Avenue & Chaplin CLC - Construction Update: January 5, 2022Crosstown TO
The document provides updates on construction activities at Chaplin Station and Avenue Station of the Eglinton Crosstown LRT. At Chaplin Station, work is underway on the tertiary, main, and secondary entrances and the station box through winter 2022, with Chaplin Road expected to close for one month starting January 15th. At Avenue Station, work continues on the station box, main entrance, and secondary entrance through winter 2022. Eglinton Connects streetscape work between Eastbourne and Duplex Avenues will also continue into 2022, reducing traffic to one lane in each direction.
Western Works CLC - Construction Update: January 18, 2022Crosstown TO
The document provides updates on construction progress for various stations and sections of the Eglinton Crosstown LRT project. Caledonia, Keelesdale, and Mount Dennis stations are undergoing finishing work like tiling, signage installation, and landscaping through 2022. Rail corridor construction between stations includes concrete pours, utility work, and track installation. LRVs are being tested and commissioned in single and coupled configurations between Mount Dennis and Caledonia stations to ensure safety and reliability before revenue service begins.
CLC Pharmacy to Kennedy - January 25, 2022 Crosstown TO
The document provides updates on construction activities for the Eglinton Crosstown LRT project from Pharmacy Station to Kennedy Station. Recent activities include testing light rail vehicles, ongoing construction at stations including Kennedy Station, and median restoration work at Kennedy Station requiring lane reductions until February 2022. Temporary configurations like the relocated GO platform and pedestrian detour will remain in place until Spring 2022.
Eglinton & Mt pleasant CLC - November Crosstown TO
The document provides updates on construction activities for the Eglinton Crosstown LRT project, including:
- Extended hours for station box construction at Eglinton Station through early 2022.
- Berwick portal construction and a laneway closure at Berwick Avenue on November 15th for 5 hours.
- TTC works at Eglinton Station and an upcoming closure from November 13-14, 2021.
- A planned traffic configuration change at Yonge Street in late November 2021 for approximately 6 months.
- Ongoing station box, main entrance, and secondary entrance construction at Mount Pleasant Station through 2021.
Cedarvale & Forest Hill Construction Update (January 2022)Crosstown TO
This document provides a construction update for the Eglinton Crosstown LRT project in the Cedarvale-Forest Hill area of Toronto:
- Work is underway at Cedarvale Station on the pedestrian tunnel, utility installations, and construction of station entrances and boxes below Eglinton Avenue through mid-2022. Flanders Road will be closed until March 2022 for utility and road work.
- At Forest Hill Station, the main and secondary entrance construction and station box work below Eglinton Avenue will continue through early 2022 along with utility installations. The left turn from Bathurst Street onto Eglinton Avenue will be closed in February for approximately two months.
- Photos show progress on
Avenue & Chaplin CLC - Construction Update: January 5, 2022Crosstown TO
The document provides updates on construction activities at Chaplin Station and Avenue Station of the Eglinton Crosstown LRT. At Chaplin Station, work is underway on the tertiary, main, and secondary entrances and the station box through winter 2022, with Chaplin Road expected to close for one month starting January 15th. At Avenue Station, work continues on the station box, main entrance, and secondary entrance through winter 2022. Eglinton Connects streetscape work between Eastbourne and Duplex Avenues will also continue into 2022, reducing traffic to one lane in each direction.
Western Works CLC - Construction Update: January 18, 2022Crosstown TO
The document provides updates on construction progress for various stations and sections of the Eglinton Crosstown LRT project. Caledonia, Keelesdale, and Mount Dennis stations are undergoing finishing work like tiling, signage installation, and landscaping through 2022. Rail corridor construction between stations includes concrete pours, utility work, and track installation. LRVs are being tested and commissioned in single and coupled configurations between Mount Dennis and Caledonia stations to ensure safety and reliability before revenue service begins.
CLC Pharmacy to Kennedy - January 25, 2022 Crosstown TO
The document provides updates on construction activities for the Eglinton Crosstown LRT project from Pharmacy Station to Kennedy Station. Recent activities include testing light rail vehicles, ongoing construction at stations including Kennedy Station, and median restoration work at Kennedy Station requiring lane reductions until February 2022. Temporary configurations like the relocated GO platform and pedestrian detour will remain in place until Spring 2022.
Eglinton & Mt pleasant CLC - November Crosstown TO
The document provides updates on construction activities for the Eglinton Crosstown LRT project, including:
- Extended hours for station box construction at Eglinton Station through early 2022.
- Berwick portal construction and a laneway closure at Berwick Avenue on November 15th for 5 hours.
- TTC works at Eglinton Station and an upcoming closure from November 13-14, 2021.
- A planned traffic configuration change at Yonge Street in late November 2021 for approximately 6 months.
- Ongoing station box, main entrance, and secondary entrance construction at Mount Pleasant Station through 2021.
Cedarvale & Forest Hill Construction Update (January 2022)Crosstown TO
This document provides a construction update for the Eglinton Crosstown LRT project in the Cedarvale-Forest Hill area of Toronto:
- Work is underway at Cedarvale Station on the pedestrian tunnel, utility installations, and construction of station entrances and boxes below Eglinton Avenue through mid-2022. Flanders Road will be closed until March 2022 for utility and road work.
- At Forest Hill Station, the main and secondary entrance construction and station box work below Eglinton Avenue will continue through early 2022 along with utility installations. The left turn from Bathurst Street onto Eglinton Avenue will be closed in February for approximately two months.
- Photos show progress on
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptxCrosstown TO
This document summarizes construction activities for the Eglinton Crosstown LRT project from Pharmacy Station to Kennedy Station in 3 paragraphs or less:
Construction is ongoing at various stations along the route to complete platform ramps, wayfinding tiles, architectural finishes and electrical work through April 2022. Testing of light rail vehicles is also continuing between Brentcliffe Road and Kennedy Road through Spring 2022. At Kennedy Station, work continues on the main entrance, station box, GO platforms and mechanical/electrical systems and is expected to wrap up in Spring 2022. Various road restoration activities are also ongoing along Eglinton Avenue and at Kennedy Intersection through April 2022 to accommodate the construction.
Avenue & Chaplin CLC - Construction Update: November 4, 2020Crosstown TO
The document provides updates on construction progress and planned activities at Chaplin Station on the Eglinton Crosstown LRT. Construction will continue into 2021 with activities like station box construction, concrete pours, and utility works taking place. This may cause noise, lane reductions and temporary road closures. Photos show ongoing rebar installation and waterproofing work at the station.
Cedarvale & Forest Hill Construction Update (November 24, 2021)Crosstown TO
This construction update provides details on upcoming work for the Eglinton Crosstown LRT Cedarvale-Forest Hill section:
- At Cedarvale Station, major concrete pours, pedestrian tunnel construction, utility installations and road restoration will continue through early 2022 while station entrances and the station box are constructed. Flanders Road will close at Eglinton Avenue West from December 1st for approximately two months.
- At Forest Hill Station, main and secondary entrance construction along with station box work will continue through early 2022. Hilltop Road will reduce to one lane for sewer bypass removal for about a week, and Bathurst Street may reduce to one lane overnight on November 26th for utility
Fairbank-Oakwood Construction Update - January 2022Crosstown TO
This construction update provides information on progress at the Fairbank and Oakwood stations on the Eglinton Crosstown LRT project. At Fairbank Station, tactile edges have been completed on the platform level along with architectural curbs and granite stair installations. Sidewalk restoration and retaining wall work is ongoing. Interior work continues on walls, floors, tiles, lights and equipment. At Oakwood Station, work on the underground station box, main entrance and secondary entrance includes architectural, mechanical and electrical installations. Traffic configurations around both stations will continue through early 2022.
Fairbank-Oakwood Construction Update - November 2021Crosstown TO
The document provides a construction progress update for the Fairbank and Oakwood stations on the Eglinton Crosstown LRT project. For Fairbank station, elevator, escalator, and floor installations were completed in October. Wall, ceiling, and lighting installations are ongoing through 2021. Sidewalk restoration along Eglinton Avenue is also ongoing. For Oakwood station, architectural finishes and mechanical/electrical works are underway in the station box through 2021. Main and secondary entrance construction is also progressing with architectural installations. The traffic configuration around both stations will continue through 2021 as construction progresses.
Pharmacy to Kennedy - November meeting Crosstown TO
The document provides an update on construction activities along Section Three and Four of the Eglinton Crosstown LRT project from O'Connor Station to Ionview Station. Road restoration from Brentcliffe Road to Kennedy Road is ongoing and will continue through winter 2021 and 2022. Testing and commissioning of light rail vehicles is also ongoing east of Brentcliffe Road. Construction at Kennedy Station is progressing with the main entrance works nearing completion in November 2021. Road configuration changes are planned at Kennedy Station in December 2021 and Transway Crescent will be closed for approximately two months for road restoration works.
Fairbank-Oakwood Construction Update - September 2021Crosstown TO
Construction is ongoing at the Fairbank and Oakwood stations on the Fairbank-Oakwood subway extension project. At Fairbank Station, structural work is complete and interior finishes are ongoing at the station box and service building through 2021. Temporary sidewalk closures are in effect along Eglinton Avenue. At Oakwood Station, work on the station box, main entrance, and secondary entrance is underway through 2021, with periodic laneway closures. Traffic configurations are subject to change as construction progresses at both stations.
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)Crosstown TO
The document provides updates on construction activities for Section One and Section Two of the at-grade portion of the Eglinton Crosstown LRT project. For Section One from Brentcliffe Road to Sunnybrook Park Stop, work includes installing light poles and sidewalks, excavating for a retaining wall, and restoring areas around bridges. For Section Two from Aga Khan Park & Museum Stop to O'Connor Stop, work includes platform installation, guideway wall construction, and sidewalk/curb/driveway work between Bermondsey Rd and Victoria Park Ave. The Science Centre Station update outlines work like mechanical installation, deck removal, and tunnel/terminal construction.
Leaside-Laird CLC Meeting - Presentation - January 10, 2022Crosstown TO
The document provides updates on construction progress at the Leaside and Laird stations on the Eglinton Crosstown LRT. At Leaside Station, work is underway on the station box, main entrance, and secondary entrance and will continue into winter 2022. In late January 2022, the traffic configuration on Eglinton Avenue will shift north for approximately three months to facilitate road restoration work. At Laird Station, work on the main and secondary entrances and station box will continue through 2022. Tile installation, concrete pours, and glazing are ongoing at entrance areas.
Eglinton & Mt Pleasant CLC - January 2022Crosstown TO
The document provides updates on construction activities for the Eglinton Crosstown LRT project. It acknowledges that the project is operating on Indigenous lands and is committed to meaningful reconciliation. It then provides details on station construction progress at Eglinton Station including extended hours for station box construction, main entrance construction, and upcoming traffic configurations. Photos show progress on the station box and stairway. Updates are also given for Mount Pleasant Station construction including the station box, main and secondary entrances, and utility works. Current and upcoming traffic configurations are displayed.
Avenue & Chaplin CLC - Construction Update: March 3, 2021Crosstown TO
The document provides updates on construction progress and upcoming work at the Chaplin and Avenue stations on the Eglinton Crosstown LRT. At Chaplin Station, work continues on the tertiary, main, and secondary entrances through summer 2021, with periodic noise and closures expected. At Avenue Station, final lining, concrete pours and structural steel installations will take place through 2021, and Eglinton Avenue will be reduced to one lane in each direction between Lascelles Blvd and Duplex Ave as of mid-March. The Eglinton Connects streetscape project between those intersections is also underway.
Avenue & Chaplin CLC - Construction Update: November 3, 2021Crosstown TO
This document provides updates on construction progress for the Chaplin Station and Avenue Station of the Eglinton Crosstown LRT. At Chaplin Station, work continues on the tertiary, main, and secondary entrances through winter 2021, with activities like concrete works, steel installations, and mechanical works. At Avenue Station, station box construction and entrance work will continue through 2021, with potential impacts like overnight deliveries and occasional lane closures. Construction is also underway on the Eglinton Connects Streetscape and Cycle Track between Eastbourne and Duplex Avenues through 2021.
Avenue & Chaplin CLC - Construction Update: January 6, 2021Crosstown TO
The document provides updates on construction activities for the Chaplin Station and Avenue Station of the Eglinton Crosstown LRT in Toronto, Canada between January and March 2021. At Chaplin Station, work will continue on the main entrance, tertiary entrance, and station box construction, with Chaplin Crescent expected to close from January 11 to February 28, 2021. At Avenue Station, final lining, concrete pours between entrances, and Eglinton Connects streetscape work between Lascelles Boulevard and Duplex Avenue are ongoing. Traffic configurations around both stations are also provided.
Cedarvale & Forest Hill Construction Update (September 29, 2021)Crosstown TO
This construction update provides details on progress at the Cedarvale and Forest Hill stations on the Eglinton Crosstown LRT. At Cedarvale Station, major concrete pours, pedestrian tunnel construction, and mechanical works are underway through 2021. Traffic configuration on Eglinton Avenue West will also be impacted through 2021 as entrance construction continues. Forest Hill Station works include main entrance construction and secondary entrance architectural works through 2021, with the pedestrian route to be closed as of October 5, 2021 for structural activities.
Eglinton & Mt Pleasant CLC - march 9 2022Crosstown TO
The document provides updates on construction activities at the Eglinton Crosstown LRT Eglinton and Mount Pleasant stations for March 2022. At Eglinton station, work is continuing on the station box, main entrance, Berwick portal, and TTC station works. Traffic configurations are also outlined. For Mount Pleasant station, construction is ongoing for the station box, main and secondary entrances, with a traffic configuration change planned for March 26. Photos show progress on the main entrance station boxes at both locations.
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020Crosstown TO
The document provides updates on construction progress at Eglinton Station and Mount Pleasant Station for the Eglinton Crosstown LRT project. At Eglinton Station, excavation and installation of rebar and conduits is underway beneath the TTC box through 2020. Berwick Portal construction and delivery of escalator trusses is also occurring. At Mount Pleasant Station, tunnel demolition is complete and deep excavation and utility reinstatement is underway through 2021. Mount Pleasant Station also recently completed its largest concrete pour to date of 1700 cubic meters in 11 hours.
Fairbank & Oakwood Construction Liaison Committee July 2018Crosstown TO
This document provides construction updates for three stations on the Eglinton Crosstown LRT project: Caledonia Station, Fairbank Station, and Oakwood Station. For Caledonia Station, it notes that drilling dewatering wells, deep excavation, and concrete pours are ongoing through summer 2018. For Fairbank Station, it lists current and planned construction activities and staging through 2019. For Oakwood Station, it provides a rendering of the planned station design, outlines current staging, and lists planned construction activities and impacts from May to October 2018, including underground excavation, watermain lining that may require closing Times Road for two months.
CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdfCrosstown TO
Construction updates for the following locations/stops: Brentcliffe Portal, Sunnybrook Park, Science Centre, Aga Khan Park & Museum, Wynford, Sloane and O'Connor.
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptxCrosstown TO
This document summarizes construction activities for the Eglinton Crosstown LRT project from Pharmacy Station to Kennedy Station in 3 paragraphs or less:
Construction is ongoing at various stations along the route to complete platform ramps, wayfinding tiles, architectural finishes and electrical work through April 2022. Testing of light rail vehicles is also continuing between Brentcliffe Road and Kennedy Road through Spring 2022. At Kennedy Station, work continues on the main entrance, station box, GO platforms and mechanical/electrical systems and is expected to wrap up in Spring 2022. Various road restoration activities are also ongoing along Eglinton Avenue and at Kennedy Intersection through April 2022 to accommodate the construction.
Avenue & Chaplin CLC - Construction Update: November 4, 2020Crosstown TO
The document provides updates on construction progress and planned activities at Chaplin Station on the Eglinton Crosstown LRT. Construction will continue into 2021 with activities like station box construction, concrete pours, and utility works taking place. This may cause noise, lane reductions and temporary road closures. Photos show ongoing rebar installation and waterproofing work at the station.
Cedarvale & Forest Hill Construction Update (November 24, 2021)Crosstown TO
This construction update provides details on upcoming work for the Eglinton Crosstown LRT Cedarvale-Forest Hill section:
- At Cedarvale Station, major concrete pours, pedestrian tunnel construction, utility installations and road restoration will continue through early 2022 while station entrances and the station box are constructed. Flanders Road will close at Eglinton Avenue West from December 1st for approximately two months.
- At Forest Hill Station, main and secondary entrance construction along with station box work will continue through early 2022. Hilltop Road will reduce to one lane for sewer bypass removal for about a week, and Bathurst Street may reduce to one lane overnight on November 26th for utility
Fairbank-Oakwood Construction Update - January 2022Crosstown TO
This construction update provides information on progress at the Fairbank and Oakwood stations on the Eglinton Crosstown LRT project. At Fairbank Station, tactile edges have been completed on the platform level along with architectural curbs and granite stair installations. Sidewalk restoration and retaining wall work is ongoing. Interior work continues on walls, floors, tiles, lights and equipment. At Oakwood Station, work on the underground station box, main entrance and secondary entrance includes architectural, mechanical and electrical installations. Traffic configurations around both stations will continue through early 2022.
Fairbank-Oakwood Construction Update - November 2021Crosstown TO
The document provides a construction progress update for the Fairbank and Oakwood stations on the Eglinton Crosstown LRT project. For Fairbank station, elevator, escalator, and floor installations were completed in October. Wall, ceiling, and lighting installations are ongoing through 2021. Sidewalk restoration along Eglinton Avenue is also ongoing. For Oakwood station, architectural finishes and mechanical/electrical works are underway in the station box through 2021. Main and secondary entrance construction is also progressing with architectural installations. The traffic configuration around both stations will continue through 2021 as construction progresses.
Pharmacy to Kennedy - November meeting Crosstown TO
The document provides an update on construction activities along Section Three and Four of the Eglinton Crosstown LRT project from O'Connor Station to Ionview Station. Road restoration from Brentcliffe Road to Kennedy Road is ongoing and will continue through winter 2021 and 2022. Testing and commissioning of light rail vehicles is also ongoing east of Brentcliffe Road. Construction at Kennedy Station is progressing with the main entrance works nearing completion in November 2021. Road configuration changes are planned at Kennedy Station in December 2021 and Transway Crescent will be closed for approximately two months for road restoration works.
Fairbank-Oakwood Construction Update - September 2021Crosstown TO
Construction is ongoing at the Fairbank and Oakwood stations on the Fairbank-Oakwood subway extension project. At Fairbank Station, structural work is complete and interior finishes are ongoing at the station box and service building through 2021. Temporary sidewalk closures are in effect along Eglinton Avenue. At Oakwood Station, work on the station box, main entrance, and secondary entrance is underway through 2021, with periodic laneway closures. Traffic configurations are subject to change as construction progresses at both stations.
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)Crosstown TO
The document provides updates on construction activities for Section One and Section Two of the at-grade portion of the Eglinton Crosstown LRT project. For Section One from Brentcliffe Road to Sunnybrook Park Stop, work includes installing light poles and sidewalks, excavating for a retaining wall, and restoring areas around bridges. For Section Two from Aga Khan Park & Museum Stop to O'Connor Stop, work includes platform installation, guideway wall construction, and sidewalk/curb/driveway work between Bermondsey Rd and Victoria Park Ave. The Science Centre Station update outlines work like mechanical installation, deck removal, and tunnel/terminal construction.
Leaside-Laird CLC Meeting - Presentation - January 10, 2022Crosstown TO
The document provides updates on construction progress at the Leaside and Laird stations on the Eglinton Crosstown LRT. At Leaside Station, work is underway on the station box, main entrance, and secondary entrance and will continue into winter 2022. In late January 2022, the traffic configuration on Eglinton Avenue will shift north for approximately three months to facilitate road restoration work. At Laird Station, work on the main and secondary entrances and station box will continue through 2022. Tile installation, concrete pours, and glazing are ongoing at entrance areas.
Eglinton & Mt Pleasant CLC - January 2022Crosstown TO
The document provides updates on construction activities for the Eglinton Crosstown LRT project. It acknowledges that the project is operating on Indigenous lands and is committed to meaningful reconciliation. It then provides details on station construction progress at Eglinton Station including extended hours for station box construction, main entrance construction, and upcoming traffic configurations. Photos show progress on the station box and stairway. Updates are also given for Mount Pleasant Station construction including the station box, main and secondary entrances, and utility works. Current and upcoming traffic configurations are displayed.
Avenue & Chaplin CLC - Construction Update: March 3, 2021Crosstown TO
The document provides updates on construction progress and upcoming work at the Chaplin and Avenue stations on the Eglinton Crosstown LRT. At Chaplin Station, work continues on the tertiary, main, and secondary entrances through summer 2021, with periodic noise and closures expected. At Avenue Station, final lining, concrete pours and structural steel installations will take place through 2021, and Eglinton Avenue will be reduced to one lane in each direction between Lascelles Blvd and Duplex Ave as of mid-March. The Eglinton Connects streetscape project between those intersections is also underway.
Avenue & Chaplin CLC - Construction Update: November 3, 2021Crosstown TO
This document provides updates on construction progress for the Chaplin Station and Avenue Station of the Eglinton Crosstown LRT. At Chaplin Station, work continues on the tertiary, main, and secondary entrances through winter 2021, with activities like concrete works, steel installations, and mechanical works. At Avenue Station, station box construction and entrance work will continue through 2021, with potential impacts like overnight deliveries and occasional lane closures. Construction is also underway on the Eglinton Connects Streetscape and Cycle Track between Eastbourne and Duplex Avenues through 2021.
Avenue & Chaplin CLC - Construction Update: January 6, 2021Crosstown TO
The document provides updates on construction activities for the Chaplin Station and Avenue Station of the Eglinton Crosstown LRT in Toronto, Canada between January and March 2021. At Chaplin Station, work will continue on the main entrance, tertiary entrance, and station box construction, with Chaplin Crescent expected to close from January 11 to February 28, 2021. At Avenue Station, final lining, concrete pours between entrances, and Eglinton Connects streetscape work between Lascelles Boulevard and Duplex Avenue are ongoing. Traffic configurations around both stations are also provided.
Cedarvale & Forest Hill Construction Update (September 29, 2021)Crosstown TO
This construction update provides details on progress at the Cedarvale and Forest Hill stations on the Eglinton Crosstown LRT. At Cedarvale Station, major concrete pours, pedestrian tunnel construction, and mechanical works are underway through 2021. Traffic configuration on Eglinton Avenue West will also be impacted through 2021 as entrance construction continues. Forest Hill Station works include main entrance construction and secondary entrance architectural works through 2021, with the pedestrian route to be closed as of October 5, 2021 for structural activities.
Eglinton & Mt Pleasant CLC - march 9 2022Crosstown TO
The document provides updates on construction activities at the Eglinton Crosstown LRT Eglinton and Mount Pleasant stations for March 2022. At Eglinton station, work is continuing on the station box, main entrance, Berwick portal, and TTC station works. Traffic configurations are also outlined. For Mount Pleasant station, construction is ongoing for the station box, main and secondary entrances, with a traffic configuration change planned for March 26. Photos show progress on the main entrance station boxes at both locations.
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020Crosstown TO
The document provides updates on construction progress at Eglinton Station and Mount Pleasant Station for the Eglinton Crosstown LRT project. At Eglinton Station, excavation and installation of rebar and conduits is underway beneath the TTC box through 2020. Berwick Portal construction and delivery of escalator trusses is also occurring. At Mount Pleasant Station, tunnel demolition is complete and deep excavation and utility reinstatement is underway through 2021. Mount Pleasant Station also recently completed its largest concrete pour to date of 1700 cubic meters in 11 hours.
Fairbank & Oakwood Construction Liaison Committee July 2018Crosstown TO
This document provides construction updates for three stations on the Eglinton Crosstown LRT project: Caledonia Station, Fairbank Station, and Oakwood Station. For Caledonia Station, it notes that drilling dewatering wells, deep excavation, and concrete pours are ongoing through summer 2018. For Fairbank Station, it lists current and planned construction activities and staging through 2019. For Oakwood Station, it provides a rendering of the planned station design, outlines current staging, and lists planned construction activities and impacts from May to October 2018, including underground excavation, watermain lining that may require closing Times Road for two months.
CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdfCrosstown TO
Construction updates for the following locations/stops: Brentcliffe Portal, Sunnybrook Park, Science Centre, Aga Khan Park & Museum, Wynford, Sloane and O'Connor.
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdfCrosstown TO
The document provides updates on construction activities for different sections of the Eglinton Crosstown LRT project from September 2022. Vehicle testing is ongoing from Brentcliffe to Kennedy. Road and sidewalk restoration is ongoing from Brentcliffe to Don Mills through summer 2022. Landscaping along Eglinton is also ongoing through summer 2022. Finishing work at various stations including Science Centre station is ongoing through summer 2022 with periodic lane closures on Eglinton and Don Mills for inspections.
The following construction update for Pharmacy to Kennedy stations has been updated as recently as November 30, 2021. You can view the presentation here:
The document provides updates on construction activities for Sections 3 and 4 of the Eglinton Crosstown LRT project from O'Connor Station to Kennedy Station in July 2021. It notes that finishing work is largely complete at stops along this section and vehicle testing is ongoing between Brentcliffe and Kennedy through December 2021. Road restoration between these points is scheduled from August 2021 through fall 2021. It also provides details on watermain relocation work occurring at Kennedy Station from June to September 2021 and the temporary relocation of the west GO platform and pedestrian detour at Kennedy Station through August 2022.
Chaplin-Avenue CLC - March 2, 2022-compressed.pptxCrosstown TO
Metrolinx acknowledges that the Eglinton Crosstown LRT operates on Indigenous land and is committed to meaningful reconciliation. Construction is underway at Avenue Station with utility works planned for March 21st requiring lane reductions for 8 weeks. At Chaplin Station, the tertiary entrance and demolition of 6 Gilgorm Road are ongoing with Chaplin Crescent closed for 2 weeks. Eglinton Connects streetscape work between Eastbourne and Duplex Avenues continues through 2022 with one lane of traffic in each direction.
Chaplin-Avenue CLC - May 4 2022-compressed.pptxCrosstown TO
This document provides updates on construction progress and upcoming traffic changes for the Eglinton Crosstown LRT project at the Chaplin and Avenue stations. At Chaplin Station, work is underway on the tertiary, main, and secondary entrances through Spring 2022, with Chaplin Road expected to close for two weeks in mid-May. At Avenue Station, work continues on the station box, main and secondary entrances through Spring, and utility work will require lane closures at Avenue-Eglinton for one month. Streetscape work for Eglinton Connects is also ongoing between Eastbourne and Duplex Avenues.
Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdfCrosstown TO
Metrolinx acknowledges that the Crosstown LRT operates on Indigenous land and is committed to meaningful reconciliation. Construction updates were provided for the Chaplin and Avenue stations, including ongoing work on station entrances, boxes and infrastructure through summer 2022. Traffic configurations in the areas will be changing as work progresses.
Leaside-Laird CLC - May 9 2022 - Revised.pdfCrosstown TO
- Construction is ongoing at the Leaside and Laird stations on the Eglinton Crosstown LRT, including station box construction, entrance construction, and utility installations.
- At Leaside Station, traffic on Bayview Ave will shift to the east side of the street from May 16-July 2022 to accommodate construction.
- At Laird Station, traffic light pole installations from May 9-20 will reduce lanes on Eglinton Ave E and Laird Dr, and the south crosswalk will be reinstated on May 20.
- Additional works along Eglinton Ave E include vehicle testing, road and sidewalk restoration, and landscaping.
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCrosstown TO
Construction updates for the following locations/stops: Brentcliffe Portal, Sunnybrook Park, Science Centre, Aga Khan Park & Museum, Wynford, Sloane and O'Connor.
CLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdfCrosstown TO
Construction updates for the following locations/stops: Brentcliffe Portal, Sunnybrook Park, Science Centre, Aga Khan Park & Museum, Wynford and O’Connor.
The document provides updates on construction activities for the Eglinton Crosstown LRT project between Pharmacy Station and Kennedy Station from May 31 to mid-June 2022. Key activities include vehicle testing, station construction and finishing works, road restoration between Rosemount Drive and Midland Avenue requiring temporary lane reductions, and TTC bus detours. Testing of light rail vehicles is ongoing along the route in preparation for operations to begin by the end of 2022.
The document provides updates on construction progress for the Eglinton Crosstown LRT project at Leaside Station, Laird Station, and areas east of Laird. At Leaside Station, work is underway on the station box, main and secondary entrances through December 2022, along with utility, road, sidewalk and bike lane work. At Laird Station, main and secondary entrance work along with station box construction is ongoing with anticipated completion by late December 2022. East of Laird, vehicle testing and various works including landscaping and sidewalk restoration are taking place.
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCrosstown TO
The document provides updates on construction activities for the Eglinton Crosstown LRT project from Brentcliffe Road to O'Connor Drive. It notes that vehicle testing is ongoing from Brentcliffe to Kennedy, and that landscaping will continue through the summer. It also summarizes specific utility works, platform works, traffic restrictions and closures taking place between April and May 2023 at various locations along the route. Photos show examples of construction progress such as Presto machine installations and work at Aga Khan Park Station.
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCrosstown TO
This is a meeting invite for the Brentcliffe-Victoria Park CLC (Construction Liaison Committee) Monthly Meeting, covering the Brentcliffe Portal, Sunnybrook Park, Science Centre, Aga Khan, Wynford, Sloane and O’ Connor Stops.
Chaplin-Avenue CLC - Sept 14, 2022 compressed .pptxCrosstown TO
The document provides updates on construction progress for the Chaplin Station and Avenue Station of the Eglinton Crosstown LRT. For Chaplin Station, work is underway on the main, secondary and tertiary entrances through fall 2022, with potential full closure of Chaplin Cres in October for approximately one month. For Avenue Station, construction of the station box and main and secondary entrances is ongoing through fall 2022, along with Eglinton Connects streetscape work between Eastbourne and Duplex Avenues through 2022. Traffic configurations around both stations are subject to change as construction continues.
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)Crosstown TO
The document provides updates on construction activities for Sections One and Two of the Eglinton Crosstown LRT project. For Section One between Brentcliffe Road and Victoria Park Avenue, work includes road widening, retaining wall construction, bridge rehabilitation, and multi-use path building. Section Two between Aga Khan Park and O'Connor sees road work, sidewalk construction, track laying, and shelter installation at O'Connor station. Construction is ongoing at Science Centre station with mechanical and electrical work as well as entrance building.
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)Crosstown TO
The document provides updates on construction activities for Sections One and Two of the Eglinton Crosstown LRT project. For Section One between Brentcliffe Road and Victoria Park Avenue, work includes road widening, retaining wall construction, bridge rehabilitation, and multi-use path building. Section Two between Aga Khan Park and O'Connor sees road work, sidewalk construction, track laying, and shelter installation at O'Connor station. Construction is ongoing at Science Centre station with mechanical and electrical work as well as entrance building.
Similar to Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022 (20)
Western Works CLC - January 17, 2023.pdfCrosstown TO
The document provides updates on construction progress for the Eglinton Crosstown LRT project. It summarizes work completed in December 2022 and ongoing work at Caledonia Station, Keelesdale Station, and Mount Dennis Station. It also discusses track installation in the rail corridor, testing of light rail vehicles at the Eglinton Maintenance and Storage Facility, and lane reductions planned for heat trace installation works. Construction and testing activities are expected to continue through early 2023 and into 2023.
The document provides updates on construction activities for the Eglinton Crosstown LRT. Work is ongoing at Caledonia, Keelesdale, and Mount Dennis stations, and in the rail corridor, and will continue through spring 2023. This includes finishing works, system testing, and commissioning of trains. Lane reductions will occur between Weston Rd and Black Creek Dr in March for heat trace installation works. LRVs are being tested on the mainline in preparation for passenger service.
The document provides updates on construction progress for the Eglinton Crosstown LRT project, including at Leaside and Laird stations. At Leaside Station, architectural finishes, mechanical and electrical works are underway with station box and entrance construction expected to be complete in spring 2023. At Laird Station, similar finishing works are ongoing with the main and secondary entrances projected to be finished in early 2023. Utility works and asphalt restoration requiring periodic lane closures on Eglinton Avenue are also outlined.
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfCrosstown TO
The document provides updates on construction activities for the Eglinton Crosstown LRT project. It notes that work will continue through spring 2023 at Eglinton Station to finish architectural details, mechanical, electrical and testing. It also provides details on construction progress photos and updates for Mount Pleasant Station, including ongoing work on the station box and entrances through spring 2023. Traffic impacts are noted at both locations through late May 2023 for line painting and other works.
Chaplin-Avenue CLC - May 3 2023 Updated.pptxCrosstown TO
The document provides updates on construction progress for the Eglinton Crosstown LRT Chaplin Station and Avenue Station. For Chaplin Station, work is underway on the station entrances, station box, and Chaplin Parkette through Spring 2023. For Avenue Station, construction is ongoing on the station box, main and secondary entrances, and Eglinton Avenue streetscape through Summer 2023. Traffic configurations and lane closures are also outlined.
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxCrosstown TO
The document provides updates on construction activities for the Eglinton Crosstown LRT project from Pharmacy Station to Kennedy Station. It notes that vehicle testing and landscaping work will continue through spring 2023 between Brentcliffe and Kennedy stations. Between O'Connor and Ionview stops, traffic sign installation and line painting will take place through late spring. Sidewalk repairs are scheduled along Eglinton Ave East from mid-March 2023. Testing and commissioning activities are ongoing at Kennedy Station and will continue into early 2023. GO train platform service at Kennedy Station will shift east through 2023 with accessibility shuttle services provided.
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCrosstown TO
The document provides an update on construction activities for the Eglinton Crosstown LRT project from Pharmacy Station to Kennedy Station. It summarizes that testing and commissioning of light rail vehicles is ongoing between Brentcliffe Road and Kennedy Road through 2023. It also outlines ongoing construction and finishing work at multiple stations along the route including O'Connor, Pharmacy, Golden Mile, Birchmount, Ionview and Kennedy stations. Temporary traffic and pedestrian configurations are in place at 1995 Eglinton Avenue East and Kennedy Station during construction activities.
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCrosstown TO
The document provides updates on construction progress for different sections of the Eglinton Crosstown LRT project. Section One details work between Brentcliffe Portal to Sunnybrook Park Stop including vehicle testing, noise barrier removal, landscaping and utility works. Section Two details work from Aga Khan Park & Museum Stop to O'Connor Stop including vehicle testing, station finishes, and upcoming watermain restoration works. Science Centre Station work includes finishing activities and ongoing traffic configuration. Photos show ongoing signage, electrical and landscaping work throughout the alignment.
Chaplin-Avenue CLC - March 1, 2023.pptxCrosstown TO
The document provides updates on construction progress for the Chaplin Station and Avenue Station of the Eglinton Crosstown LRT. For Chaplin Station, work is underway on the station entrances, station box, and Chaplin Parkette through Spring 2023, with periodic lane closures on Chaplin Cres. For Avenue Station, construction is ongoing on the station box, entrances, and Eglinton Avenue streetscape/cycle track between Avenue Rd and Duplex Ave, with the traffic configuration shifting and lane reductions expected by March 2, 2023. Periodic lane and sidewalk closures as well as pedestrian rerouting will occur.
Leaside-Laird CLC - March 13, 2023.pdfCrosstown TO
The document provides updates on construction progress for the Eglinton Crosstown LRT project. It summarizes work happening at Leaside Station, including finishing the station box, main entrance, and secondary entrance through spring 2023. It also summarizes work at Laird Station, including main and secondary entrance construction through early 2023. Utility and road work is occurring through spring 2023 at both stations.
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCrosstown TO
The document provides updates on construction progress for different sections of the Eglinton Crosstown LRT project. Section One details work happening from Brentcliffe Portal to Sunnybrook Park Stop, including vehicle testing, noise barrier removal, landscaping, and overnight utility works. Section Two details work from Aga Khan Park & Museum Stop to O'Connor Stop, including vehicle testing, landscaping, station finishes, and upcoming watermain restoration works. Science Centre Station work includes finishing activities and ongoing traffic configuration. Photos show ongoing signage, electrical, and landscaping works.
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfCrosstown TO
The document provides updates on construction activities for the Eglinton Crosstown LRT project. It acknowledges that the project is taking place on Indigenous land and discusses the importance of reconciliation. It then details construction timelines and plans for the Eglinton and Mount Pleasant stations, including extended work hours, entrance construction, traffic shifts, and anticipated completion dates in spring 2023. Photos show progress on the station structures and entrances.
Chaplin-Avenue CLC - November 2 2022 compressed.pptxCrosstown TO
The document provides updates on construction progress at the Chaplin Station and Avenue Station sites of the Eglinton Crosstown LRT. At Chaplin Station, work is underway on the main, secondary, and tertiary entrances through December 2022, along with station box construction and road closures. At Avenue Station, station box construction and work on the main and secondary entrances is progressing through December 2022, along with Eglinton Avenue streetscape and cycle track construction between Eastbourne and Duplex Avenues. Construction photos depict ongoing work.
Chaplin-Avenue CLC - January 11 2023 (002).pptxCrosstown TO
The document provides updates on construction progress for the Chaplin Station and Avenue Station of the Eglinton Crosstown LRT. For Chaplin Station, construction of the main, secondary and tertiary entrances and Chaplin Parkette are underway through Spring 2023. Station box construction and intersection reinstatement at Chaplin Cres and Eglinton Ave are also progressing. For Avenue Station, station box construction, main and secondary entrance construction, and Eglinton Avenue streetscape work are underway through Spring 2023, with a traffic configuration change expected in early February 2023. Construction photos depict progress at station boxes, entrances and connections to local trails.
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfCrosstown TO
The document provides updates on construction progress for the Eglinton Crosstown LRT project. It discusses ongoing work at Eglinton Station including extended hours for station box construction and main entrance construction. It also discusses ongoing work at Mount Pleasant Station including station box construction and main and secondary entrance construction. Traffic configuration changes at Mount Pleasant are also noted as completed. Construction progress photos of station box work are included.
Leaside-Laird CLC - January 9, 2023.pdfCrosstown TO
The document provides updates on construction progress at the Eglinton Crosstown LRT Leaside and Laird stations. At Leaside Station, work is underway on the station box, main entrance, secondary entrance, and utility and road works, with sidewalk restoration planned for January 9-11, 2023. At Laird Station, work continues on the main entrance, secondary entrance, and station box, with sidewalk restoration and monitoring well decommissioning requiring periodic lane reductions into early-mid 2023. Photos show ongoing construction and finishing works at both stations.
Eglinton - Mt Pleasant CLC - November 9, 2022.pdfCrosstown TO
The document provides updates on construction progress for the Eglinton Crosstown LRT project. At Eglinton Station, work continues on the station box, main entrance, TTC platform extension, and utility installations through December 2022. Upcoming overnight equipment testing is scheduled for November 17th. At Mount Pleasant Station, work continues on the station box, main and secondary entrances, with utility and road restoration ongoing through November and lane shifts starting November 12th for about a week.
Construction of the Eglinton Crosstown LRT is ongoing, with testing and commissioning activities taking place between Brentcliffe Road and Kennedy Road through Summer 2022. At Kennedy Station, work continues on architectural finishes, elevators, escalators, and platforms with completion expected in Summer 2022. Pedestrian access has been detoured at Kennedy GO Station while the west platform is temporarily relocated as part of GO Transit improvements, and this configuration will remain until Summer 2022. Construction photos show ongoing concrete pours, ceiling installations, and restroom finishes throughout Kennedy Station.
Leaside-Laird CLC - March 14 2022 - v2.pdfCrosstown TO
Metrolinx acknowledges that the land they operate on is the traditional territory of Indigenous peoples. They are committed to building meaningful relationships with Indigenous peoples and working towards reconciliation.
Construction updates were provided for the Leaside and Laird stations. At Leaside station, work is ongoing on the station box, main entrance, and secondary entrance and will continue into spring 2022. Road work is scheduled to begin on March 21st for approximately two weeks. At Laird station, work on the main entrance, secondary entrance and station box is ongoing and will continue into spring 2022. Traffic configuration will remain in place through 2022.
Contributi dei parlamentari del PD - Contributi L. 3/2019Partito democratico
DI SEGUITO SONO PUBBLICATI, AI SENSI DELL'ART. 11 DELLA LEGGE N. 3/2019, GLI IMPORTI RICEVUTI DALL'ENTRATA IN VIGORE DELLA SUDDETTA NORMA (31/01/2019) E FINO AL MESE SOLARE ANTECEDENTE QUELLO DELLA PUBBLICAZIONE SUL PRESENTE SITO
Combined Illegal, Unregulated and Unreported (IUU) Vessel List.Christina Parmionova
The best available, up-to-date information on all fishing and related vessels that appear on the illegal, unregulated, and unreported (IUU) fishing vessel lists published by Regional Fisheries Management Organisations (RFMOs) and related organisations. The aim of the site is to improve the effectiveness of the original IUU lists as a tool for a wide variety of stakeholders to better understand and combat illegal fishing and broader fisheries crime.
To date, the following regional organisations maintain or share lists of vessels that have been found to carry out or support IUU fishing within their own or adjacent convention areas and/or species of competence:
Commission for the Conservation of Antarctic Marine Living Resources (CCAMLR)
Commission for the Conservation of Southern Bluefin Tuna (CCSBT)
General Fisheries Commission for the Mediterranean (GFCM)
Inter-American Tropical Tuna Commission (IATTC)
International Commission for the Conservation of Atlantic Tunas (ICCAT)
Indian Ocean Tuna Commission (IOTC)
Northwest Atlantic Fisheries Organisation (NAFO)
North East Atlantic Fisheries Commission (NEAFC)
North Pacific Fisheries Commission (NPFC)
South East Atlantic Fisheries Organisation (SEAFO)
South Pacific Regional Fisheries Management Organisation (SPRFMO)
Southern Indian Ocean Fisheries Agreement (SIOFA)
Western and Central Pacific Fisheries Commission (WCPFC)
The Combined IUU Fishing Vessel List merges all these sources into one list that provides a single reference point to identify whether a vessel is currently IUU listed. Vessels that have been IUU listed in the past and subsequently delisted (for example because of a change in ownership, or because the vessel is no longer in service) are also retained on the site, so that the site contains a full historic record of IUU listed fishing vessels.
Unlike the IUU lists published on individual RFMO websites, which may update vessel details infrequently or not at all, the Combined IUU Fishing Vessel List is kept up to date with the best available information regarding changes to vessel identity, flag state, ownership, location, and operations.
Jennifer Schaus and Associates hosts a complimentary webinar series on The FAR in 2024. Join the webinars on Wednesdays and Fridays at noon, eastern.
Recordings are on YouTube and the company website.
https://www.youtube.com/@jenniferschaus/videos
Monitoring Health for the SDGs - Global Health Statistics 2024 - WHOChristina Parmionova
The 2024 World Health Statistics edition reviews more than 50 health-related indicators from the Sustainable Development Goals and WHO’s Thirteenth General Programme of Work. It also highlights the findings from the Global health estimates 2021, notably the impact of the COVID-19 pandemic on life expectancy and healthy life expectancy.
Donate to charity during this holiday seasonSERUDS INDIA
For people who have money and are philanthropic, there are infinite opportunities to gift a needy person or child a Merry Christmas. Even if you are living on a shoestring budget, you will be surprised at how much you can do.
Donate Us
https://serudsindia.org/how-to-donate-to-charity-during-this-holiday-season/
#charityforchildren, #donateforchildren, #donateclothesforchildren, #donatebooksforchildren, #donatetoysforchildren, #sponsorforchildren, #sponsorclothesforchildren, #sponsorbooksforchildren, #sponsortoysforchildren, #seruds, #kurnool
A Guide to AI for Smarter Nonprofits - Dr. Cori Faklaris, UNC CharlotteCori Faklaris
Working with data is a challenge for many organizations. Nonprofits in particular may need to collect and analyze sensitive, incomplete, and/or biased historical data about people. In this talk, Dr. Cori Faklaris of UNC Charlotte provides an overview of current AI capabilities and weaknesses to consider when integrating current AI technologies into the data workflow. The talk is organized around three takeaways: (1) For better or sometimes worse, AI provides you with “infinite interns.” (2) Give people permission & guardrails to learn what works with these “interns” and what doesn’t. (3) Create a roadmap for adding in more AI to assist nonprofit work, along with strategies for bias mitigation.
Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022
1. January 13, 2022
Eglinton Crosstown LRT
Construction Liaison Committee Meeting
Brentcliffe Road to Victoria Park Avenue
2. METROLINX LAND ACKNOWLEDGMENT
2
Let us take a moment to acknowledge that we are on the traditional territory of Indigenous
Peoples including the Anishnabeg, the Haudenosaunee and the Wendat peoples.
We are all Treaty people. Many of us have come here as settlers and immigrants … in this
generation or generations past.
Metrolinx declares its commitment to building meaningful relationships with Indigenous Peoples.
We acknowledge the historic and continued impacts of colonization and the need to work towards
meaningful reconciliation with the original caretakers of this land.
We acknowledge that Metrolinx operates on lands covered by 20 Treaties, and that we have a
responsibility to recognize and value the rights of Indigenous Nations and Peoples and conduct
business in a matter that is built on the foundation of trust, respect and collaboration.
4. SECTION ONE AT-GRADE UPDATE
4
Activity Location Approx. Date & Duration
Vehicle Testing Brentcliffe – Kennedy Ongoing
Road Restoration Brentcliffe – Don Mills Spring 2022
Noise Barrier and Soil Nail Wall removal Brentcliffe intersection – SE side Spring 2022
Landscaping along Eglinton Brentcliffe – Kennedy Resuming Spring 2022
• Brentcliffe Retaining Wall -
Landscape Restoration Works
• East Brentcliffe Retaining Wall
North side of Eglinton Ave, east of
Brentcliffe Rd
Ongoing through Spring 2022
• Platform ramps & curbs
• Electrical finishes
Sunnybrook Park Stop Ongoing through Spring 2022
• Multi-use path construction -
Landscaping works
Serena Gundy Park – West of Leslie St. Ongoing through Spring 2022
5. EAST TESTING & COMMISSIONING
5
• On May 25, 26, 27, 31 and June 1 and 2, 6 light
rail vehicles (LRVs) were delivered to the east
end of the alignment.
• Testing and commissioning activities will be
conducted between Brentcliffe Road and
Kennedy Road through Spring 2022.
• Dynamic Testing began August 24, 2021, and
will last through Spring 2022.
• The LRVs will run mainly on the surface along a
track in the center of Eglinton Avenue.
6. WATERMAIN CONNECTION WORK – EGLINTON AVENUE EAST AND BRENTCLIFFE ROAD
6
• Phase One: Eastbound traffic on Eglinton Ave E
reduced to one lane. South sidewalk closed east
of Brentcliffe Rd. Approx. three weeks.
• Phases Two and Three: Traffic on Eglinton Ave E
reduced to one lane in each direction. Phase
Two: approx. one week ; Phase Three: approx.
three weeks
• Phase Four: Brentcliffe Rd closed at Eglinton Ave
E. Westbound traffic on Eglinton Ave E reduced
to one through-lane and one left-turn lane.
Eastbound traffic on Eglinton Ave E reduced to a
single lane. East crosswalk closed. Approx. three
weeks.
Monday, January 17, 2022 for approx. 10 weeks
• Watermain connection works on Eglinton
Avenue East between Brentcliffe Road and
Glassworks Drive.
• Will include the installation of a new watermain
line and four fire hydrants
• Work between 6:00 a.m. and 11:00 p.m.