Chaplin Station Construction Update
Activity Location Approx. Date & Duration Impacts
Excavation Main Entrance
Underway through 2019; 6:00
a.m. – 11:00 p.m.
• Closure of the east sidewalk on Chaplin
Cres between Eglinton Ave and Spadina
Rd
• Closure of the north crosswalk
• Dump trucks
Excavation Tertiary Entrance
Underway until mid-November
2019; 6:00 a.m. – 11:00 p.m.
• Closure of the south sidewalk on
Eglinton Ave between Tertiary Entrance
and Chaplin Cres
• Dump trucks
Shallow Excavation
and Roof
Construction
South Station Box (south
side of Eglinton Ave
between Spadina Rd and
Russell Hill Rd)
Underway through February
2020
• Eglinton Ave and Chaplin Cres reduced to
one lane in each direction
• Dump trucks
Concrete Roof
Pours
Chaplin Cres and
Eglinton Ave West
Three (3) concrete pours to take
place in December 2019
Tentative dates:
• December 7, 2019
• December 14, 2019
Pours will take between 14-18
hours to complete
• At least one pour will require a full
closure intersection closure of Chaplin
Cres and Eglinton Ave will be required
between Spadina Rd and Russell Rd on
both Eglinton Ave and Chaplin Cres
• Overnight noise from concrete trucks and
pumps
4. 4
Chaplin Station Construction Update
Activity Location Approx. Date & Duration Impacts
Deep Excavation
Tertiary Entrance
beneath the station roof
Mid-November 2019 through
2020; 6:00 a.m. – 11:00 p.m.
• Truck traffic in the Russell Hill-Chaplin
laneway
Concrete Works Tertiary Entrance
Periodic concrete pours
beginning mid-November 2019
• Noise from concrete truck and pumps
8. 8
Avenue Station Construction Update
Activity Location
Approx. Date &
Duration
Impact
Mining Excavation
Between the Main and
Secondary Entrances
Completed as of
October 2019
• Overnight noise from drilling activity
• Road occupation on Eglinton Ave
Mining Excavation
East of the Secondary
Entrance between
Oriole Parkway and
Eastbourne Avenue
Ongoing through July
2020
• Overnight noise from drilling activity
• Road occupation on Eglinton Ave
Concrete Pours
Between Main and
Secondary Entrances
Periodically through
2019; beginning at 3
a.m. for approx. 16
hours
• Concrete pours in December are expected to
require southbound lane closures on Avenue Rd –
one lane in each direction will be maintained
• Concrete truck traffic
• Additional temporary road occupation on the
north side of Eglinton Ave west of Main Entrance
Dewatering Well
Maintenance
Eglinton Ave between
Braemar Ave and
Lascelles Blvd
Periodically through
2021; 9 a.m. – 4 p.m.
(Mon.-Fri.)
• Road occupancy around well
• Use of hydro-vac truck
Monitoring Work
Eglinton Ave between
Braemar Ave and
Lascelles Blvd
Periodically through
2021
• Short-term road occupancy
Installation of
Connection Bore
Holes
North side of Eglinton
Ave, west of Main
Entrance
Late November 2019 for
approx. one (1) week
• Short-term road occupancy
• Noise from drilling activity
10. Avenue Station – Upcoming Works
• In late November 2019, two boreholes will be drilled to the west of the Main Entrance to
facilitate concrete delivery to cavern level
• Permanent works at the Main Entrance shaft has now started
– The work zone expanded to the west.
– A pump will be on the boulevard to the west of the main entrance for the duration of the permanent works.
– A temporary construction zone will be put in place periodically during concrete pours in the west bound curb lane.
1 Week for Borehole Drilling
Long term occupation on boulevard
Temporary occupation during pours