3. CHAPLIN STATION UPDATE
3
Activity Location Approx. Date & Duration What to Expect
Tertiary Entrance Construction
Wall construction, rebar and
formwork
South side of Eglinton Ave,
east of Chaplin Cres and
adjacent Toronto Fire Station
135
Underway into spring 2021
โข Noise from construction
equipment
โข Laneway closure
Main Entrance Construction
Waterproofing, rebar, formwork
North side of Eglinton Ave
between Chaplin Cres and
Gilgorm Rd
Underway into spring 2021
โข Noise from construction
equipment
โข Chipping
Station Box Construction
Rebar, concrete, formwork
Beneath Eglinton Ave Underway into spring 2021
โข Noise from associated
surface works, such as use of
crane and trucks
Watermain Works
Connections and reinstatement
Intersection of Eglinton Ave
and Chaplin Cres
Beginning mid-November 2020
into mid-January 2021
โข Lane reductions
โข Chaplin Cres and Eglinton
Ave intersection closure
โข Overnight work
โข Noise from construction
equipment
7. AVENUE STATION UPDATE
7INSERT FOOTER
Activity Location Approx. Date & Duration What to Expect
Final lining (waterproofing,
rebar installation, and
mechanical electrical works)
Throughout all station areas Underway through to late-2020
โข Deliveries at the main and
secondary entrances
Concrete Pours
Between the Main and Secondary
Entrances
Three times per week for approx.
12 โ 18 hours through to 2021
โข Concrete truck activity
โข Occupation of the westbound
curb lane during some pours
Eglinton Connects Streetscape
and Cycle Track
Overnight Utility Works & Water
Shut-off for fire hydrant relocation
Eglinton Ave between Lascelles Blvd
and Duplex Ave
Affected properties:
โข 174 Eglinton Ave W
โข 200 Eglinton Ave W
Underway through to early 2021
Utility works: Thursday November 5,
2020; beginning at 10:00 p.m. for
approx. seven (7) hours
โข Eglinton reduced to one lane in
each direction between
Lascelles Blvd & Duplex Ave
โข Use of excavator, hydro-vac
and concrete trucks
โข Overnight noise can be expected
during utility works
Dewatering Well Maintenance
Eglinton Ave between Braemar Ave
and Lascelles Blvd
Periodically through 2021; 9:00
a.m. โ 4:00 p.m.
โข Road occupancy around well
โข Use of hydro-vac truck
Monitoring Work
Eglinton Ave between Braemar Ave
and Lascelles Blvd
Periodically through 2021 โข Short-term road occupancy
12. EGLINTON CONNECTS CONSTRUCTION OVERVIEW
12
Construction of the new Eglinton Streetscape and Cycle Track between Lascelles Blvd and Duplex Ave will
continue into 2021.
The Eglinton Connects Streetscape and Cycle Track is being constructed in coordination with the City of
Torontoโs Streetscape and Cycle Track Design.
Construction Hours:
โข Monday โ Saturday, 7:00 a.m. โ 7:00 p.m. with periodic overnight work
Construction Activities:
โข Excavation
โข Utility Reinstatement
โข Concrete Work
โข Compaction and Paving
โข Landscaping โ installation of street furnishings, light poles, trees etc.
To accommodate this work, all street furnishings, bus shelters, and trees between Lascelles Blvd and Duplex Ave will be
removed. Notice will be provided in advance of removals.
Upon completion of Eglinton Connects, additional street furnishings and trees will be installed/planted along Eglinton Ave.
INSERT FOOTER