SlideShare a Scribd company logo
1 of 20
Download to read offline
September 2, 2021
Eglinton Crosstown LRT
Construction Liaison Meeting
Brentcliffe Road to Victoria Park Avenue
Section One At-Grade:
Brentcliffe Portal to Sunnybrook Park Stop
SECTION ONE AT-GRADE UPDATE
3
Activity Location Approx. Date & Duration
Vehicle Testing Brentcliffe – Kennedy Ongoing through December 2021
Road Restoration Brentcliffe – Kennedy August 2021 – Fall 2021
Noise Barrier and Soil Nail Wall removal Brentcliffe intersection – SE side Fall 2021
Landscaping along Eglinton Brentcliffe – Kennedy Fall 2021
Brentcliffe Retaining Wall construction
North side of Eglinton Ave, east of
Brentcliffe Rd
Ongoing through September 2021
• Platform ramps & curbs
• Electrical finishes
Sunnybrook Park Stop
Ongoing through Summer 2021
• Multi-use path construction: backfill
and compaction
• Landscaping works
Serena Gundy Park – West of Leslie St.
• Completed August 2021
• Fall 2021
Concrete and road works Don Mills Rd & Eglinton Ave E Ongoing through 2021
EAST TESTING & COMMISSIONING
4
• On May 25, 26, 27, 31 and June 1 and 2, 6 light
rail vehicles (LRVs) were delivered to the east
end of the alignment.
• Testing and commissioning activities will be
conducted between Brentcliffe Road and
Kennedy Road through December 2021.
• Dynamic Testing began August 24, 2021, and
will last for approximately six weeks.
• The LRVs will run mainly on the surface along a
track in the center of Eglinton Avenue.
RETAINING WALL CONSTRUCTION
NORTH SIDE OF EGLINTON AVENUE
EAST OF BRENTCLIFFE ROAD
5
• This retaining wall is required to hold the embankment created from
the widened Eglinton Ave.
• Retaining wall construction continues and is expected to be
complete in late September 2021
• Monitoring of the slope continues and there have been no recent
issues with the movement. Residents on Thursfield Crescent have full
use of their backyards.
• The City provided revised comments on the restoration design and approved planting trees in soil depths
that are less than the by-law requirements, which means trees will be included in the restoration plan.
• CTS reviewed and incorporated the City’s comments; the final restoration plan has been approved the City.
• CTS has shared the restoration plan with Elected Officials and Thursfield residents.
• CTS expects to begin the restoration works in Fall 2021.
FINAL ROAD RESTORATION
BRENTCLIFFE – KENNEDY
6
• Final Road Restoration works began in August 2021 and will last through Fall 2021
• The approximate timeline for road restoration of the At-Grade is:
o August 2 – August 8, 2021: Aga Khan – Wynford
o August 30 – September 2, 2021: Swift – VP
o September TBC: Eglinton Square and Victoria Park intersections
o September 8 – September 11, 2021: Eglinton Square - Warden
o September & October 2021: Pharmacy – Ionview
o Fall TBC: Ionview - Kennedy
o Fall TBC : Leslie – Aga Khan
• More specific details regarding the dates and locations of road restoration works will
be communicated to the public as they become available
NOISE BARRIER WALL AND SOIL NAIL WALL REMOVAL
7
• The noise barrier and soil nail walls, located on
the south side of Eglinton Avenue East, east of
Brentcliffe Rd., were erected in 2014 to facilitate
the construction of the east portal.
• As early as Fall 2021, CTS will begin removing
the noise barrier wall and exposed segment of
the soil nail wall. This work is expected to last
approximately one (1) month
• More detailed information about this work will
be communicated to the residents before the
work begins.
RAMP CONSTRUCTION, WEST OF LESLIE STREET
MULTI-USE PATH CONNECTING EGLINTON AVE E TO SERENA GUNDY PARK
8
• Excavation work is complete
• Final backfilling activities were completed August 2021
• Installation of topsoil, sodding, and landscaping works will take place in Fall 2021as part of the final restoration
plan
Landscaping through Fall 2021
CONSTRUCTION PROGRESS PHOTOS
9
INSTALLATION AND SLOPE
BRENTCLIFFE RETAINING WALL
EDGE TILE INSTALLATION
SUNNYBROOK PARK STOP
Science Centre Station
SCIENCE CENTRE STATION UPDATE
11
Activity Location Approx. Date & Duration
Vehicle Testing Brentcliffe – Kennedy Ongoing through December 2021
Road Restoration Brentcliffe – Kennedy August 2021 – Fall 2021
Landscaping Bus Terminal – north side Completed August 2021
Finishing Activities:
• Floor tiling, ceiling grid & tile
installation, mechanical and electrical
finishes, handrail installation
Station Box Ongoing through Fall 2021
Finishing Activities:
• Wall & floor tiling, ceiling grid & tile
installation, electrical finishes, sliding
door finishes, canopy Installation
• Bike storage
Bus Terminal
Ongoing through Fall 2021
Finishing Activities:
• Floor tiling, ceiling grid & tile
installation, electrical finishes, sliding
door finishes
Main Entrance Ongoing through Fall 2021
EAST TESTING & COMMISSIONING
12
• On May 25, 26, 27, 31 and June 1 and 2, 6 light
rail vehicles (LRVs) were delivered to the east
end of the alignment.
• Testing and commissioning activities will be
conducted between Brentcliffe Road and
Kennedy Road through December 2021.
• Dynamic Testing began August 24, 2021, and
will last for approximately six weeks.
• The LRVs will run mainly on the surface along a
track in the center of Eglinton Avenue.
SCIENCE CENTRE TRAFFIC CONFIGURATION
13
August 2021
CONSTRUCTION PROGRESS PHOTOS
14
BIKE STORAGE
BUS TERMINAL
LANDSCAPING
BUS TERMINAL – NORTH SIDE
Section Two At-Grade
Aga Khan Park & Museum Stop to O’Connor Stop
SECTION TWO AT-GRADE UPDATE
16
Activity Location Approx. Date & Duration
Vehicle Testing Brentcliffe – Kennedy Ongoing through December 2021
Road Restoration Brentcliffe – Kennedy August 2021 – Fall 2021
Road Restoration Aga Khan – Wynford Completed August 2021
• Milling
• Final Paving
Swift – Victoria Park
• Completed August 2021
• Completed September 2, 2021
• Final Paving
Eglinton Square and Victoria Park
intersections
• September 2021
Landscaping along Eglinton Brentcliffe – Kennedy Fall 2021
• Platform ramps & curbs
• Electrical finishes
Aga Khan Park & Museum Stop
• Ongoing through Summer 2021
•
• Platform ramps & curbs
• Electrical finishes
Sloane Stop
• Ongoing through Summer 2021
•
• Platform ramps & curbs
• Electrical finishes
O’Connor Stop
• Ongoing through Summer 2021
•
EAST TESTING & COMMISSIONING
17
• On May 25, 26, 27, 31 and June 1 and 2, 6 light
rail vehicles (LRVs) were delivered to the east
end of the alignment.
• Testing and commissioning activities will be
conducted between Brentcliffe Road and
Kennedy Road through December 2021.
• Dynamic Testing began August 24, 2021, and
will last for approximately six weeks.
• The LRVs will run mainly on the surface along a
track in the center of Eglinton Avenue.
FINAL ROAD RESTORATION
BRENTCLIFFE – KENNEDY
18
• Final Road Restoration works began in August 2021 and will last through Fall 2021
• The approximate timeline for road restoration of the At-Grade is:
o August 2 – August 8, 2021: Aga Khan – Wynford
o August 30 – September 2, 2021: Swift – VP
o September TBC: Eglinton Square and Victoria Park intersections
o September 8 – September 11, 2021: Eglinton Square - Warden
o September & October 2021: Pharmacy – Ionview
o Fall TBC: Ionview - Kennedy
o Fall TBC : Leslie – Aga Khan
• More specific details regarding the dates and locations of road restoration works will
be communicated to the public as they become available
CONSTRUCTION PROGRESS PHOTOS
19
FINAL ROAD PAVING
AGA KHAN - WYNFORD
FINAL ROAD PAVING & LINE PAINTING
AGA KHAN - WYNFORD
Brentcliffe-Victoria Park CLC Meeting

More Related Content

What's hot

Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021Crosstown TO
 
Fall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue StationsFall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue StationsCrosstown TO
 
Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018Crosstown TO
 
Leaside-Laird CLC Meeting - Presentation - November 8, 2021
Leaside-Laird CLC Meeting - Presentation - November 8, 2021Leaside-Laird CLC Meeting - Presentation - November 8, 2021
Leaside-Laird CLC Meeting - Presentation - November 8, 2021Crosstown TO
 
Eastern Virtual Open House Deck
Eastern Virtual Open House DeckEastern Virtual Open House Deck
Eastern Virtual Open House DeckCrosstown TO
 
Cedarvale & Forest Hill Construction Liaison Committee - July 2018
Cedarvale & Forest Hill Construction Liaison Committee - July 2018Cedarvale & Forest Hill Construction Liaison Committee - July 2018
Cedarvale & Forest Hill Construction Liaison Committee - July 2018Crosstown TO
 
CLC pharmacy to Kennedy (Nov24)
CLC pharmacy to Kennedy (Nov24)CLC pharmacy to Kennedy (Nov24)
CLC pharmacy to Kennedy (Nov24)Crosstown TO
 
Central Spring Open House Presentation Deck - March 23 2020
Central Spring Open House Presentation Deck - March 23 2020Central Spring Open House Presentation Deck - March 23 2020
Central Spring Open House Presentation Deck - March 23 2020Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: January 6, 2021
Avenue & Chaplin CLC - Construction Update: January 6, 2021Avenue & Chaplin CLC - Construction Update: January 6, 2021
Avenue & Chaplin CLC - Construction Update: January 6, 2021Crosstown TO
 
Eglinton and Mt Pleasant CLC - 12, May 2021
Eglinton and Mt Pleasant CLC - 12, May 2021Eglinton and Mt Pleasant CLC - 12, May 2021
Eglinton and Mt Pleasant CLC - 12, May 2021Crosstown TO
 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - Oct 2018
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - Oct 2018Eglinton & Mount Pleasant Construction Liaison Committee Meeting - Oct 2018
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - Oct 2018Crosstown TO
 
Central Virtual Open House 28Apr2021
Central Virtual Open House 28Apr2021Central Virtual Open House 28Apr2021
Central Virtual Open House 28Apr2021Crosstown TO
 
Cedarvale & Forest Hill Construction Update (September 29, 2021)
Cedarvale & Forest Hill Construction Update (September 29, 2021)Cedarvale & Forest Hill Construction Update (September 29, 2021)
Cedarvale & Forest Hill Construction Update (September 29, 2021)Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: March 3, 2021
Avenue & Chaplin CLC - Construction Update: March 3, 2021Avenue & Chaplin CLC - Construction Update: March 3, 2021
Avenue & Chaplin CLC - Construction Update: March 3, 2021Crosstown TO
 
Central East Crosstown Open House Presentation
Central East Crosstown Open House PresentationCentral East Crosstown Open House Presentation
Central East Crosstown Open House PresentationCrosstown TO
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingCrosstown TO
 
Leaside and Laird CLC - 10 May 2021
Leaside and Laird CLC - 10 May 2021 Leaside and Laird CLC - 10 May 2021
Leaside and Laird CLC - 10 May 2021 Crosstown TO
 
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingCrosstown TO
 

What's hot (20)

Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021
 
Fall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue StationsFall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue Stations
 
Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018
 
Leaside-Laird CLC Meeting - Presentation - November 8, 2021
Leaside-Laird CLC Meeting - Presentation - November 8, 2021Leaside-Laird CLC Meeting - Presentation - November 8, 2021
Leaside-Laird CLC Meeting - Presentation - November 8, 2021
 
Eastern Virtual Open House Deck
Eastern Virtual Open House DeckEastern Virtual Open House Deck
Eastern Virtual Open House Deck
 
Cedarvale & Forest Hill Construction Liaison Committee - July 2018
Cedarvale & Forest Hill Construction Liaison Committee - July 2018Cedarvale & Forest Hill Construction Liaison Committee - July 2018
Cedarvale & Forest Hill Construction Liaison Committee - July 2018
 
CLC pharmacy to Kennedy (Nov24)
CLC pharmacy to Kennedy (Nov24)CLC pharmacy to Kennedy (Nov24)
CLC pharmacy to Kennedy (Nov24)
 
Central Spring Open House Presentation Deck - March 23 2020
Central Spring Open House Presentation Deck - March 23 2020Central Spring Open House Presentation Deck - March 23 2020
Central Spring Open House Presentation Deck - March 23 2020
 
Avenue & Chaplin CLC - Construction Update: January 6, 2021
Avenue & Chaplin CLC - Construction Update: January 6, 2021Avenue & Chaplin CLC - Construction Update: January 6, 2021
Avenue & Chaplin CLC - Construction Update: January 6, 2021
 
Eglinton and Mt Pleasant CLC - 12, May 2021
Eglinton and Mt Pleasant CLC - 12, May 2021Eglinton and Mt Pleasant CLC - 12, May 2021
Eglinton and Mt Pleasant CLC - 12, May 2021
 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - Oct 2018
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - Oct 2018Eglinton & Mount Pleasant Construction Liaison Committee Meeting - Oct 2018
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - Oct 2018
 
Central Virtual Open House 28Apr2021
Central Virtual Open House 28Apr2021Central Virtual Open House 28Apr2021
Central Virtual Open House 28Apr2021
 
Cedarvale & Forest Hill Construction Update (September 29, 2021)
Cedarvale & Forest Hill Construction Update (September 29, 2021)Cedarvale & Forest Hill Construction Update (September 29, 2021)
Cedarvale & Forest Hill Construction Update (September 29, 2021)
 
Avenue & Chaplin CLC - Construction Update: March 3, 2021
Avenue & Chaplin CLC - Construction Update: March 3, 2021Avenue & Chaplin CLC - Construction Update: March 3, 2021
Avenue & Chaplin CLC - Construction Update: March 3, 2021
 
Central East Crosstown Open House Presentation
Central East Crosstown Open House PresentationCentral East Crosstown Open House Presentation
Central East Crosstown Open House Presentation
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
 
Leaside and Laird CLC - 10 May 2021
Leaside and Laird CLC - 10 May 2021 Leaside and Laird CLC - 10 May 2021
Leaside and Laird CLC - 10 May 2021
 
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 

Similar to Brentcliffe-Victoria Park CLC Meeting

Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021
Brentcliffe to Victoria Park CLC Meeting -  Presentation - November 4, 2021 Brentcliffe to Victoria Park CLC Meeting -  Presentation - November 4, 2021
Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021 Crosstown TO
 
Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November  Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November Crosstown TO
 
Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting Crosstown TO
 
Pharmacy to Kennedy CLC meeting
Pharmacy to Kennedy  CLC meetingPharmacy to Kennedy  CLC meeting
Pharmacy to Kennedy CLC meetingCrosstown TO
 
Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022
Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022
Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022Crosstown TO
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)Crosstown TO
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)Crosstown TO
 
Brentcliffe-Victoria Park CLC Meeting - May 6, 2021
Brentcliffe-Victoria Park CLC Meeting - May 6, 2021Brentcliffe-Victoria Park CLC Meeting - May 6, 2021
Brentcliffe-Victoria Park CLC Meeting - May 6, 2021Crosstown TO
 
Brentcliffe to Victoria Park - March 4, 2021
Brentcliffe to Victoria Park - March 4, 2021Brentcliffe to Victoria Park - March 4, 2021
Brentcliffe to Victoria Park - March 4, 2021Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdfCLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdfCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdf
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdfCLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdf
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdfCrosstown TO
 
Avenue & Chaplin CLC - Construction Update: November 3, 2021
Avenue & Chaplin CLC - Construction Update: November 3, 2021Avenue & Chaplin CLC - Construction Update: November 3, 2021
Avenue & Chaplin CLC - Construction Update: November 3, 2021Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Meeting - July 2020
Pharmacy to Kennedy Construction Liaison Meeting - July 2020Pharmacy to Kennedy Construction Liaison Meeting - July 2020
Pharmacy to Kennedy Construction Liaison Meeting - July 2020Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021Crosstown TO
 
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptxCLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdfCrosstown TO
 
Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021Crosstown TO
 
Brentcliffe to Victoria Park - CLC construction update January 2021
Brentcliffe to Victoria Park - CLC construction update January 2021Brentcliffe to Victoria Park - CLC construction update January 2021
Brentcliffe to Victoria Park - CLC construction update January 2021Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingCrosstown TO
 
Chaplin-Avenue CLC - March 2, 2022-compressed.pptx
Chaplin-Avenue CLC - March 2, 2022-compressed.pptxChaplin-Avenue CLC - March 2, 2022-compressed.pptx
Chaplin-Avenue CLC - March 2, 2022-compressed.pptxCrosstown TO
 

Similar to Brentcliffe-Victoria Park CLC Meeting (20)

Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021
Brentcliffe to Victoria Park CLC Meeting -  Presentation - November 4, 2021 Brentcliffe to Victoria Park CLC Meeting -  Presentation - November 4, 2021
Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021
 
Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November  Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November
 
Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting
 
Pharmacy to Kennedy CLC meeting
Pharmacy to Kennedy  CLC meetingPharmacy to Kennedy  CLC meeting
Pharmacy to Kennedy CLC meeting
 
Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022
Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022
Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 
Brentcliffe-Victoria Park CLC Meeting - May 6, 2021
Brentcliffe-Victoria Park CLC Meeting - May 6, 2021Brentcliffe-Victoria Park CLC Meeting - May 6, 2021
Brentcliffe-Victoria Park CLC Meeting - May 6, 2021
 
Brentcliffe to Victoria Park - March 4, 2021
Brentcliffe to Victoria Park - March 4, 2021Brentcliffe to Victoria Park - March 4, 2021
Brentcliffe to Victoria Park - March 4, 2021
 
CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdfCLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdf
 
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdf
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdfCLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdf
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdf
 
Avenue & Chaplin CLC - Construction Update: November 3, 2021
Avenue & Chaplin CLC - Construction Update: November 3, 2021Avenue & Chaplin CLC - Construction Update: November 3, 2021
Avenue & Chaplin CLC - Construction Update: November 3, 2021
 
Pharmacy to Kennedy Construction Liaison Meeting - July 2020
Pharmacy to Kennedy Construction Liaison Meeting - July 2020Pharmacy to Kennedy Construction Liaison Meeting - July 2020
Pharmacy to Kennedy Construction Liaison Meeting - July 2020
 
Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021
 
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptxCLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdf
 
Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021
 
Brentcliffe to Victoria Park - CLC construction update January 2021
Brentcliffe to Victoria Park - CLC construction update January 2021Brentcliffe to Victoria Park - CLC construction update January 2021
Brentcliffe to Victoria Park - CLC construction update January 2021
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
 
Chaplin-Avenue CLC - March 2, 2022-compressed.pptx
Chaplin-Avenue CLC - March 2, 2022-compressed.pptxChaplin-Avenue CLC - March 2, 2022-compressed.pptx
Chaplin-Avenue CLC - March 2, 2022-compressed.pptx
 

More from Crosstown TO

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfCrosstown TO
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023Crosstown TO
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Crosstown TO
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfCrosstown TO
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfCrosstown TO
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCrosstown TO
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxCrosstown TO
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCrosstown TO
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxCrosstown TO
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCrosstown TO
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfCrosstown TO
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxCrosstown TO
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCrosstown TO
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfCrosstown TO
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCrosstown TO
 

More from Crosstown TO (20)

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
 

Recently uploaded

Madurai Call Girls 7001305949 WhatsApp Number 24x7 Best Services
Madurai Call Girls 7001305949 WhatsApp Number 24x7 Best ServicesMadurai Call Girls 7001305949 WhatsApp Number 24x7 Best Services
Madurai Call Girls 7001305949 WhatsApp Number 24x7 Best Servicesnajka9823
 
call girls in moti bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in moti bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in moti bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in moti bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️saminamagar
 
How to design healthy team dynamics to deliver successful digital projects.pptx
How to design healthy team dynamics to deliver successful digital projects.pptxHow to design healthy team dynamics to deliver successful digital projects.pptx
How to design healthy team dynamics to deliver successful digital projects.pptxTechSoupConnectLondo
 
Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...
Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...
Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...narwatsonia7
 
High-Level Thematic Event on Tourism - SUSTAINABILITY WEEK 2024- United Natio...
High-Level Thematic Event on Tourism - SUSTAINABILITY WEEK 2024- United Natio...High-Level Thematic Event on Tourism - SUSTAINABILITY WEEK 2024- United Natio...
High-Level Thematic Event on Tourism - SUSTAINABILITY WEEK 2024- United Natio...Christina Parmionova
 
2024: The FAR, Federal Acquisition Regulations - Part 25
2024: The FAR, Federal Acquisition Regulations - Part 252024: The FAR, Federal Acquisition Regulations - Part 25
2024: The FAR, Federal Acquisition Regulations - Part 25JSchaus & Associates
 
IFA system in MES and diffucultiess.pptx
IFA system in MES and diffucultiess.pptxIFA system in MES and diffucultiess.pptx
IFA system in MES and diffucultiess.pptxSauravAnand68
 
history of 1935 philippine constitution.pptx
history of 1935 philippine constitution.pptxhistory of 1935 philippine constitution.pptx
history of 1935 philippine constitution.pptxhellokittymaearciaga
 
Enhancing Indigenous Peoples' right to self-determination in the context of t...
Enhancing Indigenous Peoples' right to self-determination in the context of t...Enhancing Indigenous Peoples' right to self-determination in the context of t...
Enhancing Indigenous Peoples' right to self-determination in the context of t...Christina Parmionova
 
办理约克大学毕业证成绩单|购买加拿大文凭证书
办理约克大学毕业证成绩单|购买加拿大文凭证书办理约克大学毕业证成绩单|购买加拿大文凭证书
办理约克大学毕业证成绩单|购买加拿大文凭证书zdzoqco
 
Start Donating your Old Clothes to Poor People
Start Donating your Old Clothes to Poor PeopleStart Donating your Old Clothes to Poor People
Start Donating your Old Clothes to Poor PeopleSERUDS INDIA
 
call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️saminamagar
 
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urges
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual UrgesCall Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urges
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urgesnarwatsonia7
 
call girls in Mehrauli DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Mehrauli  DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Mehrauli  DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Mehrauli DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️saminamagar
 
Panet vs.Plastics - Earth Day 2024 - 22 APRIL
Panet vs.Plastics - Earth Day 2024 - 22 APRILPanet vs.Plastics - Earth Day 2024 - 22 APRIL
Panet vs.Plastics - Earth Day 2024 - 22 APRILChristina Parmionova
 
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...narwatsonia7
 
No.1 Call Girls in Basavanagudi ! 7001305949 ₹2999 Only and Free Hotel Delive...
No.1 Call Girls in Basavanagudi ! 7001305949 ₹2999 Only and Free Hotel Delive...No.1 Call Girls in Basavanagudi ! 7001305949 ₹2999 Only and Free Hotel Delive...
No.1 Call Girls in Basavanagudi ! 7001305949 ₹2999 Only and Free Hotel Delive...narwatsonia7
 
Premium Call Girls Btm Layout - 7001305949 Escorts Service with Real Photos a...
Premium Call Girls Btm Layout - 7001305949 Escorts Service with Real Photos a...Premium Call Girls Btm Layout - 7001305949 Escorts Service with Real Photos a...
Premium Call Girls Btm Layout - 7001305949 Escorts Service with Real Photos a...narwatsonia7
 

Recently uploaded (20)

Madurai Call Girls 7001305949 WhatsApp Number 24x7 Best Services
Madurai Call Girls 7001305949 WhatsApp Number 24x7 Best ServicesMadurai Call Girls 7001305949 WhatsApp Number 24x7 Best Services
Madurai Call Girls 7001305949 WhatsApp Number 24x7 Best Services
 
call girls in moti bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in moti bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in moti bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in moti bagh DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
 
How to design healthy team dynamics to deliver successful digital projects.pptx
How to design healthy team dynamics to deliver successful digital projects.pptxHow to design healthy team dynamics to deliver successful digital projects.pptx
How to design healthy team dynamics to deliver successful digital projects.pptx
 
Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...
Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...
Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...
 
High-Level Thematic Event on Tourism - SUSTAINABILITY WEEK 2024- United Natio...
High-Level Thematic Event on Tourism - SUSTAINABILITY WEEK 2024- United Natio...High-Level Thematic Event on Tourism - SUSTAINABILITY WEEK 2024- United Natio...
High-Level Thematic Event on Tourism - SUSTAINABILITY WEEK 2024- United Natio...
 
2024: The FAR, Federal Acquisition Regulations - Part 25
2024: The FAR, Federal Acquisition Regulations - Part 252024: The FAR, Federal Acquisition Regulations - Part 25
2024: The FAR, Federal Acquisition Regulations - Part 25
 
IFA system in MES and diffucultiess.pptx
IFA system in MES and diffucultiess.pptxIFA system in MES and diffucultiess.pptx
IFA system in MES and diffucultiess.pptx
 
history of 1935 philippine constitution.pptx
history of 1935 philippine constitution.pptxhistory of 1935 philippine constitution.pptx
history of 1935 philippine constitution.pptx
 
Enhancing Indigenous Peoples' right to self-determination in the context of t...
Enhancing Indigenous Peoples' right to self-determination in the context of t...Enhancing Indigenous Peoples' right to self-determination in the context of t...
Enhancing Indigenous Peoples' right to self-determination in the context of t...
 
办理约克大学毕业证成绩单|购买加拿大文凭证书
办理约克大学毕业证成绩单|购买加拿大文凭证书办理约克大学毕业证成绩单|购买加拿大文凭证书
办理约克大学毕业证成绩单|购买加拿大文凭证书
 
Start Donating your Old Clothes to Poor People
Start Donating your Old Clothes to Poor PeopleStart Donating your Old Clothes to Poor People
Start Donating your Old Clothes to Poor People
 
call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Narela DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
 
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urges
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual UrgesCall Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urges
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urges
 
Hot Sexy call girls in Palam Vihar🔝 9953056974 🔝 escort Service
Hot Sexy call girls in Palam Vihar🔝 9953056974 🔝 escort ServiceHot Sexy call girls in Palam Vihar🔝 9953056974 🔝 escort Service
Hot Sexy call girls in Palam Vihar🔝 9953056974 🔝 escort Service
 
call girls in Mehrauli DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Mehrauli  DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️call girls in Mehrauli  DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
call girls in Mehrauli DELHI 🔝 >༒9540349809 🔝 genuine Escort Service 🔝✔️✔️
 
Panet vs.Plastics - Earth Day 2024 - 22 APRIL
Panet vs.Plastics - Earth Day 2024 - 22 APRILPanet vs.Plastics - Earth Day 2024 - 22 APRIL
Panet vs.Plastics - Earth Day 2024 - 22 APRIL
 
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
 
9953330565 Low Rate Call Girls In Adarsh Nagar Delhi NCR
9953330565 Low Rate Call Girls In Adarsh Nagar Delhi NCR9953330565 Low Rate Call Girls In Adarsh Nagar Delhi NCR
9953330565 Low Rate Call Girls In Adarsh Nagar Delhi NCR
 
No.1 Call Girls in Basavanagudi ! 7001305949 ₹2999 Only and Free Hotel Delive...
No.1 Call Girls in Basavanagudi ! 7001305949 ₹2999 Only and Free Hotel Delive...No.1 Call Girls in Basavanagudi ! 7001305949 ₹2999 Only and Free Hotel Delive...
No.1 Call Girls in Basavanagudi ! 7001305949 ₹2999 Only and Free Hotel Delive...
 
Premium Call Girls Btm Layout - 7001305949 Escorts Service with Real Photos a...
Premium Call Girls Btm Layout - 7001305949 Escorts Service with Real Photos a...Premium Call Girls Btm Layout - 7001305949 Escorts Service with Real Photos a...
Premium Call Girls Btm Layout - 7001305949 Escorts Service with Real Photos a...
 

Brentcliffe-Victoria Park CLC Meeting

  • 1. September 2, 2021 Eglinton Crosstown LRT Construction Liaison Meeting Brentcliffe Road to Victoria Park Avenue
  • 2. Section One At-Grade: Brentcliffe Portal to Sunnybrook Park Stop
  • 3. SECTION ONE AT-GRADE UPDATE 3 Activity Location Approx. Date & Duration Vehicle Testing Brentcliffe – Kennedy Ongoing through December 2021 Road Restoration Brentcliffe – Kennedy August 2021 – Fall 2021 Noise Barrier and Soil Nail Wall removal Brentcliffe intersection – SE side Fall 2021 Landscaping along Eglinton Brentcliffe – Kennedy Fall 2021 Brentcliffe Retaining Wall construction North side of Eglinton Ave, east of Brentcliffe Rd Ongoing through September 2021 • Platform ramps & curbs • Electrical finishes Sunnybrook Park Stop Ongoing through Summer 2021 • Multi-use path construction: backfill and compaction • Landscaping works Serena Gundy Park – West of Leslie St. • Completed August 2021 • Fall 2021 Concrete and road works Don Mills Rd & Eglinton Ave E Ongoing through 2021
  • 4. EAST TESTING & COMMISSIONING 4 • On May 25, 26, 27, 31 and June 1 and 2, 6 light rail vehicles (LRVs) were delivered to the east end of the alignment. • Testing and commissioning activities will be conducted between Brentcliffe Road and Kennedy Road through December 2021. • Dynamic Testing began August 24, 2021, and will last for approximately six weeks. • The LRVs will run mainly on the surface along a track in the center of Eglinton Avenue.
  • 5. RETAINING WALL CONSTRUCTION NORTH SIDE OF EGLINTON AVENUE EAST OF BRENTCLIFFE ROAD 5 • This retaining wall is required to hold the embankment created from the widened Eglinton Ave. • Retaining wall construction continues and is expected to be complete in late September 2021 • Monitoring of the slope continues and there have been no recent issues with the movement. Residents on Thursfield Crescent have full use of their backyards. • The City provided revised comments on the restoration design and approved planting trees in soil depths that are less than the by-law requirements, which means trees will be included in the restoration plan. • CTS reviewed and incorporated the City’s comments; the final restoration plan has been approved the City. • CTS has shared the restoration plan with Elected Officials and Thursfield residents. • CTS expects to begin the restoration works in Fall 2021.
  • 6. FINAL ROAD RESTORATION BRENTCLIFFE – KENNEDY 6 • Final Road Restoration works began in August 2021 and will last through Fall 2021 • The approximate timeline for road restoration of the At-Grade is: o August 2 – August 8, 2021: Aga Khan – Wynford o August 30 – September 2, 2021: Swift – VP o September TBC: Eglinton Square and Victoria Park intersections o September 8 – September 11, 2021: Eglinton Square - Warden o September & October 2021: Pharmacy – Ionview o Fall TBC: Ionview - Kennedy o Fall TBC : Leslie – Aga Khan • More specific details regarding the dates and locations of road restoration works will be communicated to the public as they become available
  • 7. NOISE BARRIER WALL AND SOIL NAIL WALL REMOVAL 7 • The noise barrier and soil nail walls, located on the south side of Eglinton Avenue East, east of Brentcliffe Rd., were erected in 2014 to facilitate the construction of the east portal. • As early as Fall 2021, CTS will begin removing the noise barrier wall and exposed segment of the soil nail wall. This work is expected to last approximately one (1) month • More detailed information about this work will be communicated to the residents before the work begins.
  • 8. RAMP CONSTRUCTION, WEST OF LESLIE STREET MULTI-USE PATH CONNECTING EGLINTON AVE E TO SERENA GUNDY PARK 8 • Excavation work is complete • Final backfilling activities were completed August 2021 • Installation of topsoil, sodding, and landscaping works will take place in Fall 2021as part of the final restoration plan Landscaping through Fall 2021
  • 9. CONSTRUCTION PROGRESS PHOTOS 9 INSTALLATION AND SLOPE BRENTCLIFFE RETAINING WALL EDGE TILE INSTALLATION SUNNYBROOK PARK STOP
  • 11. SCIENCE CENTRE STATION UPDATE 11 Activity Location Approx. Date & Duration Vehicle Testing Brentcliffe – Kennedy Ongoing through December 2021 Road Restoration Brentcliffe – Kennedy August 2021 – Fall 2021 Landscaping Bus Terminal – north side Completed August 2021 Finishing Activities: • Floor tiling, ceiling grid & tile installation, mechanical and electrical finishes, handrail installation Station Box Ongoing through Fall 2021 Finishing Activities: • Wall & floor tiling, ceiling grid & tile installation, electrical finishes, sliding door finishes, canopy Installation • Bike storage Bus Terminal Ongoing through Fall 2021 Finishing Activities: • Floor tiling, ceiling grid & tile installation, electrical finishes, sliding door finishes Main Entrance Ongoing through Fall 2021
  • 12. EAST TESTING & COMMISSIONING 12 • On May 25, 26, 27, 31 and June 1 and 2, 6 light rail vehicles (LRVs) were delivered to the east end of the alignment. • Testing and commissioning activities will be conducted between Brentcliffe Road and Kennedy Road through December 2021. • Dynamic Testing began August 24, 2021, and will last for approximately six weeks. • The LRVs will run mainly on the surface along a track in the center of Eglinton Avenue.
  • 13. SCIENCE CENTRE TRAFFIC CONFIGURATION 13 August 2021
  • 14. CONSTRUCTION PROGRESS PHOTOS 14 BIKE STORAGE BUS TERMINAL LANDSCAPING BUS TERMINAL – NORTH SIDE
  • 15. Section Two At-Grade Aga Khan Park & Museum Stop to O’Connor Stop
  • 16. SECTION TWO AT-GRADE UPDATE 16 Activity Location Approx. Date & Duration Vehicle Testing Brentcliffe – Kennedy Ongoing through December 2021 Road Restoration Brentcliffe – Kennedy August 2021 – Fall 2021 Road Restoration Aga Khan – Wynford Completed August 2021 • Milling • Final Paving Swift – Victoria Park • Completed August 2021 • Completed September 2, 2021 • Final Paving Eglinton Square and Victoria Park intersections • September 2021 Landscaping along Eglinton Brentcliffe – Kennedy Fall 2021 • Platform ramps & curbs • Electrical finishes Aga Khan Park & Museum Stop • Ongoing through Summer 2021 • • Platform ramps & curbs • Electrical finishes Sloane Stop • Ongoing through Summer 2021 • • Platform ramps & curbs • Electrical finishes O’Connor Stop • Ongoing through Summer 2021 •
  • 17. EAST TESTING & COMMISSIONING 17 • On May 25, 26, 27, 31 and June 1 and 2, 6 light rail vehicles (LRVs) were delivered to the east end of the alignment. • Testing and commissioning activities will be conducted between Brentcliffe Road and Kennedy Road through December 2021. • Dynamic Testing began August 24, 2021, and will last for approximately six weeks. • The LRVs will run mainly on the surface along a track in the center of Eglinton Avenue.
  • 18. FINAL ROAD RESTORATION BRENTCLIFFE – KENNEDY 18 • Final Road Restoration works began in August 2021 and will last through Fall 2021 • The approximate timeline for road restoration of the At-Grade is: o August 2 – August 8, 2021: Aga Khan – Wynford o August 30 – September 2, 2021: Swift – VP o September TBC: Eglinton Square and Victoria Park intersections o September 8 – September 11, 2021: Eglinton Square - Warden o September & October 2021: Pharmacy – Ionview o Fall TBC: Ionview - Kennedy o Fall TBC : Leslie – Aga Khan • More specific details regarding the dates and locations of road restoration works will be communicated to the public as they become available
  • 19. CONSTRUCTION PROGRESS PHOTOS 19 FINAL ROAD PAVING AGA KHAN - WYNFORD FINAL ROAD PAVING & LINE PAINTING AGA KHAN - WYNFORD