SlideShare a Scribd company logo
November 3, 2022
Eglinton Crosstown LRT
Construction Liaison Meeting
Brentcliffe Road to Victoria Park Avenue
LAND ACKNOWLEDGEMENT
2
Let us take a moment to acknowledge we are on lands that have been, and continue to be, home to many
Indigenous Peoples including the Anishnabeg, the Haudenosaunee and the Huron-Wendat peoples.
We are all Treaty people. Many of us have come here as settlers, as immigrants or involuntarily as part of the
trans-Atlantic slave trade, in this generation, or generations past.
We acknowledge the historic and continued impacts of colonization and the need to work towards
meaningful reconciliation with the original caretakers of this land.
We acknowledge that Metrolinx operates on territories and lands covered by many treaties that affirm and
value the rights of Indigenous communities, Nations and Peoples.
We understand the importance of working towards reconciliation with the original caretakers of this land. At
Metrolinx, we will conduct business in a manner that is built on a foundation of trust, respect and
collaboration.
Section One At-Grade:
Brentcliffe Portal to Sunnybrook Park Stop
SECTION ONE AT-GRADEUPDATE
4
Activity Location Approx. Date & Duration
Vehicle Testing Brentcliffe – Kennedy Ongoing
Noise Barrier and Soil Nail Wall removal Brentcliffe intersection– SE side Resuming late Fall2022
Landscaping along Eglinton Brentcliffe – Kennedy
Resuming late-February,andanticipatedto
be completedby approx.mid-Spring 2023
Brentcliffe Retaining Wall: Landscape
Restoration Works
North side of EglintonAve,east of
Brentcliffe Rd
Resuming late-February,andanticipatedto
be completedby approx.mid-Spring 2023
Multi-use path construction:
Landscaping works
Serena Gundy Park – West of Leslie St.
Resuming late-February,andanticipatedto
be completedby approx.mid-Spring 2023
Architectural and Electrical Finishes Sunnybrook Park Stop
Ongoing throughFall andanticipatedto be
completedby approx.late-December2022
EAST TESTING & COMMISSIONING
5
• On May 25, 26, 27, 31 and June 1 and 2, 6 light
rail vehicles (LRVs) were delivered to the east
end of the alignment.
• Testing and commissioning activities will be
conducted between Brentcliffe Road and
Kennedy Road through 2022.
• Dynamic Testing began August 24, 2021, and
will last through 2022.
• The LRVs will run mainly on the surface along a
track in the center of Eglinton Avenue.
NOISE BARRIER AND SOILNAIL WALLREMOVALON EGLINTON AVE EAST,EASTOF BRENTCLIFFE RD
6
In late Fall 2022 for approximately two (2) months
• In late Fall 2022,crewswill begin
removing the temporary noise barrier
wall and soil nail wall located on the
south side of Eglinton Avenue East,
east of BrentcliffeRoad.
• The temporary walls were erected in
2014to facilitatethe constructionof
the east portal.
• No changesto the current trafficor
pedestrian routes as a result of this
work.
• Noise from constructionactivitiescan
be expected.
• Work will take place between 7am
and 5pm.
LESLIETRAFFIC CONFIGURATION
7
Through 2022
CONSTRUCTIONPROGRESSPHOTOS
8
LESLIE SOUTH STAIRCASE GUARDRAIL
INSTALLATION COMPLETED
DON MILLS TO BRENTCLIFFE
TOPSOIL COMPLETED
Science Centre Station
SCIENCE CENTRE STATION UPDATE
10
Activity Location Approx. Date & Duration
Vehicle Testing Brentcliffe – Kennedy Ongoing
Landscaping along Eglinton Brentcliffe – Kennedy
Resuming late-February,andanticipatedto be
completedby approx.mid-Spring 2023
Finishing Activities:
• Ceiling tiling,claddingsignband
installations,mechanical,electrical,
and architectural finishes.Systems
testing andinspections,andstation
cleaning.
StationBox
Ongoing throughFall andanticipatedto be
completedby approx.late-December2022
Finishing Activities:
• Ceiling tiling,cladding,glazing,and
electrical andarchitectural finishes.
Stationcleaning.
Bus Terminal
Ongoing throughFall andanticipatedto be
completedby approx.late-December2022
Finishing Activities:
• Ceiling tiling,cladding,electricaland
architectural installations.Cable pulls
and signband installations.Station
testing andinspections andstation
cleaning.
MainEntrance
Ongoing throughFall andanticipatedto be
completedby approx.late-December2022
SCIENCE CENTRE TRAFFIC CONFIGURATION
11
Through 2022
CONSTRUCTIONPROGRESSPHOTOS
12
SIGNAGE INSTALLATION ONGOING
THROUGHOUT THE STATION
CLADDING AT ELEVATORS
ONGOING
Section Two At-Grade
Aga Khan Park & Museum Stop to O’Connor Stop
SECTIONTWOAT-GRADEUPDATE
14
Activity Location Approx. Date & Duration
Vehicle Testing Brentcliffe – Kennedy Ongoing
Landscaping along Eglinton Brentcliffe – Kennedy
Resuming late-February,andanticipatedto
be completedby approx.mid-Spring 2023
Architectural and electrical finishes
Aga KhanPark & Museum Stop
Sloane Stop
O’ConnorStop
Ongoing throughFall andanticipatedto be
completedby approx.late-December2022
Final Paving DVP Ramps
Ongoing until approximately November4,
2022
Watermain Restoration Works Eglintonat Gervais Drive
Ongoing until approximately mid-December
2022
SCIENCE CENTRE TRAFFIC CONFIGURATION
15
Ongoing until approximately November 4, 2022
• Crews will perform road
restoration works on the
northeast, northwest, and
southwest, DVP ramps.
• The northeast, northwest, and
southwest DVP ramps will be
reduced to one lane in each
direction.
• No changesto the pedestrian routes
as a result of this work.
• Noise from constructionactivitiescan
be expected.
• Work may be longer or shorter
than expected.
• Work will take place between 7am
and 5pm.
WATERMAINRESTORATIONWORKSON EGLINTONAVENUE EASTAT GERVAIS DRIVE
16
Ongoing until approximately mid-December 2022
Phase One: Northbound traffic to Gervais
Drive will be restricted. Two lanes of
southbound traffic on Gervais Drive will
be maintained. The left turn from Gervais
Drive onto Eglinton Avenue East will
remain restricted. Westbound traffic on
Eglinton Avenue East will be reduced to
one through lane at Gervais Drive.
Phase Two: Northbound traffic to Gervais
Drive will be restricted. Two lanes of
southbound traffic on Gervais Drive will be
maintained. The left turn from Gervais
Drive onto Eglinton Avenue East will
remain restricted.
Phase Three: Northbound traffic to
Gervais Drive will be restricted. One lane
of southbound traffic on Gervais Drive
will be maintained. The left turn from
Gervais Drive onto Eglinton Avenue East
will remain restricted.
Note: Duration of each phase will be approximately two (2) weeks.
CONSTRUCTIONPROGRESSPHOTOS
17
DRIVEWAY PAVING COMPLETED
AT VICTORIA PARK
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf

More Related Content

Similar to CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf

Leaside-Laird CLC - Nov 14, 2022.pdf
Leaside-Laird CLC - Nov 14, 2022.pdfLeaside-Laird CLC - Nov 14, 2022.pdf
Leaside-Laird CLC - Nov 14, 2022.pdf
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdf
Crosstown TO
 
Pharmacy to Kennedy CLC meeting
Pharmacy to Kennedy  CLC meetingPharmacy to Kennedy  CLC meeting
Pharmacy to Kennedy CLC meeting
Crosstown TO
 
Leaside-Laird CLC - Sept 12, 2022.pdf
Leaside-Laird CLC - Sept 12, 2022.pdfLeaside-Laird CLC - Sept 12, 2022.pdf
Leaside-Laird CLC - Sept 12, 2022.pdf
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdfCLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdf
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdfCLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdf
Crosstown TO
 
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptxCLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
Crosstown TO
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
Crosstown TO
 
Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdf
Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdfChaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdf
Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdf
Crosstown TO
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
Crosstown TO
 
CLC Pharmacy to Kennedy - July 26, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - July 26, 2022 Compressed.pptxCLC Pharmacy to Kennedy - July 26, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - July 26, 2022 Compressed.pptx
Crosstown TO
 
Brentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingBrentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC Meeting
Crosstown TO
 
Chaplin-Avenue CLC - May 4 2022-compressed.pptx
Chaplin-Avenue CLC - May 4 2022-compressed.pptxChaplin-Avenue CLC - May 4 2022-compressed.pptx
Chaplin-Avenue CLC - May 4 2022-compressed.pptx
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
Crosstown TO
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Crosstown TO
 
Eglinton - Mt Pleasant CLC - November 9, 2022.pdf
Eglinton - Mt Pleasant CLC - November 9, 2022.pdfEglinton - Mt Pleasant CLC - November 9, 2022.pdf
Eglinton - Mt Pleasant CLC - November 9, 2022.pdf
Crosstown TO
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
Crosstown TO
 

Similar to CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf (20)

Leaside-Laird CLC - Nov 14, 2022.pdf
Leaside-Laird CLC - Nov 14, 2022.pdfLeaside-Laird CLC - Nov 14, 2022.pdf
Leaside-Laird CLC - Nov 14, 2022.pdf
 
CLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdf
 
Pharmacy to Kennedy CLC meeting
Pharmacy to Kennedy  CLC meetingPharmacy to Kennedy  CLC meeting
Pharmacy to Kennedy CLC meeting
 
Leaside-Laird CLC - Sept 12, 2022.pdf
Leaside-Laird CLC - Sept 12, 2022.pdfLeaside-Laird CLC - Sept 12, 2022.pdf
Leaside-Laird CLC - Sept 12, 2022.pdf
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdfCLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdf
 
CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdfCLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdf
 
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptxCLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
 
Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdf
Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdfChaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdf
Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdf
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
 
Test
TestTest
Test
 
CLC Pharmacy to Kennedy - July 26, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - July 26, 2022 Compressed.pptxCLC Pharmacy to Kennedy - July 26, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - July 26, 2022 Compressed.pptx
 
Brentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingBrentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC Meeting
 
Chaplin-Avenue CLC - May 4 2022-compressed.pptx
Chaplin-Avenue CLC - May 4 2022-compressed.pptxChaplin-Avenue CLC - May 4 2022-compressed.pptx
Chaplin-Avenue CLC - May 4 2022-compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
 
Eglinton - Mt Pleasant CLC - November 9, 2022.pdf
Eglinton - Mt Pleasant CLC - November 9, 2022.pdfEglinton - Mt Pleasant CLC - November 9, 2022.pdf
Eglinton - Mt Pleasant CLC - November 9, 2022.pdf
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
 

More from Crosstown TO

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
Crosstown TO
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
Crosstown TO
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
Crosstown TO
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Crosstown TO
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Crosstown TO
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
Crosstown TO
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
Crosstown TO
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Crosstown TO
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Crosstown TO
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Crosstown TO
 
Leaside-Laird CLC - May 9 2022 - Revised.pdf
Leaside-Laird CLC - May 9 2022 - Revised.pdfLeaside-Laird CLC - May 9 2022 - Revised.pdf
Leaside-Laird CLC - May 9 2022 - Revised.pdf
Crosstown TO
 
Leaside-Laird CLC - March 14 2022 - v2.pdf
Leaside-Laird CLC - March 14 2022 - v2.pdfLeaside-Laird CLC - March 14 2022 - v2.pdf
Leaside-Laird CLC - March 14 2022 - v2.pdf
Crosstown TO
 

More from Crosstown TO (12)

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
 
Leaside-Laird CLC - May 9 2022 - Revised.pdf
Leaside-Laird CLC - May 9 2022 - Revised.pdfLeaside-Laird CLC - May 9 2022 - Revised.pdf
Leaside-Laird CLC - May 9 2022 - Revised.pdf
 
Leaside-Laird CLC - March 14 2022 - v2.pdf
Leaside-Laird CLC - March 14 2022 - v2.pdfLeaside-Laird CLC - March 14 2022 - v2.pdf
Leaside-Laird CLC - March 14 2022 - v2.pdf
 

Recently uploaded

2024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 362024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 36
JSchaus & Associates
 
Russian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale warRussian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale war
Antti Rautiainen
 
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
ukyewh
 
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Congressional Budget Office
 
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
ehbuaw
 
一比一原版(WSU毕业证)西悉尼大学毕业证成绩单
一比一原版(WSU毕业证)西悉尼大学毕业证成绩单一比一原版(WSU毕业证)西悉尼大学毕业证成绩单
一比一原版(WSU毕业证)西悉尼大学毕业证成绩单
evkovas
 
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
ehbuaw
 
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
ehbuaw
 
PPT Item # 5 - 5330 Broadway ARB Case # 930F
PPT Item # 5 - 5330 Broadway ARB Case # 930FPPT Item # 5 - 5330 Broadway ARB Case # 930F
PPT Item # 5 - 5330 Broadway ARB Case # 930F
ahcitycouncil
 
PACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdfPACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdf
Mohammed325561
 
PPT Item # 7 - BB Inspection Services Agmt
PPT Item # 7 - BB Inspection Services AgmtPPT Item # 7 - BB Inspection Services Agmt
PPT Item # 7 - BB Inspection Services Agmt
ahcitycouncil
 
Up the Ratios Bylaws - a Comprehensive Process of Our Organization
Up the Ratios Bylaws - a Comprehensive Process of Our OrganizationUp the Ratios Bylaws - a Comprehensive Process of Our Organization
Up the Ratios Bylaws - a Comprehensive Process of Our Organization
uptheratios
 
The Role of a Process Server in real estate
The Role of a Process Server in real estateThe Role of a Process Server in real estate
The Role of a Process Server in real estate
oklahomajudicialproc1
 
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptxPD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
RIDPRO11
 
Counting Class for Micro Observers 2024.pptx
Counting Class for Micro Observers 2024.pptxCounting Class for Micro Observers 2024.pptx
Counting Class for Micro Observers 2024.pptx
Revenue Department Kerala State
 
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
850fcj96
 
Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200
GrantManagementInsti
 
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
850fcj96
 
Many ways to support street children.pptx
Many ways to support street children.pptxMany ways to support street children.pptx
Many ways to support street children.pptx
SERUDS INDIA
 
Understanding the Challenges of Street Children
Understanding the Challenges of Street ChildrenUnderstanding the Challenges of Street Children
Understanding the Challenges of Street Children
SERUDS INDIA
 

Recently uploaded (20)

2024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 362024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 36
 
Russian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale warRussian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale war
 
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
 
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
 
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
 
一比一原版(WSU毕业证)西悉尼大学毕业证成绩单
一比一原版(WSU毕业证)西悉尼大学毕业证成绩单一比一原版(WSU毕业证)西悉尼大学毕业证成绩单
一比一原版(WSU毕业证)西悉尼大学毕业证成绩单
 
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
 
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
 
PPT Item # 5 - 5330 Broadway ARB Case # 930F
PPT Item # 5 - 5330 Broadway ARB Case # 930FPPT Item # 5 - 5330 Broadway ARB Case # 930F
PPT Item # 5 - 5330 Broadway ARB Case # 930F
 
PACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdfPACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdf
 
PPT Item # 7 - BB Inspection Services Agmt
PPT Item # 7 - BB Inspection Services AgmtPPT Item # 7 - BB Inspection Services Agmt
PPT Item # 7 - BB Inspection Services Agmt
 
Up the Ratios Bylaws - a Comprehensive Process of Our Organization
Up the Ratios Bylaws - a Comprehensive Process of Our OrganizationUp the Ratios Bylaws - a Comprehensive Process of Our Organization
Up the Ratios Bylaws - a Comprehensive Process of Our Organization
 
The Role of a Process Server in real estate
The Role of a Process Server in real estateThe Role of a Process Server in real estate
The Role of a Process Server in real estate
 
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptxPD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
 
Counting Class for Micro Observers 2024.pptx
Counting Class for Micro Observers 2024.pptxCounting Class for Micro Observers 2024.pptx
Counting Class for Micro Observers 2024.pptx
 
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
 
Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200
 
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
 
Many ways to support street children.pptx
Many ways to support street children.pptxMany ways to support street children.pptx
Many ways to support street children.pptx
 
Understanding the Challenges of Street Children
Understanding the Challenges of Street ChildrenUnderstanding the Challenges of Street Children
Understanding the Challenges of Street Children
 

CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf

  • 1. November 3, 2022 Eglinton Crosstown LRT Construction Liaison Meeting Brentcliffe Road to Victoria Park Avenue
  • 2. LAND ACKNOWLEDGEMENT 2 Let us take a moment to acknowledge we are on lands that have been, and continue to be, home to many Indigenous Peoples including the Anishnabeg, the Haudenosaunee and the Huron-Wendat peoples. We are all Treaty people. Many of us have come here as settlers, as immigrants or involuntarily as part of the trans-Atlantic slave trade, in this generation, or generations past. We acknowledge the historic and continued impacts of colonization and the need to work towards meaningful reconciliation with the original caretakers of this land. We acknowledge that Metrolinx operates on territories and lands covered by many treaties that affirm and value the rights of Indigenous communities, Nations and Peoples. We understand the importance of working towards reconciliation with the original caretakers of this land. At Metrolinx, we will conduct business in a manner that is built on a foundation of trust, respect and collaboration.
  • 3. Section One At-Grade: Brentcliffe Portal to Sunnybrook Park Stop
  • 4. SECTION ONE AT-GRADEUPDATE 4 Activity Location Approx. Date & Duration Vehicle Testing Brentcliffe – Kennedy Ongoing Noise Barrier and Soil Nail Wall removal Brentcliffe intersection– SE side Resuming late Fall2022 Landscaping along Eglinton Brentcliffe – Kennedy Resuming late-February,andanticipatedto be completedby approx.mid-Spring 2023 Brentcliffe Retaining Wall: Landscape Restoration Works North side of EglintonAve,east of Brentcliffe Rd Resuming late-February,andanticipatedto be completedby approx.mid-Spring 2023 Multi-use path construction: Landscaping works Serena Gundy Park – West of Leslie St. Resuming late-February,andanticipatedto be completedby approx.mid-Spring 2023 Architectural and Electrical Finishes Sunnybrook Park Stop Ongoing throughFall andanticipatedto be completedby approx.late-December2022
  • 5. EAST TESTING & COMMISSIONING 5 • On May 25, 26, 27, 31 and June 1 and 2, 6 light rail vehicles (LRVs) were delivered to the east end of the alignment. • Testing and commissioning activities will be conducted between Brentcliffe Road and Kennedy Road through 2022. • Dynamic Testing began August 24, 2021, and will last through 2022. • The LRVs will run mainly on the surface along a track in the center of Eglinton Avenue.
  • 6. NOISE BARRIER AND SOILNAIL WALLREMOVALON EGLINTON AVE EAST,EASTOF BRENTCLIFFE RD 6 In late Fall 2022 for approximately two (2) months • In late Fall 2022,crewswill begin removing the temporary noise barrier wall and soil nail wall located on the south side of Eglinton Avenue East, east of BrentcliffeRoad. • The temporary walls were erected in 2014to facilitatethe constructionof the east portal. • No changesto the current trafficor pedestrian routes as a result of this work. • Noise from constructionactivitiescan be expected. • Work will take place between 7am and 5pm.
  • 8. CONSTRUCTIONPROGRESSPHOTOS 8 LESLIE SOUTH STAIRCASE GUARDRAIL INSTALLATION COMPLETED DON MILLS TO BRENTCLIFFE TOPSOIL COMPLETED
  • 10. SCIENCE CENTRE STATION UPDATE 10 Activity Location Approx. Date & Duration Vehicle Testing Brentcliffe – Kennedy Ongoing Landscaping along Eglinton Brentcliffe – Kennedy Resuming late-February,andanticipatedto be completedby approx.mid-Spring 2023 Finishing Activities: • Ceiling tiling,claddingsignband installations,mechanical,electrical, and architectural finishes.Systems testing andinspections,andstation cleaning. StationBox Ongoing throughFall andanticipatedto be completedby approx.late-December2022 Finishing Activities: • Ceiling tiling,cladding,glazing,and electrical andarchitectural finishes. Stationcleaning. Bus Terminal Ongoing throughFall andanticipatedto be completedby approx.late-December2022 Finishing Activities: • Ceiling tiling,cladding,electricaland architectural installations.Cable pulls and signband installations.Station testing andinspections andstation cleaning. MainEntrance Ongoing throughFall andanticipatedto be completedby approx.late-December2022
  • 11. SCIENCE CENTRE TRAFFIC CONFIGURATION 11 Through 2022
  • 13. Section Two At-Grade Aga Khan Park & Museum Stop to O’Connor Stop
  • 14. SECTIONTWOAT-GRADEUPDATE 14 Activity Location Approx. Date & Duration Vehicle Testing Brentcliffe – Kennedy Ongoing Landscaping along Eglinton Brentcliffe – Kennedy Resuming late-February,andanticipatedto be completedby approx.mid-Spring 2023 Architectural and electrical finishes Aga KhanPark & Museum Stop Sloane Stop O’ConnorStop Ongoing throughFall andanticipatedto be completedby approx.late-December2022 Final Paving DVP Ramps Ongoing until approximately November4, 2022 Watermain Restoration Works Eglintonat Gervais Drive Ongoing until approximately mid-December 2022
  • 15. SCIENCE CENTRE TRAFFIC CONFIGURATION 15 Ongoing until approximately November 4, 2022 • Crews will perform road restoration works on the northeast, northwest, and southwest, DVP ramps. • The northeast, northwest, and southwest DVP ramps will be reduced to one lane in each direction. • No changesto the pedestrian routes as a result of this work. • Noise from constructionactivitiescan be expected. • Work may be longer or shorter than expected. • Work will take place between 7am and 5pm.
  • 16. WATERMAINRESTORATIONWORKSON EGLINTONAVENUE EASTAT GERVAIS DRIVE 16 Ongoing until approximately mid-December 2022 Phase One: Northbound traffic to Gervais Drive will be restricted. Two lanes of southbound traffic on Gervais Drive will be maintained. The left turn from Gervais Drive onto Eglinton Avenue East will remain restricted. Westbound traffic on Eglinton Avenue East will be reduced to one through lane at Gervais Drive. Phase Two: Northbound traffic to Gervais Drive will be restricted. Two lanes of southbound traffic on Gervais Drive will be maintained. The left turn from Gervais Drive onto Eglinton Avenue East will remain restricted. Phase Three: Northbound traffic to Gervais Drive will be restricted. One lane of southbound traffic on Gervais Drive will be maintained. The left turn from Gervais Drive onto Eglinton Avenue East will remain restricted. Note: Duration of each phase will be approximately two (2) weeks.