  1. 1. November 24, 2020 Eglinton Crosstown LRT Construction Liaison Committee Victoria Park Avenue to Kennedy Station
  2. 2. Section Three and Four At-Grade: O’Connor Stop to Ionview Stop
  3. 3. CONSTRUCTION ACTIVITIES 3 Location Activity Approx. Date & Duration O’Connor Stop • Concrete work and formwork installation for ramps and curbs • Sidewalk construction at 4 corners of Eglinton Square intersection Ongoing through to late November 2020 November 23, 2020 for two weeks Pharmacy Stop • Sidewalk construction at four corners of the intersection Complete Hakimi Lebovic Stop • Roadworks and sidewalk construction at east side of intersection November 23 for one week Golden Mile Stop • Concrete works for stop ramps November – Mid December 2020 Birchmount Stop • Track works November – Mid December 2020 Rosemount Drive • Massey Creek Culvert: Fill old culvert and build west wing wall. • Concrete works, west of Rosemount Drive, sidewalk construction (north side) November – Mid December 2020 Ionview Stop • Formwork and concrete for stop ramps and curbs • Stop shelter installation Ongoing through to early December 2020 Early December 2020 for one week
  4. 4. SIDEWALK CONSTRUCTION – EGLINTON SQUARE 4 November 23, 2020 November 30, 2020 • Crews will be constructing final sidewalks at the four corners of the Eglinton Ave E and Eglinton Square intersection • Closure of one eastbound and westbound lane at the intersection. • Closure of the northbound lane at the intersection for construction activities on the east side. • Closure of one southbound lane at the intersection for construction activities on the west side. • The east crosswalk will be closed while crews are working on the east side. • All crosswalks will be open while crews work on the west side.
  5. 5. SIDEWALK CONSTRUCTION – HAKIMI AND LEBOVIC AVE AT EGLINTON AVE E EAST SIDE 5 November 18 – November 27, 2020 • Crews will be constructing final sidewalks at the four corners of the Eglinton Ave E and Hakimi Lebovic Ave intersection. Work on the east side will take place November 18 – November 27, 2020 • The Eglinton Ave driveways for 1910 and 1920 Eglinton Ave E will be closed for one week. Alternate driveways will remain accessible on Hakimi Ave and Eglinton Ave E for the duration of the works. • Closure of one eastbound and westbound lane at the intersection. • Closure of one northbound lane at the intersection for construction activities on the east side of the intersection.
  6. 6. ROSEMOUNT DRIVE AND EGLINTON AVE E 6 Early January – Late December 2020 • North side closure for Massey Creek Construction • Crews will fill the old culvert and then construct the west wing wall MASSEY CREEK ROOF SLAB CONSTRUCTION IS NOW COMPLETE
  7. 7. CONSTRUCTION PROGRESS PHOTOS 7 SIDEWALK CONSTRUCTION AT HAKIMI LEBOVIC INTERSECTION TRACK WORK WEST OF BIRCHMOUNT GUARDRAIL INSTALLATION COMPLETE AT BIRCHMOUTN STOP
  8. 8. Kennedy Station
  9. 9. KENNEDY STATION UPDATE 9 Location Activity Approx. Date & Duration Kennedy Station Main Entrance • Concrete and masonry works • Conduit installation, plumbing and sheet metal works, tiling, masonry works • Structural steel and decking • Elevator installation and painting Ongoing through to late 2020 Kennedy Station – East of GO • Concrete works • Electrical and mechanical works Ongoing through to late 2020 Kennedy Station Concourse Level • Excavation and waterproofing • Concrete works, rebar and shoring Ongoing through to late 2020 Kennedy Portal (west of Kennedy Road) • Railing installation • Installation of light fixtures • Track works Ongoing through to late 2020 Kennedy Station Go Platform • Curtain wall and glazing • Excavation for new east platform • Installation of metal railing • Roofing at GO shelters, painting of shelter and railing • Mechanical and electrical works Ongoing through to late 2020
  10. 10. CURRENT TRAFFIC CONFIGURATION EGLINTON AVENUE EAST AND KENNEDY ROAD INTERSECTION 10 • Crews will be performing road works within the four corners of the Eglinton Ave East and Kennedy Road intersection. • A shared through and right turn lane will be implemented for northbound and southbound traffic at the intersection. • Periodic crosswalk closures will be required to complete the work. A minimum of three crosswalks will be maintained all times. Signage will be installed directing pedestrians to available crosswalks. Mid July – Early December 2020
  11. 11. TRAFFIC CHANGE AT KENNEDY STATION, EAST OF KENNEDY ROAD EARLY DECEMBER 2020 FOR 9 MONTHS 11 Traffic Details:  Vehicles entering Transway Crescent will not be permitted beyond the Kennedy Station Passenger Pick- Up and south parking lot access points.  Signal timing will be changed at Kennedy Road as well as the North and South Service Road to accommodate these changes.  Right turn from eastbound lane on Eglinton and left turn from westbound lane on Eglinton onto South Service Rd will be prohibited.  Left turn from eastbound lane on Eglinton onto North Service Rd will be prohibited.  Traffic entering South Service Road will be restricted to TTC vehicles only.
  12. 12. GO WEST PLATFORM RELOCATION AND PEDESTRIAN DETOUR KENNEDY STATION AUGUST 17, 2020 12 • As part of GO Transit improvements at Kennedy GO Station, crews at Kennedy Station will be temporarily relocating the west GO Transit platform as early as August 17, 2020. • Pedestrians will be rerouted through the Kennedy TTC Station • This configuration will remain in place for approximately one year.
  13. 13. CONSTRUCTION PROGRESS PHOTOS 13 MAIN ENTRANCE ESCALATOR AND ELEVATOR INSTALLATION AND BUILD PAINTING STRUCTURAL STEEL AT MAIN ENTRANCE

×