SlideShare a Scribd company logo
1 of 15
Download to read offline
November 4, 2020
Eglinton Crosstown LRT
Chaplin-Avenue CLC
Chaplin Station
CHAPLIN STATION UPDATE
3
Activity Location Approx. Date & Duration What to Expect
Tertiary Entrance Construction
Wall construction, rebar and
formwork
South side of Eglinton Ave,
east of Chaplin Cres and
adjacent Toronto Fire Station
135
Underway into spring 2021
โ€ข Noise from construction
equipment
โ€ข Laneway closure
Main Entrance Construction
Waterproofing, rebar, formwork
North side of Eglinton Ave
between Chaplin Cres and
Gilgorm Rd
Underway into spring 2021
โ€ข Noise from construction
equipment
โ€ข Chipping
Station Box Construction
Rebar, concrete, formwork
Beneath Eglinton Ave Underway into spring 2021
โ€ข Noise from associated
surface works, such as use of
crane and trucks
Watermain Works
Connections and reinstatement
Intersection of Eglinton Ave
and Chaplin Cres
Beginning mid-November 2020
into mid-January 2021
โ€ข Lane reductions
โ€ข Chaplin Cres and Eglinton
Ave intersection closure
โ€ข Overnight work
โ€ข Noise from construction
equipment
CURRENT TRAFFIC CONFIGURATION
4
Until mid-November 2020
CONSTRUCTION PROGRESS PHOTOS
5CENTRAL WEST WORKS MONTHLY MEETING
STATION BOXTERTIARY ENTRANCE
Avenue Station
AVENUE STATION UPDATE
7INSERT FOOTER
Activity Location Approx. Date & Duration What to Expect
Final lining (waterproofing,
rebar installation, and
mechanical electrical works)
Throughout all station areas Underway through to late-2020
โ€ข Deliveries at the main and
secondary entrances
Concrete Pours
Between the Main and Secondary
Entrances
Three times per week for approx.
12 โ€“ 18 hours through to 2021
โ€ข Concrete truck activity
โ€ข Occupation of the westbound
curb lane during some pours
Eglinton Connects Streetscape
and Cycle Track
Overnight Utility Works & Water
Shut-off for fire hydrant relocation
Eglinton Ave between Lascelles Blvd
and Duplex Ave
Affected properties:
โ€ข 174 Eglinton Ave W
โ€ข 200 Eglinton Ave W
Underway through to early 2021
Utility works: Thursday November 5,
2020; beginning at 10:00 p.m. for
approx. seven (7) hours
โ€ข Eglinton reduced to one lane in
each direction between
Lascelles Blvd & Duplex Ave
โ€ข Use of excavator, hydro-vac
and concrete trucks
โ€ข Overnight noise can be expected
during utility works
Dewatering Well Maintenance
Eglinton Ave between Braemar Ave
and Lascelles Blvd
Periodically through 2021; 9:00
a.m. โ€“ 4:00 p.m.
โ€ข Road occupancy around well
โ€ข Use of hydro-vac truck
Monitoring Work
Eglinton Ave between Braemar Ave
and Lascelles Blvd
Periodically through 2021 โ€ข Short-term road occupancy
CURRENT TRAFFIC CONFIGURATION
8
Through September 2021
INSERT FOOTER
CURRENT TRAFFIC CONFIGURATION: LASCELLES BLVD TO DUPLEX AVE
9INSERT FOOTER
Through Winter 2020
EGLINTON AVE FUTURE CONFIGURATION โ€“ ORIOLE PKWY TO LASCELLES BLVD
10INSERT FOOTER
EGLINTON AVE FUTURE CONFIGURATION โ€“ LASCELLES BLVD โ€“ DUPLEX AVE
11INSERT FOOTER
EGLINTON CONNECTS CONSTRUCTION OVERVIEW
12
Construction of the new Eglinton Streetscape and Cycle Track between Lascelles Blvd and Duplex Ave will
continue into 2021.
The Eglinton Connects Streetscape and Cycle Track is being constructed in coordination with the City of
Torontoโ€™s Streetscape and Cycle Track Design.
Construction Hours:
โ€ข Monday โ€“ Saturday, 7:00 a.m. โ€“ 7:00 p.m. with periodic overnight work
Construction Activities:
โ€ข Excavation
โ€ข Utility Reinstatement
โ€ข Concrete Work
โ€ข Compaction and Paving
โ€ข Landscaping โ€“ installation of street furnishings, light poles, trees etc.
To accommodate this work, all street furnishings, bus shelters, and trees between Lascelles Blvd and Duplex Ave will be
removed. Notice will be provided in advance of removals.
Upon completion of Eglinton Connects, additional street furnishings and trees will be installed/planted along Eglinton Ave.
INSERT FOOTER
CONSTRUCTION PROGRESS PHOTOS
13INSERT FOOTER
REBAR INSTALLATION โ€“
MAIN ENTRANCE
WATERPROOFING โ€“
SECONDARY ENTRACE HEADWALL
CONSTRUCTION PROGRESS PHOTOS
14INSERT FOOTER
REBAR INSTALLATION
- STATION BOX CONCOURSE LEVEL
Avenue & Chaplin CLC - Construction Update: November 4, 2020

More Related Content

What's hot

Leaside and Laird CLC - January 11, 2021
Leaside and Laird CLC - January 11, 2021Leaside and Laird CLC - January 11, 2021
Leaside and Laird CLC - January 11, 2021Crosstown TO
ย 
West works open house deck March 12 2020
West works open house deck   March 12 2020 West works open house deck   March 12 2020
West works open house deck March 12 2020 Crosstown TO
ย 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingCrosstown TO
ย 
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020Crosstown TO
ย 
Fairbank-Oakwood Construction Update - May 2021
Fairbank-Oakwood Construction Update - May 2021Fairbank-Oakwood Construction Update - May 2021
Fairbank-Oakwood Construction Update - May 2021Crosstown TO
ย 
Cedarvale & Forest Hill Construction Update (September 29, 2021)
Cedarvale & Forest Hill Construction Update (September 29, 2021)Cedarvale & Forest Hill Construction Update (September 29, 2021)
Cedarvale & Forest Hill Construction Update (September 29, 2021)Crosstown TO
ย 
Avenue & Chaplin CLC - Construction Update: March 3, 2021
Avenue & Chaplin CLC - Construction Update: March 3, 2021Avenue & Chaplin CLC - Construction Update: March 3, 2021
Avenue & Chaplin CLC - Construction Update: March 3, 2021Crosstown TO
ย 
Leaside-Laird CLC Meeting - Presentation - November 8, 2021
Leaside-Laird CLC Meeting - Presentation - November 8, 2021Leaside-Laird CLC Meeting - Presentation - November 8, 2021
Leaside-Laird CLC Meeting - Presentation - November 8, 2021Crosstown TO
ย 
Chaplin & Avenue Construction Liaison Committee Meeting
Chaplin & Avenue Construction Liaison Committee MeetingChaplin & Avenue Construction Liaison Committee Meeting
Chaplin & Avenue Construction Liaison Committee MeetingCrosstown TO
ย 
Eglinton & Mount Pleasant CLC - 14July2021
Eglinton & Mount Pleasant CLC - 14July2021Eglinton & Mount Pleasant CLC - 14July2021
Eglinton & Mount Pleasant CLC - 14July2021Crosstown TO
ย 
Eglinton & Mt pleasant CLC - November
Eglinton & Mt pleasant CLC - November Eglinton & Mt pleasant CLC - November
Eglinton & Mt pleasant CLC - November Crosstown TO
ย 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)Crosstown TO
ย 
Central Spring Open House Presentation Deck - March 23 2020
Central Spring Open House Presentation Deck - March 23 2020Central Spring Open House Presentation Deck - March 23 2020
Central Spring Open House Presentation Deck - March 23 2020Crosstown TO
ย 
Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021Crosstown TO
ย 
Final central east open house oct282020
Final central east open house oct282020Final central east open house oct282020
Final central east open house oct282020Crosstown TO
ย 
Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018Crosstown TO
ย 
Cedarvale & Forest Hill Construction Update (March 31, 2021)
Cedarvale & Forest Hill Construction Update (March 31, 2021)Cedarvale & Forest Hill Construction Update (March 31, 2021)
Cedarvale & Forest Hill Construction Update (March 31, 2021)Crosstown TO
ย 
CLC pharmacy to Kennedy (Nov24)
CLC pharmacy to Kennedy (Nov24)CLC pharmacy to Kennedy (Nov24)
CLC pharmacy to Kennedy (Nov24)Crosstown TO
ย 
Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021Crosstown TO
ย 
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2020
Eglinton and Mount Pleasant Construction Liaison Committee Meeting  - Jan 2020Eglinton and Mount Pleasant Construction Liaison Committee Meeting  - Jan 2020
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2020Crosstown TO
ย 

What's hot (20)

Leaside and Laird CLC - January 11, 2021
Leaside and Laird CLC - January 11, 2021Leaside and Laird CLC - January 11, 2021
Leaside and Laird CLC - January 11, 2021
ย 
West works open house deck March 12 2020
West works open house deck   March 12 2020 West works open house deck   March 12 2020
West works open house deck March 12 2020
ย 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
ย 
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
ย 
Fairbank-Oakwood Construction Update - May 2021
Fairbank-Oakwood Construction Update - May 2021Fairbank-Oakwood Construction Update - May 2021
Fairbank-Oakwood Construction Update - May 2021
ย 
Cedarvale & Forest Hill Construction Update (September 29, 2021)
Cedarvale & Forest Hill Construction Update (September 29, 2021)Cedarvale & Forest Hill Construction Update (September 29, 2021)
Cedarvale & Forest Hill Construction Update (September 29, 2021)
ย 
Avenue & Chaplin CLC - Construction Update: March 3, 2021
Avenue & Chaplin CLC - Construction Update: March 3, 2021Avenue & Chaplin CLC - Construction Update: March 3, 2021
Avenue & Chaplin CLC - Construction Update: March 3, 2021
ย 
Leaside-Laird CLC Meeting - Presentation - November 8, 2021
Leaside-Laird CLC Meeting - Presentation - November 8, 2021Leaside-Laird CLC Meeting - Presentation - November 8, 2021
Leaside-Laird CLC Meeting - Presentation - November 8, 2021
ย 
Chaplin & Avenue Construction Liaison Committee Meeting
Chaplin & Avenue Construction Liaison Committee MeetingChaplin & Avenue Construction Liaison Committee Meeting
Chaplin & Avenue Construction Liaison Committee Meeting
ย 
Eglinton & Mount Pleasant CLC - 14July2021
Eglinton & Mount Pleasant CLC - 14July2021Eglinton & Mount Pleasant CLC - 14July2021
Eglinton & Mount Pleasant CLC - 14July2021
ย 
Eglinton & Mt pleasant CLC - November
Eglinton & Mt pleasant CLC - November Eglinton & Mt pleasant CLC - November
Eglinton & Mt pleasant CLC - November
ย 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
ย 
Central Spring Open House Presentation Deck - March 23 2020
Central Spring Open House Presentation Deck - March 23 2020Central Spring Open House Presentation Deck - March 23 2020
Central Spring Open House Presentation Deck - March 23 2020
ย 
Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021
ย 
Final central east open house oct282020
Final central east open house oct282020Final central east open house oct282020
Final central east open house oct282020
ย 
Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018
ย 
Cedarvale & Forest Hill Construction Update (March 31, 2021)
Cedarvale & Forest Hill Construction Update (March 31, 2021)Cedarvale & Forest Hill Construction Update (March 31, 2021)
Cedarvale & Forest Hill Construction Update (March 31, 2021)
ย 
CLC pharmacy to Kennedy (Nov24)
CLC pharmacy to Kennedy (Nov24)CLC pharmacy to Kennedy (Nov24)
CLC pharmacy to Kennedy (Nov24)
ย 
Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021
ย 
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2020
Eglinton and Mount Pleasant Construction Liaison Committee Meeting  - Jan 2020Eglinton and Mount Pleasant Construction Liaison Committee Meeting  - Jan 2020
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2020
ย 

Similar to Avenue & Chaplin CLC - Construction Update: November 4, 2020

Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020Crosstown TO
ย 
Avenue & Chaplin CLC - Construction Update: November 3, 2021
Avenue & Chaplin CLC - Construction Update: November 3, 2021Avenue & Chaplin CLC - Construction Update: November 3, 2021
Avenue & Chaplin CLC - Construction Update: November 3, 2021Crosstown TO
ย 
Avenue & Chaplin CLC - Construction Update: July 7, 2021
Avenue & Chaplin CLC - Construction Update: July 7, 2021Avenue & Chaplin CLC - Construction Update: July 7, 2021
Avenue & Chaplin CLC - Construction Update: July 7, 2021Crosstown TO
ย 
Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021Crosstown TO
ย 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)Crosstown TO
ย 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)Crosstown TO
ย 
Chaplin-Avenue CLC - May 4 2022-compressed.pptx
Chaplin-Avenue CLC - May 4 2022-compressed.pptxChaplin-Avenue CLC - May 4 2022-compressed.pptx
Chaplin-Avenue CLC - May 4 2022-compressed.pptxCrosstown TO
ย 
Chaplin-Avenue CLC - March 2, 2022-compressed.pptx
Chaplin-Avenue CLC - March 2, 2022-compressed.pptxChaplin-Avenue CLC - March 2, 2022-compressed.pptx
Chaplin-Avenue CLC - March 2, 2022-compressed.pptxCrosstown TO
ย 
Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020Crosstown TO
ย 
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020Crosstown TO
ย 
Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November  Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November Crosstown TO
ย 
Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting Crosstown TO
ย 
Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021
Brentcliffe to Victoria Park CLC Meeting -  Presentation - November 4, 2021 Brentcliffe to Victoria Park CLC Meeting -  Presentation - November 4, 2021
Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021 Crosstown TO
ย 
Brentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingBrentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingCrosstown TO
ย 
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...Crosstown TO
ย 
Avenue & Chaplin CLC - Construction Update: January 5, 2022
Avenue & Chaplin CLC - Construction Update: January 5, 2022Avenue & Chaplin CLC - Construction Update: January 5, 2022
Avenue & Chaplin CLC - Construction Update: January 5, 2022Crosstown TO
ย 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxCrosstown TO
ย 
Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020Crosstown TO
ย 
Eglinton and Mount Pleasant CLC - March 10, 2021
Eglinton and Mount Pleasant CLC - March 10, 2021Eglinton and Mount Pleasant CLC - March 10, 2021
Eglinton and Mount Pleasant CLC - March 10, 2021Crosstown TO
ย 
Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdf
Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdfChaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdf
Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdfCrosstown TO
ย 

Similar to Avenue & Chaplin CLC - Construction Update: November 4, 2020 (20)

Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020
ย 
Avenue & Chaplin CLC - Construction Update: November 3, 2021
Avenue & Chaplin CLC - Construction Update: November 3, 2021Avenue & Chaplin CLC - Construction Update: November 3, 2021
Avenue & Chaplin CLC - Construction Update: November 3, 2021
ย 
Avenue & Chaplin CLC - Construction Update: July 7, 2021
Avenue & Chaplin CLC - Construction Update: July 7, 2021Avenue & Chaplin CLC - Construction Update: July 7, 2021
Avenue & Chaplin CLC - Construction Update: July 7, 2021
ย 
Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021
ย 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
ย 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
ย 
Chaplin-Avenue CLC - May 4 2022-compressed.pptx
Chaplin-Avenue CLC - May 4 2022-compressed.pptxChaplin-Avenue CLC - May 4 2022-compressed.pptx
Chaplin-Avenue CLC - May 4 2022-compressed.pptx
ย 
Chaplin-Avenue CLC - March 2, 2022-compressed.pptx
Chaplin-Avenue CLC - March 2, 2022-compressed.pptxChaplin-Avenue CLC - March 2, 2022-compressed.pptx
Chaplin-Avenue CLC - March 2, 2022-compressed.pptx
ย 
Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020
ย 
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
ย 
Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November  Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November
ย 
Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting
ย 
Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021
Brentcliffe to Victoria Park CLC Meeting -  Presentation - November 4, 2021 Brentcliffe to Victoria Park CLC Meeting -  Presentation - November 4, 2021
Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021
ย 
Brentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingBrentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC Meeting
ย 
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
ย 
Avenue & Chaplin CLC - Construction Update: January 5, 2022
Avenue & Chaplin CLC - Construction Update: January 5, 2022Avenue & Chaplin CLC - Construction Update: January 5, 2022
Avenue & Chaplin CLC - Construction Update: January 5, 2022
ย 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
ย 
Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020
ย 
Eglinton and Mount Pleasant CLC - March 10, 2021
Eglinton and Mount Pleasant CLC - March 10, 2021Eglinton and Mount Pleasant CLC - March 10, 2021
Eglinton and Mount Pleasant CLC - March 10, 2021
ย 
Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdf
Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdfChaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdf
Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdf
ย 

More from Crosstown TO

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfCrosstown TO
ย 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023Crosstown TO
ย 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Crosstown TO
ย 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfCrosstown TO
ย 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfCrosstown TO
ย 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxCrosstown TO
ย 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCrosstown TO
ย 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxCrosstown TO
ย 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCrosstown TO
ย 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCrosstown TO
ย 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxCrosstown TO
ย 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfCrosstown TO
ย 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCrosstown TO
ย 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfCrosstown TO
ย 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxCrosstown TO
ย 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCrosstown TO
ย 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfCrosstown TO
ย 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfCrosstown TO
ย 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCrosstown TO
ย 
Leaside-Laird CLC - Nov 14, 2022.pdf
Leaside-Laird CLC - Nov 14, 2022.pdfLeaside-Laird CLC - Nov 14, 2022.pdf
Leaside-Laird CLC - Nov 14, 2022.pdfCrosstown TO
ย 

More from Crosstown TO (20)

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
ย 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
ย 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
ย 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
ย 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
ย 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
ย 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
ย 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
ย 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
ย 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
ย 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
ย 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
ย 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
ย 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
ย 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
ย 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
ย 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
ย 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
ย 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
ย 
Leaside-Laird CLC - Nov 14, 2022.pdf
Leaside-Laird CLC - Nov 14, 2022.pdfLeaside-Laird CLC - Nov 14, 2022.pdf
Leaside-Laird CLC - Nov 14, 2022.pdf
ย 

Recently uploaded

Call Girls in Sarita Vihar Delhi Just Call ๐Ÿ‘‰๐Ÿ‘‰7065000506 Independent Female Es...
Call Girls in Sarita Vihar Delhi Just Call ๐Ÿ‘‰๐Ÿ‘‰7065000506 Independent Female Es...Call Girls in Sarita Vihar Delhi Just Call ๐Ÿ‘‰๐Ÿ‘‰7065000506 Independent Female Es...
Call Girls in Sarita Vihar Delhi Just Call ๐Ÿ‘‰๐Ÿ‘‰7065000506 Independent Female Es...Inaayaeventcompany
ย 
Premium Prayagraj โค๏ธ๐Ÿ‘ 6378878445 ๐Ÿ‘„๐ŸซฆIndependent Escort Service
Premium  Prayagraj โค๏ธ๐Ÿ‘ 6378878445 ๐Ÿ‘„๐ŸซฆIndependent Escort ServicePremium  Prayagraj โค๏ธ๐Ÿ‘ 6378878445 ๐Ÿ‘„๐ŸซฆIndependent Escort Service
Premium Prayagraj โค๏ธ๐Ÿ‘ 6378878445 ๐Ÿ‘„๐ŸซฆIndependent Escort Servicevershagrag
ย 
Finance strategies for adaptation. Presentation for CANCC
Finance strategies for adaptation. Presentation for CANCCFinance strategies for adaptation. Presentation for CANCC
Finance strategies for adaptation. Presentation for CANCCNAP Global Network
ย 
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...gajnagarg
ย 
Nagerbazar @ Independent Call Girls Kolkata - 450+ Call Girl Cash Payment 800...
Nagerbazar @ Independent Call Girls Kolkata - 450+ Call Girl Cash Payment 800...Nagerbazar @ Independent Call Girls Kolkata - 450+ Call Girl Cash Payment 800...
Nagerbazar @ Independent Call Girls Kolkata - 450+ Call Girl Cash Payment 800...HyderabadDolls
ย 
Time, Stress & Work Life Balance for Clerks with Beckie Whitehouse
Time, Stress & Work Life Balance for Clerks with Beckie WhitehouseTime, Stress & Work Life Balance for Clerks with Beckie Whitehouse
Time, Stress & Work Life Balance for Clerks with Beckie Whitehousesubs7
ย 
PPT Item # 7&8 6900 Broadway P&Z Case # 438
PPT Item # 7&8 6900 Broadway P&Z Case # 438PPT Item # 7&8 6900 Broadway P&Z Case # 438
PPT Item # 7&8 6900 Broadway P&Z Case # 438ahcitycouncil
ย 
Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'NAP Global Network
ย 
Call Girl In Prayagraj Call Girls Service ๐Ÿ‘‰ 6378878445 ๐Ÿ‘‰ Just๐Ÿ“ฒ Call Ruhi Call...
Call Girl In Prayagraj Call Girls Service ๐Ÿ‘‰ 6378878445 ๐Ÿ‘‰ Just๐Ÿ“ฒ Call Ruhi Call...Call Girl In Prayagraj Call Girls Service ๐Ÿ‘‰ 6378878445 ๐Ÿ‘‰ Just๐Ÿ“ฒ Call Ruhi Call...
Call Girl In Prayagraj Call Girls Service ๐Ÿ‘‰ 6378878445 ๐Ÿ‘‰ Just๐Ÿ“ฒ Call Ruhi Call...vershagrag
ย 
Call Girl Service in Korba 9332606886 High Profile Call Girls You Can Get ...
Call Girl Service in Korba   9332606886  High Profile Call Girls You Can Get ...Call Girl Service in Korba   9332606886  High Profile Call Girls You Can Get ...
Call Girl Service in Korba 9332606886 High Profile Call Girls You Can Get ...kumargunjan9515
ย 
YHRGeorgetown Spring 2024 America should Take Her Share
YHRGeorgetown Spring 2024 America should Take Her ShareYHRGeorgetown Spring 2024 America should Take Her Share
YHRGeorgetown Spring 2024 America should Take Her Shareyalehistoricalreview
ย 
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and Number
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and NumberCall Girls Mehsana / 8250092165 Genuine Call girls with real Photos and Number
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and NumberSareena Khatun
ย 
2024 UN Civil Society Conference in Support of the Summit of the Future.
2024 UN Civil Society Conference in Support of the Summit of the Future.2024 UN Civil Society Conference in Support of the Summit of the Future.
2024 UN Civil Society Conference in Support of the Summit of the Future.Christina Parmionova
ย 
Adajan < Russian Call Girls Ahmedabad | Starting โ‚น,5K To @25k with A/C 800573...
Adajan < Russian Call Girls Ahmedabad | Starting โ‚น,5K To @25k with A/C 800573...Adajan < Russian Call Girls Ahmedabad | Starting โ‚น,5K To @25k with A/C 800573...
Adajan < Russian Call Girls Ahmedabad | Starting โ‚น,5K To @25k with A/C 800573...gragfaguni
ย 
Call Girls in North Sikkim 9332606886 HOT & SEXY Models beautiful and charmi...
Call Girls in North Sikkim  9332606886 HOT & SEXY Models beautiful and charmi...Call Girls in North Sikkim  9332606886 HOT & SEXY Models beautiful and charmi...
Call Girls in North Sikkim 9332606886 HOT & SEXY Models beautiful and charmi...Sareena Khatun
ย 
NGO working for orphan childrenโ€™s education
NGO working for orphan childrenโ€™s educationNGO working for orphan childrenโ€™s education
NGO working for orphan childrenโ€™s educationSERUDS INDIA
ย 
The Outlook for the Budget and the Economy
The Outlook for the Budget and the EconomyThe Outlook for the Budget and the Economy
The Outlook for the Budget and the EconomyCongressional Budget Office
ย 
Cheap Call Girls In Hyderabad Phone No ๐Ÿ“ž 9352988975 ๐Ÿ“ž Elite Escort Service Av...
Cheap Call Girls In Hyderabad Phone No ๐Ÿ“ž 9352988975 ๐Ÿ“ž Elite Escort Service Av...Cheap Call Girls In Hyderabad Phone No ๐Ÿ“ž 9352988975 ๐Ÿ“ž Elite Escort Service Av...
Cheap Call Girls In Hyderabad Phone No ๐Ÿ“ž 9352988975 ๐Ÿ“ž Elite Escort Service Av...kajalverma014
ย 
Call Girls Umbergaon / 8250092165 Genuine Call girls with real Photos and Number
Call Girls Umbergaon / 8250092165 Genuine Call girls with real Photos and NumberCall Girls Umbergaon / 8250092165 Genuine Call girls with real Photos and Number
Call Girls Umbergaon / 8250092165 Genuine Call girls with real Photos and NumberSareena Khatun
ย 

Recently uploaded (20)

AHMR volume 10 number 1 January-April 2024
AHMR volume 10 number 1 January-April 2024AHMR volume 10 number 1 January-April 2024
AHMR volume 10 number 1 January-April 2024
ย 
Call Girls in Sarita Vihar Delhi Just Call ๐Ÿ‘‰๐Ÿ‘‰7065000506 Independent Female Es...
Call Girls in Sarita Vihar Delhi Just Call ๐Ÿ‘‰๐Ÿ‘‰7065000506 Independent Female Es...Call Girls in Sarita Vihar Delhi Just Call ๐Ÿ‘‰๐Ÿ‘‰7065000506 Independent Female Es...
Call Girls in Sarita Vihar Delhi Just Call ๐Ÿ‘‰๐Ÿ‘‰7065000506 Independent Female Es...
ย 
Premium Prayagraj โค๏ธ๐Ÿ‘ 6378878445 ๐Ÿ‘„๐ŸซฆIndependent Escort Service
Premium  Prayagraj โค๏ธ๐Ÿ‘ 6378878445 ๐Ÿ‘„๐ŸซฆIndependent Escort ServicePremium  Prayagraj โค๏ธ๐Ÿ‘ 6378878445 ๐Ÿ‘„๐ŸซฆIndependent Escort Service
Premium Prayagraj โค๏ธ๐Ÿ‘ 6378878445 ๐Ÿ‘„๐ŸซฆIndependent Escort Service
ย 
Finance strategies for adaptation. Presentation for CANCC
Finance strategies for adaptation. Presentation for CANCCFinance strategies for adaptation. Presentation for CANCC
Finance strategies for adaptation. Presentation for CANCC
ย 
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
ย 
Nagerbazar @ Independent Call Girls Kolkata - 450+ Call Girl Cash Payment 800...
Nagerbazar @ Independent Call Girls Kolkata - 450+ Call Girl Cash Payment 800...Nagerbazar @ Independent Call Girls Kolkata - 450+ Call Girl Cash Payment 800...
Nagerbazar @ Independent Call Girls Kolkata - 450+ Call Girl Cash Payment 800...
ย 
Time, Stress & Work Life Balance for Clerks with Beckie Whitehouse
Time, Stress & Work Life Balance for Clerks with Beckie WhitehouseTime, Stress & Work Life Balance for Clerks with Beckie Whitehouse
Time, Stress & Work Life Balance for Clerks with Beckie Whitehouse
ย 
PPT Item # 7&8 6900 Broadway P&Z Case # 438
PPT Item # 7&8 6900 Broadway P&Z Case # 438PPT Item # 7&8 6900 Broadway P&Z Case # 438
PPT Item # 7&8 6900 Broadway P&Z Case # 438
ย 
Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'
ย 
Call Girl In Prayagraj Call Girls Service ๐Ÿ‘‰ 6378878445 ๐Ÿ‘‰ Just๐Ÿ“ฒ Call Ruhi Call...
Call Girl In Prayagraj Call Girls Service ๐Ÿ‘‰ 6378878445 ๐Ÿ‘‰ Just๐Ÿ“ฒ Call Ruhi Call...Call Girl In Prayagraj Call Girls Service ๐Ÿ‘‰ 6378878445 ๐Ÿ‘‰ Just๐Ÿ“ฒ Call Ruhi Call...
Call Girl In Prayagraj Call Girls Service ๐Ÿ‘‰ 6378878445 ๐Ÿ‘‰ Just๐Ÿ“ฒ Call Ruhi Call...
ย 
Call Girl Service in Korba 9332606886 High Profile Call Girls You Can Get ...
Call Girl Service in Korba   9332606886  High Profile Call Girls You Can Get ...Call Girl Service in Korba   9332606886  High Profile Call Girls You Can Get ...
Call Girl Service in Korba 9332606886 High Profile Call Girls You Can Get ...
ย 
YHRGeorgetown Spring 2024 America should Take Her Share
YHRGeorgetown Spring 2024 America should Take Her ShareYHRGeorgetown Spring 2024 America should Take Her Share
YHRGeorgetown Spring 2024 America should Take Her Share
ย 
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and Number
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and NumberCall Girls Mehsana / 8250092165 Genuine Call girls with real Photos and Number
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and Number
ย 
2024 UN Civil Society Conference in Support of the Summit of the Future.
2024 UN Civil Society Conference in Support of the Summit of the Future.2024 UN Civil Society Conference in Support of the Summit of the Future.
2024 UN Civil Society Conference in Support of the Summit of the Future.
ย 
Adajan < Russian Call Girls Ahmedabad | Starting โ‚น,5K To @25k with A/C 800573...
Adajan < Russian Call Girls Ahmedabad | Starting โ‚น,5K To @25k with A/C 800573...Adajan < Russian Call Girls Ahmedabad | Starting โ‚น,5K To @25k with A/C 800573...
Adajan < Russian Call Girls Ahmedabad | Starting โ‚น,5K To @25k with A/C 800573...
ย 
Call Girls in North Sikkim 9332606886 HOT & SEXY Models beautiful and charmi...
Call Girls in North Sikkim  9332606886 HOT & SEXY Models beautiful and charmi...Call Girls in North Sikkim  9332606886 HOT & SEXY Models beautiful and charmi...
Call Girls in North Sikkim 9332606886 HOT & SEXY Models beautiful and charmi...
ย 
NGO working for orphan childrenโ€™s education
NGO working for orphan childrenโ€™s educationNGO working for orphan childrenโ€™s education
NGO working for orphan childrenโ€™s education
ย 
The Outlook for the Budget and the Economy
The Outlook for the Budget and the EconomyThe Outlook for the Budget and the Economy
The Outlook for the Budget and the Economy
ย 
Cheap Call Girls In Hyderabad Phone No ๐Ÿ“ž 9352988975 ๐Ÿ“ž Elite Escort Service Av...
Cheap Call Girls In Hyderabad Phone No ๐Ÿ“ž 9352988975 ๐Ÿ“ž Elite Escort Service Av...Cheap Call Girls In Hyderabad Phone No ๐Ÿ“ž 9352988975 ๐Ÿ“ž Elite Escort Service Av...
Cheap Call Girls In Hyderabad Phone No ๐Ÿ“ž 9352988975 ๐Ÿ“ž Elite Escort Service Av...
ย 
Call Girls Umbergaon / 8250092165 Genuine Call girls with real Photos and Number
Call Girls Umbergaon / 8250092165 Genuine Call girls with real Photos and NumberCall Girls Umbergaon / 8250092165 Genuine Call girls with real Photos and Number
Call Girls Umbergaon / 8250092165 Genuine Call girls with real Photos and Number
ย 

Avenue & Chaplin CLC - Construction Update: November 4, 2020

  • 1. November 4, 2020 Eglinton Crosstown LRT Chaplin-Avenue CLC
  • 3. CHAPLIN STATION UPDATE 3 Activity Location Approx. Date & Duration What to Expect Tertiary Entrance Construction Wall construction, rebar and formwork South side of Eglinton Ave, east of Chaplin Cres and adjacent Toronto Fire Station 135 Underway into spring 2021 โ€ข Noise from construction equipment โ€ข Laneway closure Main Entrance Construction Waterproofing, rebar, formwork North side of Eglinton Ave between Chaplin Cres and Gilgorm Rd Underway into spring 2021 โ€ข Noise from construction equipment โ€ข Chipping Station Box Construction Rebar, concrete, formwork Beneath Eglinton Ave Underway into spring 2021 โ€ข Noise from associated surface works, such as use of crane and trucks Watermain Works Connections and reinstatement Intersection of Eglinton Ave and Chaplin Cres Beginning mid-November 2020 into mid-January 2021 โ€ข Lane reductions โ€ข Chaplin Cres and Eglinton Ave intersection closure โ€ข Overnight work โ€ข Noise from construction equipment
  • 5. CONSTRUCTION PROGRESS PHOTOS 5CENTRAL WEST WORKS MONTHLY MEETING STATION BOXTERTIARY ENTRANCE
  • 7. AVENUE STATION UPDATE 7INSERT FOOTER Activity Location Approx. Date & Duration What to Expect Final lining (waterproofing, rebar installation, and mechanical electrical works) Throughout all station areas Underway through to late-2020 โ€ข Deliveries at the main and secondary entrances Concrete Pours Between the Main and Secondary Entrances Three times per week for approx. 12 โ€“ 18 hours through to 2021 โ€ข Concrete truck activity โ€ข Occupation of the westbound curb lane during some pours Eglinton Connects Streetscape and Cycle Track Overnight Utility Works & Water Shut-off for fire hydrant relocation Eglinton Ave between Lascelles Blvd and Duplex Ave Affected properties: โ€ข 174 Eglinton Ave W โ€ข 200 Eglinton Ave W Underway through to early 2021 Utility works: Thursday November 5, 2020; beginning at 10:00 p.m. for approx. seven (7) hours โ€ข Eglinton reduced to one lane in each direction between Lascelles Blvd & Duplex Ave โ€ข Use of excavator, hydro-vac and concrete trucks โ€ข Overnight noise can be expected during utility works Dewatering Well Maintenance Eglinton Ave between Braemar Ave and Lascelles Blvd Periodically through 2021; 9:00 a.m. โ€“ 4:00 p.m. โ€ข Road occupancy around well โ€ข Use of hydro-vac truck Monitoring Work Eglinton Ave between Braemar Ave and Lascelles Blvd Periodically through 2021 โ€ข Short-term road occupancy
  • 8. CURRENT TRAFFIC CONFIGURATION 8 Through September 2021 INSERT FOOTER
  • 9. CURRENT TRAFFIC CONFIGURATION: LASCELLES BLVD TO DUPLEX AVE 9INSERT FOOTER Through Winter 2020
  • 10. EGLINTON AVE FUTURE CONFIGURATION โ€“ ORIOLE PKWY TO LASCELLES BLVD 10INSERT FOOTER
  • 11. EGLINTON AVE FUTURE CONFIGURATION โ€“ LASCELLES BLVD โ€“ DUPLEX AVE 11INSERT FOOTER
  • 12. EGLINTON CONNECTS CONSTRUCTION OVERVIEW 12 Construction of the new Eglinton Streetscape and Cycle Track between Lascelles Blvd and Duplex Ave will continue into 2021. The Eglinton Connects Streetscape and Cycle Track is being constructed in coordination with the City of Torontoโ€™s Streetscape and Cycle Track Design. Construction Hours: โ€ข Monday โ€“ Saturday, 7:00 a.m. โ€“ 7:00 p.m. with periodic overnight work Construction Activities: โ€ข Excavation โ€ข Utility Reinstatement โ€ข Concrete Work โ€ข Compaction and Paving โ€ข Landscaping โ€“ installation of street furnishings, light poles, trees etc. To accommodate this work, all street furnishings, bus shelters, and trees between Lascelles Blvd and Duplex Ave will be removed. Notice will be provided in advance of removals. Upon completion of Eglinton Connects, additional street furnishings and trees will be installed/planted along Eglinton Ave. INSERT FOOTER
  • 13. CONSTRUCTION PROGRESS PHOTOS 13INSERT FOOTER REBAR INSTALLATION โ€“ MAIN ENTRANCE WATERPROOFING โ€“ SECONDARY ENTRACE HEADWALL
  • 14. CONSTRUCTION PROGRESS PHOTOS 14INSERT FOOTER REBAR INSTALLATION - STATION BOX CONCOURSE LEVEL