Project Management
Key Concepts
Earned Value Analysis
What is it?
Earned value provides a current view on scope,
schedule, and cost performance. It compares the
performance measurement baseline (what was
planned) to the actual schedule and cost
performance.
Earned Value Analysis
Earned Value Management develops and
monitors three key dimensions for your project
and work packages:
1. Planned Value
2. Earned Value
3. Actual Cost
You will also need your project budget, “Budget at
Completion” or BAC.
Earned Value Analysis
Earned Value Analysis
Planned Value (PV)
It is the authorized budget allocated by phase over the life of
the project, but at a given point in time.
Planned value defines the physical work that should have
been accomplished.
Project budget of $10,000, where 30%
completed, against 40% planned and $5,000
spent so far.
PV = 40% of $10,000
= $4,000
Earned Value Analysis
Earned Value (EV)
Is the budget associated with the authorized work that has
been completed. The EV is often used to calculate the
percent complete of a project.
Project budget of $10,000, where 30%
completed, against 40% planned and $5,000
spent so far.
EV = 30% of $10,000
= $3,000
Earned Value Analysis
Actual Cost (AC)
Is simply the total cost incurred in accomplishing the work so
far.
Project budget of $10,000, where 30%
completed, against 40% planned and $5,000
spent so far.
AC = $5,000
We can then use Variance Analysis to see how our
project is tracking, for example:
• Cost Performance Index
• Schedule Performance Index
• Cost Variance
• Schedule Variance
Earned Value Analysis

7.4 Earned Value Analysis

  • 1.
  • 2.
  • 3.
    What is it? Earnedvalue provides a current view on scope, schedule, and cost performance. It compares the performance measurement baseline (what was planned) to the actual schedule and cost performance. Earned Value Analysis
  • 4.
    Earned Value Managementdevelops and monitors three key dimensions for your project and work packages: 1. Planned Value 2. Earned Value 3. Actual Cost You will also need your project budget, “Budget at Completion” or BAC. Earned Value Analysis
  • 5.
    Earned Value Analysis PlannedValue (PV) It is the authorized budget allocated by phase over the life of the project, but at a given point in time. Planned value defines the physical work that should have been accomplished. Project budget of $10,000, where 30% completed, against 40% planned and $5,000 spent so far. PV = 40% of $10,000 = $4,000
  • 6.
    Earned Value Analysis EarnedValue (EV) Is the budget associated with the authorized work that has been completed. The EV is often used to calculate the percent complete of a project. Project budget of $10,000, where 30% completed, against 40% planned and $5,000 spent so far. EV = 30% of $10,000 = $3,000
  • 7.
    Earned Value Analysis ActualCost (AC) Is simply the total cost incurred in accomplishing the work so far. Project budget of $10,000, where 30% completed, against 40% planned and $5,000 spent so far. AC = $5,000
  • 8.
    We can thenuse Variance Analysis to see how our project is tracking, for example: • Cost Performance Index • Schedule Performance Index • Cost Variance • Schedule Variance Earned Value Analysis