ILS Management Overview
INTRO
ILS Management can take on many different shapes, as a contract may
dictate. In this presentation, I will address a classic view of ILS
management germane to the acquisition logistics process. The ILS
Manager has a dynamic set of tasks to perform that exhibit a significant
complexity. In many ways (and most times), it is no different than
staffing, planning, leading, and reporting at the level of a Program
Manager. The subject matter spans the breadth and depth of the entire
program and often requires a significant staff to implement a parallel,
shadow-like effort.
ILS Manager Key Functions
Program Staff Liaison
Personnel Guidance and Leadership
ILS Program Planning
Product Development and Scheduling
Product Development Oversight
Engineering Liaison
Cost Account Management
Risk management.
Program Staff liaison
The ILS Manager directly supports programmatic functions for
business planning and business pursuits:
 Proposal support; writing the logistics volume of a proposal; ensuring the detailed
scope fits within the company’s systems engineering model
 Establishes the Work Breakdown Structure (WBS) for logistics products
 Establishes the Cost Breakdown Structure (CBS)
 Accurately interpreting the Statement of Work (SOW)
 Contract negotiations; validating the Performance Work Statements (PWS)
 Personnel support; recruiting and hiring a broad sample of skill sets of engineers,
analysts, and documentation specialists
Personnel Guidance and Leadership
Managers inherently lead a team of professionals:
 Recognize personnel performance
 Mitigate personnel issues
 Implements personnel training
 Communicates weekly on progress (in open forum preferably)
 Permits the contiguous nature of logistics to act as the performance driver for the
team
The ILS Manager in Short
To summarize the first two slides, I would put forth that the ILS
Manager’s job is to:
 Represent the Board of Directors in all things contractually expedient with regard to
logistics requirements
 At the same time, makes their boss look good
 Ensures the team has everything they need to perform their tasks
 Plugs his team into systems engineering
ILS Program Planning
The ILS Manager is the Planner-In-Chief. They will establish policy by
writing plans that become the guiding principles for the major elements
of logistics:
 Integrated Logistics Plan (ILSP)
 Reliability Program Plan (RPP)
 Maintenance Support Plan (MSP)
 Technical Manual Support Plan (TMSP)
 At times, assist customers with their Life Cycle Support Plan (LCSP)
Product Development Scheduling
Pursuant to the planning process, product development must be
mapped across the Period of Performance (POP) of the Program:
 It will be integrated with the system’s engineering master schedule
 Engineering and Logistics milestones will drive the product development schedule
 Tasks must have periodic reporting granularity (driven by the company accounting
cycle)
 Tasks will be resource loaded with the appropriate skill sets
Product Development Oversight
The ILS Manager must implement processes that are achievable and
reportable for the following efforts:
 Logistics Engineering
 Logistics Analyses
 End User Documentation
Each of these efforts are significantly different than the other and each
is dependent upon the completion of the effort that proceeds it
Process Implementation
Process implementation should be an exercise in finding efficiencies by
analyzing processes and communicating the inner workings of
processes for each team member on the team:
 Draft work flows
 Validate the work flow with the SME so that they have a buy-in to their process(es)
 Detail each step in the process and assign a weight to each step (minutes on the hour)
Estimating and Reporting
For every process step, on every product or study, the time to perform
each step is directly related to the artifact subject to the research
Which is to say, you can factor the weight of each step against the
number of artifacts you are adjudicating – and arrive at a pretty
accurate estimate
 The Bill of Materials (BOM) parts count
 Number of Engineering drawings
 Number of systems
 Number of subsystems
 Number of LRUs
 Number of pages, presentation slides, and illustrations…and many more
Product Liability
The ILS Manager must also mitigate any liability issues for all logistics
products
To ensure all products are traceable to the Engineering Technical
Documentation Package (TDP)
To ensure all products are signed off by engineering
Without these formal requirements being met if anything were to
happen (where personnel or equipment are injured or damaged), while
using Logistics processes, it could result in litigation (see slide 6)
Engineering Liaison
The ILS Manger defines entrance criteria/engineering data points for
logistics products
Communicates reliability predictions to engineering
Communicates failure predictions to engineering
Communicates maintainability issues to engineering
Operates as part of the systems engineering team
 Design Engineering
 Test Engineering
 Quality Assurance
 Safety Factors
 Manufacturing Engineering
 And Logistics
Cost Account management
Reports cost and schedule variances over the whole POP as well as, the
monthly POP:
 Reporting on Issues, Variances, Corrective actions for total and monthly POPs
 Understands the CAM formulas for cost and schedule indications
Mitigates risk based on the cost account indicators:
 Costs
 Schedule
 Watch items
 Risks
 Issues
 Mitigation
Summary
In closing, the ILS Manager plans and leads a complete program
initiative parallel to the overall program
They are hiring managers
They are the planners and administrators of a program
They implement processes that support the requisite reporting and
provide guidance for the team
Perpetuates new business by producing meaningful estimates and
planning for management staff

More Related Content

What's hot

Project scheduling and tracking
Project scheduling and trackingProject scheduling and tracking
Project scheduling and tracking
Computer_ at_home
 
project monitoring and control
project monitoring and controlproject monitoring and control
project monitoring and control
ChandraShekhar Patel
 
Project Management 12
Project Management 12Project Management 12
Project Management 12
Tathagat Varma
 
Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost control
Guhan M
 
Project Tracking & SPC
Project Tracking & SPCProject Tracking & SPC
Project Tracking & SPC
Meghaj Mallick
 
Project control. Management
Project control. ManagementProject control. Management
Project control. Management
Marius Miron
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
Shivangi Saini
 
TGE Project Controls
TGE Project ControlsTGE Project Controls
TGE Project ControlsDavid Mathews
 
Project Controls Processes
Project Controls ProcessesProject Controls Processes
Project Controls Processes
PMA Consultants
 
Project cost management
Project cost management Project cost management
Project cost management
PALLA NARASIMHUDU
 
Project monitoring lecture 1
Project monitoring lecture 1Project monitoring lecture 1
Project monitoring lecture 1
BECM, RUET, Bangladesh
 
Scheduling
SchedulingScheduling
Project control & Monitoring
Project control & MonitoringProject control & Monitoring
Project control & Monitoring
Jawad Ahmad
 
SDPM - Lecture 7 - Project monitoring and control
SDPM - Lecture 7 - Project monitoring and controlSDPM - Lecture 7 - Project monitoring and control
SDPM - Lecture 7 - Project monitoring and controlOpenLearningLab
 
IWP Timeline
IWP TimelineIWP Timeline
IWP TimelineScot Fyfe
 
How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2
Abdelhay Ghanem
 
construction project planing
 construction project planing construction project planing
construction project planing
SANJEEV Wazir
 
Project Management Control
Project Management ControlProject Management Control
Project Management Control
ahmad bassiouny
 
041 Integrating Lean Construction (PART 2)
041 Integrating Lean Construction (PART 2)041 Integrating Lean Construction (PART 2)
041 Integrating Lean Construction (PART 2)
Dr Fereidoun Dejahang
 
Implement risk responses
Implement risk responses Implement risk responses
Implement risk responses
Shereef Sabri
 

What's hot (20)

Project scheduling and tracking
Project scheduling and trackingProject scheduling and tracking
Project scheduling and tracking
 
project monitoring and control
project monitoring and controlproject monitoring and control
project monitoring and control
 
Project Management 12
Project Management 12Project Management 12
Project Management 12
 
Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost control
 
Project Tracking & SPC
Project Tracking & SPCProject Tracking & SPC
Project Tracking & SPC
 
Project control. Management
Project control. ManagementProject control. Management
Project control. Management
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
TGE Project Controls
TGE Project ControlsTGE Project Controls
TGE Project Controls
 
Project Controls Processes
Project Controls ProcessesProject Controls Processes
Project Controls Processes
 
Project cost management
Project cost management Project cost management
Project cost management
 
Project monitoring lecture 1
Project monitoring lecture 1Project monitoring lecture 1
Project monitoring lecture 1
 
Scheduling
SchedulingScheduling
Scheduling
 
Project control & Monitoring
Project control & MonitoringProject control & Monitoring
Project control & Monitoring
 
SDPM - Lecture 7 - Project monitoring and control
SDPM - Lecture 7 - Project monitoring and controlSDPM - Lecture 7 - Project monitoring and control
SDPM - Lecture 7 - Project monitoring and control
 
IWP Timeline
IWP TimelineIWP Timeline
IWP Timeline
 
How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2
 
construction project planing
 construction project planing construction project planing
construction project planing
 
Project Management Control
Project Management ControlProject Management Control
Project Management Control
 
041 Integrating Lean Construction (PART 2)
041 Integrating Lean Construction (PART 2)041 Integrating Lean Construction (PART 2)
041 Integrating Lean Construction (PART 2)
 
Implement risk responses
Implement risk responses Implement risk responses
Implement risk responses
 

Similar to Ils management overview

MIS Project management
MIS Project managementMIS Project management
MIS Project management
Josephine Claire
 
Software Engineering
Software EngineeringSoftware Engineering
Software Engineering
Dr. Anthony Vincent. B
 
Running head critical path method1 critical path method7critic
Running head critical path method1 critical path method7criticRunning head critical path method1 critical path method7critic
Running head critical path method1 critical path method7critic
DIPESH30
 
Project Scope StatementProject NameStudent NameDateI.docx
Project Scope StatementProject NameStudent NameDateI.docxProject Scope StatementProject NameStudent NameDateI.docx
Project Scope StatementProject NameStudent NameDateI.docx
wkyra78
 
spm1.ppt
spm1.pptspm1.ppt
spm1.ppt
Vinoth Kumar
 
Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"
David Pedreno
 
Ch23
Ch23Ch23
041 integrating lean construction (2)
041 integrating lean construction (2)041 integrating lean construction (2)
041 integrating lean construction (2)
drdej19
 
Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"
David Pedreno
 
Ch23-Software Engineering 9
Ch23-Software Engineering 9Ch23-Software Engineering 9
Ch23-Software Engineering 9Ian Sommerville
 
Unified process,agile process,process assesment ppt
Unified process,agile process,process assesment pptUnified process,agile process,process assesment ppt
Unified process,agile process,process assesment pptShweta Ghate
 
Project control and process instrumentation
Project control and process instrumentationProject control and process instrumentation
Project control and process instrumentation
Kuppusamy P
 
Overview of SDLC - Waterfall, Agile, and more
Overview of SDLC - Waterfall, Agile, and moreOverview of SDLC - Waterfall, Agile, and more
Overview of SDLC - Waterfall, Agile, and more
Steve Gladstone
 
A Broad Survey of Acquisition Logistics for DoD
A Broad Survey of Acquisition Logistics for DoDA Broad Survey of Acquisition Logistics for DoD
A Broad Survey of Acquisition Logistics for DoD
Daniel Pappas
 
Computing Project
Computing Project Computing Project
Computing Project
Er. Nawaraj Bhandari
 
Pm0011 project planning and scheduling (1)
Pm0011 project planning and scheduling (1)Pm0011 project planning and scheduling (1)
Pm0011 project planning and scheduling (1)
smumbahelp
 
Software project management- Software Engineering
Software project management- Software EngineeringSoftware project management- Software Engineering
Software project management- Software Engineering
Muhammad Yousuf Abdul Qadir
 
Project management case analysis
Project management case analysisProject management case analysis
Project management case analysis
Service_supportAssignment
 
iNetwork Services Deployement Overview
iNetwork Services Deployement OverviewiNetwork Services Deployement Overview
iNetwork Services Deployement Overview
ClaudeChateauvert
 

Similar to Ils management overview (20)

MIS Project management
MIS Project managementMIS Project management
MIS Project management
 
Software Engineering
Software EngineeringSoftware Engineering
Software Engineering
 
Running head critical path method1 critical path method7critic
Running head critical path method1 critical path method7criticRunning head critical path method1 critical path method7critic
Running head critical path method1 critical path method7critic
 
Project Scope StatementProject NameStudent NameDateI.docx
Project Scope StatementProject NameStudent NameDateI.docxProject Scope StatementProject NameStudent NameDateI.docx
Project Scope StatementProject NameStudent NameDateI.docx
 
spm1.ppt
spm1.pptspm1.ppt
spm1.ppt
 
Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"
 
Ch23
Ch23Ch23
Ch23
 
041 integrating lean construction (2)
041 integrating lean construction (2)041 integrating lean construction (2)
041 integrating lean construction (2)
 
Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"
 
Ch23-Software Engineering 9
Ch23-Software Engineering 9Ch23-Software Engineering 9
Ch23-Software Engineering 9
 
Unified process,agile process,process assesment ppt
Unified process,agile process,process assesment pptUnified process,agile process,process assesment ppt
Unified process,agile process,process assesment ppt
 
Project control and process instrumentation
Project control and process instrumentationProject control and process instrumentation
Project control and process instrumentation
 
Overview of SDLC - Waterfall, Agile, and more
Overview of SDLC - Waterfall, Agile, and moreOverview of SDLC - Waterfall, Agile, and more
Overview of SDLC - Waterfall, Agile, and more
 
Incremental model
Incremental modelIncremental model
Incremental model
 
A Broad Survey of Acquisition Logistics for DoD
A Broad Survey of Acquisition Logistics for DoDA Broad Survey of Acquisition Logistics for DoD
A Broad Survey of Acquisition Logistics for DoD
 
Computing Project
Computing Project Computing Project
Computing Project
 
Pm0011 project planning and scheduling (1)
Pm0011 project planning and scheduling (1)Pm0011 project planning and scheduling (1)
Pm0011 project planning and scheduling (1)
 
Software project management- Software Engineering
Software project management- Software EngineeringSoftware project management- Software Engineering
Software project management- Software Engineering
 
Project management case analysis
Project management case analysisProject management case analysis
Project management case analysis
 
iNetwork Services Deployement Overview
iNetwork Services Deployement OverviewiNetwork Services Deployement Overview
iNetwork Services Deployement Overview
 

Recently uploaded

在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
ChristineTorrepenida1
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
aqil azizi
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
symbo111
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 

Recently uploaded (20)

在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 

Ils management overview

  • 1. DAN PAPPAS 3 AUGUST, 2016 ILS Management Overview
  • 2. INTRO ILS Management can take on many different shapes, as a contract may dictate. In this presentation, I will address a classic view of ILS management germane to the acquisition logistics process. The ILS Manager has a dynamic set of tasks to perform that exhibit a significant complexity. In many ways (and most times), it is no different than staffing, planning, leading, and reporting at the level of a Program Manager. The subject matter spans the breadth and depth of the entire program and often requires a significant staff to implement a parallel, shadow-like effort.
  • 3. ILS Manager Key Functions Program Staff Liaison Personnel Guidance and Leadership ILS Program Planning Product Development and Scheduling Product Development Oversight Engineering Liaison Cost Account Management Risk management.
  • 4. Program Staff liaison The ILS Manager directly supports programmatic functions for business planning and business pursuits:  Proposal support; writing the logistics volume of a proposal; ensuring the detailed scope fits within the company’s systems engineering model  Establishes the Work Breakdown Structure (WBS) for logistics products  Establishes the Cost Breakdown Structure (CBS)  Accurately interpreting the Statement of Work (SOW)  Contract negotiations; validating the Performance Work Statements (PWS)  Personnel support; recruiting and hiring a broad sample of skill sets of engineers, analysts, and documentation specialists
  • 5. Personnel Guidance and Leadership Managers inherently lead a team of professionals:  Recognize personnel performance  Mitigate personnel issues  Implements personnel training  Communicates weekly on progress (in open forum preferably)  Permits the contiguous nature of logistics to act as the performance driver for the team
  • 6. The ILS Manager in Short To summarize the first two slides, I would put forth that the ILS Manager’s job is to:  Represent the Board of Directors in all things contractually expedient with regard to logistics requirements  At the same time, makes their boss look good  Ensures the team has everything they need to perform their tasks  Plugs his team into systems engineering
  • 7. ILS Program Planning The ILS Manager is the Planner-In-Chief. They will establish policy by writing plans that become the guiding principles for the major elements of logistics:  Integrated Logistics Plan (ILSP)  Reliability Program Plan (RPP)  Maintenance Support Plan (MSP)  Technical Manual Support Plan (TMSP)  At times, assist customers with their Life Cycle Support Plan (LCSP)
  • 8. Product Development Scheduling Pursuant to the planning process, product development must be mapped across the Period of Performance (POP) of the Program:  It will be integrated with the system’s engineering master schedule  Engineering and Logistics milestones will drive the product development schedule  Tasks must have periodic reporting granularity (driven by the company accounting cycle)  Tasks will be resource loaded with the appropriate skill sets
  • 9. Product Development Oversight The ILS Manager must implement processes that are achievable and reportable for the following efforts:  Logistics Engineering  Logistics Analyses  End User Documentation Each of these efforts are significantly different than the other and each is dependent upon the completion of the effort that proceeds it
  • 10. Process Implementation Process implementation should be an exercise in finding efficiencies by analyzing processes and communicating the inner workings of processes for each team member on the team:  Draft work flows  Validate the work flow with the SME so that they have a buy-in to their process(es)  Detail each step in the process and assign a weight to each step (minutes on the hour)
  • 11. Estimating and Reporting For every process step, on every product or study, the time to perform each step is directly related to the artifact subject to the research Which is to say, you can factor the weight of each step against the number of artifacts you are adjudicating – and arrive at a pretty accurate estimate  The Bill of Materials (BOM) parts count  Number of Engineering drawings  Number of systems  Number of subsystems  Number of LRUs  Number of pages, presentation slides, and illustrations…and many more
  • 12. Product Liability The ILS Manager must also mitigate any liability issues for all logistics products To ensure all products are traceable to the Engineering Technical Documentation Package (TDP) To ensure all products are signed off by engineering Without these formal requirements being met if anything were to happen (where personnel or equipment are injured or damaged), while using Logistics processes, it could result in litigation (see slide 6)
  • 13. Engineering Liaison The ILS Manger defines entrance criteria/engineering data points for logistics products Communicates reliability predictions to engineering Communicates failure predictions to engineering Communicates maintainability issues to engineering Operates as part of the systems engineering team  Design Engineering  Test Engineering  Quality Assurance  Safety Factors  Manufacturing Engineering  And Logistics
  • 14. Cost Account management Reports cost and schedule variances over the whole POP as well as, the monthly POP:  Reporting on Issues, Variances, Corrective actions for total and monthly POPs  Understands the CAM formulas for cost and schedule indications Mitigates risk based on the cost account indicators:  Costs  Schedule  Watch items  Risks  Issues  Mitigation
  • 15. Summary In closing, the ILS Manager plans and leads a complete program initiative parallel to the overall program They are hiring managers They are the planners and administrators of a program They implement processes that support the requisite reporting and provide guidance for the team Perpetuates new business by producing meaningful estimates and planning for management staff