(1) Deep excavation work will begin at Eglinton station between Duplex Avenue and Yonge Street to excavate for the station box reaching depths of 22 meters. Excavation will occur as early as 6am starting in December 2018 and 4am starting in January 2019. (2) At Mount Pleasant station, pile installation is complete and shallow excavation will continue through early April 2019 with other utility and traffic work occurring through March 2019. (3) Manhole construction at Mount Pleasant station will require extended work hours of 6am to 1am from January 10 to complete the new storm sewer system.
Central Eastern Works Open House - October 2019Crosstown TO
Contains current and upcoming stages of construction for the stations/stops of: Eglinton, Mount Pleasant, Leaside, Laird, Brentcliffe (Portal), Sunnybrook Park and Science Centre.
Central Eastern Works Open House - October 2019Crosstown TO
Contains current and upcoming stages of construction for the stations/stops of: Eglinton, Mount Pleasant, Leaside, Laird, Brentcliffe (Portal), Sunnybrook Park and Science Centre.
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCrosstown TO
This is a meeting invite for the Brentcliffe-Victoria Park CLC (Construction Liaison Committee) Monthly Meeting, covering the Brentcliffe Portal, Sunnybrook Park, Science Centre, Aga Khan, Wynford, Sloane and O’ Connor Stops.
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCrosstown TO
Construction updates for the following locations/stops: Brentcliffe Portal, Sunnybrook Park, Science Centre, Aga Khan Park & Museum, Wynford, Sloane and O'Connor.
This session provides a comprehensive overview of the latest updates to the Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (commonly known as the Uniform Guidance) outlined in the 2 CFR 200.
With a focus on the 2024 revisions issued by the Office of Management and Budget (OMB), participants will gain insight into the key changes affecting federal grant recipients. The session will delve into critical regulatory updates, providing attendees with the knowledge and tools necessary to navigate and comply with the evolving landscape of federal grant management.
Learning Objectives:
- Understand the rationale behind the 2024 updates to the Uniform Guidance outlined in 2 CFR 200, and their implications for federal grant recipients.
- Identify the key changes and revisions introduced by the Office of Management and Budget (OMB) in the 2024 edition of 2 CFR 200.
- Gain proficiency in applying the updated regulations to ensure compliance with federal grant requirements and avoid potential audit findings.
- Develop strategies for effectively implementing the new guidelines within the grant management processes of their respective organizations, fostering efficiency and accountability in federal grant administration.
ZGB - The Role of Generative AI in Government transformation.pdfSaeed Al Dhaheri
This keynote was presented during the the 7th edition of the UAE Hackathon 2024. It highlights the role of AI and Generative AI in addressing government transformation to achieve zero government bureaucracy
What is the point of small housing associations.pptxPaul Smith
Given the small scale of housing associations and their relative high cost per home what is the point of them and how do we justify their continued existance
Presentation by Jared Jageler, David Adler, Noelia Duchovny, and Evan Herrnstadt, analysts in CBO’s Microeconomic Studies and Health Analysis Divisions, at the Association of Environmental and Resource Economists Summer Conference.
Understanding the Challenges of Street ChildrenSERUDS INDIA
By raising awareness, providing support, advocating for change, and offering assistance to children in need, individuals can play a crucial role in improving the lives of street children and helping them realize their full potential
Donate Us
https://serudsindia.org/how-individuals-can-support-street-children-in-india/
#donatefororphan, #donateforhomelesschildren, #childeducation, #ngochildeducation, #donateforeducation, #donationforchildeducation, #sponsorforpoorchild, #sponsororphanage #sponsororphanchild, #donation, #education, #charity, #educationforchild, #seruds, #kurnool, #joyhome
Russian anarchist and anti-war movement in the third year of full-scale warAntti Rautiainen
Anarchist group ANA Regensburg hosted my online-presentation on 16th of May 2024, in which I discussed tactics of anti-war activism in Russia, and reasons why the anti-war movement has not been able to make an impact to change the course of events yet. Cases of anarchists repressed for anti-war activities are presented, as well as strategies of support for political prisoners, and modest successes in supporting their struggles.
Thumbnail picture is by MediaZona, you may read their report on anti-war arson attacks in Russia here: https://en.zona.media/article/2022/10/13/burn-map
Links:
Autonomous Action
http://Avtonom.org
Anarchist Black Cross Moscow
http://Avtonom.org/abc
Solidarity Zone
https://t.me/solidarity_zone
Memorial
https://memopzk.org/, https://t.me/pzk_memorial
OVD-Info
https://en.ovdinfo.org/antiwar-ovd-info-guide
RosUznik
https://rosuznik.org/
Uznik Online
http://uznikonline.tilda.ws/
Russian Reader
https://therussianreader.com/
ABC Irkutsk
https://abc38.noblogs.org/
Send mail to prisoners from abroad:
http://Prisonmail.online
YouTube: https://youtu.be/c5nSOdU48O8
Spotify: https://podcasters.spotify.com/pod/show/libertarianlifecoach/episodes/Russian-anarchist-and-anti-war-movement-in-the-third-year-of-full-scale-war-e2k8ai4
A process server is a authorized person for delivering legal documents, such as summons, complaints, subpoenas, and other court papers, to peoples involved in legal proceedings.
5. 5
Eglinton Station: What to Expect in 2019
ACTIVITY AREA IMPACT DURATION
Shallow excavation
and decking
Eglinton west of Yonge
• Noise and vibration from excavation
activities
Through early 2019
Pile Installation,
shallow excavation,
and decking
South side of Eglinton
at Holly Street
• Noise and vibration from drilling activity Through early 2019
Stage 7 Traffic
Update
Duplex – Holly
• All crosswalks open up, Yonge opens to 4
lanes, and bike lanes added to Eglinton
2019
Berwick TTC Service
Building
Berwick Avenue at
Yonge Street
• Overnight work and noise due to crane and
other activities
• Weekend subway closures for TTC upgrades
• Tentatively February 9-10, March 2-3, 16-17,
23-24, April 6-7
• Additional weekend subway closures are
anticipated throughout 2019.
2019
Deep Excavation
TTC Bus Depot and
Salvation Army sites
• Noise and vibration from jackhammer
• Noise from Excavator
• 6am starts in December 2018
• 4am starts as early as January 2019
2019
TVS Pile Installation
Yonge Street north of
Eglinton
• Noise and vibration from drilling activity 3-4 months; 2019
6. 6
Eglinton Station – Deep Excavation Staging for 2019
Excavation
Activities
Excavation
Activities
• Deep excavation work will get underway between Duplex Avenue and Yonge Street.
– This work includes excavating to the bottom of the future station box (approximately 22
meters at the deepest point).
– Spoils from the excavation will be extracted and hauled from the existing TTC bus depot site
at the southeast corner of Duplex Avenue and Eglinton Avenue West, and the Salvation Army
site at the corner of Eglinton Avenue East and Cowbell Lane.
– In order to maintain schedule, excavation work will begin as early as 6:00 a.m. Monday –
Saturday on December 10, 2018, and 4:00 a.m. Monday – Saturday as early as January 2,
2019.
7. 7
Eglinton Station – Deep Excavation Noise Mitigation Plan
• Operation controls will include:
• White noise/broadband back-up alarms on all trucks and equipment.
• Loading soil only into the trucks (no large debris or rocks that would
create banging noises).
• Avoiding shaking of the excavator buckets.
• Lowering the drop height so soil/debris falls closer to the truck bed.
• Securing tailgates on trucks to limit banging noise.
• Limiting acceleration of the trucks as they ingress/egress.
• Turning off truck engines while they wait or are staging.
• Crosslinx will offer, upon request, noise mitigation instruments for
residents in the immediate vicinity of the work including noise
dampening drapes, white noise machines, and noise-cancelling
headphones.
• Crosslinx will continuously monitor for improvements and endeavor to
minimize noise throughout the delivery period.7
10. 10
Mount Pleasant Station Construction Update
ACTIVITY LOCATION APPROX. DATE AND DURATION
Pile Installation South side of Eglinton Ave E Complete
Shallow Excavation South side of Eglinton Ave E Through to early April 2019
Manhole Construction for Wet
Utilities (extended hours)
Southeast corner or Mt Pleasant Rd
and Eglinton Ave E
Through January 2019
Hydro Ductbank Work Mt Pleasant Rd and Eglinton Ave E Through March 2019
Taunton Road Watermain
Restoration
Southbound lane of Taunton Road at
Eglinton Ave E
Mid-January 2019 for three (3) weeks
Traffic Bridge Installation
Southeast corner or Mt Pleasant Rd
and Eglinton Ave E
As early as mid-February 2019
Traffic Change
Shift traffic on Mt Pleasant Rd to the
east
Late January 2019
Concrete Roof Pour Southwest Station Box Area As early as mid-February 2019
11. 11
Extended Hours for Manhole Construction
• As part of the new storm sewer system crews must install a
manhole at the southeast corner of the intersection
• To maintain schedule, crews will work extended hours, 6:00 a.m. –
1:00 a.m., Monday through Saturday, for approximately three (3)
weeks, beginning as early as Friday January 10, 2019
• Anticipated equipment and activities before 7:00 a.m. and after
11:00 p.m. include:
– mini-excavator and excavator
– forklift to move materials around the site
– hand tools
12. 12
Taunton Road Watermain Restoration Work
• As part of the new storm sewer system, crews must restore
the previously cut-and-capped watermain at Taunton Rd
and Eglinton Ave E
• To complete this works, crews must occupy the southbound
lane on Taunton Rd at Eglinton Ave; no eastbound right
turns onto Taunton Rd and no northbound right turns onto
Eglinton Ave will be permitted
• Work will begin as early as mid-January 2019 for
approximately three (3) weeks, working between 7:00 a.m.
and 7:00 p.m., Monday through Friday