SlideShare a Scribd company logo
Eglinton Crosstown LRT
MX/CTS Construction Liaison
Committee
November 26th, 2019
O’Connor Stop to Ionview Stop
Victoria Park Ave to Ionview Rd
Completed Works
 Westbound left turn removal at Pharmacy and Eglinton –
Jun 2019
 Westbound left turn removal at Victoria Park Ave – Oct
2019
 Westbound left turn removal at Birchmount Rd – Nov 13
 Intersection guideway construction at Victoria Park,
Pharmacy, Hakimi Lebovic, Warden, Birchmount and
Ionview
3
Victoria Park Avenue to Birchmount Road Look
Ahead
4
ACTIVITY LOCATION APPROX. DATE AND DURATION
Stop Construction and Track
Installation
Eglinton Ave E b/w Victoria Park Ave
and Pharmacy Ave
Underway through spring 2020
Stop Construction and Track
Installation
Eglinton Ave E b/w Pharmacy Ave
and Hakimi Lebovic Ave
Underway through spring 2020
Stop Construction and Track
Installation
Eglinton Ave E b/w Hakimi Lebovic
Ave and Warden Ave
Underway through spring 2020
Midblock Guideway, Stop
Construction and Track Installation
Eglinton Ave E b/w Warden Ave and
Birchmount Rd
Underway through spring 2020
Midblock Guideway, Stop
Construction and Track Installation
Eglinton Ave E b/w Birchmount Rd
and Ionview Rd
Underway through spring 2020
Road Work Eglinton Ave E b/w Ionview Rd and
Kennedy Rd
Starts spring 2020
Victoria Park Avenue to Birchmount Road Look
Ahead (cont’d)
5
ACTIVITY LOCATION APPROX. DATE AND DURATION
Intersection Guideway Construction SB Rosemount Dr at Eglinton Ave E
Nov 3, 2019 for approximately six (6)
weeks
TPSS 11 Delivery Warden Ave and Eglinton Ave E Mon Nov 25 – Fri Nov 29, 2019
Temporary Lane Closures for Utility
Relocation Victoria Park Ave at Eglinton Ave E Nov 27 & 28
Traffic Flip
Rosemount Dr at Eglinton Ave E
Intersection
Sat Nov 30, 2019
Traffic Flip Intersection Opens
Rosemount Dr at Eglinton Ave E
Mon Dec 16, 2019 – Jan 2
Eastbound Left Lane Turn Removal Birchmount Rd and Eglinton Ave E Mon Dec 16, 2019
Southbound Road Closure
Massey Creek (Rosemount Dr at
Eglinton Ave E)
Thu Jan 2, 2019
Northbound and Southbound Left Turn
Removals
Pharmacy Ave and Eglinton Ave E Spring 2020
6
Current Traffic Configuration: Victoria Park to Birchmount
Road
Permanent Left Turn Lane Removals
7
What to Expect - Guideway and Stop Construction
Eglinton Ave E from Victoria Park Ave to Birchmount Rd
Traffic and Pedestrian Impacts
• Daily temporary lane closures
• Periodic sidewalk and crosswalk closures
• Noise from construction equipment, generators and vehicles
• Nearby businesses and residents can expect noise from excavation, bobcats, trucks and other construction
equipment as well as site lighting
• A minimum of one lane of eastbound and westbound through traffic will be maintained during this work
Hours of Work
• Construction will take place between the hours of 7:00 a.m. and 11:00 p.m.
• The contractor may not always work during the permitted hours but may do so at its discretion.
• Work may be rescheduled due to weather conditions or unforeseen circumstances.
• Emergency services access will be maintained.
8
9
December 16 – The eastbound
and westbound left turn will be
prohibited at Birchmount Road
permanently. Left turns are
available at nearby streets
including Warden Ave and
Kennedy Rd.
November 13 – The westbound left
turn will be prohibited at Birchmount
Road permanently. Left turns are
available at nearby streets including
Warden Ave and Kennedy Rd.
Birchmount Road – Left Turn Removals
10
Current Traffic Configuration: Rosemount Dr and Eglinton
Ave E
Sunday, November 3, 2019 for approximately six (6)
weeks
Upcoming Traffic Configuration: Rosemount Dr and Eglinton Ave E –
Nov 30
11
• Rosemount Drive north of Eglinton Avenue East will remain closed, local access will be
maintained south bound traffic will be diverted north
• Westbound traffic will be shifted north of the work zone on Eglinton Avenue East
• Left turns are prohibited at the intersection in all directions
• North-south through traffic on Rosemount Drive will be prohibited, north bound traffic
must turn right
Upcoming Traffic Configuration: Rosemount Dr and Eglinton Ave E
– Dec 16
12
Upcoming Traffic Configuration: Rosemount Dr and Eglinton Ave E –
Jan 2
13
14
Track installation from Pharmacy to
Hakimi Lebovic
Victoria Park Avenue
Victoria Park to Birchmount Road - Progress Photos
East At-Grade – Progress Photos
Massey Creek Culvert
Rosemount Intersection
Kennedy Station
Kennedy Station:
GO Transit Improvements
17
Kennedy Station Look Ahead
ACTIVITY LOCATION
APPROX. DATE AND
DURATION
 Portal Excavation, lagging and tie backs
 The west portal was completed ahead of schedule
 East of GO excavation, lagging and tie backs
Kennedy Station Complete
Backfilling and Road Restoration
Kennedy Rd and Eglinton
Ave E
Completed Nov. 25
Traffic Configuration Change
Kennedy Rd and Eglinton
Ave E
As early as November
30, 2019
• Dewatering activities
• Support of excavation
• Underground mechanical and electrical works
• Waterproofing
• Bulk excavation work
Kennedy Station - Main
Station Box
Underway through late
2019
Underpinning of TTC Infrastructure Kennedy Station - SRT
Underway through late
2019
Concrete, Electrical and Mechanical Works
Kennedy Station – East of
GO
Underway through early
2020
Backfilling and Installation of Structural Streel
Kennedy Station – West
Portal and GO platform
Underway through early
2020
Current Traffic Configuration: Kennedy
Station
19
Current Traffic Configuration: Kennedy
Station
20
21
Current Traffic Configuration: Kennedy Rd and Eglinton
Ave E
Until November 30, 2019
Upcoming Traffic Configuration: Kennedy Rd and Eglinton
Ave E
As early as November 30, 2019
Kennedy Station- Progress Photos
East Portal
Main Entrance Waterproofing Portal

More Related Content

What's hot

Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019
Crosstown TO
 
Eglinton & Mt pleasant CLC - November
Eglinton & Mt pleasant CLC - November Eglinton & Mt pleasant CLC - November
Eglinton & Mt pleasant CLC - November
Crosstown TO
 
Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting
Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: January 6, 2021
Avenue & Chaplin CLC - Construction Update: January 6, 2021Avenue & Chaplin CLC - Construction Update: January 6, 2021
Avenue & Chaplin CLC - Construction Update: January 6, 2021
Crosstown TO
 
Pharmacy to Kennedy CLC meeting
Pharmacy to Kennedy  CLC meetingPharmacy to Kennedy  CLC meeting
Pharmacy to Kennedy CLC meeting
Crosstown TO
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
Crosstown TO
 
Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021
Brentcliffe to Victoria Park CLC Meeting -  Presentation - November 4, 2021 Brentcliffe to Victoria Park CLC Meeting -  Presentation - November 4, 2021
Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021
Crosstown TO
 
Cedarvale & Forest Hill Construction Update (January 2022)
Cedarvale & Forest Hill Construction Update (January 2022)Cedarvale & Forest Hill Construction Update (January 2022)
Cedarvale & Forest Hill Construction Update (January 2022)
Crosstown TO
 
Eglinton-Mt Pleasant Construction Liaison Committee July 8, 2020
Eglinton-Mt Pleasant Construction Liaison Committee July 8, 2020Eglinton-Mt Pleasant Construction Liaison Committee July 8, 2020
Eglinton-Mt Pleasant Construction Liaison Committee July 8, 2020
Crosstown TO
 
CLC Pharmacy to Kennedy - January 25, 2022
CLC Pharmacy to Kennedy - January 25, 2022 CLC Pharmacy to Kennedy - January 25, 2022
CLC Pharmacy to Kennedy - January 25, 2022
Crosstown TO
 
Chaplin & Avenue Construction Liaison Committee Meeting
Chaplin & Avenue Construction Liaison Committee MeetingChaplin & Avenue Construction Liaison Committee Meeting
Chaplin & Avenue Construction Liaison Committee Meeting
Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: May 6, 2020
Avenue & Chaplin CLC - Construction Update: May 6, 2020Avenue & Chaplin CLC - Construction Update: May 6, 2020
Avenue & Chaplin CLC - Construction Update: May 6, 2020
Crosstown TO
 
Fall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue StationsFall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue Stations
Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020
Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021
Crosstown TO
 
Eastern Works Open House
Eastern Works Open House Eastern Works Open House
Eastern Works Open House
Crosstown TO
 
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptxCLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
Crosstown TO
 
Central Eastern Works Open House - October 2019
Central Eastern Works Open House - October 2019Central Eastern Works Open House - October 2019
Central Eastern Works Open House - October 2019
Crosstown TO
 
Western works final
Western works final Western works final
Western works final
Crosstown TO
 

What's hot (20)

Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019
 
Eglinton & Mt pleasant CLC - November
Eglinton & Mt pleasant CLC - November Eglinton & Mt pleasant CLC - November
Eglinton & Mt pleasant CLC - November
 
Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
 
Avenue & Chaplin CLC - Construction Update: January 6, 2021
Avenue & Chaplin CLC - Construction Update: January 6, 2021Avenue & Chaplin CLC - Construction Update: January 6, 2021
Avenue & Chaplin CLC - Construction Update: January 6, 2021
 
Pharmacy to Kennedy CLC meeting
Pharmacy to Kennedy  CLC meetingPharmacy to Kennedy  CLC meeting
Pharmacy to Kennedy CLC meeting
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 
Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021
Brentcliffe to Victoria Park CLC Meeting -  Presentation - November 4, 2021 Brentcliffe to Victoria Park CLC Meeting -  Presentation - November 4, 2021
Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021
 
Cedarvale & Forest Hill Construction Update (January 2022)
Cedarvale & Forest Hill Construction Update (January 2022)Cedarvale & Forest Hill Construction Update (January 2022)
Cedarvale & Forest Hill Construction Update (January 2022)
 
Eglinton-Mt Pleasant Construction Liaison Committee July 8, 2020
Eglinton-Mt Pleasant Construction Liaison Committee July 8, 2020Eglinton-Mt Pleasant Construction Liaison Committee July 8, 2020
Eglinton-Mt Pleasant Construction Liaison Committee July 8, 2020
 
CLC Pharmacy to Kennedy - January 25, 2022
CLC Pharmacy to Kennedy - January 25, 2022 CLC Pharmacy to Kennedy - January 25, 2022
CLC Pharmacy to Kennedy - January 25, 2022
 
Chaplin & Avenue Construction Liaison Committee Meeting
Chaplin & Avenue Construction Liaison Committee MeetingChaplin & Avenue Construction Liaison Committee Meeting
Chaplin & Avenue Construction Liaison Committee Meeting
 
Avenue & Chaplin CLC - Construction Update: May 6, 2020
Avenue & Chaplin CLC - Construction Update: May 6, 2020Avenue & Chaplin CLC - Construction Update: May 6, 2020
Avenue & Chaplin CLC - Construction Update: May 6, 2020
 
Fall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue StationsFall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue Stations
 
Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020
 
Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021
 
Eastern Works Open House
Eastern Works Open House Eastern Works Open House
Eastern Works Open House
 
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptxCLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
 
Central Eastern Works Open House - October 2019
Central Eastern Works Open House - October 2019Central Eastern Works Open House - October 2019
Central Eastern Works Open House - October 2019
 
Western works final
Western works final Western works final
Western works final
 

Similar to Pharmacy to Kennedy Construction Liaison Committee Meeting - Nov 2019

Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020
Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020
Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020
Crosstown TO
 
Pharmacy kennedy clc meeting- april 30, 2019
Pharmacy kennedy clc meeting- april 30, 2019Pharmacy kennedy clc meeting- april 30, 2019
Pharmacy kennedy clc meeting- april 30, 2019
Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
Crosstown TO
 
CLC Pharmacy to Kennedy - May 31 2022
CLC Pharmacy to Kennedy - May 31 2022CLC Pharmacy to Kennedy - May 31 2022
CLC Pharmacy to Kennedy - May 31 2022
Crosstown TO
 
CLC pharmacy to Kennedy (Nov24)
CLC pharmacy to Kennedy (Nov24)CLC pharmacy to Kennedy (Nov24)
CLC pharmacy to Kennedy (Nov24)
Crosstown TO
 
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Crosstown TO
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdf
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdfCLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdf
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdf
Crosstown TO
 
East At-Grade Town Hall Meeting
East At-Grade Town Hall MeetingEast At-Grade Town Hall Meeting
East At-Grade Town Hall Meeting
Crosstown TO
 
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Crosstown TO
 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - July 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - July 2019Eglinton & Mount Pleasant Construction Liaison Committee Meeting - July 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - July 2019
Crosstown TO
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
Crosstown TO
 
Pharmacy kennedy clc meeting -january 29 2019
Pharmacy kennedy clc meeting -january 29 2019Pharmacy kennedy clc meeting -january 29 2019
Pharmacy kennedy clc meeting -january 29 2019
Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020
Crosstown TO
 
Eglinton & Mount Pleasant Construction Liaison Committee - Sep 2019
Eglinton & Mount Pleasant Construction Liaison Committee - Sep 2019Eglinton & Mount Pleasant Construction Liaison Committee - Sep 2019
Eglinton & Mount Pleasant Construction Liaison Committee - Sep 2019
Crosstown TO
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
Crosstown TO
 
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Crosstown TO
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdfCLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdf
Crosstown TO
 

Similar to Pharmacy to Kennedy Construction Liaison Committee Meeting - Nov 2019 (20)

Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020
Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020
Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020
 
Pharmacy kennedy clc meeting- april 30, 2019
Pharmacy kennedy clc meeting- april 30, 2019Pharmacy kennedy clc meeting- april 30, 2019
Pharmacy kennedy clc meeting- april 30, 2019
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
 
CLC Pharmacy to Kennedy - May 31 2022
CLC Pharmacy to Kennedy - May 31 2022CLC Pharmacy to Kennedy - May 31 2022
CLC Pharmacy to Kennedy - May 31 2022
 
CLC pharmacy to Kennedy (Nov24)
CLC pharmacy to Kennedy (Nov24)CLC pharmacy to Kennedy (Nov24)
CLC pharmacy to Kennedy (Nov24)
 
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdf
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdfCLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdf
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdf
 
East At-Grade Town Hall Meeting
East At-Grade Town Hall MeetingEast At-Grade Town Hall Meeting
East At-Grade Town Hall Meeting
 
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - July 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - July 2019Eglinton & Mount Pleasant Construction Liaison Committee Meeting - July 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - July 2019
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
 
Pharmacy kennedy clc meeting -january 29 2019
Pharmacy kennedy clc meeting -january 29 2019Pharmacy kennedy clc meeting -january 29 2019
Pharmacy kennedy clc meeting -january 29 2019
 
Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020
 
Eglinton & Mount Pleasant Construction Liaison Committee - Sep 2019
Eglinton & Mount Pleasant Construction Liaison Committee - Sep 2019Eglinton & Mount Pleasant Construction Liaison Committee - Sep 2019
Eglinton & Mount Pleasant Construction Liaison Committee - Sep 2019
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
 
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdfCLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdf
 

More from Crosstown TO

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
Crosstown TO
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
Crosstown TO
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
Crosstown TO
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Crosstown TO
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Crosstown TO
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Crosstown TO
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
Crosstown TO
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
Crosstown TO
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Crosstown TO
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Crosstown TO
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
Crosstown TO
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Crosstown TO
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
Crosstown TO
 
Leaside-Laird CLC - Nov 14, 2022.pdf
Leaside-Laird CLC - Nov 14, 2022.pdfLeaside-Laird CLC - Nov 14, 2022.pdf
Leaside-Laird CLC - Nov 14, 2022.pdf
Crosstown TO
 
Eglinton - Mt Pleasant CLC - November 9, 2022.pdf
Eglinton - Mt Pleasant CLC - November 9, 2022.pdfEglinton - Mt Pleasant CLC - November 9, 2022.pdf
Eglinton - Mt Pleasant CLC - November 9, 2022.pdf
Crosstown TO
 
Test
TestTest

More from Crosstown TO (20)

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
 
Leaside-Laird CLC - Nov 14, 2022.pdf
Leaside-Laird CLC - Nov 14, 2022.pdfLeaside-Laird CLC - Nov 14, 2022.pdf
Leaside-Laird CLC - Nov 14, 2022.pdf
 
Eglinton - Mt Pleasant CLC - November 9, 2022.pdf
Eglinton - Mt Pleasant CLC - November 9, 2022.pdfEglinton - Mt Pleasant CLC - November 9, 2022.pdf
Eglinton - Mt Pleasant CLC - November 9, 2022.pdf
 
Test
TestTest
Test
 

Recently uploaded

Texas Water Development Board Updates June 2024
Texas Water Development Board Updates June 2024Texas Water Development Board Updates June 2024
Texas Water Development Board Updates June 2024
Texas Alliance of Groundwater Districts
 
About Potato, The scientific name of the plant is Solanum tuberosum (L).
About Potato, The scientific name of the plant is Solanum tuberosum (L).About Potato, The scientific name of the plant is Solanum tuberosum (L).
About Potato, The scientific name of the plant is Solanum tuberosum (L).
Christina Parmionova
 
AHMR volume 10 number 1 January-April 2024
AHMR volume 10 number 1 January-April 2024AHMR volume 10 number 1 January-April 2024
AHMR volume 10 number 1 January-April 2024
Scalabrini Institute for Human Mobility in Africa
 
2024: The FAR - Federal Acquisition Regulations, Part 38
2024: The FAR - Federal Acquisition Regulations, Part 382024: The FAR - Federal Acquisition Regulations, Part 38
2024: The FAR - Federal Acquisition Regulations, Part 38
JSchaus & Associates
 
快速办理(Bristol毕业证书)布里斯托大学毕业证Offer一模一样
快速办理(Bristol毕业证书)布里斯托大学毕业证Offer一模一样快速办理(Bristol毕业证书)布里斯托大学毕业证Offer一模一样
快速办理(Bristol毕业证书)布里斯托大学毕业证Offer一模一样
3woawyyl
 
Transit-Oriented Development Study Working Group Meeting
Transit-Oriented Development Study Working Group MeetingTransit-Oriented Development Study Working Group Meeting
Transit-Oriented Development Study Working Group Meeting
Cuyahoga County Planning Commission
 
Antyodaya saral portal haryana govt schemes
Antyodaya saral portal haryana govt schemesAntyodaya saral portal haryana govt schemes
Antyodaya saral portal haryana govt schemes
narinav14
 
Awaken new depths - World Ocean Day 2024, June 8th.
Awaken new depths - World Ocean Day 2024, June 8th.Awaken new depths - World Ocean Day 2024, June 8th.
Awaken new depths - World Ocean Day 2024, June 8th.
Christina Parmionova
 
Item # 10 -- Historical Presv. Districts
Item # 10 -- Historical Presv. DistrictsItem # 10 -- Historical Presv. Districts
Item # 10 -- Historical Presv. Districts
ahcitycouncil
 
PPT Item # 8&9 - Demolition Code Amendments
PPT Item # 8&9 - Demolition Code AmendmentsPPT Item # 8&9 - Demolition Code Amendments
PPT Item # 8&9 - Demolition Code Amendments
ahcitycouncil
 
A Guide to AI for Smarter Nonprofits - Dr. Cori Faklaris, UNC Charlotte
A Guide to AI for Smarter Nonprofits - Dr. Cori Faklaris, UNC CharlotteA Guide to AI for Smarter Nonprofits - Dr. Cori Faklaris, UNC Charlotte
A Guide to AI for Smarter Nonprofits - Dr. Cori Faklaris, UNC Charlotte
Cori Faklaris
 
RFP for Reno's Community Assistance Center
RFP for Reno's Community Assistance CenterRFP for Reno's Community Assistance Center
RFP for Reno's Community Assistance Center
This Is Reno
 
2024: The FAR - Federal Acquisition Regulations, Part 39
2024: The FAR - Federal Acquisition Regulations, Part 392024: The FAR - Federal Acquisition Regulations, Part 39
2024: The FAR - Federal Acquisition Regulations, Part 39
JSchaus & Associates
 
2024: The FAR - Federal Acquisition Regulations, Part 40
2024: The FAR - Federal Acquisition Regulations, Part 402024: The FAR - Federal Acquisition Regulations, Part 40
2024: The FAR - Federal Acquisition Regulations, Part 40
JSchaus & Associates
 
PPT Item # 5 - 318 Tuxedo Ave. (sign. review)
PPT Item # 5 - 318 Tuxedo Ave. (sign. review)PPT Item # 5 - 318 Tuxedo Ave. (sign. review)
PPT Item # 5 - 318 Tuxedo Ave. (sign. review)
ahcitycouncil
 
Bangladesh studies presentation on Liberation War 1971 Indepence-of-Banglades...
Bangladesh studies presentation on Liberation War 1971 Indepence-of-Banglades...Bangladesh studies presentation on Liberation War 1971 Indepence-of-Banglades...
Bangladesh studies presentation on Liberation War 1971 Indepence-of-Banglades...
ssuser05e8f3
 
2024: The FAR - Federal Acquisition Regulations, Part 41
2024: The FAR - Federal Acquisition Regulations, Part 412024: The FAR - Federal Acquisition Regulations, Part 41
2024: The FAR - Federal Acquisition Regulations, Part 41
JSchaus & Associates
 
PAS PSDF Mop Up Workshop Presentation 2024 .pptx
PAS PSDF Mop Up Workshop Presentation 2024 .pptxPAS PSDF Mop Up Workshop Presentation 2024 .pptx
PAS PSDF Mop Up Workshop Presentation 2024 .pptx
PAS_Team
 
Milton Keynes Hospital Charity - A guide to leaving a gift in your Will
Milton Keynes Hospital Charity - A guide to leaving a gift in your WillMilton Keynes Hospital Charity - A guide to leaving a gift in your Will
Milton Keynes Hospital Charity - A guide to leaving a gift in your Will
fundraising4
 
Item #s 8&9 -- Demolition Code Amendment
Item #s 8&9 -- Demolition Code AmendmentItem #s 8&9 -- Demolition Code Amendment
Item #s 8&9 -- Demolition Code Amendment
ahcitycouncil
 

Recently uploaded (20)

Texas Water Development Board Updates June 2024
Texas Water Development Board Updates June 2024Texas Water Development Board Updates June 2024
Texas Water Development Board Updates June 2024
 
About Potato, The scientific name of the plant is Solanum tuberosum (L).
About Potato, The scientific name of the plant is Solanum tuberosum (L).About Potato, The scientific name of the plant is Solanum tuberosum (L).
About Potato, The scientific name of the plant is Solanum tuberosum (L).
 
AHMR volume 10 number 1 January-April 2024
AHMR volume 10 number 1 January-April 2024AHMR volume 10 number 1 January-April 2024
AHMR volume 10 number 1 January-April 2024
 
2024: The FAR - Federal Acquisition Regulations, Part 38
2024: The FAR - Federal Acquisition Regulations, Part 382024: The FAR - Federal Acquisition Regulations, Part 38
2024: The FAR - Federal Acquisition Regulations, Part 38
 
快速办理(Bristol毕业证书)布里斯托大学毕业证Offer一模一样
快速办理(Bristol毕业证书)布里斯托大学毕业证Offer一模一样快速办理(Bristol毕业证书)布里斯托大学毕业证Offer一模一样
快速办理(Bristol毕业证书)布里斯托大学毕业证Offer一模一样
 
Transit-Oriented Development Study Working Group Meeting
Transit-Oriented Development Study Working Group MeetingTransit-Oriented Development Study Working Group Meeting
Transit-Oriented Development Study Working Group Meeting
 
Antyodaya saral portal haryana govt schemes
Antyodaya saral portal haryana govt schemesAntyodaya saral portal haryana govt schemes
Antyodaya saral portal haryana govt schemes
 
Awaken new depths - World Ocean Day 2024, June 8th.
Awaken new depths - World Ocean Day 2024, June 8th.Awaken new depths - World Ocean Day 2024, June 8th.
Awaken new depths - World Ocean Day 2024, June 8th.
 
Item # 10 -- Historical Presv. Districts
Item # 10 -- Historical Presv. DistrictsItem # 10 -- Historical Presv. Districts
Item # 10 -- Historical Presv. Districts
 
PPT Item # 8&9 - Demolition Code Amendments
PPT Item # 8&9 - Demolition Code AmendmentsPPT Item # 8&9 - Demolition Code Amendments
PPT Item # 8&9 - Demolition Code Amendments
 
A Guide to AI for Smarter Nonprofits - Dr. Cori Faklaris, UNC Charlotte
A Guide to AI for Smarter Nonprofits - Dr. Cori Faklaris, UNC CharlotteA Guide to AI for Smarter Nonprofits - Dr. Cori Faklaris, UNC Charlotte
A Guide to AI for Smarter Nonprofits - Dr. Cori Faklaris, UNC Charlotte
 
RFP for Reno's Community Assistance Center
RFP for Reno's Community Assistance CenterRFP for Reno's Community Assistance Center
RFP for Reno's Community Assistance Center
 
2024: The FAR - Federal Acquisition Regulations, Part 39
2024: The FAR - Federal Acquisition Regulations, Part 392024: The FAR - Federal Acquisition Regulations, Part 39
2024: The FAR - Federal Acquisition Regulations, Part 39
 
2024: The FAR - Federal Acquisition Regulations, Part 40
2024: The FAR - Federal Acquisition Regulations, Part 402024: The FAR - Federal Acquisition Regulations, Part 40
2024: The FAR - Federal Acquisition Regulations, Part 40
 
PPT Item # 5 - 318 Tuxedo Ave. (sign. review)
PPT Item # 5 - 318 Tuxedo Ave. (sign. review)PPT Item # 5 - 318 Tuxedo Ave. (sign. review)
PPT Item # 5 - 318 Tuxedo Ave. (sign. review)
 
Bangladesh studies presentation on Liberation War 1971 Indepence-of-Banglades...
Bangladesh studies presentation on Liberation War 1971 Indepence-of-Banglades...Bangladesh studies presentation on Liberation War 1971 Indepence-of-Banglades...
Bangladesh studies presentation on Liberation War 1971 Indepence-of-Banglades...
 
2024: The FAR - Federal Acquisition Regulations, Part 41
2024: The FAR - Federal Acquisition Regulations, Part 412024: The FAR - Federal Acquisition Regulations, Part 41
2024: The FAR - Federal Acquisition Regulations, Part 41
 
PAS PSDF Mop Up Workshop Presentation 2024 .pptx
PAS PSDF Mop Up Workshop Presentation 2024 .pptxPAS PSDF Mop Up Workshop Presentation 2024 .pptx
PAS PSDF Mop Up Workshop Presentation 2024 .pptx
 
Milton Keynes Hospital Charity - A guide to leaving a gift in your Will
Milton Keynes Hospital Charity - A guide to leaving a gift in your WillMilton Keynes Hospital Charity - A guide to leaving a gift in your Will
Milton Keynes Hospital Charity - A guide to leaving a gift in your Will
 
Item #s 8&9 -- Demolition Code Amendment
Item #s 8&9 -- Demolition Code AmendmentItem #s 8&9 -- Demolition Code Amendment
Item #s 8&9 -- Demolition Code Amendment
 

Pharmacy to Kennedy Construction Liaison Committee Meeting - Nov 2019

  • 1. Eglinton Crosstown LRT MX/CTS Construction Liaison Committee November 26th, 2019
  • 2. O’Connor Stop to Ionview Stop Victoria Park Ave to Ionview Rd
  • 3. Completed Works  Westbound left turn removal at Pharmacy and Eglinton – Jun 2019  Westbound left turn removal at Victoria Park Ave – Oct 2019  Westbound left turn removal at Birchmount Rd – Nov 13  Intersection guideway construction at Victoria Park, Pharmacy, Hakimi Lebovic, Warden, Birchmount and Ionview 3
  • 4. Victoria Park Avenue to Birchmount Road Look Ahead 4 ACTIVITY LOCATION APPROX. DATE AND DURATION Stop Construction and Track Installation Eglinton Ave E b/w Victoria Park Ave and Pharmacy Ave Underway through spring 2020 Stop Construction and Track Installation Eglinton Ave E b/w Pharmacy Ave and Hakimi Lebovic Ave Underway through spring 2020 Stop Construction and Track Installation Eglinton Ave E b/w Hakimi Lebovic Ave and Warden Ave Underway through spring 2020 Midblock Guideway, Stop Construction and Track Installation Eglinton Ave E b/w Warden Ave and Birchmount Rd Underway through spring 2020 Midblock Guideway, Stop Construction and Track Installation Eglinton Ave E b/w Birchmount Rd and Ionview Rd Underway through spring 2020 Road Work Eglinton Ave E b/w Ionview Rd and Kennedy Rd Starts spring 2020
  • 5. Victoria Park Avenue to Birchmount Road Look Ahead (cont’d) 5 ACTIVITY LOCATION APPROX. DATE AND DURATION Intersection Guideway Construction SB Rosemount Dr at Eglinton Ave E Nov 3, 2019 for approximately six (6) weeks TPSS 11 Delivery Warden Ave and Eglinton Ave E Mon Nov 25 – Fri Nov 29, 2019 Temporary Lane Closures for Utility Relocation Victoria Park Ave at Eglinton Ave E Nov 27 & 28 Traffic Flip Rosemount Dr at Eglinton Ave E Intersection Sat Nov 30, 2019 Traffic Flip Intersection Opens Rosemount Dr at Eglinton Ave E Mon Dec 16, 2019 – Jan 2 Eastbound Left Lane Turn Removal Birchmount Rd and Eglinton Ave E Mon Dec 16, 2019 Southbound Road Closure Massey Creek (Rosemount Dr at Eglinton Ave E) Thu Jan 2, 2019 Northbound and Southbound Left Turn Removals Pharmacy Ave and Eglinton Ave E Spring 2020
  • 6. 6 Current Traffic Configuration: Victoria Park to Birchmount Road
  • 7. Permanent Left Turn Lane Removals 7
  • 8. What to Expect - Guideway and Stop Construction Eglinton Ave E from Victoria Park Ave to Birchmount Rd Traffic and Pedestrian Impacts • Daily temporary lane closures • Periodic sidewalk and crosswalk closures • Noise from construction equipment, generators and vehicles • Nearby businesses and residents can expect noise from excavation, bobcats, trucks and other construction equipment as well as site lighting • A minimum of one lane of eastbound and westbound through traffic will be maintained during this work Hours of Work • Construction will take place between the hours of 7:00 a.m. and 11:00 p.m. • The contractor may not always work during the permitted hours but may do so at its discretion. • Work may be rescheduled due to weather conditions or unforeseen circumstances. • Emergency services access will be maintained. 8
  • 9. 9 December 16 – The eastbound and westbound left turn will be prohibited at Birchmount Road permanently. Left turns are available at nearby streets including Warden Ave and Kennedy Rd. November 13 – The westbound left turn will be prohibited at Birchmount Road permanently. Left turns are available at nearby streets including Warden Ave and Kennedy Rd. Birchmount Road – Left Turn Removals
  • 10. 10 Current Traffic Configuration: Rosemount Dr and Eglinton Ave E Sunday, November 3, 2019 for approximately six (6) weeks
  • 11. Upcoming Traffic Configuration: Rosemount Dr and Eglinton Ave E – Nov 30 11 • Rosemount Drive north of Eglinton Avenue East will remain closed, local access will be maintained south bound traffic will be diverted north • Westbound traffic will be shifted north of the work zone on Eglinton Avenue East • Left turns are prohibited at the intersection in all directions • North-south through traffic on Rosemount Drive will be prohibited, north bound traffic must turn right
  • 12. Upcoming Traffic Configuration: Rosemount Dr and Eglinton Ave E – Dec 16 12
  • 13. Upcoming Traffic Configuration: Rosemount Dr and Eglinton Ave E – Jan 2 13
  • 14. 14 Track installation from Pharmacy to Hakimi Lebovic Victoria Park Avenue Victoria Park to Birchmount Road - Progress Photos
  • 15. East At-Grade – Progress Photos Massey Creek Culvert Rosemount Intersection
  • 17. Kennedy Station: GO Transit Improvements 17
  • 18. Kennedy Station Look Ahead ACTIVITY LOCATION APPROX. DATE AND DURATION  Portal Excavation, lagging and tie backs  The west portal was completed ahead of schedule  East of GO excavation, lagging and tie backs Kennedy Station Complete Backfilling and Road Restoration Kennedy Rd and Eglinton Ave E Completed Nov. 25 Traffic Configuration Change Kennedy Rd and Eglinton Ave E As early as November 30, 2019 • Dewatering activities • Support of excavation • Underground mechanical and electrical works • Waterproofing • Bulk excavation work Kennedy Station - Main Station Box Underway through late 2019 Underpinning of TTC Infrastructure Kennedy Station - SRT Underway through late 2019 Concrete, Electrical and Mechanical Works Kennedy Station – East of GO Underway through early 2020 Backfilling and Installation of Structural Streel Kennedy Station – West Portal and GO platform Underway through early 2020
  • 19. Current Traffic Configuration: Kennedy Station 19
  • 20. Current Traffic Configuration: Kennedy Station 20
  • 21. 21 Current Traffic Configuration: Kennedy Rd and Eglinton Ave E Until November 30, 2019
  • 22. Upcoming Traffic Configuration: Kennedy Rd and Eglinton Ave E As early as November 30, 2019
  • 23. Kennedy Station- Progress Photos East Portal Main Entrance Waterproofing Portal