SlideShare a Scribd company logo
September 30, 2020
Eglinton Crosstown-LRT
Cedarvale – Forest Hill CLC
Cedarvale Station
CEDARVALE STATION UPDATE
3
CEDARVALE –FOREST HILL CLC
Activity Location Approx. Date & Duration
Deep Excavation & Tieback Installation Station’s Main Entrance Complete!
Major Concrete Pours Throughout all station areas
Underway throughout 2020 into 2021
Starting as early as 5:00 a.m. ranging from 12-18
hours
Geotechnical Monitoring
Eastbound curb lane of Eglinton Ave between
Winnett Ave and Allen Rd N
Through early 2021
Tuesdays between 11:00 a.m. – 2:00 p.m.
Pedestrian Tunnel Construction Area surrounding Eglinton West Station
Underway through 2021
Monday – Saturday; 6:00 a.m. – 2:00 a.m.
Eglinton West Station Support of
Excavation and Underpinning Works
Eglinton West Station
Underway through 2020
Monday – Saturday; 6:00 a.m. – 5:00 p.m.
Eglinton West Station Bus Loop Closure
for Roof Construction
Eglinton West Station Underway – Fall 2020
Temporary Traffic Deck Removal, Roof
Construction, and Permanent Utility
Installation
Eglinton Avenue West March 29, 2020 – early 2021
CURRENT TRAFFIC CONFIGURATION
4
Through Fall 2020
CEDARVALE –FOREST HILL CLC
CONSTRUCTION PROGRESS PHOTOS
5
CEDARVALE –FOREST HILL CLC
CONCRETE POUR FOR LAST
MAIN STATION INVERT SLAB
REMOVAL OF TEMPORARY SUPPORT BEAMS
UNDERNEATH THE TTC STATION BOX
Forest Hill Station
FOREST HILL STATION UPDATE
7
Activity Location Approx. Date & Duration
Deep Excavation
Beneath the station roof from the Main
Entrance
Complete
Main Entrance Construction
Excavation, installation of struts, lagging
and tie-backs
Northeast corner of Bathurst St and
Eglinton Ave
Underway through 2020
Secondary Entrance Construction
Formwork, rebar, conduit installation
and beam excavation
North side of Eglinton Ave, west of
Bathurst St
Underway through fall 2020
Station Box Construction
Waterproofing, shotcrete application
and duct bank construction
Beneath Eglinton Ave Underway through 2020
Concrete Pours Secondary Entrance
Periodically through fall 2020
Upcoming pours:
• October 5, 2020
Traffic Configuration Change Secondary Entrance
Monday October 5, 2020
*date subject to change
CURRENT TRAFFIC CONFIGURATION
8
Until October 5, 2020
UPCOMING TRAFFIC CONFIGURATION
9
October 5, 2020 – February 2021
CONSTRUCTION PROGRESS PHOTOS
10
REBAR INSTALLATION
SECONDARY ENTRANCE
WALL CONSTRUCTION
Cedarvale & Forest Hill Construction Update (September 30, 2020)

More Related Content

What's hot

Cedarvale & Forest Hill Construction Update (January 27, 2021)
Cedarvale & Forest Hill Construction Update (January 27, 2021)Cedarvale & Forest Hill Construction Update (January 27, 2021)
Cedarvale & Forest Hill Construction Update (January 27, 2021)
Crosstown TO
 
Brentcliffe to Victoria Park - CLC construction update January 2021
Brentcliffe to Victoria Park - CLC construction update January 2021Brentcliffe to Victoria Park - CLC construction update January 2021
Brentcliffe to Victoria Park - CLC construction update January 2021
Crosstown TO
 
Cedarvale & Forest Hill Construction Liaison Committee - July 2018
Cedarvale & Forest Hill Construction Liaison Committee - July 2018Cedarvale & Forest Hill Construction Liaison Committee - July 2018
Cedarvale & Forest Hill Construction Liaison Committee - July 2018
Crosstown TO
 
Cedarvale & Forest Hill CLC - September 25, 2019
Cedarvale & Forest Hill CLC - September 25, 2019Cedarvale & Forest Hill CLC - September 25, 2019
Cedarvale & Forest Hill CLC - September 25, 2019
Crosstown TO
 
Cedarvale- Forest Hill Construction Update (July 29, 2020)
Cedarvale- Forest Hill Construction Update (July 29, 2020)Cedarvale- Forest Hill Construction Update (July 29, 2020)
Cedarvale- Forest Hill Construction Update (July 29, 2020)
Crosstown TO
 
Fairbank-Oakwood Construction Update - May 2021
Fairbank-Oakwood Construction Update - May 2021Fairbank-Oakwood Construction Update - May 2021
Fairbank-Oakwood Construction Update - May 2021
Crosstown TO
 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - February 2018
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - February 2018Eglinton & Mount Pleasant Construction Liaison Committee Meeting - February 2018
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - February 2018
Crosstown TO
 
Pharmacy to Kennedy CLC meeting
Pharmacy to Kennedy  CLC meetingPharmacy to Kennedy  CLC meeting
Pharmacy to Kennedy CLC meeting
Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021
Crosstown TO
 
Fairbank-Oakwood Construction Update - July 2021
Fairbank-Oakwood Construction Update - July 2021Fairbank-Oakwood Construction Update - July 2021
Fairbank-Oakwood Construction Update - July 2021
Crosstown TO
 
Cedarvale & Forest Hill Construction Liaison Committee Meeting - February 2018
Cedarvale & Forest Hill Construction Liaison Committee Meeting - February 2018Cedarvale & Forest Hill Construction Liaison Committee Meeting - February 2018
Cedarvale & Forest Hill Construction Liaison Committee Meeting - February 2018
Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: May 6, 2020
Avenue & Chaplin CLC - Construction Update: May 6, 2020Avenue & Chaplin CLC - Construction Update: May 6, 2020
Avenue & Chaplin CLC - Construction Update: May 6, 2020
Crosstown TO
 
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Crosstown TO
 
Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021
Crosstown TO
 
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Jan 29, 2020
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Jan 29, 2020Cedarvale & Forest Hill Construction Liaison Committee Meeting - Jan 29, 2020
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Jan 29, 2020
Crosstown TO
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
Crosstown TO
 
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Mar 25, 2020
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Mar 25, 2020Cedarvale & Forest Hill Construction Liaison Committee Meeting - Mar 25, 2020
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Mar 25, 2020
Crosstown TO
 
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - May 2019
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - May 2019Eglinton and Mount Pleasant Construction Liaison Committee Meeting - May 2019
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - May 2019
Crosstown TO
 
Eglinton-Mount Pleasant Construction Liaison Committee Meeting - May 2018
Eglinton-Mount Pleasant Construction Liaison Committee Meeting - May 2018Eglinton-Mount Pleasant Construction Liaison Committee Meeting - May 2018
Eglinton-Mount Pleasant Construction Liaison Committee Meeting - May 2018
Crosstown TO
 
Fairbank-Oakwood Construction Update - January 2021
Fairbank-Oakwood Construction Update - January 2021Fairbank-Oakwood Construction Update - January 2021
Fairbank-Oakwood Construction Update - January 2021
Crosstown TO
 

What's hot (20)

Cedarvale & Forest Hill Construction Update (January 27, 2021)
Cedarvale & Forest Hill Construction Update (January 27, 2021)Cedarvale & Forest Hill Construction Update (January 27, 2021)
Cedarvale & Forest Hill Construction Update (January 27, 2021)
 
Brentcliffe to Victoria Park - CLC construction update January 2021
Brentcliffe to Victoria Park - CLC construction update January 2021Brentcliffe to Victoria Park - CLC construction update January 2021
Brentcliffe to Victoria Park - CLC construction update January 2021
 
Cedarvale & Forest Hill Construction Liaison Committee - July 2018
Cedarvale & Forest Hill Construction Liaison Committee - July 2018Cedarvale & Forest Hill Construction Liaison Committee - July 2018
Cedarvale & Forest Hill Construction Liaison Committee - July 2018
 
Cedarvale & Forest Hill CLC - September 25, 2019
Cedarvale & Forest Hill CLC - September 25, 2019Cedarvale & Forest Hill CLC - September 25, 2019
Cedarvale & Forest Hill CLC - September 25, 2019
 
Cedarvale- Forest Hill Construction Update (July 29, 2020)
Cedarvale- Forest Hill Construction Update (July 29, 2020)Cedarvale- Forest Hill Construction Update (July 29, 2020)
Cedarvale- Forest Hill Construction Update (July 29, 2020)
 
Fairbank-Oakwood Construction Update - May 2021
Fairbank-Oakwood Construction Update - May 2021Fairbank-Oakwood Construction Update - May 2021
Fairbank-Oakwood Construction Update - May 2021
 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - February 2018
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - February 2018Eglinton & Mount Pleasant Construction Liaison Committee Meeting - February 2018
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - February 2018
 
Pharmacy to Kennedy CLC meeting
Pharmacy to Kennedy  CLC meetingPharmacy to Kennedy  CLC meeting
Pharmacy to Kennedy CLC meeting
 
Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021
 
Fairbank-Oakwood Construction Update - July 2021
Fairbank-Oakwood Construction Update - July 2021Fairbank-Oakwood Construction Update - July 2021
Fairbank-Oakwood Construction Update - July 2021
 
Cedarvale & Forest Hill Construction Liaison Committee Meeting - February 2018
Cedarvale & Forest Hill Construction Liaison Committee Meeting - February 2018Cedarvale & Forest Hill Construction Liaison Committee Meeting - February 2018
Cedarvale & Forest Hill Construction Liaison Committee Meeting - February 2018
 
Avenue & Chaplin CLC - Construction Update: May 6, 2020
Avenue & Chaplin CLC - Construction Update: May 6, 2020Avenue & Chaplin CLC - Construction Update: May 6, 2020
Avenue & Chaplin CLC - Construction Update: May 6, 2020
 
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
 
Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021
 
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Jan 29, 2020
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Jan 29, 2020Cedarvale & Forest Hill Construction Liaison Committee Meeting - Jan 29, 2020
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Jan 29, 2020
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
 
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Mar 25, 2020
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Mar 25, 2020Cedarvale & Forest Hill Construction Liaison Committee Meeting - Mar 25, 2020
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Mar 25, 2020
 
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - May 2019
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - May 2019Eglinton and Mount Pleasant Construction Liaison Committee Meeting - May 2019
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - May 2019
 
Eglinton-Mount Pleasant Construction Liaison Committee Meeting - May 2018
Eglinton-Mount Pleasant Construction Liaison Committee Meeting - May 2018Eglinton-Mount Pleasant Construction Liaison Committee Meeting - May 2018
Eglinton-Mount Pleasant Construction Liaison Committee Meeting - May 2018
 
Fairbank-Oakwood Construction Update - January 2021
Fairbank-Oakwood Construction Update - January 2021Fairbank-Oakwood Construction Update - January 2021
Fairbank-Oakwood Construction Update - January 2021
 

Similar to Cedarvale & Forest Hill Construction Update (September 30, 2020)

Cedarvale & Forest Hill Construction Update (March 31, 2021)
Cedarvale & Forest Hill Construction Update (March 31, 2021)Cedarvale & Forest Hill Construction Update (March 31, 2021)
Cedarvale & Forest Hill Construction Update (March 31, 2021)
Crosstown TO
 
Eglinton and Mount Pleasant CLC - March 10, 2021
Eglinton and Mount Pleasant CLC - March 10, 2021Eglinton and Mount Pleasant CLC - March 10, 2021
Eglinton and Mount Pleasant CLC - March 10, 2021
Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: July 7, 2021
Avenue & Chaplin CLC - Construction Update: July 7, 2021Avenue & Chaplin CLC - Construction Update: July 7, 2021
Avenue & Chaplin CLC - Construction Update: July 7, 2021
Crosstown TO
 
Pharmacy to Kennedy CLC - March 2020
Pharmacy to Kennedy CLC - March 2020Pharmacy to Kennedy CLC - March 2020
Pharmacy to Kennedy CLC - March 2020
Crosstown TO
 
Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020
Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020
Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020
Crosstown TO
 
Fairbank-Oakwood Construction Update - March 2021
Fairbank-Oakwood Construction Update - March 2021Fairbank-Oakwood Construction Update - March 2021
Fairbank-Oakwood Construction Update - March 2021
Crosstown TO
 
Cedarvale & Forest Hill Construction Update (September 29, 2021)
Cedarvale & Forest Hill Construction Update (September 29, 2021)Cedarvale & Forest Hill Construction Update (September 29, 2021)
Cedarvale & Forest Hill Construction Update (September 29, 2021)
Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020
Crosstown TO
 
Eglinton and Mt Pleasant CLC - 12, May 2021
Eglinton and Mt Pleasant CLC - 12, May 2021Eglinton and Mt Pleasant CLC - 12, May 2021
Eglinton and Mt Pleasant CLC - 12, May 2021
Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020
Crosstown TO
 
Eglinton-Mount Pleasant Construction update - May 2020
Eglinton-Mount Pleasant Construction update - May 2020Eglinton-Mount Pleasant Construction update - May 2020
Eglinton-Mount Pleasant Construction update - May 2020
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
Crosstown TO
 
Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
Crosstown TO
 
Brentcliffe to Victoria Park - March 4, 2021
Brentcliffe to Victoria Park - March 4, 2021Brentcliffe to Victoria Park - March 4, 2021
Brentcliffe to Victoria Park - March 4, 2021
Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021
Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - Jan 2020
Pharmacy to Kennedy Construction Liaison Committee Meeting - Jan 2020Pharmacy to Kennedy Construction Liaison Committee Meeting - Jan 2020
Pharmacy to Kennedy Construction Liaison Committee Meeting - Jan 2020
Crosstown TO
 
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2020
Eglinton and Mount Pleasant Construction Liaison Committee Meeting  - Jan 2020Eglinton and Mount Pleasant Construction Liaison Committee Meeting  - Jan 2020
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2020
Crosstown TO
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Crosstown TO
 

Similar to Cedarvale & Forest Hill Construction Update (September 30, 2020) (20)

Cedarvale & Forest Hill Construction Update (March 31, 2021)
Cedarvale & Forest Hill Construction Update (March 31, 2021)Cedarvale & Forest Hill Construction Update (March 31, 2021)
Cedarvale & Forest Hill Construction Update (March 31, 2021)
 
Eglinton and Mount Pleasant CLC - March 10, 2021
Eglinton and Mount Pleasant CLC - March 10, 2021Eglinton and Mount Pleasant CLC - March 10, 2021
Eglinton and Mount Pleasant CLC - March 10, 2021
 
Avenue & Chaplin CLC - Construction Update: July 7, 2021
Avenue & Chaplin CLC - Construction Update: July 7, 2021Avenue & Chaplin CLC - Construction Update: July 7, 2021
Avenue & Chaplin CLC - Construction Update: July 7, 2021
 
Pharmacy to Kennedy CLC - March 2020
Pharmacy to Kennedy CLC - March 2020Pharmacy to Kennedy CLC - March 2020
Pharmacy to Kennedy CLC - March 2020
 
Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020
Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020
Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020
 
Fairbank-Oakwood Construction Update - March 2021
Fairbank-Oakwood Construction Update - March 2021Fairbank-Oakwood Construction Update - March 2021
Fairbank-Oakwood Construction Update - March 2021
 
Cedarvale & Forest Hill Construction Update (September 29, 2021)
Cedarvale & Forest Hill Construction Update (September 29, 2021)Cedarvale & Forest Hill Construction Update (September 29, 2021)
Cedarvale & Forest Hill Construction Update (September 29, 2021)
 
Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020
 
Eglinton and Mt Pleasant CLC - 12, May 2021
Eglinton and Mt Pleasant CLC - 12, May 2021Eglinton and Mt Pleasant CLC - 12, May 2021
Eglinton and Mt Pleasant CLC - 12, May 2021
 
Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020
 
Eglinton-Mount Pleasant Construction update - May 2020
Eglinton-Mount Pleasant Construction update - May 2020Eglinton-Mount Pleasant Construction update - May 2020
Eglinton-Mount Pleasant Construction update - May 2020
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
 
Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
 
Brentcliffe to Victoria Park - March 4, 2021
Brentcliffe to Victoria Park - March 4, 2021Brentcliffe to Victoria Park - March 4, 2021
Brentcliffe to Victoria Park - March 4, 2021
 
Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - Jan 2020
Pharmacy to Kennedy Construction Liaison Committee Meeting - Jan 2020Pharmacy to Kennedy Construction Liaison Committee Meeting - Jan 2020
Pharmacy to Kennedy Construction Liaison Committee Meeting - Jan 2020
 
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2020
Eglinton and Mount Pleasant Construction Liaison Committee Meeting  - Jan 2020Eglinton and Mount Pleasant Construction Liaison Committee Meeting  - Jan 2020
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2020
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
 

More from Crosstown TO

Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
Crosstown TO
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
Crosstown TO
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
Crosstown TO
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Crosstown TO
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Crosstown TO
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Crosstown TO
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
Crosstown TO
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
Crosstown TO
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
Crosstown TO
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Crosstown TO
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Crosstown TO
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Crosstown TO
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
Crosstown TO
 
Leaside-Laird CLC - Nov 14, 2022.pdf
Leaside-Laird CLC - Nov 14, 2022.pdfLeaside-Laird CLC - Nov 14, 2022.pdf
Leaside-Laird CLC - Nov 14, 2022.pdf
Crosstown TO
 
Eglinton - Mt Pleasant CLC - November 9, 2022.pdf
Eglinton - Mt Pleasant CLC - November 9, 2022.pdfEglinton - Mt Pleasant CLC - November 9, 2022.pdf
Eglinton - Mt Pleasant CLC - November 9, 2022.pdf
Crosstown TO
 
Leaside-Laird CLC - May 9 2022 - Revised.pdf
Leaside-Laird CLC - May 9 2022 - Revised.pdfLeaside-Laird CLC - May 9 2022 - Revised.pdf
Leaside-Laird CLC - May 9 2022 - Revised.pdf
Crosstown TO
 

More from Crosstown TO (20)

Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
 
Leaside-Laird CLC - Nov 14, 2022.pdf
Leaside-Laird CLC - Nov 14, 2022.pdfLeaside-Laird CLC - Nov 14, 2022.pdf
Leaside-Laird CLC - Nov 14, 2022.pdf
 
Eglinton - Mt Pleasant CLC - November 9, 2022.pdf
Eglinton - Mt Pleasant CLC - November 9, 2022.pdfEglinton - Mt Pleasant CLC - November 9, 2022.pdf
Eglinton - Mt Pleasant CLC - November 9, 2022.pdf
 
Test
TestTest
Test
 
Leaside-Laird CLC - May 9 2022 - Revised.pdf
Leaside-Laird CLC - May 9 2022 - Revised.pdfLeaside-Laird CLC - May 9 2022 - Revised.pdf
Leaside-Laird CLC - May 9 2022 - Revised.pdf
 

Recently uploaded

MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptxMHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
ILC- UK
 
ZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdfZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdf
Saeed Al Dhaheri
 
Russian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale warRussian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale war
Antti Rautiainen
 
PACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdfPACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdf
Mohammed325561
 
The Role of a Process Server in real estate
The Role of a Process Server in real estateThe Role of a Process Server in real estate
The Role of a Process Server in real estate
oklahomajudicialproc1
 
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
ukyewh
 
Get Government Grants and Assistance Program
Get Government Grants and Assistance ProgramGet Government Grants and Assistance Program
Get Government Grants and Assistance Program
Get Government Grants
 
2024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 362024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 36
JSchaus & Associates
 
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Congressional Budget Office
 
Opinions on EVs: Metro Atlanta Speaks 2023
Opinions on EVs: Metro Atlanta Speaks 2023Opinions on EVs: Metro Atlanta Speaks 2023
Opinions on EVs: Metro Atlanta Speaks 2023
ARCResearch
 
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
850fcj96
 
NHAI_Under_Implementation_01-05-2024.pdf
NHAI_Under_Implementation_01-05-2024.pdfNHAI_Under_Implementation_01-05-2024.pdf
NHAI_Under_Implementation_01-05-2024.pdf
AjayVejendla3
 
Many ways to support street children.pptx
Many ways to support street children.pptxMany ways to support street children.pptx
Many ways to support street children.pptx
SERUDS INDIA
 
2024: The FAR - Federal Acquisition Regulations, Part 37
2024: The FAR - Federal Acquisition Regulations, Part 372024: The FAR - Federal Acquisition Regulations, Part 37
2024: The FAR - Federal Acquisition Regulations, Part 37
JSchaus & Associates
 
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
ehbuaw
 
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
ehbuaw
 
PPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way StopPPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way Stop
ahcitycouncil
 
PPT Item # 7 - BB Inspection Services Agmt
PPT Item # 7 - BB Inspection Services AgmtPPT Item # 7 - BB Inspection Services Agmt
PPT Item # 7 - BB Inspection Services Agmt
ahcitycouncil
 
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdfPNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
ClaudioTebaldi2
 
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
ehbuaw
 

Recently uploaded (20)

MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptxMHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
 
ZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdfZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdf
 
Russian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale warRussian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale war
 
PACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdfPACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdf
 
The Role of a Process Server in real estate
The Role of a Process Server in real estateThe Role of a Process Server in real estate
The Role of a Process Server in real estate
 
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
 
Get Government Grants and Assistance Program
Get Government Grants and Assistance ProgramGet Government Grants and Assistance Program
Get Government Grants and Assistance Program
 
2024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 362024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 36
 
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
 
Opinions on EVs: Metro Atlanta Speaks 2023
Opinions on EVs: Metro Atlanta Speaks 2023Opinions on EVs: Metro Atlanta Speaks 2023
Opinions on EVs: Metro Atlanta Speaks 2023
 
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
 
NHAI_Under_Implementation_01-05-2024.pdf
NHAI_Under_Implementation_01-05-2024.pdfNHAI_Under_Implementation_01-05-2024.pdf
NHAI_Under_Implementation_01-05-2024.pdf
 
Many ways to support street children.pptx
Many ways to support street children.pptxMany ways to support street children.pptx
Many ways to support street children.pptx
 
2024: The FAR - Federal Acquisition Regulations, Part 37
2024: The FAR - Federal Acquisition Regulations, Part 372024: The FAR - Federal Acquisition Regulations, Part 37
2024: The FAR - Federal Acquisition Regulations, Part 37
 
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
 
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
 
PPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way StopPPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way Stop
 
PPT Item # 7 - BB Inspection Services Agmt
PPT Item # 7 - BB Inspection Services AgmtPPT Item # 7 - BB Inspection Services Agmt
PPT Item # 7 - BB Inspection Services Agmt
 
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdfPNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
 
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
 

Cedarvale & Forest Hill Construction Update (September 30, 2020)

  • 1. September 30, 2020 Eglinton Crosstown-LRT Cedarvale – Forest Hill CLC
  • 3. CEDARVALE STATION UPDATE 3 CEDARVALE –FOREST HILL CLC Activity Location Approx. Date & Duration Deep Excavation & Tieback Installation Station’s Main Entrance Complete! Major Concrete Pours Throughout all station areas Underway throughout 2020 into 2021 Starting as early as 5:00 a.m. ranging from 12-18 hours Geotechnical Monitoring Eastbound curb lane of Eglinton Ave between Winnett Ave and Allen Rd N Through early 2021 Tuesdays between 11:00 a.m. – 2:00 p.m. Pedestrian Tunnel Construction Area surrounding Eglinton West Station Underway through 2021 Monday – Saturday; 6:00 a.m. – 2:00 a.m. Eglinton West Station Support of Excavation and Underpinning Works Eglinton West Station Underway through 2020 Monday – Saturday; 6:00 a.m. – 5:00 p.m. Eglinton West Station Bus Loop Closure for Roof Construction Eglinton West Station Underway – Fall 2020 Temporary Traffic Deck Removal, Roof Construction, and Permanent Utility Installation Eglinton Avenue West March 29, 2020 – early 2021
  • 4. CURRENT TRAFFIC CONFIGURATION 4 Through Fall 2020 CEDARVALE –FOREST HILL CLC
  • 5. CONSTRUCTION PROGRESS PHOTOS 5 CEDARVALE –FOREST HILL CLC CONCRETE POUR FOR LAST MAIN STATION INVERT SLAB REMOVAL OF TEMPORARY SUPPORT BEAMS UNDERNEATH THE TTC STATION BOX
  • 7. FOREST HILL STATION UPDATE 7 Activity Location Approx. Date & Duration Deep Excavation Beneath the station roof from the Main Entrance Complete Main Entrance Construction Excavation, installation of struts, lagging and tie-backs Northeast corner of Bathurst St and Eglinton Ave Underway through 2020 Secondary Entrance Construction Formwork, rebar, conduit installation and beam excavation North side of Eglinton Ave, west of Bathurst St Underway through fall 2020 Station Box Construction Waterproofing, shotcrete application and duct bank construction Beneath Eglinton Ave Underway through 2020 Concrete Pours Secondary Entrance Periodically through fall 2020 Upcoming pours: • October 5, 2020 Traffic Configuration Change Secondary Entrance Monday October 5, 2020 *date subject to change
  • 9. UPCOMING TRAFFIC CONFIGURATION 9 October 5, 2020 – February 2021
  • 10. CONSTRUCTION PROGRESS PHOTOS 10 REBAR INSTALLATION SECONDARY ENTRANCE WALL CONSTRUCTION