Earned Value Analysis
 EVA is a system for planning and controlling project
cost performance.
 It establishes a work package earned value baseline by
integrating project scope, time , schedule and cost
objectives. This baseline is called control account is
used for performance evaluation on a given date.
 Analysis of variance from baseline provides cost
related information for problem identification, trend
analysis and corrective action.
Earned Value Analysis
 Earned value analysis serve 2 main purposes-
 1. To analyze the cost changes resulting in time and
cost over-runs or under-runs for taking timely
corrective actions such as modifying cash flow, and
updating financial forecasts and project profitability
expectations.
 2.To update key personnel on anticipated cost changes
in their field of responsibility, so as to create cost
consciousness for exploring means of minimizing
wastage and reducing costs.
Earned Value Analysis
 Consider a project with projected cost at completion of
Rs 1,60,000 and completion period of 20 weeks. When
reviewed at the end of 10th week, it shows that as
against the planned cost of Rs 92000/- at the end of 10
the week provided all the work is done as planned; it
has incurred expenditure of Rs 90,000.
 It raises many question such as how well is the project
actually performing; is it nor performing well as actual
expenses spent are less than budgeted, is the project
behind the schedule work or could be that the work
has been done nicely and project may be completed at
a cost that is below budget.
Earned Value Analysis
 Analysis of variance from baseline using EVA yields
variety of variances that are analyzed to determine the
current status, initiate corrective actions and forecast
the future trends.
 EVM is the process of measuring performance of
project work against a baseline plan. The application
of EVM enables better integration of cost and time
schedule control with responsibility defined in OBS.
 It provides better overall picture of performance and
gives better forecast of the final costs at completion.
 Thus EV represents a translation of project cost into
work progress.
Earned Value Analysis
 Planned Value(PV): It is the cumulative planned
value of the authorized work, scheduled for
completion to date at contract rate. It represents time-
phased cost projections of planned value in the
budget. For example, if a project has budget of Rs
1,00,000 and 5 month schedule shows that 40 % of the
value of project work should be completed at the end
oof 5th month, then PV at the end of 5th month is Rs
4,00,000/-. The planned value is also called as
Budgeted Cost of Work Scheduled(BCWS).
Earned Value Analysis
 Earned Value (EV) : It is the cumulative value of the
authorized work completed to date at contract rate.
 For example, if a project has budget of Rs 1,00,000 and
work completed to date represents 25 % of the value of
entire project work as against the 40 % planned, then
EV at the end of 5th month is Rs 2,50,000/-. The
Earned value is also called as Budgeted Cost of Work
Performed.(BCWP).
Earned Value Analysis
 Actual Cost (AC) : It is the cumulative actual expenses
including apportioned management reserve incurred
in the project to date..
 For example, if a project has budget of Rs 10,00,000
and Rs 5,00,000 has been spent on the project to date,
the AC of the project would be Rs 5,00,000 . Actual
Cost is also known as Actual Cost of Work
Performed.(ACWP).
Earned Value Analysis
 If a project progresses exactly as per cost and time integrated plan, the
3 parameters will be identical. But this rarely happens.
 The difference (EV-AC) and (EV-PV) during implementation phases
generates variances.
 Cost Variance: Cost Variance is computed by comparing actual
performance (AC) with the budgeted cost of work performed (EV).
 Cost Variance(CV)= EV-AC.
 =2,50,000-500000
 =-250000/-
 If CV is positive the project has under-run, i.e. the cost incurred is less
than planned or budgeted cost.
 If CV is negative the project has over-run, i.e. the cost incurred is more
than planned or budgeted cost.
 If CV is zero, then the project is proceeding according to the budgeted
cost.
Earned Value Analysis
 Schedule Variance(SV): Schedule Variance is computed by
comparing planned performance (PV) with the budgeted cost of
work performed (EV).
 Schedule Variance(SV)= EV-PV.
 =250000-400000
 =-150000
 If SV is positive then the project is ahead of its planned cost or
planned schedule, i.e. earned value of the work performed is
higher than planned or scheduled earned value.
 If SV is negative, then the project is behind its planned cost or
planned schedule, i.e. earned value of the work performed is less
than planned or scheduled earned value.
 If SV is zero, then the project is proceeding according to the
planned schedule.
Earned Value Analysis
 Performance Indices:- It determines how efficiently the
task was done and what its implications will be on future
trends. The future trends in productivity, cost and time
performance can be predicted as under
 Cost Performance Index (CPI)= EV/AC
 =250000/500000
 =0.5
 Schedule Performance Index(SPI)=EV/PV
 =250000/400000
 =0.625
 An index of 1.0 or greater indicates a favorable performance
and less than 1.0 implies an unfavorable trend.
Earned Value Analysis
 Estimate at completion- The project manager
should prepare a to-complete forecast, which is an
estimate of time and cost needed to complete the
project.
 This forecast plus the current status of the project
provide a forecast of the date and cost of the project at
completion.
 Estimated Cost to complete the project(ETC) =(BAC-EV)/CPI
 Where BAC is the budgeted cost at completion for the project (the
same as the total planned value as of the target completion date)
 ETC= (1000000-250000)/0.5
 = 1500000/-
Earned Value Analysis
 EAC (Estimated cost at completion)=AC+ ETC
 =500000+1500000
 =2000000
Earned Value Analysis
Problem from tutorial
Solution
 1.Planned Value(BCWS)= 4 robots x 100000
 = Rs 400000 /-
 2.Earned Value (BCWP)=3 robots x 100000
 =Rs 300000/-
 3.Actual Cost(ACWP) =3 robots x 150000
 =Rs 450000
 4.Cost Variance(CV)= EV-AC
 = 300000-450000
 =-150000
 The project has overrun by Rs 150000 till date
Solution
 5. Cost Performance Index (CPI)= EV/AC
 =300000/450000
 =2/3=0.667
 6. Schedule Variance(SV)= EV-PV.
 =300000-400000
 =-100000
 The project is behind schedule by Rs 100000 work
 7. Schedule Performance Index(SPI)=EV/PV
 =300000/400000
 =0.75
 The project is behind schedule by 25 % time.
Solution
 8. Estimated Cost to complete the project(ETC) =(BAC-EV)/CPI
 =(400000-300000)/0.667
 =Rs 150000
 The project will require additional Rs 150000 to complete.
 9. EAC (Estimated cost at completion)=AC+ ETC
 =450000+150000
 =Rs 600000
 The estimated project cost will be Rs 600000 as against the budgeted
cost of Rs 400000 if it continues in the same way.
Earned value analysis (1)

More Related Content

What's hot

09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost ManagementBhuWan Khadka
 
Earned value analysis - presentation
Earned value analysis  -  presentationEarned value analysis  -  presentation
Earned value analysis - presentationProPM Academy
 
Earned value management for Beginners
Earned value management for Beginners Earned value management for Beginners
Earned value management for Beginners Shenin Hassan
 
Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management A Makwana
 
Construction Project management
Construction Project management Construction Project management
Construction Project management Anupama holla
 
Earned value
Earned valueEarned value
Earned valueOliver
 
Project controls
Project controlsProject controls
Project controlsAshok Kumar
 
Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost controlGuhan M
 
Work breakdown structure in project management ppt by kiran j
Work breakdown structure in project management ppt by kiran jWork breakdown structure in project management ppt by kiran j
Work breakdown structure in project management ppt by kiran jIIT delhi
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project schedulingSoe Naing Win
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of schedulingjmd2011
 
Project management & Network analysis
Project management & Network analysisProject management & Network analysis
Project management & Network analysisHarinadh Karimikonda
 
Role and Responsibilities of Project Manager
Role and Responsibilities of Project ManagerRole and Responsibilities of Project Manager
Role and Responsibilities of Project Managerkanti choudhary
 
construction project planing
 construction project planing construction project planing
construction project planingSANJEEV Wazir
 
Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysisADITYA GHUMARE
 
Project Scope Management -
Project Scope Management - Project Scope Management -
Project Scope Management - dyaksa hanindito
 

What's hot (20)

09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost Management
 
Earned value analysis - presentation
Earned value analysis  -  presentationEarned value analysis  -  presentation
Earned value analysis - presentation
 
Earned value management for Beginners
Earned value management for Beginners Earned value management for Beginners
Earned value management for Beginners
 
Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management
 
Construction Project management
Construction Project management Construction Project management
Construction Project management
 
Earned value
Earned valueEarned value
Earned value
 
Project controls
Project controlsProject controls
Project controls
 
Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost control
 
Work breakdown structure in project management ppt by kiran j
Work breakdown structure in project management ppt by kiran jWork breakdown structure in project management ppt by kiran j
Work breakdown structure in project management ppt by kiran j
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of scheduling
 
Contingency and management reserve
Contingency and management reserveContingency and management reserve
Contingency and management reserve
 
Project management & Network analysis
Project management & Network analysisProject management & Network analysis
Project management & Network analysis
 
Role and Responsibilities of Project Manager
Role and Responsibilities of Project ManagerRole and Responsibilities of Project Manager
Role and Responsibilities of Project Manager
 
construction project planing
 construction project planing construction project planing
construction project planing
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structure
 
Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysis
 
Project Scope Management -
Project Scope Management - Project Scope Management -
Project Scope Management -
 

Similar to Earned value analysis (1)

Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)Ejaz Bhatti
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisBECM, RUET, Bangladesh
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementBaroness PM
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.pptProfDrAnbalaganChinn
 
PM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfPM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfNajm Naqvi
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneWaleed Hamdy Albana
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 waleed hamdy
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxsagarlesley
 
Earned Value Probabilistic Forecasting Using Monte Carlo Simulation
Earned Value Probabilistic Forecasting Using Monte Carlo SimulationEarned Value Probabilistic Forecasting Using Monte Carlo Simulation
Earned Value Probabilistic Forecasting Using Monte Carlo SimulationRicardo Viana Vargas
 
What Is Earned Value Analysis
What Is Earned Value AnalysisWhat Is Earned Value Analysis
What Is Earned Value AnalysisSimonRobertson
 

Similar to Earned value analysis (1) (20)

Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
Project Management EVM & SCBA
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)
 
Project cost control
Project cost controlProject cost control
Project cost control
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysis
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value Management
 
PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
 
Earned value management
Earned value managementEarned value management
Earned value management
 
PM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfPM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdf
 
EVA - Metrics.ppt
EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.ppt
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part One
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
Project monitoring lecture 1
Project monitoring lecture 1Project monitoring lecture 1
Project monitoring lecture 1
 
Earned Value Probabilistic Forecasting Using Monte Carlo Simulation
Earned Value Probabilistic Forecasting Using Monte Carlo SimulationEarned Value Probabilistic Forecasting Using Monte Carlo Simulation
Earned Value Probabilistic Forecasting Using Monte Carlo Simulation
 
What Is Earned Value Analysis
What Is Earned Value AnalysisWhat Is Earned Value Analysis
What Is Earned Value Analysis
 

Recently uploaded

Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 

Recently uploaded (20)

Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 

Earned value analysis (1)

  • 1. Earned Value Analysis  EVA is a system for planning and controlling project cost performance.  It establishes a work package earned value baseline by integrating project scope, time , schedule and cost objectives. This baseline is called control account is used for performance evaluation on a given date.  Analysis of variance from baseline provides cost related information for problem identification, trend analysis and corrective action.
  • 2. Earned Value Analysis  Earned value analysis serve 2 main purposes-  1. To analyze the cost changes resulting in time and cost over-runs or under-runs for taking timely corrective actions such as modifying cash flow, and updating financial forecasts and project profitability expectations.  2.To update key personnel on anticipated cost changes in their field of responsibility, so as to create cost consciousness for exploring means of minimizing wastage and reducing costs.
  • 3. Earned Value Analysis  Consider a project with projected cost at completion of Rs 1,60,000 and completion period of 20 weeks. When reviewed at the end of 10th week, it shows that as against the planned cost of Rs 92000/- at the end of 10 the week provided all the work is done as planned; it has incurred expenditure of Rs 90,000.  It raises many question such as how well is the project actually performing; is it nor performing well as actual expenses spent are less than budgeted, is the project behind the schedule work or could be that the work has been done nicely and project may be completed at a cost that is below budget.
  • 4. Earned Value Analysis  Analysis of variance from baseline using EVA yields variety of variances that are analyzed to determine the current status, initiate corrective actions and forecast the future trends.  EVM is the process of measuring performance of project work against a baseline plan. The application of EVM enables better integration of cost and time schedule control with responsibility defined in OBS.  It provides better overall picture of performance and gives better forecast of the final costs at completion.  Thus EV represents a translation of project cost into work progress.
  • 5. Earned Value Analysis  Planned Value(PV): It is the cumulative planned value of the authorized work, scheduled for completion to date at contract rate. It represents time- phased cost projections of planned value in the budget. For example, if a project has budget of Rs 1,00,000 and 5 month schedule shows that 40 % of the value of project work should be completed at the end oof 5th month, then PV at the end of 5th month is Rs 4,00,000/-. The planned value is also called as Budgeted Cost of Work Scheduled(BCWS).
  • 6. Earned Value Analysis  Earned Value (EV) : It is the cumulative value of the authorized work completed to date at contract rate.  For example, if a project has budget of Rs 1,00,000 and work completed to date represents 25 % of the value of entire project work as against the 40 % planned, then EV at the end of 5th month is Rs 2,50,000/-. The Earned value is also called as Budgeted Cost of Work Performed.(BCWP).
  • 7. Earned Value Analysis  Actual Cost (AC) : It is the cumulative actual expenses including apportioned management reserve incurred in the project to date..  For example, if a project has budget of Rs 10,00,000 and Rs 5,00,000 has been spent on the project to date, the AC of the project would be Rs 5,00,000 . Actual Cost is also known as Actual Cost of Work Performed.(ACWP).
  • 8. Earned Value Analysis  If a project progresses exactly as per cost and time integrated plan, the 3 parameters will be identical. But this rarely happens.  The difference (EV-AC) and (EV-PV) during implementation phases generates variances.  Cost Variance: Cost Variance is computed by comparing actual performance (AC) with the budgeted cost of work performed (EV).  Cost Variance(CV)= EV-AC.  =2,50,000-500000  =-250000/-  If CV is positive the project has under-run, i.e. the cost incurred is less than planned or budgeted cost.  If CV is negative the project has over-run, i.e. the cost incurred is more than planned or budgeted cost.  If CV is zero, then the project is proceeding according to the budgeted cost.
  • 9. Earned Value Analysis  Schedule Variance(SV): Schedule Variance is computed by comparing planned performance (PV) with the budgeted cost of work performed (EV).  Schedule Variance(SV)= EV-PV.  =250000-400000  =-150000  If SV is positive then the project is ahead of its planned cost or planned schedule, i.e. earned value of the work performed is higher than planned or scheduled earned value.  If SV is negative, then the project is behind its planned cost or planned schedule, i.e. earned value of the work performed is less than planned or scheduled earned value.  If SV is zero, then the project is proceeding according to the planned schedule.
  • 10. Earned Value Analysis  Performance Indices:- It determines how efficiently the task was done and what its implications will be on future trends. The future trends in productivity, cost and time performance can be predicted as under  Cost Performance Index (CPI)= EV/AC  =250000/500000  =0.5  Schedule Performance Index(SPI)=EV/PV  =250000/400000  =0.625  An index of 1.0 or greater indicates a favorable performance and less than 1.0 implies an unfavorable trend.
  • 11. Earned Value Analysis  Estimate at completion- The project manager should prepare a to-complete forecast, which is an estimate of time and cost needed to complete the project.  This forecast plus the current status of the project provide a forecast of the date and cost of the project at completion.  Estimated Cost to complete the project(ETC) =(BAC-EV)/CPI  Where BAC is the budgeted cost at completion for the project (the same as the total planned value as of the target completion date)  ETC= (1000000-250000)/0.5  = 1500000/-
  • 12. Earned Value Analysis  EAC (Estimated cost at completion)=AC+ ETC  =500000+1500000  =2000000
  • 15. Solution  1.Planned Value(BCWS)= 4 robots x 100000  = Rs 400000 /-  2.Earned Value (BCWP)=3 robots x 100000  =Rs 300000/-  3.Actual Cost(ACWP) =3 robots x 150000  =Rs 450000  4.Cost Variance(CV)= EV-AC  = 300000-450000  =-150000  The project has overrun by Rs 150000 till date
  • 16. Solution  5. Cost Performance Index (CPI)= EV/AC  =300000/450000  =2/3=0.667  6. Schedule Variance(SV)= EV-PV.  =300000-400000  =-100000  The project is behind schedule by Rs 100000 work  7. Schedule Performance Index(SPI)=EV/PV  =300000/400000  =0.75  The project is behind schedule by 25 % time.
  • 17. Solution  8. Estimated Cost to complete the project(ETC) =(BAC-EV)/CPI  =(400000-300000)/0.667  =Rs 150000  The project will require additional Rs 150000 to complete.  9. EAC (Estimated cost at completion)=AC+ ETC  =450000+150000  =Rs 600000  The estimated project cost will be Rs 600000 as against the budgeted cost of Rs 400000 if it continues in the same way.