5. 5
Eglinton Station Update
Recently Completed
• THESL 2A
• Shoring - Stage 5
Ongoing
• Shoring - Stage 6 – NE corner of Yonge-Eglinton
• Weekend subway closures for TTC upgrades
– Tentatively October 27/28, November 3/4, 24/25, December 8/9, 15/16
– Additional weekend subway closures are anticipated throughout 2019. More details to follow.
Upcoming
• Shoring - Stage 6a – South side of Eglinton from Cowbell to Dunfield
– Scheduled for October 10
12. 12
Mount Pleasant Station Construction Update
ACTIVITY LOCATION APPROXIMATE DURATION
Pile Installation Southside of Eglinton Ave E Until mid-November 2018
Traffic Change Flip traffic on Mt. Pleasant Rd Early November 2018
Shallow Excavation South side of Eglinton E
Mid-November 2018 – Late
January 2019
Traffic Change Flip traffic on Mt. Pleasant Rd Late December 2018
Concrete Roof Construction South side of Eglinton Ave E
Mid-January 2019 – Mid-April
2019
Road Reinstatement and Traffic
Change
Return to north side of Eglinton
Ave E
As early as Mid-April 2019
14. 14
Upcoming Construction Staging
Early November 2018 – Late December 2018
Activities: pile installation and storm sewer installation
Taunton road will be open in November