5. COST MANAGEMENT
Project Management Training,
Qais Ur Rehman Rasooli, PMP
Cost Management
• Project cost management includes the
processes involved in,
• Planning
• Estimating
• Budgeting
• Financing
• Funding
• Managing and Controlling cost
So What is Project Cost Management?..cont’d
Financial
performance
of the
product
Product Life
cycle costing
Stakeholder
Cost
Management
Requirements
Acquisition decision,
Order placed,
Delivered
Actual cost incurred / recorded
Cost of Use – Operating Cost
Maintenance,
Support of the product
RoI, Return on investment
Investment payback
Discounted Cash Flow
1. Plan Cost Management
2. Estimate costs
3. Determine budget
4. Control cost
Plan Cost Management
• Establishes policies , procedures and documentation for
planning managing, expending, controlling costs,
• Provides guidance and direction on project cost
management throughout the project,
• Inputs: PMP, Charter,EEF,OPA
Plan Cost Management: Inputs
Project Management Plan
Scope Baseline – project scope statement + WBS Details
Schedule baseline
Project Charter
Summary Budget
Project Approval Criteria
Enterprise Environmental Factors
Market Conditions
Currency Exchange rates
Published commercial Information
Organizational Process Assets
Financial control procedures
Historical Information and lessons learned
Existing formal/Informal cost estimating policies,
procedures and guidelines
Plan Cost Management: Tool &
Technics
• Tools and technics include
• Expert Judgement
• Analytical Technics
• Payback Period,
• Return on Investment RoI,
• Internal Rate of return,
• Net Present Value,
• Meetings
Plan Cost Management: Output
• Cost Management Plan
• Units of Measure
• Level of accuracy and precision
• Control Thresholds
• Rules of performance Measurement
• Define control Accounts,
• Establish Earned value measurement
technics
• Reporting Formats and frequency
• Cost change control procedures
Cost
Management
plan
1. Plan Cost Management
2. Estimate costs
3. Determine budget
4. Control cost
Cost included in estimates
• Cost of quality efforts,
• Cost of risk efforts,
• Cost of PM Time,
• Cost directly associated with the project,
• Expenses of physical office spaces,
• Profit,
• Overhead costs
Types of Cost
• Variable Cost :
Change with the amount of production or work,
Material , supplies, Wages
• Fixed Cost:
Cost does not change as production changes,
Setup, rent, utilities
• Direct Cost: directly attributable to work of the project
Indirect Costs: cost incurred for the benefit of more than
one project
Estimate Cost: Inputs
Human Resource Management Plan
• Project staffing plan,
• Personnel Rates,
• Reward and recognition
Project Schedule
• Type and quantity of resource req
• Equipment and material required
• Activity durations can impact Costs
Scope baseline
• Product description, WBS & Dictionary
• Key deliverables and acceptance Criteria,
• Project boundaries and assumptions
Risk Register
• Risk Response costs,
• Threats or Opportunities
Estimate Costs: Tools and Techniques
• Includes,
• Expert Judgment
• Analogous Estimating
• Parametric Estimating
• Bottom up estimating
• Three point estimating
• Reserve Analysis
• Cost of Quality
• Project Management Software
• Vendor Bid Analysis
• Group Decision Making
Estimate Costs: Outputs
Activity Cost
Estimates
Basis of Estimates
Project Document
Updates
Accuracy of Estimates
• Rough order of Magnitude:
Done during initiating
Range : -25% to +75%
• Budget Estimate:
Done during Planning
Range:-10% to +25%
• Definitive Estimate:
Done when project progress and more info is available
Range: -5% to 10% from actual
1. Plan Cost Management
2. Estimate costs
3. Determine budget
4. Control cost
Determine Budget
• Determine the amount of funding required for the project,
• Risk management to be applied to include reserves in
estimates ,
• Inputs include;
Activity Cost estimates, BoE, Scope
baseline, Project schedule, Resource
calendars, OPA, Contracts
• Cost baseline and Cost Budget
Determine Budget: Tools and
Techniques
• Cost Aggregation
• Reserve analysis
• Expert judgment
• Historical relationships
• Funding limit reconciliation
-Check cashflow,
-Reconciliation with cost constraints in the project charter
Determine Budget: Output
• Includes,
• Cost Baseline
• Project Funding Requirements
• Project Document updates
1. Plan Cost Management
2. Estimate costs
3. Determine budget
4. Control cost
Control Costs
• Monitor the status of the project to update project costs,
• Manage changes to the cost baseline,
• Provides the means to recognize variance,
• Influence the root causes of changes to cost baseline,
• Timely processing of change requests,
• Monitor use of funds to physical work completed,
• Prevent unapproved changes from being included,
• Communicate the status of changes to stakeholders
• Bring expected cost overrun within acceptable ranges
Control Costs: Tools & Techniques
• Progress Reporting,
• Reserve Analysis,
• Earned Value Management
Earned Value Management
• Earned value used to measure project performance against
Performance measurement baseline (PMB),
• EV analysis indicates potential deviations from PMB,
• EV measurements
integrate cost time and scope,
used to forecast future performance,
Forecasted project completion date and costs
Terms to know for EVM
Acronym Term Interpretation
PV Planned Value
EV Earned Value
AC Actual Cost
BAC Budget At
completion
EAC Estimate at
Completion
ETC Estimate to
Complete
VAC Variance at
Completion
As of today, what is the estimated value of the work
planned to be done?
As of today, what is the estimated value of the work
actually accomplished?
what is the actual cost incurred for the work
accomplished?
How much did we BUDGET for the TOTAL project effort?
What do we currently expect the TOTAL project to cost
(a forecast)?
how much MORE do we expect it to cost
to finish the project (a forecast)?
As of today, how much over or under budget do we
expect to be at the end of the project?
Earned Value Management
Terms to know for EVM
Name Formula Interpretation
Cost variance EV-AC
Schedule variance EV-PV
Cost Performance
Index (CPI)
EV/AC
Schedule
Performance Index
(SPI)
EV/PV
Neg is over budget and positive is under budget
Neg is behind schedule, Positive is ahead of schedule
We are getting $X worth of work for every $1 spent.
Funds are or are not being used efficiently. Greater
than 1 is good and <1 is bad
We are progressing at X% of the rate originally planned.
>1 is good and <1 is bad
How efficiently are we using time..
Terms to know for EVM
Term Formula Interpretation
Estimate at
Completion
(EAC)
AC+ ETC
BAC/CPI
AC+(BAC-EV)
AC+[ (BAC-EV)/
(CPI * SPI)]
TCPI (BAC-EV)/
(BAC-AC)
Estimate to
Complete
(ETC)
ETC= EAC-AC
Actual cost of work plus the budgeted cost of remaining
work, used original estimated was flawed
If no variance from BAC have occurred or the same burn
rate is expected to continue
Used when current variances are thought to be typical
of future
Remaining budget modified by performance. Current
variances typical, influenced by schedule constraint
How efficiently do we need to complete the remaining
work, <1 is good and >1 is bad
How much more the project cost?
Re-estimate
Test your EVM Knowledge
Exercise - 1
• You have a project to install 12 Telecom Tower in 12 Weeks.
The budget for the project is $10K
each a total of $120K
• We are in the 6th week,
• We have installed four Towers
• We have incurred a cost of $60K to
date
Exercise - EV calculations
Acronym Term Calculation
PV Planned Value
EV Earned Value
AC Actual Cost
BAC Budget At
completion
ETC Estimate to
Complete
EAC Estimate at
Completion
VAC Variance at
Completion
As we are in the 6th week, the PV would be 6*$10K=
$60K
We have installed four towers to date EV = 4* $10k=
$40k
We have incurred in cost $60K
The total budget for the project is $120K
We still have to install eight more towers to install, ETC=
8*$10K= $80K
AC+ETC= $60k+$80k= $140k
BAC-EAC= $120k - $140k = -$20k , Trending to be over
budget by $20K
Exercise EVM Calculations
Name Formula Calculation
Cost variance EV-AC
Schedule variance EV-PV
Cost Performance
Index (CPI)
EV/AC
Schedule
Performance Index
(SPI)
EV/PV
$40K-$60K = -$20K
$40K-$60K= -$20K
$40K/$60K = 0.66 - CPI is 0.66 meaning for each dollar
spent we are earning only 66 cents,
$40K/$60K = 0.66 - SPI is 0.66 meaning We are
progressing at 66% of the rate originally planned.
Exercise - 2
• On a project you have the CV= $10,000, your SV is -$3,000
PV is $100,000, What is the SPI?
• What is the AC in this case?
• In an earned value report for your project , you see the CPI
is 1.2 and SPI is 0.8, the PV is $ 600K, and the SV is -
$120K, you couldn’t find CV , How much is it?
The Active PMP Learner
Visit www.projectsatwork.com to get
exposed to information from industry
leaders …
PM Quote of the day
We all need people who provide us
feedback, this is how we grow.
~ Bill Gates

More Related Content

What's hot

Brief introduction to project management and project management tools
Brief introduction to project management and project management toolsBrief introduction to project management and project management tools
Brief introduction to project management and project management tools
Nathan Petralia
 
project management
project managementproject management
project management
Sanchita Siromoni
 
Project Management Concepts
Project Management ConceptsProject Management Concepts
Project Management Concepts
Jeremy Jay V. Lim, MBB, PMP
 
PMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkPMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkejlp12
 
Project management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areasProject management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areas
Mazen Zbib
 
Project management
Project managementProject management
Project management
Jay Raval
 
Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)
Jeremy Jay Lim
 
Project integration management
Project  integration managementProject  integration management
Project integration management
deep sharma
 
The Effective Program Management Office (PgMO) (c) 2010
The Effective Program Management Office (PgMO) (c) 2010The Effective Program Management Office (PgMO) (c) 2010
The Effective Program Management Office (PgMO) (c) 2010
Karen Y. Lucas PMP, PgMP, CISA, CISSP
 
Introduction to project management
Introduction to project managementIntroduction to project management
Introduction to project management
Barun_agnihotri
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
Kris Kimmerle
 
Practical Project Management - full course
Practical Project Management - full coursePractical Project Management - full course
Practical Project Management - full course
Marten Schoonman
 
Introduction to Project Management (workshop) - v.1
Introduction to Project Management (workshop) - v.1Introduction to Project Management (workshop) - v.1
Introduction to Project Management (workshop) - v.1
Mena M. Eissa
 
Project Metrics & Measures
Project Metrics & MeasuresProject Metrics & Measures
Project Metrics & Measures
Anand Subramaniam
 
Project Closure Process Steps PowerPoint Presentation Slides
Project Closure Process Steps PowerPoint Presentation Slides Project Closure Process Steps PowerPoint Presentation Slides
Project Closure Process Steps PowerPoint Presentation Slides
SlideTeam
 
Pmbok6 to 7 transformation
Pmbok6 to 7 transformationPmbok6 to 7 transformation
Pmbok6 to 7 transformation
Zaur Ahmadov, PMP
 
Project Management Tools & Techniques | PMP® Training Videos | Project Manage...
Project Management Tools & Techniques | PMP® Training Videos | Project Manage...Project Management Tools & Techniques | PMP® Training Videos | Project Manage...
Project Management Tools & Techniques | PMP® Training Videos | Project Manage...
Edureka!
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
Procept Associates
 
PMP 47 process definitions
PMP 47 process definitionsPMP 47 process definitions
PMP 47 process definitions
Anand Bobade
 

What's hot (20)

Brief introduction to project management and project management tools
Brief introduction to project management and project management toolsBrief introduction to project management and project management tools
Brief introduction to project management and project management tools
 
project management
project managementproject management
project management
 
Project Management Concepts
Project Management ConceptsProject Management Concepts
Project Management Concepts
 
PMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkPMP Training - 01 introduction to framework
PMP Training - 01 introduction to framework
 
Project management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areasProject management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areas
 
Project management
Project managementProject management
Project management
 
Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)
 
Project integration management
Project  integration managementProject  integration management
Project integration management
 
The Effective Program Management Office (PgMO) (c) 2010
The Effective Program Management Office (PgMO) (c) 2010The Effective Program Management Office (PgMO) (c) 2010
The Effective Program Management Office (PgMO) (c) 2010
 
Introduction to project management
Introduction to project managementIntroduction to project management
Introduction to project management
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
Practical Project Management - full course
Practical Project Management - full coursePractical Project Management - full course
Practical Project Management - full course
 
Introduction to Project Management (workshop) - v.1
Introduction to Project Management (workshop) - v.1Introduction to Project Management (workshop) - v.1
Introduction to Project Management (workshop) - v.1
 
Project Metrics & Measures
Project Metrics & MeasuresProject Metrics & Measures
Project Metrics & Measures
 
Project Closure Process Steps PowerPoint Presentation Slides
Project Closure Process Steps PowerPoint Presentation Slides Project Closure Process Steps PowerPoint Presentation Slides
Project Closure Process Steps PowerPoint Presentation Slides
 
Pmbok6 to 7 transformation
Pmbok6 to 7 transformationPmbok6 to 7 transformation
Pmbok6 to 7 transformation
 
Project Management Tools & Techniques | PMP® Training Videos | Project Manage...
Project Management Tools & Techniques | PMP® Training Videos | Project Manage...Project Management Tools & Techniques | PMP® Training Videos | Project Manage...
Project Management Tools & Techniques | PMP® Training Videos | Project Manage...
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 
Project managment ppt
Project managment pptProject managment ppt
Project managment ppt
 
PMP 47 process definitions
PMP 47 process definitionsPMP 47 process definitions
PMP 47 process definitions
 

Viewers also liked

9- PMP Training - Communication Management
9- PMP Training - Communication Management9- PMP Training - Communication Management
9- PMP Training - Communication Management
Qais Ur Rehman Rasooli, PMP
 
11- PMP Training - Procurement Management
11- PMP Training - Procurement Management 11- PMP Training - Procurement Management
11- PMP Training - Procurement Management
Qais Ur Rehman Rasooli, PMP
 
Path to PMP
Path to PMPPath to PMP
Path to PMP
Edureka!
 
7- PMP Training - Quality Management
7- PMP Training - Quality Management7- PMP Training - Quality Management
7- PMP Training - Quality Management
Qais Ur Rehman Rasooli, PMP
 
Introduction to PMP
Introduction to PMPIntroduction to PMP
Introduction to PMPEdureka!
 
10- PMP Training - Risk Management
10- PMP Training - Risk Management 10- PMP Training - Risk Management
10- PMP Training - Risk Management
Qais Ur Rehman Rasooli, PMP
 
Learning pmp formulas the easy way
Learning pmp formulas the easy wayLearning pmp formulas the easy way
Learning pmp formulas the easy way
Mark Troncone MBA, PMP, CBAP, ITILv3, CSM
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost managementejlp12
 
8- PMP Training - Human Resource Management
8- PMP Training - Human Resource Management8- PMP Training - Human Resource Management
8- PMP Training - Human Resource Management
Qais Ur Rehman Rasooli, PMP
 
PMP Training - 10 project communication management
PMP Training - 10 project communication managementPMP Training - 10 project communication management
PMP Training - 10 project communication managementejlp12
 
PMP Training - 11 project risk management
PMP Training - 11 project risk managementPMP Training - 11 project risk management
PMP Training - 11 project risk managementejlp12
 
PMP Training - 05 project scope management
PMP Training - 05 project scope managementPMP Training - 05 project scope management
PMP Training - 05 project scope managementejlp12
 

Viewers also liked (13)

9- PMP Training - Communication Management
9- PMP Training - Communication Management9- PMP Training - Communication Management
9- PMP Training - Communication Management
 
11- PMP Training - Procurement Management
11- PMP Training - Procurement Management 11- PMP Training - Procurement Management
11- PMP Training - Procurement Management
 
Path to PMP
Path to PMPPath to PMP
Path to PMP
 
7- PMP Training - Quality Management
7- PMP Training - Quality Management7- PMP Training - Quality Management
7- PMP Training - Quality Management
 
Introduction to PMP
Introduction to PMPIntroduction to PMP
Introduction to PMP
 
10- PMP Training - Risk Management
10- PMP Training - Risk Management 10- PMP Training - Risk Management
10- PMP Training - Risk Management
 
PMP
PMPPMP
PMP
 
Learning pmp formulas the easy way
Learning pmp formulas the easy wayLearning pmp formulas the easy way
Learning pmp formulas the easy way
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost management
 
8- PMP Training - Human Resource Management
8- PMP Training - Human Resource Management8- PMP Training - Human Resource Management
8- PMP Training - Human Resource Management
 
PMP Training - 10 project communication management
PMP Training - 10 project communication managementPMP Training - 10 project communication management
PMP Training - 10 project communication management
 
PMP Training - 11 project risk management
PMP Training - 11 project risk managementPMP Training - 11 project risk management
PMP Training - 11 project risk management
 
PMP Training - 05 project scope management
PMP Training - 05 project scope managementPMP Training - 05 project scope management
PMP Training - 05 project scope management
 

Similar to 6- PMP Training - Cost Management

07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
Dhamo daran
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
Imran Jamil
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 
Topic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfTopic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdf
HuyNguyen657394
 
projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)Nita Cristian
 
Project cost & control
Project cost & controlProject cost & control
Project cost & control
AMARAYYA
 
CostManagementSlides.pdf
CostManagementSlides.pdfCostManagementSlides.pdf
CostManagementSlides.pdf
AmrishTyagi8
 
Project Management Day 4 Cost ٌ R02.pdf
Project Management Day 4 Cost ٌ R02.pdfProject Management Day 4 Cost ٌ R02.pdf
Project Management Day 4 Cost ٌ R02.pdf
Dr Mohamed Elfarran
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.ppt
RedhaElhuni
 
PMP Exam Preparation Course: 06 Project Cost Management
PMP Exam Preparation Course: 06 Project Cost ManagementPMP Exam Preparation Course: 06 Project Cost Management
PMP Exam Preparation Course: 06 Project Cost Management
B M Shahrier Majumder, PMP, CSM
 
Chapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxChapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptx
ssusercf695b
 
Cert iv cost part 2
Cert iv  cost part 2Cert iv  cost part 2
Cert iv cost part 2Skript
 
PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
Bhaskara Reddy Sannapureddy
 
Project Management C8 -cost_estimation_and_budgeting
Project Management C8  -cost_estimation_and_budgetingProject Management C8  -cost_estimation_and_budgeting
Project Management C8 -cost_estimation_and_budgetingIzah Asmadi
 
Project Cost Management - PMP preparation course
Project Cost Management - PMP preparation courseProject Cost Management - PMP preparation course
Project Cost Management - PMP preparation course
Vladimir Vujovic
 
Lecture 5- Monitoring and Controlling Projects.ppt
Lecture 5- Monitoring and Controlling Projects.pptLecture 5- Monitoring and Controlling Projects.ppt
Lecture 5- Monitoring and Controlling Projects.ppt
vitumbikokhoswe1
 
L06 cost management
L06 cost managementL06 cost management
L06 cost managementAsa Chan
 
4.Cost management
4.Cost management4.Cost management
4.Cost management
Panos Fitsilis
 
PMP-Cost Management area
PMP-Cost Management areaPMP-Cost Management area
PMP-Cost Management area
Zaur Ahmadov, PMP
 
Software Project Cost Management and estimation
Software Project Cost Management and estimationSoftware Project Cost Management and estimation
Software Project Cost Management and estimation
ssuser9d62d6
 

Similar to 6- PMP Training - Cost Management (20)

07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Topic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfTopic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdf
 
projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)
 
Project cost & control
Project cost & controlProject cost & control
Project cost & control
 
CostManagementSlides.pdf
CostManagementSlides.pdfCostManagementSlides.pdf
CostManagementSlides.pdf
 
Project Management Day 4 Cost ٌ R02.pdf
Project Management Day 4 Cost ٌ R02.pdfProject Management Day 4 Cost ٌ R02.pdf
Project Management Day 4 Cost ٌ R02.pdf
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.ppt
 
PMP Exam Preparation Course: 06 Project Cost Management
PMP Exam Preparation Course: 06 Project Cost ManagementPMP Exam Preparation Course: 06 Project Cost Management
PMP Exam Preparation Course: 06 Project Cost Management
 
Chapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxChapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptx
 
Cert iv cost part 2
Cert iv  cost part 2Cert iv  cost part 2
Cert iv cost part 2
 
PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
 
Project Management C8 -cost_estimation_and_budgeting
Project Management C8  -cost_estimation_and_budgetingProject Management C8  -cost_estimation_and_budgeting
Project Management C8 -cost_estimation_and_budgeting
 
Project Cost Management - PMP preparation course
Project Cost Management - PMP preparation courseProject Cost Management - PMP preparation course
Project Cost Management - PMP preparation course
 
Lecture 5- Monitoring and Controlling Projects.ppt
Lecture 5- Monitoring and Controlling Projects.pptLecture 5- Monitoring and Controlling Projects.ppt
Lecture 5- Monitoring and Controlling Projects.ppt
 
L06 cost management
L06 cost managementL06 cost management
L06 cost management
 
4.Cost management
4.Cost management4.Cost management
4.Cost management
 
PMP-Cost Management area
PMP-Cost Management areaPMP-Cost Management area
PMP-Cost Management area
 
Software Project Cost Management and estimation
Software Project Cost Management and estimationSoftware Project Cost Management and estimation
Software Project Cost Management and estimation
 

Recently uploaded

Enriching engagement with ethical review processes
Enriching engagement with ethical review processesEnriching engagement with ethical review processes
Enriching engagement with ethical review processes
strikingabalance
 
Addiction to Winning Across Diverse Populations.pdf
Addiction to Winning Across Diverse Populations.pdfAddiction to Winning Across Diverse Populations.pdf
Addiction to Winning Across Diverse Populations.pdf
Bill641377
 
Senior Project and Engineering Leader Jim Smith.pdf
Senior Project and Engineering Leader Jim Smith.pdfSenior Project and Engineering Leader Jim Smith.pdf
Senior Project and Engineering Leader Jim Smith.pdf
Jim Smith
 
The Management Guide: From Projects to Portfolio
The Management Guide: From Projects to PortfolioThe Management Guide: From Projects to Portfolio
The Management Guide: From Projects to Portfolio
Ahmed AbdelMoneim
 
CV Ensio Suopanki1.pdf ENGLISH Russian Finnish German
CV Ensio Suopanki1.pdf ENGLISH Russian Finnish GermanCV Ensio Suopanki1.pdf ENGLISH Russian Finnish German
CV Ensio Suopanki1.pdf ENGLISH Russian Finnish German
EUS+ Management & Consulting Excellence
 
Employment Practices Regulation and Multinational Corporations
Employment PracticesRegulation and Multinational CorporationsEmployment PracticesRegulation and Multinational Corporations
Employment Practices Regulation and Multinational Corporations
RoopaTemkar
 
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
gcljeuzdu
 
Leadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact PlanLeadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact Plan
Muhammad Adil Jamil
 
Comparing Stability and Sustainability in Agile Systems
Comparing Stability and Sustainability in Agile SystemsComparing Stability and Sustainability in Agile Systems
Comparing Stability and Sustainability in Agile Systems
Rob Healy
 
Case Analysis - The Sky is the Limit | Principles of Management
Case Analysis - The Sky is the Limit | Principles of ManagementCase Analysis - The Sky is the Limit | Principles of Management
Case Analysis - The Sky is the Limit | Principles of Management
A. F. M. Rubayat-Ul Jannat
 
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
tdt5v4b
 
20240608 QFM019 Engineering Leadership Reading List May 2024
20240608 QFM019 Engineering Leadership Reading List May 202420240608 QFM019 Engineering Leadership Reading List May 2024
20240608 QFM019 Engineering Leadership Reading List May 2024
Matthew Sinclair
 
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
tdt5v4b
 
Strategic Org Design with Org Topologies™
Strategic Org Design with Org Topologies™Strategic Org Design with Org Topologies™
Strategic Org Design with Org Topologies™
Alexey Krivitsky
 
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
William (Bill) H. Bender, FCSI
 
Public Speaking Tips to Help You Be A Strong Leader.pdf
Public Speaking Tips to Help You Be A Strong Leader.pdfPublic Speaking Tips to Help You Be A Strong Leader.pdf
Public Speaking Tips to Help You Be A Strong Leader.pdf
Pinta Partners
 
12 steps to transform your organization into the agile org you deserve
12 steps to transform your organization into the agile org you deserve12 steps to transform your organization into the agile org you deserve
12 steps to transform your organization into the agile org you deserve
Pierre E. NEIS
 
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
tdt5v4b
 
Risk-Management-presentation for cooperatives
Risk-Management-presentation for cooperativesRisk-Management-presentation for cooperatives
Risk-Management-presentation for cooperatives
bernanbumatay1
 
Integrity in leadership builds trust by ensuring consistency between words an...
Integrity in leadership builds trust by ensuring consistency between words an...Integrity in leadership builds trust by ensuring consistency between words an...
Integrity in leadership builds trust by ensuring consistency between words an...
Ram V Chary
 

Recently uploaded (20)

Enriching engagement with ethical review processes
Enriching engagement with ethical review processesEnriching engagement with ethical review processes
Enriching engagement with ethical review processes
 
Addiction to Winning Across Diverse Populations.pdf
Addiction to Winning Across Diverse Populations.pdfAddiction to Winning Across Diverse Populations.pdf
Addiction to Winning Across Diverse Populations.pdf
 
Senior Project and Engineering Leader Jim Smith.pdf
Senior Project and Engineering Leader Jim Smith.pdfSenior Project and Engineering Leader Jim Smith.pdf
Senior Project and Engineering Leader Jim Smith.pdf
 
The Management Guide: From Projects to Portfolio
The Management Guide: From Projects to PortfolioThe Management Guide: From Projects to Portfolio
The Management Guide: From Projects to Portfolio
 
CV Ensio Suopanki1.pdf ENGLISH Russian Finnish German
CV Ensio Suopanki1.pdf ENGLISH Russian Finnish GermanCV Ensio Suopanki1.pdf ENGLISH Russian Finnish German
CV Ensio Suopanki1.pdf ENGLISH Russian Finnish German
 
Employment Practices Regulation and Multinational Corporations
Employment PracticesRegulation and Multinational CorporationsEmployment PracticesRegulation and Multinational Corporations
Employment Practices Regulation and Multinational Corporations
 
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
 
Leadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact PlanLeadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact Plan
 
Comparing Stability and Sustainability in Agile Systems
Comparing Stability and Sustainability in Agile SystemsComparing Stability and Sustainability in Agile Systems
Comparing Stability and Sustainability in Agile Systems
 
Case Analysis - The Sky is the Limit | Principles of Management
Case Analysis - The Sky is the Limit | Principles of ManagementCase Analysis - The Sky is the Limit | Principles of Management
Case Analysis - The Sky is the Limit | Principles of Management
 
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
 
20240608 QFM019 Engineering Leadership Reading List May 2024
20240608 QFM019 Engineering Leadership Reading List May 202420240608 QFM019 Engineering Leadership Reading List May 2024
20240608 QFM019 Engineering Leadership Reading List May 2024
 
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
 
Strategic Org Design with Org Topologies™
Strategic Org Design with Org Topologies™Strategic Org Design with Org Topologies™
Strategic Org Design with Org Topologies™
 
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
 
Public Speaking Tips to Help You Be A Strong Leader.pdf
Public Speaking Tips to Help You Be A Strong Leader.pdfPublic Speaking Tips to Help You Be A Strong Leader.pdf
Public Speaking Tips to Help You Be A Strong Leader.pdf
 
12 steps to transform your organization into the agile org you deserve
12 steps to transform your organization into the agile org you deserve12 steps to transform your organization into the agile org you deserve
12 steps to transform your organization into the agile org you deserve
 
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
 
Risk-Management-presentation for cooperatives
Risk-Management-presentation for cooperativesRisk-Management-presentation for cooperatives
Risk-Management-presentation for cooperatives
 
Integrity in leadership builds trust by ensuring consistency between words an...
Integrity in leadership builds trust by ensuring consistency between words an...Integrity in leadership builds trust by ensuring consistency between words an...
Integrity in leadership builds trust by ensuring consistency between words an...
 

6- PMP Training - Cost Management

  • 1. 5. COST MANAGEMENT Project Management Training, Qais Ur Rehman Rasooli, PMP
  • 2. Cost Management • Project cost management includes the processes involved in, • Planning • Estimating • Budgeting • Financing • Funding • Managing and Controlling cost
  • 3. So What is Project Cost Management?..cont’d Financial performance of the product Product Life cycle costing Stakeholder Cost Management Requirements Acquisition decision, Order placed, Delivered Actual cost incurred / recorded Cost of Use – Operating Cost Maintenance, Support of the product RoI, Return on investment Investment payback Discounted Cash Flow
  • 4. 1. Plan Cost Management 2. Estimate costs 3. Determine budget 4. Control cost
  • 5. Plan Cost Management • Establishes policies , procedures and documentation for planning managing, expending, controlling costs, • Provides guidance and direction on project cost management throughout the project, • Inputs: PMP, Charter,EEF,OPA
  • 6. Plan Cost Management: Inputs Project Management Plan Scope Baseline – project scope statement + WBS Details Schedule baseline Project Charter Summary Budget Project Approval Criteria Enterprise Environmental Factors Market Conditions Currency Exchange rates Published commercial Information Organizational Process Assets Financial control procedures Historical Information and lessons learned Existing formal/Informal cost estimating policies, procedures and guidelines
  • 7. Plan Cost Management: Tool & Technics • Tools and technics include • Expert Judgement • Analytical Technics • Payback Period, • Return on Investment RoI, • Internal Rate of return, • Net Present Value, • Meetings
  • 8. Plan Cost Management: Output • Cost Management Plan • Units of Measure • Level of accuracy and precision • Control Thresholds • Rules of performance Measurement • Define control Accounts, • Establish Earned value measurement technics • Reporting Formats and frequency • Cost change control procedures Cost Management plan
  • 9. 1. Plan Cost Management 2. Estimate costs 3. Determine budget 4. Control cost
  • 10. Cost included in estimates • Cost of quality efforts, • Cost of risk efforts, • Cost of PM Time, • Cost directly associated with the project, • Expenses of physical office spaces, • Profit, • Overhead costs
  • 11. Types of Cost • Variable Cost : Change with the amount of production or work, Material , supplies, Wages • Fixed Cost: Cost does not change as production changes, Setup, rent, utilities • Direct Cost: directly attributable to work of the project Indirect Costs: cost incurred for the benefit of more than one project
  • 12. Estimate Cost: Inputs Human Resource Management Plan • Project staffing plan, • Personnel Rates, • Reward and recognition Project Schedule • Type and quantity of resource req • Equipment and material required • Activity durations can impact Costs Scope baseline • Product description, WBS & Dictionary • Key deliverables and acceptance Criteria, • Project boundaries and assumptions Risk Register • Risk Response costs, • Threats or Opportunities
  • 13. Estimate Costs: Tools and Techniques • Includes, • Expert Judgment • Analogous Estimating • Parametric Estimating • Bottom up estimating • Three point estimating • Reserve Analysis • Cost of Quality • Project Management Software • Vendor Bid Analysis • Group Decision Making
  • 14. Estimate Costs: Outputs Activity Cost Estimates Basis of Estimates Project Document Updates
  • 15. Accuracy of Estimates • Rough order of Magnitude: Done during initiating Range : -25% to +75% • Budget Estimate: Done during Planning Range:-10% to +25% • Definitive Estimate: Done when project progress and more info is available Range: -5% to 10% from actual
  • 16. 1. Plan Cost Management 2. Estimate costs 3. Determine budget 4. Control cost
  • 17. Determine Budget • Determine the amount of funding required for the project, • Risk management to be applied to include reserves in estimates , • Inputs include; Activity Cost estimates, BoE, Scope baseline, Project schedule, Resource calendars, OPA, Contracts • Cost baseline and Cost Budget
  • 18. Determine Budget: Tools and Techniques • Cost Aggregation • Reserve analysis • Expert judgment • Historical relationships • Funding limit reconciliation -Check cashflow, -Reconciliation with cost constraints in the project charter
  • 19. Determine Budget: Output • Includes, • Cost Baseline • Project Funding Requirements • Project Document updates
  • 20. 1. Plan Cost Management 2. Estimate costs 3. Determine budget 4. Control cost
  • 21. Control Costs • Monitor the status of the project to update project costs, • Manage changes to the cost baseline, • Provides the means to recognize variance, • Influence the root causes of changes to cost baseline, • Timely processing of change requests, • Monitor use of funds to physical work completed, • Prevent unapproved changes from being included, • Communicate the status of changes to stakeholders • Bring expected cost overrun within acceptable ranges
  • 22. Control Costs: Tools & Techniques • Progress Reporting, • Reserve Analysis, • Earned Value Management
  • 23. Earned Value Management • Earned value used to measure project performance against Performance measurement baseline (PMB), • EV analysis indicates potential deviations from PMB, • EV measurements integrate cost time and scope, used to forecast future performance, Forecasted project completion date and costs
  • 24. Terms to know for EVM Acronym Term Interpretation PV Planned Value EV Earned Value AC Actual Cost BAC Budget At completion EAC Estimate at Completion ETC Estimate to Complete VAC Variance at Completion As of today, what is the estimated value of the work planned to be done? As of today, what is the estimated value of the work actually accomplished? what is the actual cost incurred for the work accomplished? How much did we BUDGET for the TOTAL project effort? What do we currently expect the TOTAL project to cost (a forecast)? how much MORE do we expect it to cost to finish the project (a forecast)? As of today, how much over or under budget do we expect to be at the end of the project?
  • 26. Terms to know for EVM Name Formula Interpretation Cost variance EV-AC Schedule variance EV-PV Cost Performance Index (CPI) EV/AC Schedule Performance Index (SPI) EV/PV Neg is over budget and positive is under budget Neg is behind schedule, Positive is ahead of schedule We are getting $X worth of work for every $1 spent. Funds are or are not being used efficiently. Greater than 1 is good and <1 is bad We are progressing at X% of the rate originally planned. >1 is good and <1 is bad How efficiently are we using time..
  • 27. Terms to know for EVM Term Formula Interpretation Estimate at Completion (EAC) AC+ ETC BAC/CPI AC+(BAC-EV) AC+[ (BAC-EV)/ (CPI * SPI)] TCPI (BAC-EV)/ (BAC-AC) Estimate to Complete (ETC) ETC= EAC-AC Actual cost of work plus the budgeted cost of remaining work, used original estimated was flawed If no variance from BAC have occurred or the same burn rate is expected to continue Used when current variances are thought to be typical of future Remaining budget modified by performance. Current variances typical, influenced by schedule constraint How efficiently do we need to complete the remaining work, <1 is good and >1 is bad How much more the project cost? Re-estimate
  • 28. Test your EVM Knowledge
  • 29. Exercise - 1 • You have a project to install 12 Telecom Tower in 12 Weeks. The budget for the project is $10K each a total of $120K • We are in the 6th week, • We have installed four Towers • We have incurred a cost of $60K to date
  • 30. Exercise - EV calculations Acronym Term Calculation PV Planned Value EV Earned Value AC Actual Cost BAC Budget At completion ETC Estimate to Complete EAC Estimate at Completion VAC Variance at Completion As we are in the 6th week, the PV would be 6*$10K= $60K We have installed four towers to date EV = 4* $10k= $40k We have incurred in cost $60K The total budget for the project is $120K We still have to install eight more towers to install, ETC= 8*$10K= $80K AC+ETC= $60k+$80k= $140k BAC-EAC= $120k - $140k = -$20k , Trending to be over budget by $20K
  • 31. Exercise EVM Calculations Name Formula Calculation Cost variance EV-AC Schedule variance EV-PV Cost Performance Index (CPI) EV/AC Schedule Performance Index (SPI) EV/PV $40K-$60K = -$20K $40K-$60K= -$20K $40K/$60K = 0.66 - CPI is 0.66 meaning for each dollar spent we are earning only 66 cents, $40K/$60K = 0.66 - SPI is 0.66 meaning We are progressing at 66% of the rate originally planned.
  • 32. Exercise - 2 • On a project you have the CV= $10,000, your SV is -$3,000 PV is $100,000, What is the SPI? • What is the AC in this case? • In an earned value report for your project , you see the CPI is 1.2 and SPI is 0.8, the PV is $ 600K, and the SV is - $120K, you couldn’t find CV , How much is it?