This construction update provides details on upcoming work for the Eglinton Crosstown LRT Cedarvale-Forest Hill section: - At Cedarvale Station, major concrete pours, pedestrian tunnel construction, utility installations and road restoration will continue through early 2022 while station entrances and the station box are constructed. Flanders Road will close at Eglinton Avenue West from December 1st for approximately two months. - At Forest Hill Station, main and secondary entrance construction along with station box work will continue through early 2022. Hilltop Road will reduce to one lane for sewer bypass removal for about a week, and Bathurst Street may reduce to one lane overnight on November 26th for utility