SlideShare a Scribd company logo
Earned Value
Management
What is Earned
Value
Management?
Earned Value Management (EVM) is comprised
of several formulas that provide an analysis of a
project and its current state regarding budget
and schedule.
EARNED VALUE
MANAGEMENT:
DEFINITION OF VALUES
Budget At
Completion
(BAC)
The Planned
Expected Costs to
Complete the Project
Actual Cost
(AC)
The actual amount of
money spent at a
given point
Planned
Value (PV)
The value of the work that should have
been completed at any given point for the
total project to remain on budget and
schedule
PV =
(Planned Percentage Completed)
Multiplied by the Budget At Completion
(BAC)
Planned
Value (PV):
Example
•Budget At Completion: $20,000
•Planned Schedule Duration: 100 Days
•Current Day in the Project: 15 Days
•Actual Work Completed: 12%
•Actual Costs (AC): $3,000
•Planned Percent Completed: 15 Days / 100 Days = 0.15 = 15%
15% X $20,000 = $3,000
Planned Value = $3,000
Earned
Value (EV)
The estimated value of the work
completed at any given point
EV = (Actual Percentage
Completed) X BAC
Earned Value
(EV):
Example
•Budget At Completion: $20,000
•Planned Schedule Duration: 100 Days
•Current Day in the Project: 15 Days
•Actual Work Completed: 12%
•Actual Costs (AC): $3,000
•Planned Percent Completed: 15 Days / 100 Days = 0.15 = 15%
•Planned Value: $3,000
12% X $20,000 = $2,400
Earned Value = $2,400
Cost
Variance
(CV)
The difference between the Earned Value
(EV) and the Actual Cost (AC) that shows
how much ahead or behind in the budget
the project is at any given point
A negative CV is the amount the project is
over budget
A positive CV is the amount the project is
under budget
Cost
Variance
(CV):
Example
•Budget At Completion: $20,000
•Planned Schedule Duration: 100 Days
•Current Day in the Project: 15 Days
•Actual Work Completed: 12%
•Actual Costs (AC): $3,000
•Planned Percent Completed: 15 Days / 100 Days = 0.15 = 15%
•Planned Value: $3,000
•Earned Value: $2,400
$2,400 - $3,000 = -$600
Cost Variance = -$600
This Project is over budget
Cost
Performance
Index (CPI)
An indicator into the speed or rate of spending compared
to the value being generated (Is the project budget on
track)
CPI less than 1 shows the project is spending too fast and is
over budget
CPI equal to 1 shows the project budget is on track
CPI greater than 1 shows the project is under budget
Cost Performance Index = Earned Value Divided by Actual
Cost
Cost
Performance
Index (CPI):
Example
•Budget At Completion: $20,000
•Planned Schedule Duration: 100 Days
•Current Day in the Project: 15 Days
•Actual Work Completed: 12%
•Actual Costs (AC): $3,000
•Planned Percent Completed: 15 Days / 100 Days = 0.15 = 15%
•Planned Value: $3,000
•Earned Value: $2,400
•Cost Variance: -$600
$2,400/$3,000 = 0.8
Cost Performance Index = 0.8
This Project is over budget
Schedule
Variance
(SV)
The difference between the planned work
completed versus the amount of work that
was completed
A negative SV is an estimate of how much
the project is behind schedule
A positive SV is an estimate of how much
the project is ahead of schedule
Schedule Variance = Earned Value – Planned
Value
Schedule
Variance
(SV):
Example
•Budget At Completion: $20,000
•Planned Schedule Duration: 100 Days
•Current Day in the Project: 15 Days
•Actual Work Completed: 12%
•Actual Costs (AC): $3,000
•Planned Percent Completed: 15 Days / 100 Days = 0.15 = 15%
•Planned Value: $3,000
•Earned Value: $2,400
•Cost Variance: -$600
•Cost Performance Index: 0.8
$2,400 - $3,000 = -$600
Schedule Variance = -$600
This Project is $600 worth of work
behind schedule
Schedule
Performance
Index (SPI)
The indicator into the speed or rate of the work being getting
completed compared to the work that was expected to be
completed
SPI less than 1 shows the project as being behind schedule
SPI equal to 1 shows the project as being on track
SPI greater than 1 shows that the project is ahead of
schedule
Schedule Performance Index = Earned Value divided by
Planned Value
Schedule
Performance
Index (SPI):
Example
•Budget At Completion: $20,000
•Planned Schedule Duration: 100 Days
•Current Day in the Project: 15 Days
•Actual Work Completed: 12%
•Actual Costs (AC): $3,000
•Planned Percent Completed: 15 Days / 100 Days = 0.15 = 15%
•Planned Value: $3,000
•Earned Value: $2,400
•Cost Variance: -$600
•Cost Performance Index: 0.8
•Schedule Variance: -$600
$2,400/$3,000 = 0.8
Schedule Performance Index = 0.8
This Project is behind schedule
Other EVM Values
Estimate At Completion
(EAC)
• Based on the current
spending rate, EAC is
an estimate of how
much it will actually
cost to complete the
whole project
• EAC = BAC/CPI
Estimate To Completion
(ETC)
• Based on the current
spending rate, ETC is an
estimate of how much
it will actually cost
from a specified point
forward to complete
the project; it is simply
the EAC minus the
current actual costs
• ETC = EAC – AC
Variance At Completion
(VAC)
• The difference
between the planned
budget (BAC) and the
new forecast budget
(EAC)
• VAC = BAC – EAC
To-Complete
Performance Index
• An estimate of how
hard it would be to
meet the project’s
objectives
• TCPI (BAC – EV)/(BAC –
AC)
Earned Value
Management
Joshua Render
https://agile-mercurial.com
https://twentyfirstcenturyworkfor
ce.com/

More Related Content

What's hot

7.4 Earned Value Analysis
7.4 Earned Value Analysis7.4 Earned Value Analysis
7.4 Earned Value Analysis
DavidMcLachlan1
 
Lec 03 project life cycle
Lec 03 project life cycleLec 03 project life cycle
Lec 03 project life cycle
SAJID ALI RUK
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)
Harshit Mahajan
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
Mansoor Shoaib
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
waleed hamdy
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
Ahmed Rami Elsherif, PMP, ITBMC
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
mohamed elashri
 
Earned value analysis - presentation
Earned value analysis  -  presentationEarned value analysis  -  presentation
Earned value analysis - presentation
ProPM Academy
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Schedulingsslovepk
 
An Introduction To Project Management
An Introduction To Project ManagementAn Introduction To Project Management
An Introduction To Project ManagementAshish Mittal
 
Project Management
Project ManagementProject Management
Project Management
Hamdard University
 
Project Management Tools and Techniques
Project Management Tools and TechniquesProject Management Tools and Techniques
Project Management Tools and Techniques
MaRS Discovery District
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure pptnazi2020
 
Earned Value Analysis - Basic Concepts
Earned Value Analysis  - Basic ConceptsEarned Value Analysis  - Basic Concepts
Earned Value Analysis - Basic Concepts
Ricardo Viana Vargas
 
Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Project Cost Management - PMBOK6
Project Cost Management - PMBOK6
Agus Suhanto
 
Project Management Concepts
Project Management ConceptsProject Management Concepts
Project Management Concepts
Jeremy Jay V. Lim, MBB, PMP
 
Project cost management PMBOK 5th Edition
Project cost management PMBOK 5th EditionProject cost management PMBOK 5th Edition
Project cost management PMBOK 5th Edition
pankajsh10
 

What's hot (20)

7.4 Earned Value Analysis
7.4 Earned Value Analysis7.4 Earned Value Analysis
7.4 Earned Value Analysis
 
Lec 03 project life cycle
Lec 03 project life cycleLec 03 project life cycle
Lec 03 project life cycle
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Earned value analysis - presentation
Earned value analysis  -  presentationEarned value analysis  -  presentation
Earned value analysis - presentation
 
Project Control Process
Project Control ProcessProject Control Process
Project Control Process
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Scheduling
 
An Introduction To Project Management
An Introduction To Project ManagementAn Introduction To Project Management
An Introduction To Project Management
 
Project Management
Project ManagementProject Management
Project Management
 
Project Management Tools and Techniques
Project Management Tools and TechniquesProject Management Tools and Techniques
Project Management Tools and Techniques
 
Project cost management-slides
Project cost management-slidesProject cost management-slides
Project cost management-slides
 
Work Breakdown Structure
Work Breakdown StructureWork Breakdown Structure
Work Breakdown Structure
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure ppt
 
Earned Value Analysis - Basic Concepts
Earned Value Analysis  - Basic ConceptsEarned Value Analysis  - Basic Concepts
Earned Value Analysis - Basic Concepts
 
Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Project Cost Management - PMBOK6
Project Cost Management - PMBOK6
 
Project Management Concepts
Project Management ConceptsProject Management Concepts
Project Management Concepts
 
Project cost management PMBOK 5th Edition
Project cost management PMBOK 5th EditionProject cost management PMBOK 5th Edition
Project cost management PMBOK 5th Edition
 

Similar to Earned value management (EVM)

Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
sagarlesley
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
Ahmed Elshaboury,PMP,LEED GA
 
EVA - Metrics.ppt
EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.ppt
NivethaSampath3
 
CAPM study session 4
CAPM study session 4CAPM study session 4
CAPM study session 4
Kinetic Potential
 
Culture Check on using Earned Value in Organization
Culture Check on using Earned Value in OrganizationCulture Check on using Earned Value in Organization
Culture Check on using Earned Value in Organization
Ghassan Kabbara
 
Basics of EVM.pdf
Basics of  EVM.pdfBasics of  EVM.pdf
Basics of EVM.pdf
sajidkhan82714
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
Dhamo daran
 
Module 06 Adv PM Budget Mgmt.ppt
Module 06 Adv PM Budget Mgmt.pptModule 06 Adv PM Budget Mgmt.ppt
Module 06 Adv PM Budget Mgmt.ppt
SandeepChauhan334237
 
Module 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.pptModule 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.ppt
AsBali1
 
Earnvalue analysis in Software engineering
Earnvalue analysis in Software engineeringEarnvalue analysis in Software engineering
Earnvalue analysis in Software engineering
Nitish Kumar
 
Pm 8 cost_management
Pm 8 cost_managementPm 8 cost_management
Pm 8 cost_managementRadiant Minds
 
Pm 8 cost_management
Pm 8 cost_managementPm 8 cost_management
Pm 8 cost_management
Radiant Minds
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
ProfDrAnbalaganChinn
 
PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
Bhaskara Reddy Sannapureddy
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysis
Nikhil Raj
 
COST MANAGEMENT REPORT
COST MANAGEMENT REPORT COST MANAGEMENT REPORT
COST MANAGEMENT REPORT
Jo Balucanag - Bitonio
 
October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6
October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6
October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6
HARDIK PARIKH
 

Similar to Earned value management (EVM) (20)

Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
Project Management EVM & SCBA
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
EVA - Metrics.ppt
EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.ppt
 
CAPM study session 4
CAPM study session 4CAPM study session 4
CAPM study session 4
 
Culture Check on using Earned Value in Organization
Culture Check on using Earned Value in OrganizationCulture Check on using Earned Value in Organization
Culture Check on using Earned Value in Organization
 
Basics of EVM.pdf
Basics of  EVM.pdfBasics of  EVM.pdf
Basics of EVM.pdf
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
 
Module 06 Adv PM Budget Mgmt.ppt
Module 06 Adv PM Budget Mgmt.pptModule 06 Adv PM Budget Mgmt.ppt
Module 06 Adv PM Budget Mgmt.ppt
 
Module 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.pptModule 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.ppt
 
Earnvalue analysis in Software engineering
Earnvalue analysis in Software engineeringEarnvalue analysis in Software engineering
Earnvalue analysis in Software engineering
 
Pm 8 cost_management
Pm 8 cost_managementPm 8 cost_management
Pm 8 cost_management
 
Pm 8 cost_management
Pm 8 cost_managementPm 8 cost_management
Pm 8 cost_management
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
 
PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
 
Project managment 6 (a)
Project managment 6 (a)Project managment 6 (a)
Project managment 6 (a)
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysis
 
COST MANAGEMENT REPORT
COST MANAGEMENT REPORT COST MANAGEMENT REPORT
COST MANAGEMENT REPORT
 
October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6
October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6
October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6
 

More from Joshua Render

Setting SMART Goals - What are SMART Goals?
Setting SMART Goals - What are SMART Goals?Setting SMART Goals - What are SMART Goals?
Setting SMART Goals - What are SMART Goals?
Joshua Render
 
Alderfer's ERG theory of motivation
Alderfer's ERG theory of motivationAlderfer's ERG theory of motivation
Alderfer's ERG theory of motivation
Joshua Render
 
MacGregor’s XY Theory and Ouchi’s Theory Z
MacGregor’s XY Theory and Ouchi’s Theory ZMacGregor’s XY Theory and Ouchi’s Theory Z
MacGregor’s XY Theory and Ouchi’s Theory Z
Joshua Render
 
Big Five Personality Traits: The Five Factor Model
Big Five Personality Traits: The Five Factor ModelBig Five Personality Traits: The Five Factor Model
Big Five Personality Traits: The Five Factor Model
Joshua Render
 
Drexler-Sibbet Team Performance Model
Drexler-Sibbet Team Performance ModelDrexler-Sibbet Team Performance Model
Drexler-Sibbet Team Performance Model
Joshua Render
 
What is Kanban?
What is Kanban?What is Kanban?
What is Kanban?
Joshua Render
 
7 Core Concepts of Lean
7 Core Concepts of Lean7 Core Concepts of Lean
7 Core Concepts of Lean
Joshua Render
 
Guide to User Story Creation
Guide to User Story CreationGuide to User Story Creation
Guide to User Story Creation
Joshua Render
 
Tuckman's Model
Tuckman's ModelTuckman's Model
Tuckman's Model
Joshua Render
 
Project Management Processes
Project Management ProcessesProject Management Processes
Project Management Processes
Joshua Render
 
Stakeholder Management Knowledge Area
Stakeholder Management Knowledge AreaStakeholder Management Knowledge Area
Stakeholder Management Knowledge Area
Joshua Render
 
Procurement Management Knowledge Area
Procurement Management Knowledge AreaProcurement Management Knowledge Area
Procurement Management Knowledge Area
Joshua Render
 
Risk Management Knowledge Area
Risk Management Knowledge AreaRisk Management Knowledge Area
Risk Management Knowledge Area
Joshua Render
 
Communication Management Knowledge Area
Communication Management Knowledge AreaCommunication Management Knowledge Area
Communication Management Knowledge Area
Joshua Render
 
Resource Management Knowledge Area
Resource Management Knowledge AreaResource Management Knowledge Area
Resource Management Knowledge Area
Joshua Render
 
Quality Management Knowledge Area
Quality Management Knowledge AreaQuality Management Knowledge Area
Quality Management Knowledge Area
Joshua Render
 
Project Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge AreaProject Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge Area
Joshua Render
 
Project Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge AreaProject Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge Area
Joshua Render
 
What is Osmotic Communication?
What is Osmotic Communication?What is Osmotic Communication?
What is Osmotic Communication?
Joshua Render
 
Project Scope Management Knowledge Area
Project Scope Management Knowledge AreaProject Scope Management Knowledge Area
Project Scope Management Knowledge Area
Joshua Render
 

More from Joshua Render (20)

Setting SMART Goals - What are SMART Goals?
Setting SMART Goals - What are SMART Goals?Setting SMART Goals - What are SMART Goals?
Setting SMART Goals - What are SMART Goals?
 
Alderfer's ERG theory of motivation
Alderfer's ERG theory of motivationAlderfer's ERG theory of motivation
Alderfer's ERG theory of motivation
 
MacGregor’s XY Theory and Ouchi’s Theory Z
MacGregor’s XY Theory and Ouchi’s Theory ZMacGregor’s XY Theory and Ouchi’s Theory Z
MacGregor’s XY Theory and Ouchi’s Theory Z
 
Big Five Personality Traits: The Five Factor Model
Big Five Personality Traits: The Five Factor ModelBig Five Personality Traits: The Five Factor Model
Big Five Personality Traits: The Five Factor Model
 
Drexler-Sibbet Team Performance Model
Drexler-Sibbet Team Performance ModelDrexler-Sibbet Team Performance Model
Drexler-Sibbet Team Performance Model
 
What is Kanban?
What is Kanban?What is Kanban?
What is Kanban?
 
7 Core Concepts of Lean
7 Core Concepts of Lean7 Core Concepts of Lean
7 Core Concepts of Lean
 
Guide to User Story Creation
Guide to User Story CreationGuide to User Story Creation
Guide to User Story Creation
 
Tuckman's Model
Tuckman's ModelTuckman's Model
Tuckman's Model
 
Project Management Processes
Project Management ProcessesProject Management Processes
Project Management Processes
 
Stakeholder Management Knowledge Area
Stakeholder Management Knowledge AreaStakeholder Management Knowledge Area
Stakeholder Management Knowledge Area
 
Procurement Management Knowledge Area
Procurement Management Knowledge AreaProcurement Management Knowledge Area
Procurement Management Knowledge Area
 
Risk Management Knowledge Area
Risk Management Knowledge AreaRisk Management Knowledge Area
Risk Management Knowledge Area
 
Communication Management Knowledge Area
Communication Management Knowledge AreaCommunication Management Knowledge Area
Communication Management Knowledge Area
 
Resource Management Knowledge Area
Resource Management Knowledge AreaResource Management Knowledge Area
Resource Management Knowledge Area
 
Quality Management Knowledge Area
Quality Management Knowledge AreaQuality Management Knowledge Area
Quality Management Knowledge Area
 
Project Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge AreaProject Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge Area
 
Project Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge AreaProject Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge Area
 
What is Osmotic Communication?
What is Osmotic Communication?What is Osmotic Communication?
What is Osmotic Communication?
 
Project Scope Management Knowledge Area
Project Scope Management Knowledge AreaProject Scope Management Knowledge Area
Project Scope Management Knowledge Area
 

Recently uploaded

Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
Workforce Group
 
Exploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social DreamingExploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social Dreaming
Nicola Wreford-Howard
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
Cynthia Clay
 
The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...
awaisafdar
 
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
taqyed
 
Memorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.pptMemorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.ppt
seri bangash
 
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
PaulBryant58
 
FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134
LR1709MUSIC
 
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdfDigital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
Jos Voskuil
 
What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
seoforlegalpillers
 
Improving profitability for small business
Improving profitability for small businessImproving profitability for small business
Improving profitability for small business
Ben Wann
 
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
BBPMedia1
 
Project File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdfProject File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdf
RajPriye
 
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Navpack & Print
 
20240425_ TJ Communications Credentials_compressed.pdf
20240425_ TJ Communications Credentials_compressed.pdf20240425_ TJ Communications Credentials_compressed.pdf
20240425_ TJ Communications Credentials_compressed.pdf
tjcomstrang
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
ofm712785
 
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdfSearch Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Arihant Webtech Pvt. Ltd
 
Business Valuation Principles for Entrepreneurs
Business Valuation Principles for EntrepreneursBusiness Valuation Principles for Entrepreneurs
Business Valuation Principles for Entrepreneurs
Ben Wann
 
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
Kumar Satyam
 
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptxCADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
fakeloginn69
 

Recently uploaded (20)

Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
 
Exploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social DreamingExploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social Dreaming
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...
 
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
 
Memorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.pptMemorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.ppt
 
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
 
FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134
 
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdfDigital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
 
What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
 
Improving profitability for small business
Improving profitability for small businessImproving profitability for small business
Improving profitability for small business
 
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
 
Project File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdfProject File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdf
 
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
 
20240425_ TJ Communications Credentials_compressed.pdf
20240425_ TJ Communications Credentials_compressed.pdf20240425_ TJ Communications Credentials_compressed.pdf
20240425_ TJ Communications Credentials_compressed.pdf
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
 
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdfSearch Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
 
Business Valuation Principles for Entrepreneurs
Business Valuation Principles for EntrepreneursBusiness Valuation Principles for Entrepreneurs
Business Valuation Principles for Entrepreneurs
 
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
 
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptxCADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
 

Earned value management (EVM)

  • 2. What is Earned Value Management? Earned Value Management (EVM) is comprised of several formulas that provide an analysis of a project and its current state regarding budget and schedule.
  • 4. Budget At Completion (BAC) The Planned Expected Costs to Complete the Project
  • 5. Actual Cost (AC) The actual amount of money spent at a given point
  • 6. Planned Value (PV) The value of the work that should have been completed at any given point for the total project to remain on budget and schedule PV = (Planned Percentage Completed) Multiplied by the Budget At Completion (BAC)
  • 7. Planned Value (PV): Example •Budget At Completion: $20,000 •Planned Schedule Duration: 100 Days •Current Day in the Project: 15 Days •Actual Work Completed: 12% •Actual Costs (AC): $3,000 •Planned Percent Completed: 15 Days / 100 Days = 0.15 = 15% 15% X $20,000 = $3,000 Planned Value = $3,000
  • 8. Earned Value (EV) The estimated value of the work completed at any given point EV = (Actual Percentage Completed) X BAC
  • 9. Earned Value (EV): Example •Budget At Completion: $20,000 •Planned Schedule Duration: 100 Days •Current Day in the Project: 15 Days •Actual Work Completed: 12% •Actual Costs (AC): $3,000 •Planned Percent Completed: 15 Days / 100 Days = 0.15 = 15% •Planned Value: $3,000 12% X $20,000 = $2,400 Earned Value = $2,400
  • 10. Cost Variance (CV) The difference between the Earned Value (EV) and the Actual Cost (AC) that shows how much ahead or behind in the budget the project is at any given point A negative CV is the amount the project is over budget A positive CV is the amount the project is under budget
  • 11. Cost Variance (CV): Example •Budget At Completion: $20,000 •Planned Schedule Duration: 100 Days •Current Day in the Project: 15 Days •Actual Work Completed: 12% •Actual Costs (AC): $3,000 •Planned Percent Completed: 15 Days / 100 Days = 0.15 = 15% •Planned Value: $3,000 •Earned Value: $2,400 $2,400 - $3,000 = -$600 Cost Variance = -$600 This Project is over budget
  • 12. Cost Performance Index (CPI) An indicator into the speed or rate of spending compared to the value being generated (Is the project budget on track) CPI less than 1 shows the project is spending too fast and is over budget CPI equal to 1 shows the project budget is on track CPI greater than 1 shows the project is under budget Cost Performance Index = Earned Value Divided by Actual Cost
  • 13. Cost Performance Index (CPI): Example •Budget At Completion: $20,000 •Planned Schedule Duration: 100 Days •Current Day in the Project: 15 Days •Actual Work Completed: 12% •Actual Costs (AC): $3,000 •Planned Percent Completed: 15 Days / 100 Days = 0.15 = 15% •Planned Value: $3,000 •Earned Value: $2,400 •Cost Variance: -$600 $2,400/$3,000 = 0.8 Cost Performance Index = 0.8 This Project is over budget
  • 14. Schedule Variance (SV) The difference between the planned work completed versus the amount of work that was completed A negative SV is an estimate of how much the project is behind schedule A positive SV is an estimate of how much the project is ahead of schedule Schedule Variance = Earned Value – Planned Value
  • 15. Schedule Variance (SV): Example •Budget At Completion: $20,000 •Planned Schedule Duration: 100 Days •Current Day in the Project: 15 Days •Actual Work Completed: 12% •Actual Costs (AC): $3,000 •Planned Percent Completed: 15 Days / 100 Days = 0.15 = 15% •Planned Value: $3,000 •Earned Value: $2,400 •Cost Variance: -$600 •Cost Performance Index: 0.8 $2,400 - $3,000 = -$600 Schedule Variance = -$600 This Project is $600 worth of work behind schedule
  • 16. Schedule Performance Index (SPI) The indicator into the speed or rate of the work being getting completed compared to the work that was expected to be completed SPI less than 1 shows the project as being behind schedule SPI equal to 1 shows the project as being on track SPI greater than 1 shows that the project is ahead of schedule Schedule Performance Index = Earned Value divided by Planned Value
  • 17. Schedule Performance Index (SPI): Example •Budget At Completion: $20,000 •Planned Schedule Duration: 100 Days •Current Day in the Project: 15 Days •Actual Work Completed: 12% •Actual Costs (AC): $3,000 •Planned Percent Completed: 15 Days / 100 Days = 0.15 = 15% •Planned Value: $3,000 •Earned Value: $2,400 •Cost Variance: -$600 •Cost Performance Index: 0.8 •Schedule Variance: -$600 $2,400/$3,000 = 0.8 Schedule Performance Index = 0.8 This Project is behind schedule
  • 18. Other EVM Values Estimate At Completion (EAC) • Based on the current spending rate, EAC is an estimate of how much it will actually cost to complete the whole project • EAC = BAC/CPI Estimate To Completion (ETC) • Based on the current spending rate, ETC is an estimate of how much it will actually cost from a specified point forward to complete the project; it is simply the EAC minus the current actual costs • ETC = EAC – AC Variance At Completion (VAC) • The difference between the planned budget (BAC) and the new forecast budget (EAC) • VAC = BAC – EAC To-Complete Performance Index • An estimate of how hard it would be to meet the project’s objectives • TCPI (BAC – EV)/(BAC – AC)