Dwight Potter Boeing Exploration Launch Systems Deputy, IUA Program Manager
Boeing Producibility Team Boeing has been selected as the USPC and IUAC Producibility and Design Support Manufacturing Operations Sustaining Engineering USP Program Manager – Jim Chilton IUA Program Manager – Dwight Potter Team is engaged with NASA Design Team (NDT) Manufacturing Value Stream Mapping Producibility Summit Tooling Design Support Schedule Development Component Cost Updates Test Article Planning Support Special Studies
Our Objective – Safe and Affordable  Ares I Upper Stage We used the Value Stream  approach to develop “how” Imperatives guide  our approach Determined needed resources  using proven methods Value added from Delta IV  and other processes to  NDTs existing approach Production – Strategic Overview Objective Value Stream Mapping Four Manufacturing Imperatives: Safety, Incremental Transition, Innovation, R&O Management Resource Needs:   Facilities Staffing Supply & Tooling Chain Manufacturing Processes: Friction Stir Welding, Ultrasonic Inspection,  Robotic SOFI…
Manufacturing Imperatives Workforce, hardware and  mission safety Achieve design phase objectives Flow time Team size Surge capability Structured production  readiness process MAF capability re-use
The Production Strategy Requires Designing the Production Flow Along with the Product The Value Stream Approach A Program Leadership Tool Step #1 Start with the Answer: Program Sets Targets Objectives Customer expectations Quality improvement Cycle time reduction On-time delivery Improve cost Step #2 Value Stream Mapping Engage teams in the “How” Identify waste in the process (starbursts) Seek new value A Baseline   Step #3 Value Stream Analysis Design to achieve program vision Integrate Lean Best  Practices to reduce waste Integrate Program Management Best Practices for Execution Step #4 Action Plan Program commitment/ownership Team improvement targets Team Lean plans Seize Opportunities Visible to all
Lean Approach is Driving Upper Stage and Instrument Unit Integration Updated and mature production for a right sized production system, timeline and simulation Improve production layouts at MAF. Add definition to flows  Reduce flow times for materials, people, hardware, information, tooling IUA manufacturing & assembly flow integrated  to improve and mature the overall flow.  Define details on IU process flow (All integration and testing) Seek opportunities to reduce IU process flow time. Identify missing support hardware/software Include any process flow to turn over the IU structure (DD250 baseline) Any flow to turn over the integrated assembly (DD250 baseline) back to the US contract IU Box Installation Simulation IU Assembly onto Upper Stage
Engaging the Supply Chain Source Control Item and Component End Item Procurements Underway Upper Stage Production Ullage Settling Motors: Proposals received and in evaluation Pyros: Proposals received and in evaluation  Instrument Unit Avionics Flight Computer/Command Telemetry Computer: Proposals received and in evaluation  Battery:  RFP released to industry this month Combined Control System Electronics:  RFP released to industry All remaining procurements to be completed in 2009 Exceeding Supplier Diversity Goals & Reaching Out  Mentoring and Developing Small Businesses
Summary Supporting NASA in the development of a safe & affordable Upper Stage Made extensive producibility inputs into the design process Optimize manufacturing costs through lean approaches Have a plan to engage and integrate the Supply Chain into the program

Ares I Instrument Unit Status and Progress

  • 1.
    Dwight Potter BoeingExploration Launch Systems Deputy, IUA Program Manager
  • 2.
    Boeing Producibility TeamBoeing has been selected as the USPC and IUAC Producibility and Design Support Manufacturing Operations Sustaining Engineering USP Program Manager – Jim Chilton IUA Program Manager – Dwight Potter Team is engaged with NASA Design Team (NDT) Manufacturing Value Stream Mapping Producibility Summit Tooling Design Support Schedule Development Component Cost Updates Test Article Planning Support Special Studies
  • 3.
    Our Objective –Safe and Affordable Ares I Upper Stage We used the Value Stream approach to develop “how” Imperatives guide our approach Determined needed resources using proven methods Value added from Delta IV and other processes to NDTs existing approach Production – Strategic Overview Objective Value Stream Mapping Four Manufacturing Imperatives: Safety, Incremental Transition, Innovation, R&O Management Resource Needs: Facilities Staffing Supply & Tooling Chain Manufacturing Processes: Friction Stir Welding, Ultrasonic Inspection, Robotic SOFI…
  • 4.
    Manufacturing Imperatives Workforce,hardware and mission safety Achieve design phase objectives Flow time Team size Surge capability Structured production readiness process MAF capability re-use
  • 5.
    The Production StrategyRequires Designing the Production Flow Along with the Product The Value Stream Approach A Program Leadership Tool Step #1 Start with the Answer: Program Sets Targets Objectives Customer expectations Quality improvement Cycle time reduction On-time delivery Improve cost Step #2 Value Stream Mapping Engage teams in the “How” Identify waste in the process (starbursts) Seek new value A Baseline Step #3 Value Stream Analysis Design to achieve program vision Integrate Lean Best Practices to reduce waste Integrate Program Management Best Practices for Execution Step #4 Action Plan Program commitment/ownership Team improvement targets Team Lean plans Seize Opportunities Visible to all
  • 6.
    Lean Approach isDriving Upper Stage and Instrument Unit Integration Updated and mature production for a right sized production system, timeline and simulation Improve production layouts at MAF. Add definition to flows Reduce flow times for materials, people, hardware, information, tooling IUA manufacturing & assembly flow integrated to improve and mature the overall flow. Define details on IU process flow (All integration and testing) Seek opportunities to reduce IU process flow time. Identify missing support hardware/software Include any process flow to turn over the IU structure (DD250 baseline) Any flow to turn over the integrated assembly (DD250 baseline) back to the US contract IU Box Installation Simulation IU Assembly onto Upper Stage
  • 7.
    Engaging the SupplyChain Source Control Item and Component End Item Procurements Underway Upper Stage Production Ullage Settling Motors: Proposals received and in evaluation Pyros: Proposals received and in evaluation Instrument Unit Avionics Flight Computer/Command Telemetry Computer: Proposals received and in evaluation Battery: RFP released to industry this month Combined Control System Electronics: RFP released to industry All remaining procurements to be completed in 2009 Exceeding Supplier Diversity Goals & Reaching Out Mentoring and Developing Small Businesses
  • 8.
    Summary Supporting NASAin the development of a safe & affordable Upper Stage Made extensive producibility inputs into the design process Optimize manufacturing costs through lean approaches Have a plan to engage and integrate the Supply Chain into the program

Editor's Notes

  • #2 09/07 Welcome, and thank you for taking this time with me. I would like to share with you some of the exciting things being done by your space program.