5. 5
Caledonia Station Update
Summer 2018
• Drilling dewatering wells
• Continue deep excavation and tunnel demolition
• Concrete pours
5
6. 6
Overnight Concrete Pours
• Beginning in late July through August 2019
• 1-2 pours per week (total of 90)
• 1:00 a.m. until 7:00 a.m.
• Truck staging on Westside Mall (subject to
owner approval)
10. 10
Fairbank Station Update
ACTIVITY LOCATION START DATE APPROX DURATION
Piling
South side of Eglinton
Ave W
Began Feb 8, 2018 Complete
Shallow Excavation Main Entrance Late March 2018
Through Summer
2018
Shallow Excavation Southeast Station Box Late May 2018
Through Summer
2018
Roof Pour Southeast Station Box Late summer 2018 One (1) day
Shallow Excavation Service Building July 2018 Through Fall 2018
18. 18
Construction Activities Area & Impacts Timing Duration
Mining
- Underground excavation
underway for next few
weeks
- Work to increase depth
of main shaft mid-late
May
• Main Entrance
• North side work zone
Underway - 24
hours
End of 2019
Excavation at Secondary
Entrance
• Excavation is completed level by
level, tiebacks and braces installed
at each level
• Increase in truck traffic removing
soil from site
• Traffic impacts to be determined.
Underway Approximately
3 months
Monitoring instruments,
incl. leak detection
(installations, surveying
and monitoring)
• Crews move from location to
location around the station area
between Times Road and east of
Oakwood.
Ongoing Ongoing
Oakwood Station: What to Expect
19. 19
Construction Activities Area & Impacts Timing Duration
Watermain Lining • Temporary water supply will be
installed to connect impacted
properties during the work.
• Lining activities will take place
between Times Road and
Oakwood Avenue.
• Works include valve installations in
the following locations:
• Eglinton Ave just west of
Oakwood
• Eglinton Ave at Oakwood
Avenue
• Eglinton Ave at Times Road
• During approximately 2 months,
Times Road is proposed to be
closed to facilitate lining operation
and associated equipment.
Early August
*Majority of
work to be
completed
overnight
*Some lining
works are
completed on a
24 hour
continuous
schedule
August to late
October 2018
Oakwood Station: What to Expect
20. 20
Watermain Lining - Overnight
Watermain valve work locations
Watermain lining zone
Proposed closure
during works.