The document provides an update on construction activities for the Eglinton Crosstown LRT project from Pharmacy Station to Kennedy Station. It summarizes that testing and commissioning of light rail vehicles is ongoing between Brentcliffe Road and Kennedy Road through 2023. It also outlines ongoing construction and finishing work at multiple stations along the route including O'Connor, Pharmacy, Golden Mile, Birchmount, Ionview and Kennedy stations. Temporary traffic and pedestrian configurations are in place at 1995 Eglinton Avenue East and Kennedy Station during construction activities.
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCrosstown TO
This is a meeting invite for the Brentcliffe-Victoria Park CLC (Construction Liaison Committee) Monthly Meeting, covering the Brentcliffe Portal, Sunnybrook Park, Science Centre, Aga Khan, Wynford, Sloane and O’ Connor Stops.
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCrosstown TO
This is a meeting invite for the Brentcliffe-Victoria Park CLC (Construction Liaison Committee) Monthly Meeting, covering the Brentcliffe Portal, Sunnybrook Park, Science Centre, Aga Khan, Wynford, Sloane and O’ Connor Stops.
Eglinton - Mt Pleasant CLC - September 14, 2022Crosstown TO
The following construction update for Eglinton and Mount Pleasant stations has been updated as recently as September 14, 2022. You can view the presentation here:
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCrosstown TO
Construction updates for the following locations/stops: Brentcliffe Portal, Sunnybrook Park, Science Centre, Aga Khan Park & Museum, Wynford, Sloane and O'Connor.
More Related Content
Similar to CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
Eglinton - Mt Pleasant CLC - September 14, 2022Crosstown TO
The following construction update for Eglinton and Mount Pleasant stations has been updated as recently as September 14, 2022. You can view the presentation here:
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCrosstown TO
Construction updates for the following locations/stops: Brentcliffe Portal, Sunnybrook Park, Science Centre, Aga Khan Park & Museum, Wynford, Sloane and O'Connor.
Eglinton - Mt Pleasant CLC - November 9, 2022.pdfCrosstown TO
The following construction updates for Eglinton and Mount Pleasant stations has been updated as recently as November 9, 2022. You can view the presentation here:
CLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdfCrosstown TO
Construction updates for the following locations/stops: Brentcliffe Portal, Sunnybrook Park, Science Centre, Aga Khan Park & Museum, Wynford and O’Connor.
CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdfCrosstown TO
Construction updates for the following locations/stops: Brentcliffe Portal, Sunnybrook Park, Science Centre, Aga Khan Park & Museum, Wynford, Sloane and O'Connor.
Canadian Immigration Tracker March 2024 - Key SlidesAndrew Griffith
Highlights
Permanent Residents decrease along with percentage of TR2PR decline to 52 percent of all Permanent Residents.
March asylum claim data not issued as of May 27 (unusually late). Irregular arrivals remain very small.
Study permit applications experiencing sharp decrease as a result of announced caps over 50 percent compared to February.
Citizenship numbers remain stable.
Slide 3 has the overall numbers and change.
Jennifer Schaus and Associates hosts a complimentary webinar series on The FAR in 2024. Join the webinars on Wednesdays and Fridays at noon, eastern.
Recordings are on YouTube and the company website.
https://www.youtube.com/@jenniferschaus/videos
Presentation by Jared Jageler, David Adler, Noelia Duchovny, and Evan Herrnstadt, analysts in CBO’s Microeconomic Studies and Health Analysis Divisions, at the Association of Environmental and Resource Economists Summer Conference.
A process server is a authorized person for delivering legal documents, such as summons, complaints, subpoenas, and other court papers, to peoples involved in legal proceedings.
What is the point of small housing associations.pptxPaul Smith
Given the small scale of housing associations and their relative high cost per home what is the point of them and how do we justify their continued existance
Many ways to support street children.pptxSERUDS INDIA
By raising awareness, providing support, advocating for change, and offering assistance to children in need, individuals can play a crucial role in improving the lives of street children and helping them realize their full potential
Donate Us
https://serudsindia.org/how-individuals-can-support-street-children-in-india/
#donatefororphan, #donateforhomelesschildren, #childeducation, #ngochildeducation, #donateforeducation, #donationforchildeducation, #sponsorforpoorchild, #sponsororphanage #sponsororphanchild, #donation, #education, #charity, #educationforchild, #seruds, #kurnool, #joyhome
ZGB - The Role of Generative AI in Government transformation.pdfSaeed Al Dhaheri
This keynote was presented during the the 7th edition of the UAE Hackathon 2024. It highlights the role of AI and Generative AI in addressing government transformation to achieve zero government bureaucracy
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
1. March 28, 2023
Eglinton Crosstown LRT
Pharmacy to Kennedy Station
Construction Liaison Committee
Meeting
2. LAND ACKNOWLEDGEMENT
2
Let us take a moment to acknowledge we are on lands that have been, and continue to be, home to many
Indigenous Peoples including the Anishnabeg, the Haudenosaunee and the Huron-Wendat peoples.
We are all Treaty people. Many of us have come here as settlers, as immigrants or involuntarily as part of the
trans-Atlantic slave trade, in this generation, or generations past.
We acknowledge the historic and continued impacts of colonization and the need to work towards meaningful
reconciliation with the original caretakers of this land.
We acknowledge that Metrolinx operates on territories and lands covered by many treaties that affirm and value
the rights of Indigenous communities, Nations and Peoples.
We understand the importance of working towards reconciliation with the original caretakers of this land. At
Metrolinx, we will conduct business in a manner that is built on a foundation of trust, respect and collaboration.
4. CONSTRUCTION ACTIVITIES
4
Location Activity Approx. Date & Duration
Brentcliffe – Kennedy
• Vehicle testing
• Landscaping and green track installation
and maintenance along Eglinton
• Ongoing through 2023
• Ongoing and anticipated to be completed
by approx. early-Summer 2023
O’Connor – Ionview Stop
• Traffic Sign Installations
• Line Painting
• Underway through Spring 2023
Sidewalk Segment Restoration
• Along Eglinton Ave East (various
locations)
• As early as March 20, 2023, and ongoing
until approx. early-Summer 2023
• O’Connor Stop (Victoria Park
Ave)
• Pharmacy Stop
• Hakimi Lebovic Stop
• Golden Mile Stop (Warden Ave)
• Birchmount Stop
• Ionview Stop
• Architectural finishes / details
• Electrical finishes
• Underway through Spring 2023
5. EAST TESTING & COMMISSIONING
5
• On May 25, 26, 27, 31 and June 1 and 2, 6 light
rail vehicles (LRVs) were delivered to the east end
of the alignment.
• Testing and commissioning activities will be
conducted between Brentcliffe Road and Kennedy
Road through 2023.
• Dynamic Testing began August 24, 2021, and will
last through 2023.
• The LRVs will run mainly on the surface along a
track in the center of Eglinton Avenue.
6. RESTORATION WORKS AT 1995 EGLINTON AVENUE EAST
6
• Eastbound traffic on Eglinton Ave
East will be reduced to one lane
at 1995 Eglinton Ave East.
• A portion of the parking lot at
1995 Eglinton Ave East will be
restricted.
• Access to property will be
maintained at all times.
• Pedestrians will be safely
rerouted around the work zone.
• Work will take place on Monday –
Friday between 7am and 5pm for
approx. three (3) weeks.
Ongoing until approximately mid-April 2023
9. KENNEDY STATION UPDATE
9
Location Activity Approx. Date & Duration
Brentcliffe –
Kennedy
Vehicle Testing • Ongoing
Kennedy Station
Main Entrance
• Electrical, mechanical and architectural finishes
• Landscaping works
• Station and systems testing and inspections and station
cleaning
• Underway through Spring 2023
Kennedy Station Box
• Electrical, mechanical and architectural finishes
• Station and systems testing and inspections and station
cleaning
• Underway through Spring 2023
Kennedy Station GO
Entrance and
Platform
• Electrical, mechanical and architectural finishes
• Station and systems testing and inspections and station
cleaning
• Underway through Spring 2023
Kennedy Station –
East of GO
• Tiling, glazing, cladding, sign band installations, and other
architectural finishes
• Pedestrian tunnel works
• Electrical and mechanical installations
• Landscaping works
• Underway through Spring 2023
10. CURRENT PEDESTRIAN CONFIGURATION AT KENNEDY STATION
10
• GO Train service will continue at the east
platform through 2023.
• Pedestrians will be rerouted through
Kennedy TTC Subway Station.
• Accessibility shuttle services will be
provided to riders with disabilities who
wish to travel to and from Kennedy GO East
Platform and Kennedy TTC Subway Station.
• Accessibility shuttle services will require
a 48-hour advanced booking.
• Pick-up and drop-off locations for the
accessibility shuttle will be located in the
Kennedy Station parking lot and the GO
customer pick-up and drop-off (PPUDO)
parking lot (refer to map).
Ongoing through 2023
13. CONSTRUCTION PROGRESS PHOTOS
13
PAI INSTALLATION COMPLETED
FURNITURE INSTALLATION
COMPLETED
LANDSCAPING PREPERATION AND SIDEWALK
RESTORATION WORK ONGOING