SlideShare a Scribd company logo
July 8, 2021
Eglinton Crosstown LRT
Construction Liaison Meeting
Brentcliffe Road to Victoria Park Avenue
Section One At-Grade:
Brentcliffe Portal to Sunnybrook Park Stop
SECTION ONE AT-GRADE UPDATE
3
Activity Location Approx. Date & Duration
Vehicle Testing Brentcliffe – Kennedy Ongoing through December 2021
Road Restoration Brentcliffe – Kennedy Late July 2021 – Fall 2021
Noise Barrier and Soil Nail Wall removal Brentcliffe – SE side August 2021 – September 2021
Brentcliffe Retaining Wall construction
North side of Eglinton Ave, east of
Brentcliffe Rd
Ongoing through Summer 2021
Waterproofing West Don River Bridge Completed June 2021
• Shelter finishing activities
• Handrail installation
• Platform ramps & curbs
• Electrical finishes
Sunnybrook Park Stop
• Largely completed June 2021
•
• Ongoing through Summer 2021
•
Multi-use path construction: backfill and
compaction
Landscaping works
Serena Gundy Park – West of Leslie St.
Ongoing through July 2021
Fall 2021
Concrete and road works Don Mills Rd & Eglinton Ave E Ongoing through 2021
EAST TESTING & COMMISSIONING
4
• On May 25, 26, 27, 31 and June 1 and 2, 6 light
rail vehicles (LRVs) were delivered to the east
end of the alignment.
• Testing and commissioning activities will be
conducted between Brentcliffe Road and
Kennedy Road through December 2021
• The LRVs will run mainly on the surface along a
track in the center of Eglinton Avenue.
RETAINING WALL CONSTRUCTION
NORTH SIDE OF EGLINTON AVENUE
EAST OF BRENTCLIFFE ROAD
5
• This retaining wall is required to hold the embankment created from
the widened Eglinton Ave.
• Retaining wall construction continues and is expected to be
complete in late Summer 2021
• Monitoring of the slope continues and there have been no recent
issues with the movement. Residents on Thursfield Crescent have full
use of their backyards.
• The City provided revised comments on the restoration design and approved planting trees in soil depths
that are less than the by-law requirements, which means trees will be included in the restoration plan.
• CTS has reviewed and incorporated the City’s comments; the final restoration plan is now with the City. CTS
expects approval shortly.
• CTS will share the restoration plan with Elected Officials and Thursfield residents upon completion.
• CTS expects to begin the restoration works in Fall 2021.
FINAL ROAD RESTORATION
BRENTCLIFFE – KENNEDY
6
• Final Road Restoration works will begin in Summer 2021 and last through Fall 2021
• The approximate timeline for road restoration of the At-Grade is:
o Late July 2021: Sloane – Victoria Park
o July – August 2021: Victoria Park – Birchmount
o September – October 2021: Sloane – Leslie
o October 2021: West of Leslie & east of Birchmount
• More specific details regarding the dates and locations of road restoration works will
be communicated to the public as they become available
NOISE BARRIER WALL AND SOIL NAIL WALL REMOVAL
7
• The noise barrier and soil nail walls, located on
the south side of Eglinton Avenue East, east of
Brentcliffe Rd., were erected in 2014 to facilitate
the construction of the east portal.
• As early as August 2021, CTS will begin
removing the noise barrier wall and exposed
segment of the soil nail wall. This work is
expected to last approximately one (1) month
• More detailed information about this work will
be communicated to the residents before the
work begins.
RAMP CONSTRUCTION, WEST OF LESLIE STREET
MULTI-USE PATH CONNECTING EGLINTON AVE E TO SERENA GUNDY PARK
8
• Excavation work is complete
• Final backfilling activities are underway, and are expected to be completed in July 2021
• After backfilling activities are completed, installation of topsoil, sodding, and landscaping works will take place in
Fall 2021as part of the final restoration plan
Mid-July 2020 through July 2021
CONSTRUCTION PROGRESS PHOTOS
9
WATERPROOFING
WEST DON RIVER BRIDGE
BACKFILL
LESLIE TRAIL
Science Centre Station
SCIENCE CENTRE STATION UPDATE
11
Activity Location Approx. Date & Duration
Vehicle Testing Brentcliffe – Kennedy Ongoing through December 2021
Road Restoration Brentcliffe – Kennedy Late July 2021 – Fall 2021
Door Installation Main Entrance – retail space Completed June 2021
Finishing Activities:
• Floor tiling, ceiling grid & tile
installation, mechanical and electrical
finishes, handrail installation
Station Box Ongoing through July 2021
Finishing Activities:
• Wall & floor tiling, ceiling grid & tile
installation, electrical finishes, sliding
door finishes, canopy Installation
Bus Terminal Ongoing through July 2021
Finishing Activities:
• Floor tiling, ceiling grid & tile
installation, electrical finishes, sliding
door finishes
Main Entrance Ongoing through July 2021
EAST TESTING & COMMISSIONING
12
• On May 25, 26, 27, 31 and June 1 and 2, 6 light
rail vehicles (LRVs) were delivered to the east
end of the alignment.
• Testing and commissioning activities will be
conducted between Brentcliffe Road and
Kennedy Road through December 2021
• The LRVs will run mainly on the surface along a
track in the center of Eglinton Avenue.
SCIENCE CENTRE TRAFFIC CONFIGURATION
13
December 6, 2020 for approx. eight months
CONSTRUCTION PROGRESS PHOTOS
14
GLAZING
CONCOURSE LEVEL
STAIR RAILING INSTALLATION
MAIN ENTRANCE
CONSTRUCTION PROGRESS PHOTOS
15
SIDEWALK RESTORATION
SOUTH SIDE OF EGLINTON AT DON MILLS
ROAD WIDENING
DON MILLS INTERSECTION
Section Two At-Grade
Aga Khan Park & Museum Stop to O’Connor Stop
SECTION TWO AT-GRADE UPDATE
17
Activity Location Approx. Date & Duration
Vehicle Testing Brentcliffe – Kennedy Ongoing through December 2021
Road Restoration Brentcliffe – Kennedy Late July 2021 – Fall 2021
Waterproofing East Don River Bridge Completed June 2021
• Shelter finishing activities
• Handrail installation
• Platform ramps & curbs
• Electrical finishes
Aga Khan Park & Museum Stop
• Largely completed June 2021
•
• Ongoing through Summer 2021
•
• Shelter finishing activities
• Handrail installation
• Platform ramps & curbs
• Electrical finishes
Sloane Stop
• Largely completed June 2021
•
• Ongoing through Summer 2021
•
• Shelter finishing activities
• Handrail installation
• Platform ramps & curbs
• Electrical finishes
O’Connor Stop
• Largely completed June 2021
•
• Ongoing through Summer 2021
•
EAST TESTING & COMMISSIONING
18
• On May 25, 26, 27, 31 and June 1 and 2, 6 light
rail vehicles (LRVs) were delivered to the east
end of the alignment.
• Testing and commissioning activities will be
conducted between Brentcliffe Road and
Kennedy Road through December 2021
• The LRVs will run mainly on the surface along a
track in the center of Eglinton Avenue.
CONSTRUCTION PROGRESS PHOTOS
19
WATERPROOFING
EAST DON RIVER BRIDGE
EDGE TILE INSTALLATION
WYNFORD STOP
Brentcliffe-Victoria Park CLC Meeting

More Related Content

What's hot

Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022
Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022
Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022
Crosstown TO
 
Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting - ...
Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting  - ...Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting  - ...
Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting - ...
Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Crosstown TO
 
Cedarvale & Forest Hill Construction Update (September 29, 2021)
Cedarvale & Forest Hill Construction Update (September 29, 2021)Cedarvale & Forest Hill Construction Update (September 29, 2021)
Cedarvale & Forest Hill Construction Update (September 29, 2021)
Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020
Crosstown TO
 
Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021
Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: January 5, 2022
Avenue & Chaplin CLC - Construction Update: January 5, 2022Avenue & Chaplin CLC - Construction Update: January 5, 2022
Avenue & Chaplin CLC - Construction Update: January 5, 2022
Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
Crosstown TO
 
Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021
Crosstown TO
 
Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020
Crosstown TO
 
CLC pharmacy to Kennedy (Nov24)
CLC pharmacy to Kennedy (Nov24)CLC pharmacy to Kennedy (Nov24)
CLC pharmacy to Kennedy (Nov24)
Crosstown TO
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
Crosstown TO
 
Eastern Works Open House
Eastern Works Open House Eastern Works Open House
Eastern Works Open House
Crosstown TO
 
Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting
Crosstown TO
 
Final central east open house oct282020
Final central east open house oct282020Final central east open house oct282020
Final central east open house oct282020
Crosstown TO
 
Chaplin & Avenue Construction Liaison Committee Meeting
Chaplin & Avenue Construction Liaison Committee MeetingChaplin & Avenue Construction Liaison Committee Meeting
Chaplin & Avenue Construction Liaison Committee Meeting
Crosstown TO
 
CLC Pharmacy to Kennedy January
CLC Pharmacy to Kennedy JanuaryCLC Pharmacy to Kennedy January
CLC Pharmacy to Kennedy January
Crosstown TO
 
Brentcliffe to Victoria Park - March 4, 2021
Brentcliffe to Victoria Park - March 4, 2021Brentcliffe to Victoria Park - March 4, 2021
Brentcliffe to Victoria Park - March 4, 2021
Crosstown TO
 
Eastern Virtual Open House Deck
Eastern Virtual Open House DeckEastern Virtual Open House Deck
Eastern Virtual Open House Deck
Crosstown TO
 
Western Works CLC - Construction Update: January 18, 2022
Western Works CLC - Construction Update: January 18, 2022Western Works CLC - Construction Update: January 18, 2022
Western Works CLC - Construction Update: January 18, 2022
Crosstown TO
 

What's hot (20)

Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022
Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022
Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022
 
Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting - ...
Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting  - ...Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting  - ...
Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting - ...
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Cedarvale & Forest Hill Construction Update (September 29, 2021)
Cedarvale & Forest Hill Construction Update (September 29, 2021)Cedarvale & Forest Hill Construction Update (September 29, 2021)
Cedarvale & Forest Hill Construction Update (September 29, 2021)
 
Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020
 
Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021
 
Avenue & Chaplin CLC - Construction Update: January 5, 2022
Avenue & Chaplin CLC - Construction Update: January 5, 2022Avenue & Chaplin CLC - Construction Update: January 5, 2022
Avenue & Chaplin CLC - Construction Update: January 5, 2022
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
 
Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021
 
Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020
 
CLC pharmacy to Kennedy (Nov24)
CLC pharmacy to Kennedy (Nov24)CLC pharmacy to Kennedy (Nov24)
CLC pharmacy to Kennedy (Nov24)
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
 
Eastern Works Open House
Eastern Works Open House Eastern Works Open House
Eastern Works Open House
 
Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting
 
Final central east open house oct282020
Final central east open house oct282020Final central east open house oct282020
Final central east open house oct282020
 
Chaplin & Avenue Construction Liaison Committee Meeting
Chaplin & Avenue Construction Liaison Committee MeetingChaplin & Avenue Construction Liaison Committee Meeting
Chaplin & Avenue Construction Liaison Committee Meeting
 
CLC Pharmacy to Kennedy January
CLC Pharmacy to Kennedy JanuaryCLC Pharmacy to Kennedy January
CLC Pharmacy to Kennedy January
 
Brentcliffe to Victoria Park - March 4, 2021
Brentcliffe to Victoria Park - March 4, 2021Brentcliffe to Victoria Park - March 4, 2021
Brentcliffe to Victoria Park - March 4, 2021
 
Eastern Virtual Open House Deck
Eastern Virtual Open House DeckEastern Virtual Open House Deck
Eastern Virtual Open House Deck
 
Western Works CLC - Construction Update: January 18, 2022
Western Works CLC - Construction Update: January 18, 2022Western Works CLC - Construction Update: January 18, 2022
Western Works CLC - Construction Update: January 18, 2022
 

Similar to Brentcliffe-Victoria Park CLC Meeting

Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November  Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November
Crosstown TO
 
Brentcliffe-Victoria Park CLC Meeting - May 6, 2021
Brentcliffe-Victoria Park CLC Meeting - May 6, 2021Brentcliffe-Victoria Park CLC Meeting - May 6, 2021
Brentcliffe-Victoria Park CLC Meeting - May 6, 2021
Crosstown TO
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
Crosstown TO
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdfCLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdf
Crosstown TO
 
Brentcliffe to Victoria Park - CLC construction update January 2021
Brentcliffe to Victoria Park - CLC construction update January 2021Brentcliffe to Victoria Park - CLC construction update January 2021
Brentcliffe to Victoria Park - CLC construction update January 2021
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdf
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdfCLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdf
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdf
Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdf
Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: November 3, 2021
Avenue & Chaplin CLC - Construction Update: November 3, 2021Avenue & Chaplin CLC - Construction Update: November 3, 2021
Avenue & Chaplin CLC - Construction Update: November 3, 2021
Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: July 7, 2021
Avenue & Chaplin CLC - Construction Update: July 7, 2021Avenue & Chaplin CLC - Construction Update: July 7, 2021
Avenue & Chaplin CLC - Construction Update: July 7, 2021
Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021
Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020
Crosstown TO
 
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptxCLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdfCLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdf
Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Meeting - July 2020
Pharmacy to Kennedy Construction Liaison Meeting - July 2020Pharmacy to Kennedy Construction Liaison Meeting - July 2020
Pharmacy to Kennedy Construction Liaison Meeting - July 2020
Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020
Crosstown TO
 
Chaplin-Avenue CLC - March 2, 2022-compressed.pptx
Chaplin-Avenue CLC - March 2, 2022-compressed.pptxChaplin-Avenue CLC - March 2, 2022-compressed.pptx
Chaplin-Avenue CLC - March 2, 2022-compressed.pptx
Crosstown TO
 
Fairbank-Oakwood Construction Update - July 2021
Fairbank-Oakwood Construction Update - July 2021Fairbank-Oakwood Construction Update - July 2021
Fairbank-Oakwood Construction Update - July 2021
Crosstown TO
 

Similar to Brentcliffe-Victoria Park CLC Meeting (20)

Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November  Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November
 
Brentcliffe-Victoria Park CLC Meeting - May 6, 2021
Brentcliffe-Victoria Park CLC Meeting - May 6, 2021Brentcliffe-Victoria Park CLC Meeting - May 6, 2021
Brentcliffe-Victoria Park CLC Meeting - May 6, 2021
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 
CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdfCLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdf
 
Brentcliffe to Victoria Park - CLC construction update January 2021
Brentcliffe to Victoria Park - CLC construction update January 2021Brentcliffe to Victoria Park - CLC construction update January 2021
Brentcliffe to Victoria Park - CLC construction update January 2021
 
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdf
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdfCLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdf
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdf
 
Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021
 
CLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdf
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
 
Avenue & Chaplin CLC - Construction Update: November 3, 2021
Avenue & Chaplin CLC - Construction Update: November 3, 2021Avenue & Chaplin CLC - Construction Update: November 3, 2021
Avenue & Chaplin CLC - Construction Update: November 3, 2021
 
Avenue & Chaplin CLC - Construction Update: July 7, 2021
Avenue & Chaplin CLC - Construction Update: July 7, 2021Avenue & Chaplin CLC - Construction Update: July 7, 2021
Avenue & Chaplin CLC - Construction Update: July 7, 2021
 
Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021
 
Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020
 
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptxCLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdfCLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdf
 
Pharmacy to Kennedy Construction Liaison Meeting - July 2020
Pharmacy to Kennedy Construction Liaison Meeting - July 2020Pharmacy to Kennedy Construction Liaison Meeting - July 2020
Pharmacy to Kennedy Construction Liaison Meeting - July 2020
 
Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020
 
Chaplin-Avenue CLC - March 2, 2022-compressed.pptx
Chaplin-Avenue CLC - March 2, 2022-compressed.pptxChaplin-Avenue CLC - March 2, 2022-compressed.pptx
Chaplin-Avenue CLC - March 2, 2022-compressed.pptx
 
Fairbank-Oakwood Construction Update - July 2021
Fairbank-Oakwood Construction Update - July 2021Fairbank-Oakwood Construction Update - July 2021
Fairbank-Oakwood Construction Update - July 2021
 

More from Crosstown TO

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
Crosstown TO
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
Crosstown TO
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
Crosstown TO
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
Crosstown TO
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Crosstown TO
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
Crosstown TO
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Crosstown TO
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
Crosstown TO
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
Crosstown TO
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
Crosstown TO
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Crosstown TO
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Crosstown TO
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
Crosstown TO
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Crosstown TO
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
Crosstown TO
 

More from Crosstown TO (20)

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
 

Recently uploaded

Practical guide for the celebration of World Environment Day on june 5th.
Practical guide for the  celebration of World Environment Day on  june 5th.Practical guide for the  celebration of World Environment Day on  june 5th.
Practical guide for the celebration of World Environment Day on june 5th.
Christina Parmionova
 
About Potato, The scientific name of the plant is Solanum tuberosum (L).
About Potato, The scientific name of the plant is Solanum tuberosum (L).About Potato, The scientific name of the plant is Solanum tuberosum (L).
About Potato, The scientific name of the plant is Solanum tuberosum (L).
Christina Parmionova
 
Milton Keynes Hospital Charity - A guide to leaving a gift in your Will
Milton Keynes Hospital Charity - A guide to leaving a gift in your WillMilton Keynes Hospital Charity - A guide to leaving a gift in your Will
Milton Keynes Hospital Charity - A guide to leaving a gift in your Will
fundraising4
 
Item #s 8&9 -- Demolition Code Amendment
Item #s 8&9 -- Demolition Code AmendmentItem #s 8&9 -- Demolition Code Amendment
Item #s 8&9 -- Demolition Code Amendment
ahcitycouncil
 
原版制作(DPU毕业证书)德保罗大学毕业证Offer一模一样
原版制作(DPU毕业证书)德保罗大学毕业证Offer一模一样原版制作(DPU毕业证书)德保罗大学毕业证Offer一模一样
原版制作(DPU毕业证书)德保罗大学毕业证Offer一模一样
yemqpj
 
Researching the client.pptxsxssssssssssssssssssssss
Researching the client.pptxsxssssssssssssssssssssssResearching the client.pptxsxssssssssssssssssssssss
Researching the client.pptxsxssssssssssssssssssssss
DanielOliver74
 
United Nations World Oceans Day 2024; June 8th " Awaken new dephts".
United Nations World Oceans Day 2024; June 8th " Awaken new dephts".United Nations World Oceans Day 2024; June 8th " Awaken new dephts".
United Nations World Oceans Day 2024; June 8th " Awaken new dephts".
Christina Parmionova
 
PPT Item # 4 - 434 College Blvd. (sign. review)
PPT Item # 4 - 434 College Blvd. (sign. review)PPT Item # 4 - 434 College Blvd. (sign. review)
PPT Item # 4 - 434 College Blvd. (sign. review)
ahcitycouncil
 
在线办理(ISU毕业证书)爱荷华州立大学毕业证学历证书一模一样
在线办理(ISU毕业证书)爱荷华州立大学毕业证学历证书一模一样在线办理(ISU毕业证书)爱荷华州立大学毕业证学历证书一模一样
在线办理(ISU毕业证书)爱荷华州立大学毕业证学历证书一模一样
yemqpj
 
Bangladesh studies presentation on Liberation War 1971 Indepence-of-Banglades...
Bangladesh studies presentation on Liberation War 1971 Indepence-of-Banglades...Bangladesh studies presentation on Liberation War 1971 Indepence-of-Banglades...
Bangladesh studies presentation on Liberation War 1971 Indepence-of-Banglades...
ssuser05e8f3
 
State crafting: Changes and challenges for managing the public finances
State crafting: Changes and challenges for managing the public financesState crafting: Changes and challenges for managing the public finances
State crafting: Changes and challenges for managing the public finances
ResolutionFoundation
 
Combined Illegal, Unregulated and Unreported (IUU) Vessel List.
Combined Illegal, Unregulated and Unreported (IUU) Vessel List.Combined Illegal, Unregulated and Unreported (IUU) Vessel List.
Combined Illegal, Unregulated and Unreported (IUU) Vessel List.
Christina Parmionova
 
CBO’s Outlook for U.S. Fertility Rates: 2024 to 2054
CBO’s Outlook for U.S. Fertility Rates: 2024 to 2054CBO’s Outlook for U.S. Fertility Rates: 2024 to 2054
CBO’s Outlook for U.S. Fertility Rates: 2024 to 2054
Congressional Budget Office
 
2024: The FAR - Federal Acquisition Regulations, Part 39
2024: The FAR - Federal Acquisition Regulations, Part 392024: The FAR - Federal Acquisition Regulations, Part 39
2024: The FAR - Federal Acquisition Regulations, Part 39
JSchaus & Associates
 
原版制作(Hope毕业证书)利物浦霍普大学毕业证文凭证书一模一样
原版制作(Hope毕业证书)利物浦霍普大学毕业证文凭证书一模一样原版制作(Hope毕业证书)利物浦霍普大学毕业证文凭证书一模一样
原版制作(Hope毕业证书)利物浦霍普大学毕业证文凭证书一模一样
ii2sh2v
 
Abiy Berehe - Texas Commission on Environmental Quality Updates
Abiy Berehe - Texas Commission on Environmental Quality UpdatesAbiy Berehe - Texas Commission on Environmental Quality Updates
Abiy Berehe - Texas Commission on Environmental Quality Updates
Texas Alliance of Groundwater Districts
 
PUBLIC FINANCIAL MANAGEMENT SYSTEM (PFMS) and DBT.pptx
PUBLIC FINANCIAL MANAGEMENT SYSTEM (PFMS) and DBT.pptxPUBLIC FINANCIAL MANAGEMENT SYSTEM (PFMS) and DBT.pptx
PUBLIC FINANCIAL MANAGEMENT SYSTEM (PFMS) and DBT.pptx
Marked12
 
Antyodaya saral portal haryana govt schemes
Antyodaya saral portal haryana govt schemesAntyodaya saral portal haryana govt schemes
Antyodaya saral portal haryana govt schemes
narinav14
 
AHMR volume 10 number 1 January-April 2024
AHMR volume 10 number 1 January-April 2024AHMR volume 10 number 1 January-April 2024
AHMR volume 10 number 1 January-April 2024
Scalabrini Institute for Human Mobility in Africa
 
PPT Item # 8&9 - Demolition Code Amendments
PPT Item # 8&9 - Demolition Code AmendmentsPPT Item # 8&9 - Demolition Code Amendments
PPT Item # 8&9 - Demolition Code Amendments
ahcitycouncil
 

Recently uploaded (20)

Practical guide for the celebration of World Environment Day on june 5th.
Practical guide for the  celebration of World Environment Day on  june 5th.Practical guide for the  celebration of World Environment Day on  june 5th.
Practical guide for the celebration of World Environment Day on june 5th.
 
About Potato, The scientific name of the plant is Solanum tuberosum (L).
About Potato, The scientific name of the plant is Solanum tuberosum (L).About Potato, The scientific name of the plant is Solanum tuberosum (L).
About Potato, The scientific name of the plant is Solanum tuberosum (L).
 
Milton Keynes Hospital Charity - A guide to leaving a gift in your Will
Milton Keynes Hospital Charity - A guide to leaving a gift in your WillMilton Keynes Hospital Charity - A guide to leaving a gift in your Will
Milton Keynes Hospital Charity - A guide to leaving a gift in your Will
 
Item #s 8&9 -- Demolition Code Amendment
Item #s 8&9 -- Demolition Code AmendmentItem #s 8&9 -- Demolition Code Amendment
Item #s 8&9 -- Demolition Code Amendment
 
原版制作(DPU毕业证书)德保罗大学毕业证Offer一模一样
原版制作(DPU毕业证书)德保罗大学毕业证Offer一模一样原版制作(DPU毕业证书)德保罗大学毕业证Offer一模一样
原版制作(DPU毕业证书)德保罗大学毕业证Offer一模一样
 
Researching the client.pptxsxssssssssssssssssssssss
Researching the client.pptxsxssssssssssssssssssssssResearching the client.pptxsxssssssssssssssssssssss
Researching the client.pptxsxssssssssssssssssssssss
 
United Nations World Oceans Day 2024; June 8th " Awaken new dephts".
United Nations World Oceans Day 2024; June 8th " Awaken new dephts".United Nations World Oceans Day 2024; June 8th " Awaken new dephts".
United Nations World Oceans Day 2024; June 8th " Awaken new dephts".
 
PPT Item # 4 - 434 College Blvd. (sign. review)
PPT Item # 4 - 434 College Blvd. (sign. review)PPT Item # 4 - 434 College Blvd. (sign. review)
PPT Item # 4 - 434 College Blvd. (sign. review)
 
在线办理(ISU毕业证书)爱荷华州立大学毕业证学历证书一模一样
在线办理(ISU毕业证书)爱荷华州立大学毕业证学历证书一模一样在线办理(ISU毕业证书)爱荷华州立大学毕业证学历证书一模一样
在线办理(ISU毕业证书)爱荷华州立大学毕业证学历证书一模一样
 
Bangladesh studies presentation on Liberation War 1971 Indepence-of-Banglades...
Bangladesh studies presentation on Liberation War 1971 Indepence-of-Banglades...Bangladesh studies presentation on Liberation War 1971 Indepence-of-Banglades...
Bangladesh studies presentation on Liberation War 1971 Indepence-of-Banglades...
 
State crafting: Changes and challenges for managing the public finances
State crafting: Changes and challenges for managing the public financesState crafting: Changes and challenges for managing the public finances
State crafting: Changes and challenges for managing the public finances
 
Combined Illegal, Unregulated and Unreported (IUU) Vessel List.
Combined Illegal, Unregulated and Unreported (IUU) Vessel List.Combined Illegal, Unregulated and Unreported (IUU) Vessel List.
Combined Illegal, Unregulated and Unreported (IUU) Vessel List.
 
CBO’s Outlook for U.S. Fertility Rates: 2024 to 2054
CBO’s Outlook for U.S. Fertility Rates: 2024 to 2054CBO’s Outlook for U.S. Fertility Rates: 2024 to 2054
CBO’s Outlook for U.S. Fertility Rates: 2024 to 2054
 
2024: The FAR - Federal Acquisition Regulations, Part 39
2024: The FAR - Federal Acquisition Regulations, Part 392024: The FAR - Federal Acquisition Regulations, Part 39
2024: The FAR - Federal Acquisition Regulations, Part 39
 
原版制作(Hope毕业证书)利物浦霍普大学毕业证文凭证书一模一样
原版制作(Hope毕业证书)利物浦霍普大学毕业证文凭证书一模一样原版制作(Hope毕业证书)利物浦霍普大学毕业证文凭证书一模一样
原版制作(Hope毕业证书)利物浦霍普大学毕业证文凭证书一模一样
 
Abiy Berehe - Texas Commission on Environmental Quality Updates
Abiy Berehe - Texas Commission on Environmental Quality UpdatesAbiy Berehe - Texas Commission on Environmental Quality Updates
Abiy Berehe - Texas Commission on Environmental Quality Updates
 
PUBLIC FINANCIAL MANAGEMENT SYSTEM (PFMS) and DBT.pptx
PUBLIC FINANCIAL MANAGEMENT SYSTEM (PFMS) and DBT.pptxPUBLIC FINANCIAL MANAGEMENT SYSTEM (PFMS) and DBT.pptx
PUBLIC FINANCIAL MANAGEMENT SYSTEM (PFMS) and DBT.pptx
 
Antyodaya saral portal haryana govt schemes
Antyodaya saral portal haryana govt schemesAntyodaya saral portal haryana govt schemes
Antyodaya saral portal haryana govt schemes
 
AHMR volume 10 number 1 January-April 2024
AHMR volume 10 number 1 January-April 2024AHMR volume 10 number 1 January-April 2024
AHMR volume 10 number 1 January-April 2024
 
PPT Item # 8&9 - Demolition Code Amendments
PPT Item # 8&9 - Demolition Code AmendmentsPPT Item # 8&9 - Demolition Code Amendments
PPT Item # 8&9 - Demolition Code Amendments
 

Brentcliffe-Victoria Park CLC Meeting

  • 1. July 8, 2021 Eglinton Crosstown LRT Construction Liaison Meeting Brentcliffe Road to Victoria Park Avenue
  • 2. Section One At-Grade: Brentcliffe Portal to Sunnybrook Park Stop
  • 3. SECTION ONE AT-GRADE UPDATE 3 Activity Location Approx. Date & Duration Vehicle Testing Brentcliffe – Kennedy Ongoing through December 2021 Road Restoration Brentcliffe – Kennedy Late July 2021 – Fall 2021 Noise Barrier and Soil Nail Wall removal Brentcliffe – SE side August 2021 – September 2021 Brentcliffe Retaining Wall construction North side of Eglinton Ave, east of Brentcliffe Rd Ongoing through Summer 2021 Waterproofing West Don River Bridge Completed June 2021 • Shelter finishing activities • Handrail installation • Platform ramps & curbs • Electrical finishes Sunnybrook Park Stop • Largely completed June 2021 • • Ongoing through Summer 2021 • Multi-use path construction: backfill and compaction Landscaping works Serena Gundy Park – West of Leslie St. Ongoing through July 2021 Fall 2021 Concrete and road works Don Mills Rd & Eglinton Ave E Ongoing through 2021
  • 4. EAST TESTING & COMMISSIONING 4 • On May 25, 26, 27, 31 and June 1 and 2, 6 light rail vehicles (LRVs) were delivered to the east end of the alignment. • Testing and commissioning activities will be conducted between Brentcliffe Road and Kennedy Road through December 2021 • The LRVs will run mainly on the surface along a track in the center of Eglinton Avenue.
  • 5. RETAINING WALL CONSTRUCTION NORTH SIDE OF EGLINTON AVENUE EAST OF BRENTCLIFFE ROAD 5 • This retaining wall is required to hold the embankment created from the widened Eglinton Ave. • Retaining wall construction continues and is expected to be complete in late Summer 2021 • Monitoring of the slope continues and there have been no recent issues with the movement. Residents on Thursfield Crescent have full use of their backyards. • The City provided revised comments on the restoration design and approved planting trees in soil depths that are less than the by-law requirements, which means trees will be included in the restoration plan. • CTS has reviewed and incorporated the City’s comments; the final restoration plan is now with the City. CTS expects approval shortly. • CTS will share the restoration plan with Elected Officials and Thursfield residents upon completion. • CTS expects to begin the restoration works in Fall 2021.
  • 6. FINAL ROAD RESTORATION BRENTCLIFFE – KENNEDY 6 • Final Road Restoration works will begin in Summer 2021 and last through Fall 2021 • The approximate timeline for road restoration of the At-Grade is: o Late July 2021: Sloane – Victoria Park o July – August 2021: Victoria Park – Birchmount o September – October 2021: Sloane – Leslie o October 2021: West of Leslie & east of Birchmount • More specific details regarding the dates and locations of road restoration works will be communicated to the public as they become available
  • 7. NOISE BARRIER WALL AND SOIL NAIL WALL REMOVAL 7 • The noise barrier and soil nail walls, located on the south side of Eglinton Avenue East, east of Brentcliffe Rd., were erected in 2014 to facilitate the construction of the east portal. • As early as August 2021, CTS will begin removing the noise barrier wall and exposed segment of the soil nail wall. This work is expected to last approximately one (1) month • More detailed information about this work will be communicated to the residents before the work begins.
  • 8. RAMP CONSTRUCTION, WEST OF LESLIE STREET MULTI-USE PATH CONNECTING EGLINTON AVE E TO SERENA GUNDY PARK 8 • Excavation work is complete • Final backfilling activities are underway, and are expected to be completed in July 2021 • After backfilling activities are completed, installation of topsoil, sodding, and landscaping works will take place in Fall 2021as part of the final restoration plan Mid-July 2020 through July 2021
  • 9. CONSTRUCTION PROGRESS PHOTOS 9 WATERPROOFING WEST DON RIVER BRIDGE BACKFILL LESLIE TRAIL
  • 11. SCIENCE CENTRE STATION UPDATE 11 Activity Location Approx. Date & Duration Vehicle Testing Brentcliffe – Kennedy Ongoing through December 2021 Road Restoration Brentcliffe – Kennedy Late July 2021 – Fall 2021 Door Installation Main Entrance – retail space Completed June 2021 Finishing Activities: • Floor tiling, ceiling grid & tile installation, mechanical and electrical finishes, handrail installation Station Box Ongoing through July 2021 Finishing Activities: • Wall & floor tiling, ceiling grid & tile installation, electrical finishes, sliding door finishes, canopy Installation Bus Terminal Ongoing through July 2021 Finishing Activities: • Floor tiling, ceiling grid & tile installation, electrical finishes, sliding door finishes Main Entrance Ongoing through July 2021
  • 12. EAST TESTING & COMMISSIONING 12 • On May 25, 26, 27, 31 and June 1 and 2, 6 light rail vehicles (LRVs) were delivered to the east end of the alignment. • Testing and commissioning activities will be conducted between Brentcliffe Road and Kennedy Road through December 2021 • The LRVs will run mainly on the surface along a track in the center of Eglinton Avenue.
  • 13. SCIENCE CENTRE TRAFFIC CONFIGURATION 13 December 6, 2020 for approx. eight months
  • 14. CONSTRUCTION PROGRESS PHOTOS 14 GLAZING CONCOURSE LEVEL STAIR RAILING INSTALLATION MAIN ENTRANCE
  • 15. CONSTRUCTION PROGRESS PHOTOS 15 SIDEWALK RESTORATION SOUTH SIDE OF EGLINTON AT DON MILLS ROAD WIDENING DON MILLS INTERSECTION
  • 16. Section Two At-Grade Aga Khan Park & Museum Stop to O’Connor Stop
  • 17. SECTION TWO AT-GRADE UPDATE 17 Activity Location Approx. Date & Duration Vehicle Testing Brentcliffe – Kennedy Ongoing through December 2021 Road Restoration Brentcliffe – Kennedy Late July 2021 – Fall 2021 Waterproofing East Don River Bridge Completed June 2021 • Shelter finishing activities • Handrail installation • Platform ramps & curbs • Electrical finishes Aga Khan Park & Museum Stop • Largely completed June 2021 • • Ongoing through Summer 2021 • • Shelter finishing activities • Handrail installation • Platform ramps & curbs • Electrical finishes Sloane Stop • Largely completed June 2021 • • Ongoing through Summer 2021 • • Shelter finishing activities • Handrail installation • Platform ramps & curbs • Electrical finishes O’Connor Stop • Largely completed June 2021 • • Ongoing through Summer 2021 •
  • 18. EAST TESTING & COMMISSIONING 18 • On May 25, 26, 27, 31 and June 1 and 2, 6 light rail vehicles (LRVs) were delivered to the east end of the alignment. • Testing and commissioning activities will be conducted between Brentcliffe Road and Kennedy Road through December 2021 • The LRVs will run mainly on the surface along a track in the center of Eglinton Avenue.
  • 19. CONSTRUCTION PROGRESS PHOTOS 19 WATERPROOFING EAST DON RIVER BRIDGE EDGE TILE INSTALLATION WYNFORD STOP