dates: • December 7, 2019 • December 14, 2019 Pours will take between 14-18 hours to complete • At least one pour will require a full closure intersection closure of Chaplin Cres and Eglinton Ave will be required between Spadina Rd and Russell Rd on both Eglinton Ave and Chaplin Cres • Overnight noise from concrete trucks and pumps
  • 4. 4 Chaplin Station Construction Update Activity Location Approx. Date & Duration Impacts Deep Excavation Tertiary Entrance beneath the station roof Mid-November 2019 through 2020; 6:00 a.m. – 11:00 p.m. • Truck traffic in the Russell Hill-Chaplin laneway Concrete Works Tertiary Entrance Periodic concrete pours beginning mid-November 2019 • Noise from concrete truck and pumps
  • 6. 6 Construction Progress Photos MAIN ENTRANCE EXCAVATION SHALLOW EXCAVATION
  • 8. 8 Avenue Station Construction Update Activity Location Approx. Date & Duration Impact Mining Excavation Between the Main and Secondary Entrances Completed as of October 2019 • Overnight noise from drilling activity • Road occupation on Eglinton Ave Mining Excavation East of the Secondary Entrance between Oriole Parkway and Eastbourne Avenue Ongoing through July 2020 • Overnight noise from drilling activity • Road occupation on Eglinton Ave Concrete Pours Between Main and Secondary Entrances Periodically through 2019; beginning at 3 a.m. for approx. 16 hours • Concrete pours in December are expected to require southbound lane closures on Avenue Rd – one lane in each direction will be maintained • Concrete truck traffic • Additional temporary road occupation on the north side of Eglinton Ave west of Main Entrance Dewatering Well Maintenance Eglinton Ave between Braemar Ave and Lascelles Blvd Periodically through 2021; 9 a.m. – 4 p.m. (Mon.-Fri.) • Road occupancy around well • Use of hydro-vac truck Monitoring Work Eglinton Ave between Braemar Ave and Lascelles Blvd Periodically through 2021 • Short-term road occupancy Installation of Connection Bore Holes North side of Eglinton Ave, west of Main Entrance Late November 2019 for approx. one (1) week • Short-term road occupancy • Noise from drilling activity
  • 9. Avenue Station – Mining Information
  • 10. Avenue Station – Upcoming Works • In late November 2019, two boreholes will be drilled to the west of the Main Entrance to facilitate concrete delivery to cavern level • Permanent works at the Main Entrance shaft has now started – The work zone expanded to the west. – A pump will be on the boulevard to the west of the main entrance for the duration of the permanent works. – A temporary construction zone will be put in place periodically during concrete pours in the west bound curb lane. 1 Week for Borehole Drilling Long term occupation on boulevard Temporary occupation during pours
  • 12. Avenue Station – Construction Progress Photos