The document provides updates on construction progress and upcoming work at the Cedarvale and Forest Hill stations on the Eglinton Crosstown LRT project. Major concrete pours will continue throughout 2020 and 2021 at all station areas. Geotechnical monitoring will occur on Eglinton Avenue between Winnett Avenue and Allen Road through early 2021. Pedestrian tunnel construction will be underway around Eglinton West station through 2021. The document also outlines upcoming traffic configuration changes and concrete pours at the Forest Hill station secondary entrance in October 2020.
Central West Fall Open House Presentation Deck - October 14, 2020Crosstown TO
Metrolinx & Eglinton Crosstown LRT Project: Presentation material for the Central West Fall Virtual Open House, held on the Metrolinx Engage website, on October 14, 2020. Stations covered: Fairbank, Oakwood, Cedarvale, Forest Hill, Chaplin, Avenue, Eglinton.
Central West Fall Open House Presentation Deck - October 14, 2020Crosstown TO
Metrolinx & Eglinton Crosstown LRT Project: Presentation material for the Central West Fall Virtual Open House, held on the Metrolinx Engage website, on October 14, 2020. Stations covered: Fairbank, Oakwood, Cedarvale, Forest Hill, Chaplin, Avenue, Eglinton.
Eglinton and Mount Pleasant CLC - March 10, 2021Crosstown TO
A bi-monthly meeting to provide construction updates regarding Eglinton and Mount Pleasant Stations . The attached presentation materials were shared with the group.
Eglinton and Mount Pleasant CLC - March 10, 2021Crosstown TO
A bi-monthly meeting to provide construction updates regarding Eglinton and Mount Pleasant Stations . The attached presentation materials were shared with the group.
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCrosstown TO
This is a meeting invite for the Brentcliffe-Victoria Park CLC (Construction Liaison Committee) Monthly Meeting, covering the Brentcliffe Portal, Sunnybrook Park, Science Centre, Aga Khan, Wynford, Sloane and O’ Connor Stops.
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCrosstown TO
Construction updates for the following locations/stops: Brentcliffe Portal, Sunnybrook Park, Science Centre, Aga Khan Park & Museum, Wynford, Sloane and O'Connor.
Eglinton - Mt Pleasant CLC - November 9, 2022.pdfCrosstown TO
The following construction updates for Eglinton and Mount Pleasant stations has been updated as recently as November 9, 2022. You can view the presentation here:
ZGB - The Role of Generative AI in Government transformation.pdfSaeed Al Dhaheri
This keynote was presented during the the 7th edition of the UAE Hackathon 2024. It highlights the role of AI and Generative AI in addressing government transformation to achieve zero government bureaucracy
Russian anarchist and anti-war movement in the third year of full-scale warAntti Rautiainen
Anarchist group ANA Regensburg hosted my online-presentation on 16th of May 2024, in which I discussed tactics of anti-war activism in Russia, and reasons why the anti-war movement has not been able to make an impact to change the course of events yet. Cases of anarchists repressed for anti-war activities are presented, as well as strategies of support for political prisoners, and modest successes in supporting their struggles.
Thumbnail picture is by MediaZona, you may read their report on anti-war arson attacks in Russia here: https://en.zona.media/article/2022/10/13/burn-map
Links:
Autonomous Action
http://Avtonom.org
Anarchist Black Cross Moscow
http://Avtonom.org/abc
Solidarity Zone
https://t.me/solidarity_zone
Memorial
https://memopzk.org/, https://t.me/pzk_memorial
OVD-Info
https://en.ovdinfo.org/antiwar-ovd-info-guide
RosUznik
https://rosuznik.org/
Uznik Online
http://uznikonline.tilda.ws/
Russian Reader
https://therussianreader.com/
ABC Irkutsk
https://abc38.noblogs.org/
Send mail to prisoners from abroad:
http://Prisonmail.online
YouTube: https://youtu.be/c5nSOdU48O8
Spotify: https://podcasters.spotify.com/pod/show/libertarianlifecoach/episodes/Russian-anarchist-and-anti-war-movement-in-the-third-year-of-full-scale-war-e2k8ai4
A process server is a authorized person for delivering legal documents, such as summons, complaints, subpoenas, and other court papers, to peoples involved in legal proceedings.
Jennifer Schaus and Associates hosts a complimentary webinar series on The FAR in 2024. Join the webinars on Wednesdays and Fridays at noon, eastern.
Recordings are on YouTube and the company website.
https://www.youtube.com/@jenniferschaus/videos
Presentation by Jared Jageler, David Adler, Noelia Duchovny, and Evan Herrnstadt, analysts in CBO’s Microeconomic Studies and Health Analysis Divisions, at the Association of Environmental and Resource Economists Summer Conference.
Many ways to support street children.pptxSERUDS INDIA
By raising awareness, providing support, advocating for change, and offering assistance to children in need, individuals can play a crucial role in improving the lives of street children and helping them realize their full potential
Donate Us
https://serudsindia.org/how-individuals-can-support-street-children-in-india/
#donatefororphan, #donateforhomelesschildren, #childeducation, #ngochildeducation, #donateforeducation, #donationforchildeducation, #sponsorforpoorchild, #sponsororphanage #sponsororphanchild, #donation, #education, #charity, #educationforchild, #seruds, #kurnool, #joyhome
Jennifer Schaus and Associates hosts a complimentary webinar series on The FAR in 2024. Join the webinars on Wednesdays and Fridays at noon, eastern.
Recordings are on YouTube and the company website.
https://www.youtube.com/@jenniferschaus/videos
3. CEDARVALE STATION UPDATE
3
CEDARVALE –FOREST HILL CLC
Activity Location Approx. Date & Duration
Deep Excavation & Tieback Installation Station’s Main Entrance Complete!
Major Concrete Pours Throughout all station areas
Underway throughout 2020 into 2021
Starting as early as 5:00 a.m. ranging from 12-18
hours
Geotechnical Monitoring
Eastbound curb lane of Eglinton Ave between
Winnett Ave and Allen Rd N
Through early 2021
Tuesdays between 11:00 a.m. – 2:00 p.m.
Pedestrian Tunnel Construction Area surrounding Eglinton West Station
Underway through 2021
Monday – Saturday; 6:00 a.m. – 2:00 a.m.
Eglinton West Station Support of
Excavation and Underpinning Works
Eglinton West Station
Underway through 2020
Monday – Saturday; 6:00 a.m. – 5:00 p.m.
Eglinton West Station Bus Loop Closure
for Roof Construction
Eglinton West Station Underway – Fall 2020
Temporary Traffic Deck Removal, Roof
Construction, and Permanent Utility
Installation
Eglinton Avenue West March 29, 2020 – early 2021
5. CONSTRUCTION PROGRESS PHOTOS
5
CEDARVALE –FOREST HILL CLC
CONCRETE POUR FOR LAST
MAIN STATION INVERT SLAB
REMOVAL OF TEMPORARY SUPPORT BEAMS
UNDERNEATH THE TTC STATION BOX
7. FOREST HILL STATION UPDATE
7
Activity Location Approx. Date & Duration
Deep Excavation
Beneath the station roof from the Main
Entrance
Complete
Main Entrance Construction
Excavation, installation of struts, lagging
and tie-backs
Northeast corner of Bathurst St and
Eglinton Ave
Underway through 2020
Secondary Entrance Construction
Formwork, rebar, conduit installation
and beam excavation
North side of Eglinton Ave, west of
Bathurst St
Underway through fall 2020
Station Box Construction
Waterproofing, shotcrete application
and duct bank construction
Beneath Eglinton Ave Underway through 2020
Concrete Pours Secondary Entrance
Periodically through fall 2020
Upcoming pours:
• October 5, 2020
Traffic Configuration Change Secondary Entrance
Monday October 5, 2020