4. Eglinton Station Construction Look-ahead
Activity Location Approx. Date/Duration
Lane Shift Duplex and Eglinton Aves As early as July 11, 2019
Extended Hours Deep
Excavation
TTC Bus Depot and Salvation
Army Sites
Underway through 2019
Berwick Ave Road Closure for
Facility Services Building
Construction – TTC Line 1
Berwick Ave b/w Yonge St and
Duplex Ave
July 5 – 15, July 19 – 22, and
July 26 – 29, 2019
Traffic Configuration Change Yonge St and Eglinton Ave Early August 2019
TBM Extraction Duplex and Eglinton Aves August 2019 for one (1) day
North Tunnel Ventilation Shaft
Construction
Yonge St north of Eglinton Ave
Late August 2019 for approx.
four (4) months
8. Berwick Ave Closures
• Three (3) closures of Berwick Ave between east of Duplex
Ave at Yonge St will take place in July 2019 for TTC Line 1
Facility Services Building construction work
• Work will take place on weekends from 7:00 a.m. Friday
until 7:00 a.m. Monday, on a 24 hour basis:
– July 5 – 15, 2019 (underway)
– July 19 – 22, 2019
– July 26 – 29, 2019
• TTC and property access will be maintained with the
exception of four parking spaces at 2180 Yonge St
10. North Tunnel Ventilation Shaft Construction
• Construction of a vent shaft beneath
Yonge St north of Eglinton Ave
• Beginning as early as Late August 2019
for approx. four (4) months
• Currently in design phase; final traffic
configuration and work schedule to be
confirmed
• What to expect:
– 1.5 meters sidewalk width
– Relocate north crosswalk and signals
further south
– Removal/relocation of signs, planters,
etc.
13. Mount Pleasant Construction Activities
Activity Location Approx. Start Date & Duration
Roof Construction South Station Box Underway through July 2019
Concrete Roof Pour #5 South Station Box
July 12, 2019 at 6:00 a.m. for
eight (8) hours
Watermain Reinstatement Work Mt Pleasant Rd and Eglinton Ave
Underway for approx. three (3)
weeks
Hydro Utility Work
Eglinton Ave between Mt Pleasant
Rd and Taunton Rd
July 2019 for approx. two (2)
weeks
Traffic Configuration Change
Shift traffic on Mt Pleasant to the
west
Early August 2019
Traffic Configuration Change
Shift traffic on Eglinton Ave to the
south
Late August 2019
Traffic Bridge Installation
Northeasterly corner of Mt Pleasant
Rd and Eglinton Ave
September 2019
Traffic Configuration Change
Shift traffic on Mt Pleasant Rd east
onto the bridge
September 2019