5. Eglinton Station Construction Look-ahead
Activity Location Approx. Date/Duration
Extended Hours Deep
Excavation
TTC Bus Depot and Salvation
Army Sites
Underway through 2019
Berwick Ave Road Closure for
Facility Services Building
Construction – TTC Line 1
Berwick Ave b/w Yonge St and
Duplex Ave
• Friday September 13, 2019
at 7:00 a.m. – Monday
September 16, 2019 at 7:00
a.m.
• Friday September 20, 2019
at 7:00 a.m. – Monday
September 23, 2019 at 7:00
a.m.
TBM Extraction Duplex and Eglinton Aves October 2019
Traffic Configuration Change Yonge St and Eglinton Ave October 2019
Tunnel Ventilation Shaft
Construction
Yonge St north of Eglinton Ave
October 2019 for approx. six (6)
months
8. North Tunnel Ventilation Shaft Construction
What to expect:
• October 2019 for approx. six (6)
months
• Sidewalk on both sides of Yonge St
between Orchard View Blvd and
Eglinton Ave to be reduced to 1.5m
• One lane of traffic in each direction,
routed around either side of the work
zone
• Removal of street furniture, such as
signs, poles, flower beds and bus
shelters in the vicinity of the
construction zone
TVS WORK
ZONE
ANITICIPATED
SIDEWALK WIDTH
9. Berwick Ave Closures
• Three (3) closures of Berwick Ave between east of Duplex Ave at
Yonge St will take place in September 2019 for TTC Line 1 Facility
Services Building construction work
• Work will take place on weekends from 7:00 a.m. Friday until 7:00
a.m. Monday, on a 24 hour basis:
– Friday September 13, 2019 at 7:00 a.m. – Monday September 16, 2019
at 7:00 a.m.
– Friday September 20, 2019 at 7:00 a.m. – Monday September 23, 2019
at 7:00 a.m.
• TTC and property access will be maintained with the exception of
four parking spaces at 2180 Yonge St
13. Mount Pleasant Construction Activities
Activity Location Approx. Start Date & Duration
Telecommunication utility work
South side of Eglinton Ave E, east of
the intersection
Underway approx. 1 week
remaining
Combination Sewer Installation
Middle of Eglinton Ave E across
from Taunton Road
Underway approx. 1 month
remaining
Scaffold removal and façade
restoration
Eglinton Junior Public School September 2019 (8 weeks)
Shallow Excavation and roof
construction
North west side of Eglinton Ave E Underway approx. 5 months
Traffic Bridge Installation
Northeasterly corner of Mt Pleasant
Rd and Eglinton Ave
Mid of October 2019
Traffic Configuration Change
Shift traffic on Mt Pleasant Rd east
onto the bridge
Late of October 2019