The document provides an update on construction progress for the Crosstown LRT project in September 2019. Work continued on guideway construction and intersections between Victoria Park and Ionview. Traction power substations 11 and 12 were under construction. Culvert reconstruction at Massey Creek was ongoing and expected to last 9 months. At Kennedy Station, excavation and underground work was progressing on the portals, station box, and areas east of GO Transit. Sidewalk closures and traffic configurations at Kennedy were also outlined.