Brentcliffe - Victoria Park Construction Liaison Committee Meeting

4,470 views

Published on

The construction liaison committee meeting of Brentcliffe - Victoria Park for November 1, 2018. You can see the presentation here:

Published in: Government & Nonprofit
  • Be the first to comment

  • Be the first to like this

Brentcliffe - Victoria Park Construction Liaison Committee Meeting

  1. 1. CROSSTOWN LRT CLC Meeting Brentcliffe to Victoria Park Stop November 2018
  2. 2. 2 Section 1 At-Grade Updates Brentcliffe Portal to Sunnybrook Park Stop
  3. 3. 3 Upcoming Construction Activities Activities Area & Impacts Duration Tentative Date Eglinton Avenue East between Brentcliffe Road and Leslie Street (see map on next page) • Eastbound and westbound traffic will be rerouted to a temporary road south of the construction zone to accommodate the continued construction of the Brentcliffe Portal. • Traffic will continue to be one lane in each direction. • The pedestrian sidewalk will be available on the south side of Eglington Avenue East only. Approx. 6 months Mid- November Celestica Bridge New traffic configuration Approx. 4 months Mid- November
  4. 4. 4 Brentcliffe Portal – Traffic Change . • Road work is underway southeast of the portal to prepare for upcoming traffic change. • Upcoming traffic change planned for mid-November 2018 • Traffic will be shifted to the south side of Eglinton Avenue, otherwise all other traffic movements and lane allowance remain the same.
  5. 5. 5 Ongoing Construction Activities Activities Area & Impacts Duration Tentative Date Celestica Bridge • New traffic configuration to be implemented mid-November • Lane reductions between Leslie Street and Don Mills Road 3-4 months Underway as of mid- August Telecommunications relocation work in the Leslie area • Work is to prepare for future Sunnybrook Park stop • Work crews along Eglinton between east of Brentcliffe Road and Leslie Street Ongoing Underway until late 2018 Watermain relocation east of Leslie • Construction zone at north east corner of Eglinton Ave East and Leslie Street intersection Approx. 4 weeks * Some overnight works Underway as of late October 2018 Green Wall (retaining wall) construction at E.T. Seton Park • Staircase removed while this work takes place. • Access from Eglinton Avenue East remains temporarily closed 4-5 months Underway since August 2018
  6. 6. 6 Brentcliffe Portal – Progress Ongoing activities within the construction zone include: • Forming, pouring concrete and placing rebar for the north and south walls and at the west headwall is ongoing • Duct banks works ongoing inside the tunnel • Forming and rebar installation on the roof slab is ongoing Progress at the headwall Duct Bank Works
  7. 7. 7 Brentcliffe Portal – Progress . Roadway works Headwall Waterproofing Backfill on top roof areas
  8. 8. 8 Science Centre Updates
  9. 9. 9 Science Centre Station Construction Activities SOE & Excavation • Excavation, tie backs and bracing continue in the station box area and east portal • Support of existing utilities at pedestrian tunnel, station box and east portal ongoing until November • Bulk excavation continues under the decking, at the pedestrian tunnel and at the west side of the bus terminal Utilities • Utility support work is on going Structural • Concrete and rebar work underway at main entrance • Strut installation is ongoing at the Pedestrian Tunnel • Form and concrete work underway at the bus terminal • Form work for the electrical/mechanical and condenser pit walls is ongoing • Rebar installation on the roof slab is in progress • Formwork installation is complete for the north inner wall • Footings rebar between the gridline is in progress and the mud slab was poured
  10. 10. 10 Current Traffic Configuration at Science Centre Station The current traffic configuration at Science Centre Station was implemented October 17,2018. This phase is expected to last (4) months. The north-south crosswalk on the east side of the intersection will be reopen for the duration of this set up.
  11. 11. 11 Science Centre Station - Progress Strut Installation at the Pedestrian Tunnel Station box Rebar Installation
  12. 12. 12 Science Centre Station - Progress Elevator Walls at the Main Entrance Formwork Installation
  13. 13. 13 Section 2 At-Grade Updates Aga Khan Park & Museum Stop to O’Connor Stop
  14. 14. 14 Upcoming Construction Activities Activities Area & Impacts Duration Tentative Date Traffic Changes for utilities works and rehabilitation of the Wynford Drive Bridge • Don Valley Parkway Ramp to Wynford Drive Bridge • Existing work zone will shift to the south side of the bridge (currently on north side). Approx. 6 months As soon as November 4 Road Reconstruction at Swift and Credit Union Drive Approx. 6 weeks As soon as November 10 Traffic change at East Don River Bridge Approx. 6 months As soon as November 15 Don Valley Parkway West Intersection - Storm Work and Road Reconstruction TBD TBD Wilson Brooke Culvert: Watermain, Sanitary and Storm Sewer Work • Construction zone will shift to south side (currently on north side) Approx. 4 months Mid- December
  15. 15. 15 Section 2 At-Grade – Traffic Change Don Valley Parkway Ramp to Wynford Drive Bridge
  16. 16. 16 • The sidewalk on the south side of Eglinton Avenue East between the Don Valley South Off-Ramp and Wynford Drive will be closed for the duration of the work to protect the safety of pedestrians. • The pedestrian staircase on the south side of the Wynford Drive Bridge will also be closed for the duration of the work. • Pedestrians will be required to use the Don Mills Intersection, the Don Valley Parkway East intersection or temporary crossing east of Wynford Drive to cross Eglington Avenue East. • The eastbound TTC bus stop located on southwest side of the Wynford Bridge will be removed for the duration of the work. Section 2 At-Grade – Wynford Drive Bridge
  17. 17. 17 Ongoing Construction Activities Activities Area & Impacts Duration Tentative Date Wilson Brook Culvert Work • Continues East of future Sloane Stop • Work zone in place on the south and north side of Eglinton in front of 1730 Eglinton Avenue East Approx. 4 months Underway as of mid- August 2018 Wynford Drive Bridge & East Don River Bridge • Bridge rehabilitation works on the north side of Eglinton, traffic shifted south Approx. 3 - 4 months (north side) Underway as of July 2018 Overnight watermain, storm and sanitary relocation at Swift Drive • Lane reductions and turn restrictions during overnight work • North-south crosswalk on the east side of Eglinton Avenue East and Swift Drive intersection will be closed during works Approx. 2-3 weeks Underway as of late October 2018
  18. 18. 18 Section 2 At-Grade – Progress . East Don River Bridge Widening In Progress

×