September 30, 2020
Eglinton Crosstown-LRT
Cedarvale – Forest Hill CLC
Cedarvale Station
CEDARVALE STATION UPDATE
3
CEDARVALE –FOREST HILL CLC
Activity Location Approx. Date & Duration
Deep Excavation & Tieback Installation Station’s Main Entrance Complete!
Major Concrete Pours Throughout all station areas
Underway throughout 2020 into 2021
Starting as early as 5:00 a.m. ranging from 12-18
hours
Geotechnical Monitoring
Eastbound curb lane of Eglinton Ave between
Winnett Ave and Allen Rd N
Through early 2021
Tuesdays between 11:00 a.m. – 2:00 p.m.
Pedestrian Tunnel Construction Area surrounding Eglinton West Station
Underway through 2021
Monday – Saturday; 6:00 a.m. – 2:00 a.m.
Eglinton West Station Support of
Excavation and Underpinning Works
Eglinton West Station
Underway through 2020
Monday – Saturday; 6:00 a.m. – 5:00 p.m.
Eglinton West Station Bus Loop Closure
for Roof Construction
Eglinton West Station Underway – Fall 2020
Temporary Traffic Deck Removal, Roof
Construction, and Permanent Utility
Installation
Eglinton Avenue West March 29, 2020 – early 2021
CURRENT TRAFFIC CONFIGURATION
4
Through Fall 2020
CEDARVALE –FOREST HILL CLC
CONSTRUCTION PROGRESS PHOTOS
5
CEDARVALE –FOREST HILL CLC
CONCRETE POUR FOR LAST
MAIN STATION INVERT SLAB
REMOVAL OF TEMPORARY SUPPORT BEAMS
UNDERNEATH THE TTC STATION BOX
Forest Hill Station
FOREST HILL STATION UPDATE
7
Activity Location Approx. Date & Duration
Deep Excavation
Beneath the station roof from the Main
Entrance
Complete
Main Entrance Construction
Excavation, installation of struts, lagging
and tie-backs
Northeast corner of Bathurst St and
Eglinton Ave
Underway through 2020
Secondary Entrance Construction
Formwork, rebar, conduit installation
and beam excavation
North side of Eglinton Ave, west of
Bathurst St
Underway through fall 2020
Station Box Construction
Waterproofing, shotcrete application
and duct bank construction
Beneath Eglinton Ave Underway through 2020
Concrete Pours Secondary Entrance
Periodically through fall 2020
Upcoming pours:
• October 5, 2020
Traffic Configuration Change Secondary Entrance
Monday October 5, 2020
*date subject to change
CURRENT TRAFFIC CONFIGURATION
8
Until October 5, 2020
UPCOMING TRAFFIC CONFIGURATION
9
October 5, 2020 – February 2021
CONSTRUCTION PROGRESS PHOTOS
10
REBAR INSTALLATION
SECONDARY ENTRANCE
WALL CONSTRUCTION
Cedarvale & Forest Hill Construction Update (September 30, 2020)

Cedarvale & Forest Hill Construction Update (September 30, 2020)

  • 1.
    September 30, 2020 EglintonCrosstown-LRT Cedarvale – Forest Hill CLC
  • 2.
  • 3.
    CEDARVALE STATION UPDATE 3 CEDARVALE–FOREST HILL CLC Activity Location Approx. Date & Duration Deep Excavation & Tieback Installation Station’s Main Entrance Complete! Major Concrete Pours Throughout all station areas Underway throughout 2020 into 2021 Starting as early as 5:00 a.m. ranging from 12-18 hours Geotechnical Monitoring Eastbound curb lane of Eglinton Ave between Winnett Ave and Allen Rd N Through early 2021 Tuesdays between 11:00 a.m. – 2:00 p.m. Pedestrian Tunnel Construction Area surrounding Eglinton West Station Underway through 2021 Monday – Saturday; 6:00 a.m. – 2:00 a.m. Eglinton West Station Support of Excavation and Underpinning Works Eglinton West Station Underway through 2020 Monday – Saturday; 6:00 a.m. – 5:00 p.m. Eglinton West Station Bus Loop Closure for Roof Construction Eglinton West Station Underway – Fall 2020 Temporary Traffic Deck Removal, Roof Construction, and Permanent Utility Installation Eglinton Avenue West March 29, 2020 – early 2021
  • 4.
    CURRENT TRAFFIC CONFIGURATION 4 ThroughFall 2020 CEDARVALE –FOREST HILL CLC
  • 5.
    CONSTRUCTION PROGRESS PHOTOS 5 CEDARVALE–FOREST HILL CLC CONCRETE POUR FOR LAST MAIN STATION INVERT SLAB REMOVAL OF TEMPORARY SUPPORT BEAMS UNDERNEATH THE TTC STATION BOX
  • 6.
  • 7.
    FOREST HILL STATIONUPDATE 7 Activity Location Approx. Date & Duration Deep Excavation Beneath the station roof from the Main Entrance Complete Main Entrance Construction Excavation, installation of struts, lagging and tie-backs Northeast corner of Bathurst St and Eglinton Ave Underway through 2020 Secondary Entrance Construction Formwork, rebar, conduit installation and beam excavation North side of Eglinton Ave, west of Bathurst St Underway through fall 2020 Station Box Construction Waterproofing, shotcrete application and duct bank construction Beneath Eglinton Ave Underway through 2020 Concrete Pours Secondary Entrance Periodically through fall 2020 Upcoming pours: • October 5, 2020 Traffic Configuration Change Secondary Entrance Monday October 5, 2020 *date subject to change
  • 8.
  • 9.
  • 10.
    CONSTRUCTION PROGRESS PHOTOS 10 REBARINSTALLATION SECONDARY ENTRANCE WALL CONSTRUCTION