SlideShare a Scribd company logo
Presented by:
Vladimir Vujović, PMP
PMI Certification Preparation: PMP / CAPM
- Project Cost Management -
Project Management Institute, Inc. All rights reserved.
October 2017
• Presenter
• Participants: profile, background, expectations
• Session: structure, approach and benefits
Introduction to the session
1. Integration management
2. Scope management
3. Time management
4. Cost management
5. Quality management
6. Human resources management
7. Communications management
8. Risk management
9. Procurement management
10. Stakeholder management
Project Management Knowledge Areas
PMI PMBOK 5th edition
1. Plan Cost Management
2. Estimate Costs
3. Determine Budget
4. Control Costs
Project Cost Management Processes:
Plan Cost Management
Inputs
• Project management plan
• Project charter
• Enterprise environmental
factors
• Organizational process assets
Tools and Techniques
• Expert judgment
• Analytical techniques
• Meetings
Outputs
• Cost management plan
Plan Cost Management: Data Flow
Plan Cost
Management
Estimate Costs
Perform
Quantitative
Risk Analysis
Identify Risks
Enterprise /
Organization
Project Cost Management
• Cost management
plan
• Project charter
• OPA
• EEF
Determine
Budget
Develop Project
Management
Plan
Develop Project
Charter
• Project
management
plan
• Units of measure
• Level of precision
• Level of accuracy
• Control thresholds
• Rules of performance measurement
• Reporting formats
Cost management plan
Estimate Costs
Inputs
• Cost management plan
• Human resource
management plan
• Scope baseline
• Project schedule
• Risk register
• Enterprise environmental
factors
• Organizational process assets
Tools and Techniques
• Expert judgment
• Analogous estimating
• Parametric estimating
• Bottom-up estimating
• Three-point estimating
• Reserve analysis
• Cost of quality
• Project management
software
• Vendor bid analysis
• Group decision-making
techniques
Outputs
• Activity cost estimates
• Basis of estimates
• Project documents updates
Estimate Costs: Data Flow
Estimate Costs
Plan Cost
Management
Plan
Procurement
Management
Estimate
Activity
Resources
Enterprise /
Organization
Project Cost Management
• Cost management
plan
• Human resource
management
plan
• OPA
• EEF
Determine
Budget
Identify Risks
Plan Human
Resource
Management
• Risk register
Develop
Schedule
Create WBS
Identify Risks
Project documents
• Project schedule
• Scope baseline
• Basis of
estimates
• Activity cost
estimates
• Project
documents
updates
• Analogous estimating
• Parametric estimating
• Bottom up estimating
• Three-point estimating:
▫ Most likely (cM)
▫ Optimistic (cO)
▫ Pessimistic (cP)
▫ Triangular distribution: cE = ( cO + cM + cP ) / 3
▫ Beta distribution: cE = ( cO + 4cM + cP ) / 6
Estimate costs
Determine Budget
Inputs
• Cost management plan
• Scope baseline
• Activity cost estimates
• Basis of estimates
• Project schedule
• Resource calendars
• Risk register
• Agreements
• Organizational process assets
Tools and Techniques
• Cost aggregation
• Reserve analysis
• Expert judgment
• Historical relationships
• Funding limit reconciliation
Outputs
• Cost baseline
• Project funding requirements
• Project documents updates
Determine Budget: Data Flow
Determine
Budget
Plan Cost
Management
Develop Project
Management
Plan
Enterprise /
Organization
Project Cost Management
• Cost management
plan
• Risk register
• OPA
Control Costs
Identify Risks
Acquire Project
Team
• Agreements
• Resource calendars
Develop
Schedule
Create WBS
Project documents
• Project schedule
• Scope baseline
• Project Funding
Requirements
• Cost baseline
• Project
documents
updates
Estimate Costs
• Activity cost estimates
• Basis of estimates
Conduct
Procurements
• Resource calendars
Cost Baseline
Control Costs
Inputs
• Project management plan
• Project funding requirements
• Work performance data
• Organizational process assets
Tools and Techniques
• Earned value management
• Forecasting
• To-complete performance
index (TCPI)
• Performance reviews
• Project management
software
• Reserve analysis
Outputs
• Work performance
information
• Cost forecasts
• Change requests
• Project management plan
updates
• Project documents updates
• Organizational process assets
updates
Control Costs: Data Flow
Control Costs
Determine
Budget
Develop Project
Management
Plan
Enterprise /
Organization
Project Cost Management
• OPA
Perform
Integrated
Change Control
Direct and
Manage Project
Work
Develop Project
Management
Plan
Project documents
• Project management plan
• Change
requests
• Project
management
plan updates
• Project funding
requirements
Monitor and
Control Project
Work
• Work performance data
• OPA updates
• Work
performance
information
• Cost forecasts
• Project
documents
updates
Earned Value Calculation (PMBOK 5, page 224) !!!
Abbreviation Name Lexicon Definition How Used Equation
Interpretation
of Result
PV Planned Value
The authorized budget
assigned to scheduled work.
The value of the work planned to be completed to
a point in time, usually the data date, or project
completion.
EV Earned Value
The measure of work
performed expressed in
terms of the budget
authorized for that work.
The planned value of all the work completed
(earned) to a point in time, usually the data date,
without reference to actual costs.
EV = sum of the
planned value of
completed work.
AC Actual Cost
The realized cost incurred
for the work performed on
an activity during a specific
time period.
The actual cost of all the work completed to a point
in time, usually the data date.
BAC
Budget at
Completion
The sum of all budgets
established for the work to
be performed.
The value of total planned work, the project cost
baseline.
Earned Value Calculation (PMBOK 5, page 224) !!!
Abbreviation Name Lexicon Definition How Used Equation Interpretation of Result
CV Cost Variance
The amount of budget deficit or surplus at a
givent point in time, expressed as the
difference between the earned value and
the actual cost.
The difference between the value of
work completed to a point in time,
usually the data date, and the actual
costs to the same point in time.
CV = EV – AC
Positive = Under
planned cost
Neutral = On planned
cost
Negative = Over
planned cost
SV
Schedule
Variance
The amount by which the project is ahead or
behind the planned delivery date, at a given
point in time, expressed as the difference
between the earned value and the planned
value.
The difference between the work
completed to a pint in time, usually the
data date, and the work planned to be
completed to the same point in time.
SV = EV – PV
Positive = Ahead of
Schedule
Neutral = On Schedule
Negative = Behind
Schedule
VAC
Variance at
Completion
A projection of the amount of budget deficit
or surplus, expressed as the difference
between the budget at completion and the
estimate at completion.
The estimated difference in cost at the
completion of the project.
VAC = BAC – EAC
Positive = Under
planned cost
Neutral = On planned
cost
Negative = Over
planned cost
Earned Value Calculation (PMBOK 5, page 224) !!!
Abbreviation Name Lexicon Definition How Used Equation
Interpretation of
Result
CPI
Cost
Performance
Index
A measure of the cost
efficiency of budgeted
resources expressed as
the ratio of earned value
to actual cost.
A CPI of 1.0 means the project is exactly on
budget, that the work actually done so far is
exactly the same as the cost so far. Other values
show the percentage of how much costs are
over or under the budgeted amount for work
accomplished.
CPI = EV / AC
Greater than 1.0 =
Under planned cost
Exactly 1.0 = On
planned cost
Less than 1.0 = Over
planned cost
SPI
Schedule
Performance
Index
A measure of schedule
efficiency expressed as
the ratio of earned value
to planned value.
An SPI of 1.0 means that the project is exactly
on schedule, that the work actually done so far
is exactly the same as the work planned to be
done so far. Other values show the percentage
of how much costs are over or under the
budgeted amount for work planned.
SPI = EV / PV
Greater than 1.0 =
Ahead of Schedule
Exactly 1.0 = On
Schedule
Less than 1.0 =
Behind schedule
EAC
Estimate at
Completion
The expected total cost
of completing all work
expressed as the sum of
the actual cost to date
and the estimate to
complete.
If the CPI is expected to be the same for the
remainder of the project, EAC can be calculated
using:
If future work will be accomplished at the
planned rate, use:
If the initial plan is no longer valid, use:
If both the CPI and SPI influence the remaining
work, use:
EAC = BAC / CPI
EAC = AC + BAC – EV
EAC = AC + Bottom-up ETC
EAC = AC + [(BAC – EV)/(CPI x SPI)]
Earned Value Calculation (PMBOK 5, page 224) !!!
Abbreviation Name Lexicon Definition How Used Equation Interpretation of Result
ETC
Extimate to
Complete
The expected cost to finish
all the remaining project
work.
Assuming work is proceeding on plan,
the cost of completing the remaining
authorized work can be calculated
using:
Reestimate the remaining work from
the bottom up:
ETC = EAC – AC
ETC = Reestimate
TCPI
To Complete
Performance
Index
A measure of the cost
performance that must be
achieved with the remaining
resources in order to meet a
specified management goal,
expressed as the ratio of the
cost to finish the outstanding
work to the budget available.
The efficiency that must be maintained
in order to complete on plan.
The efficiency that must be maintained
in order to complete the current EAC.
TCPI = (BAC-EV)/(BAC-AC)
TCPI = (BAC-EV)/(EAC-AC)
Greater than 1.0 = Harder to
complete
Exactly 1.0 = Same to complete
Less than 1.0 = Easier to complete
Greater than 1.0 = Harder to
complete
Exactly 1.0 = Same to complete
Less than 1.0 = Easier to complete
• Analogous estimating:
A. Uses bottom-up estimating techniques.
B. Is used most frequently during the executing processes of the project.
C. Uses top-down estimating techniques.
D. Uses actual detailed historical costs.
Sample question #1
• Analogous estimating:
A. Uses bottom-up estimating techniques.
B. Is used most frequently during the executing processes of the project.
C. Uses top-down estimating techniques.
D. Uses actual detailed historical costs.
Sample question #1
• The main focus of life cycle costing is to:
A. Estimate installation costs
B. Estimate the cost of operations and maintenance
C. Consider installation costs when planning the project costs
D. Consider operations and maintenance costs in making project decisions
Sample question #2
• The main focus of life cycle costing is to:
A. Estimate installation costs
B. Estimate the cost of operations and maintenance
C. Consider installation costs when planning the project costs
D. Consider operations and maintenance costs in making project decisions
Sample question #2
• Cost performance measurement is BEST done through which of the
following:
A. Asking for a percent complete from each team member and reporting that in
the monthly progress report
B. Calculating earned value and using the indexes and other calculations to report
past performance and forecast future performance
C. Using the 50/50 rule and making sure the life cyde cost is less than the project
cost
D. Focusing on the amount expended last month and what will be expended the
following month
Sample question #3
• Cost performance measurement is BEST done through which of the
following:
A. Asking for a percent complete from each team member and reporting that in
the monthly progress report
B. Calculating earned value and using the indexes and other calculations to report
past performance and forecast future performance
C. Using the 50/50 rule and making sure the life cyde cost is less than the project
cost
D. Focusing on the amount expended last month and what will be expended the
following month
Sample question #3
• A cost performance index (CPI) of 0.89 means:
A. At this time, we expect the total project to cost 89 percent more than
planned
B. When the project is completed we will have spent 89 percent more than
planned
C. The project is only progressing at 89 percent of the rate planned
D. The project is only getting 89 cents out of every dollar invested
Sample question #4
• A cost performance index (CPI) of 0.89 means:
A. At this time, we expect the total project to cost 89 percent more than
planned
B. When the project is completed we will have spent 89 percent more than
planned
C. The project is only progressing at 89 percent of the rate planned
D. The project is only getting 89 cents out of every dollar invested
Sample question #4
• A schedule performance index (SPI) of 0.76 means:
A. You are over budget
B. You are ahead of schedule
C. You are only progressing at 76 percent of the rate originally planned
D. You are only progressing at 24 percent of the rate originally planned
Sample question #5
• A schedule performance index (SPI) of 0.76 means:
A. You are over budget
B. You are ahead of schedule
C. You are only progressing at 76 percent of the rate originally planned
D. You are only progressing at 24 percent of the rate originally planned
Sample question #5
• A cost baseline is an output of which cost management process?
A. Estimate Activity Resources
B. Estimate Costs
C. Determine Budget
D. Control Costs
Sample question #6
• A cost baseline is an output of which cost management process?
A. Estimate Activity Resources
B. Estimate Costs
C. Determine Budget
D. Control Costs
Sample question #6
• During which project management process group are budget forecasts
created?
A. Monitoring and controlling
B. Planning
C. Initiating
D. Executing
Sample question #7
• During which project management process group are budget forecasts
created?
A. Monitoring and controlling
B. Planning
C. Initiating
D. Executing
Sample question #7
• Which of the following represents the estimated value of the work
actually accomplished?
A. Earned value (EV)
B. Planned value (PV)
C. Actual cost (AC)
D. Cost variance (CV)
Sample question #8
• Which of the following represents the estimated value of the work
actually accomplished?
A. Earned value (EV)
B. Planned value (PV)
C. Actual cost (AC)
D. Cost variance (CV)
Sample question #8
• The cost contingency reserve should be:
A. Hidden to prevent management from disallowing the reserve
B. Added to each activity to provide the customer with a shorter critical
path
C. Maintained by management to cover cost overruns
D. Added to the base costs of the project to account for risks
Sample question #9
• The cost contingency reserve should be:
A. Hidden to prevent management from disallowing the reserve
B. Added to each activity to provide the customer with a shorter critical
path
C. Maintained by management to cover cost overruns
D. Added to the base costs of the project to account for risks
Sample question #9
• You are the project manager for a railroad construction project. Your
Sponsor has asked you for a forecast for the cost of project
completion. The project has a total budget of $80,000 and CPI of .95 .
The project has spent $25,000 of its budget so far. How much more
money do you plan to spend on the project?
A. $59,210
B. $80,000
C. $84,210
D. $109,210
Sample question #10
• You are the project manager for a railroad construction project. Your
Sponsor has asked you for a forecast for the cost of project
completion. The project has a total budget of $80,000 and CPI of .95 .
The project has spent $25,000 of its budget so far. How much more
money do you plan to spend on the project?
A. $59,210
B. $80,000
C. $84,210
D. $109,210
Sample question #10
EAC = BAC/CPI.
ETC = EAC - AC = BAC/CPI - AC = $80,000/0.95 - $25,000 = $59,210 (A)
Vladimir VUJOVIĆ, PMP E-mail: vladimir.vujovic@gmail.com
PMO and BCM Manager
Delhaize Serbia
Sources used:
PMBOK Guide, 5th Edition
Rita Mulcahy’s PMP Exam Prep, 8th Edition
Good Luck!

More Related Content

What's hot

Project cost & control
Project cost & controlProject cost & control
Project cost & control
AMARAYYA
 
Ch 9 project monitoring & control updated
Ch 9 project monitoring & control updatedCh 9 project monitoring & control updated
Ch 9 project monitoring & control updated
Farhana Rehman
 
Curcial Factors that affect Cost Management.
Curcial Factors that affect Cost Management.Curcial Factors that affect Cost Management.
Curcial Factors that affect Cost Management.
Ahmed Al-Senosy Ph.D(cand),MSc,PMP,RMP
 
Project management : Project Monitoring and Control by iFour Technolab Pvt. Ltd.
Project management : Project Monitoring and Control by iFour Technolab Pvt. Ltd.Project management : Project Monitoring and Control by iFour Technolab Pvt. Ltd.
Project management : Project Monitoring and Control by iFour Technolab Pvt. Ltd.
iFour Institute - Sustainable Learning
 
Cost management
Cost managementCost management
Cost management
Abhi Kalyan
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost managementejlp12
 
Project cost control
Project cost controlProject cost control
Project cost control
Sourabh Modgil
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
Ahmed Elshaboury,PMP,LEED GA
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 
PMBoK6Ed.lect1.introduction
PMBoK6Ed.lect1.introductionPMBoK6Ed.lect1.introduction
PMBoK6Ed.lect1.introduction
Essam Lotffy, PMP®, CCP®
 
Project Monitoring and Controlling Processes
Project Monitoring and Controlling ProcessesProject Monitoring and Controlling Processes
Project Monitoring and Controlling Processes
Nishant Munjal
 
Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Project Cost Management - PMBOK6
Project Cost Management - PMBOK6
Agus Suhanto
 
Cost management
Cost managementCost management
Cost management
Suranji Kannangara
 
Project Management C8 -cost_estimation_and_budgeting
Project Management C8  -cost_estimation_and_budgetingProject Management C8  -cost_estimation_and_budgeting
Project Management C8 -cost_estimation_and_budgetingIzah Asmadi
 
PMP_Project Cost Management
PMP_Project Cost ManagementPMP_Project Cost Management
PMP_Project Cost Management
Hisham Haridy MBA, PMP®, RMP®, SP®
 
Cost management
Cost managementCost management
Cost management
Mostafa Elgamala
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-control
eidalin95
 

What's hot (20)

07 project cost management
07 project cost management07 project cost management
07 project cost management
 
Project cost & control
Project cost & controlProject cost & control
Project cost & control
 
Ch 9 project monitoring & control updated
Ch 9 project monitoring & control updatedCh 9 project monitoring & control updated
Ch 9 project monitoring & control updated
 
Cost Management
Cost ManagementCost Management
Cost Management
 
Curcial Factors that affect Cost Management.
Curcial Factors that affect Cost Management.Curcial Factors that affect Cost Management.
Curcial Factors that affect Cost Management.
 
Project management : Project Monitoring and Control by iFour Technolab Pvt. Ltd.
Project management : Project Monitoring and Control by iFour Technolab Pvt. Ltd.Project management : Project Monitoring and Control by iFour Technolab Pvt. Ltd.
Project management : Project Monitoring and Control by iFour Technolab Pvt. Ltd.
 
Cost management
Cost managementCost management
Cost management
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost management
 
Project cost control
Project cost controlProject cost control
Project cost control
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
PMBoK6Ed.lect1.introduction
PMBoK6Ed.lect1.introductionPMBoK6Ed.lect1.introduction
PMBoK6Ed.lect1.introduction
 
Project Monitoring and Controlling Processes
Project Monitoring and Controlling ProcessesProject Monitoring and Controlling Processes
Project Monitoring and Controlling Processes
 
Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Project Cost Management - PMBOK6
Project Cost Management - PMBOK6
 
Cost management
Cost managementCost management
Cost management
 
Project Management C8 -cost_estimation_and_budgeting
Project Management C8  -cost_estimation_and_budgetingProject Management C8  -cost_estimation_and_budgeting
Project Management C8 -cost_estimation_and_budgeting
 
PMP_Project Cost Management
PMP_Project Cost ManagementPMP_Project Cost Management
PMP_Project Cost Management
 
Cost management
Cost managementCost management
Cost management
 
Cost Control Process for Construction
Cost Control Process for ConstructionCost Control Process for Construction
Cost Control Process for Construction
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-control
 

Similar to Project Cost Management - PMP preparation course

PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
Bhaskara Reddy Sannapureddy
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
ProfDrAnbalaganChinn
 
EVA - Metrics.ppt
EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.ppt
NivethaSampath3
 
projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)Nita Cristian
 
COST MANAGEMENT REPORT
COST MANAGEMENT REPORT COST MANAGEMENT REPORT
COST MANAGEMENT REPORT
Jo Balucanag - Bitonio
 
Project Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge AreaProject Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge Area
Joshua Render
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
BECM, RUET, Bangladesh
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.ppt
RedhaElhuni
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1reddvise
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part One
Waleed Hamdy Albana
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
waleed hamdy
 
Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Tipsographic . com
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updatedShraddha PMP
 
6- PMP Training - Cost Management
6- PMP Training - Cost Management6- PMP Training - Cost Management
6- PMP Training - Cost Management
Qais Ur Rehman Rasooli, PMP
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
Anand Subramaniam
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
Dhamo daran
 
PM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfPM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdf
Najm Naqvi
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)
Harshit Mahajan
 
PMP Exam Preparation Course: 06 Project Cost Management
PMP Exam Preparation Course: 06 Project Cost ManagementPMP Exam Preparation Course: 06 Project Cost Management
PMP Exam Preparation Course: 06 Project Cost Management
B M Shahrier Majumder, PMP, CSM
 

Similar to Project Cost Management - PMP preparation course (20)

PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
 
EVA - Metrics.ppt
EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.ppt
 
projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)
 
COST MANAGEMENT REPORT
COST MANAGEMENT REPORT COST MANAGEMENT REPORT
COST MANAGEMENT REPORT
 
Project Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge AreaProject Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge Area
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.ppt
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part One
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
 
Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
Project Management EVM & SCBA
 
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updated
 
6- PMP Training - Cost Management
6- PMP Training - Cost Management6- PMP Training - Cost Management
6- PMP Training - Cost Management
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
 
PM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfPM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdf
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)
 
PMP Exam Preparation Course: 06 Project Cost Management
PMP Exam Preparation Course: 06 Project Cost ManagementPMP Exam Preparation Course: 06 Project Cost Management
PMP Exam Preparation Course: 06 Project Cost Management
 

Recently uploaded

Filing Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed GuideFiling Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed Guide
YourLegal Accounting
 
Set off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptxSet off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptx
HARSHITHV26
 
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deckPitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
HajeJanKamps
 
Skye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto AirportSkye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto Airport
marketingjdass
 
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptxCADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
fakeloginn69
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
tanyjahb
 
Buy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star ReviewsBuy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star Reviews
usawebmarket
 
BeMetals Presentation_May_22_2024 .pdf
BeMetals Presentation_May_22_2024   .pdfBeMetals Presentation_May_22_2024   .pdf
BeMetals Presentation_May_22_2024 .pdf
DerekIwanaka1
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
Cynthia Clay
 
Brand Analysis for an artist named Struan
Brand Analysis for an artist named StruanBrand Analysis for an artist named Struan
Brand Analysis for an artist named Struan
sarahvanessa51503
 
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Navpack & Print
 
Global Interconnection Group Joint Venture[960] (1).pdf
Global Interconnection Group Joint Venture[960] (1).pdfGlobal Interconnection Group Joint Venture[960] (1).pdf
Global Interconnection Group Joint Venture[960] (1).pdf
Henry Tapper
 
Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...
dylandmeas
 
20240425_ TJ Communications Credentials_compressed.pdf
20240425_ TJ Communications Credentials_compressed.pdf20240425_ TJ Communications Credentials_compressed.pdf
20240425_ TJ Communications Credentials_compressed.pdf
tjcomstrang
 
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
Kumar Satyam
 
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
BBPMedia1
 
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
BBPMedia1
 
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdfMeas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
dylandmeas
 
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptxTaurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
my Pandit
 
April 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products NewsletterApril 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products Newsletter
NathanBaughman3
 

Recently uploaded (20)

Filing Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed GuideFiling Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed Guide
 
Set off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptxSet off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptx
 
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deckPitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
 
Skye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto AirportSkye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto Airport
 
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptxCADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
 
Buy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star ReviewsBuy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star Reviews
 
BeMetals Presentation_May_22_2024 .pdf
BeMetals Presentation_May_22_2024   .pdfBeMetals Presentation_May_22_2024   .pdf
BeMetals Presentation_May_22_2024 .pdf
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
Brand Analysis for an artist named Struan
Brand Analysis for an artist named StruanBrand Analysis for an artist named Struan
Brand Analysis for an artist named Struan
 
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
 
Global Interconnection Group Joint Venture[960] (1).pdf
Global Interconnection Group Joint Venture[960] (1).pdfGlobal Interconnection Group Joint Venture[960] (1).pdf
Global Interconnection Group Joint Venture[960] (1).pdf
 
Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...
 
20240425_ TJ Communications Credentials_compressed.pdf
20240425_ TJ Communications Credentials_compressed.pdf20240425_ TJ Communications Credentials_compressed.pdf
20240425_ TJ Communications Credentials_compressed.pdf
 
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
 
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
 
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
 
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdfMeas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
 
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptxTaurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
 
April 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products NewsletterApril 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products Newsletter
 

Project Cost Management - PMP preparation course

  • 1. Presented by: Vladimir Vujović, PMP PMI Certification Preparation: PMP / CAPM - Project Cost Management - Project Management Institute, Inc. All rights reserved. October 2017
  • 2. • Presenter • Participants: profile, background, expectations • Session: structure, approach and benefits Introduction to the session
  • 3. 1. Integration management 2. Scope management 3. Time management 4. Cost management 5. Quality management 6. Human resources management 7. Communications management 8. Risk management 9. Procurement management 10. Stakeholder management Project Management Knowledge Areas PMI PMBOK 5th edition
  • 4. 1. Plan Cost Management 2. Estimate Costs 3. Determine Budget 4. Control Costs Project Cost Management Processes:
  • 5. Plan Cost Management Inputs • Project management plan • Project charter • Enterprise environmental factors • Organizational process assets Tools and Techniques • Expert judgment • Analytical techniques • Meetings Outputs • Cost management plan
  • 6. Plan Cost Management: Data Flow Plan Cost Management Estimate Costs Perform Quantitative Risk Analysis Identify Risks Enterprise / Organization Project Cost Management • Cost management plan • Project charter • OPA • EEF Determine Budget Develop Project Management Plan Develop Project Charter • Project management plan
  • 7. • Units of measure • Level of precision • Level of accuracy • Control thresholds • Rules of performance measurement • Reporting formats Cost management plan
  • 8. Estimate Costs Inputs • Cost management plan • Human resource management plan • Scope baseline • Project schedule • Risk register • Enterprise environmental factors • Organizational process assets Tools and Techniques • Expert judgment • Analogous estimating • Parametric estimating • Bottom-up estimating • Three-point estimating • Reserve analysis • Cost of quality • Project management software • Vendor bid analysis • Group decision-making techniques Outputs • Activity cost estimates • Basis of estimates • Project documents updates
  • 9. Estimate Costs: Data Flow Estimate Costs Plan Cost Management Plan Procurement Management Estimate Activity Resources Enterprise / Organization Project Cost Management • Cost management plan • Human resource management plan • OPA • EEF Determine Budget Identify Risks Plan Human Resource Management • Risk register Develop Schedule Create WBS Identify Risks Project documents • Project schedule • Scope baseline • Basis of estimates • Activity cost estimates • Project documents updates
  • 10. • Analogous estimating • Parametric estimating • Bottom up estimating • Three-point estimating: ▫ Most likely (cM) ▫ Optimistic (cO) ▫ Pessimistic (cP) ▫ Triangular distribution: cE = ( cO + cM + cP ) / 3 ▫ Beta distribution: cE = ( cO + 4cM + cP ) / 6 Estimate costs
  • 11. Determine Budget Inputs • Cost management plan • Scope baseline • Activity cost estimates • Basis of estimates • Project schedule • Resource calendars • Risk register • Agreements • Organizational process assets Tools and Techniques • Cost aggregation • Reserve analysis • Expert judgment • Historical relationships • Funding limit reconciliation Outputs • Cost baseline • Project funding requirements • Project documents updates
  • 12. Determine Budget: Data Flow Determine Budget Plan Cost Management Develop Project Management Plan Enterprise / Organization Project Cost Management • Cost management plan • Risk register • OPA Control Costs Identify Risks Acquire Project Team • Agreements • Resource calendars Develop Schedule Create WBS Project documents • Project schedule • Scope baseline • Project Funding Requirements • Cost baseline • Project documents updates Estimate Costs • Activity cost estimates • Basis of estimates Conduct Procurements • Resource calendars
  • 14. Control Costs Inputs • Project management plan • Project funding requirements • Work performance data • Organizational process assets Tools and Techniques • Earned value management • Forecasting • To-complete performance index (TCPI) • Performance reviews • Project management software • Reserve analysis Outputs • Work performance information • Cost forecasts • Change requests • Project management plan updates • Project documents updates • Organizational process assets updates
  • 15. Control Costs: Data Flow Control Costs Determine Budget Develop Project Management Plan Enterprise / Organization Project Cost Management • OPA Perform Integrated Change Control Direct and Manage Project Work Develop Project Management Plan Project documents • Project management plan • Change requests • Project management plan updates • Project funding requirements Monitor and Control Project Work • Work performance data • OPA updates • Work performance information • Cost forecasts • Project documents updates
  • 16. Earned Value Calculation (PMBOK 5, page 224) !!! Abbreviation Name Lexicon Definition How Used Equation Interpretation of Result PV Planned Value The authorized budget assigned to scheduled work. The value of the work planned to be completed to a point in time, usually the data date, or project completion. EV Earned Value The measure of work performed expressed in terms of the budget authorized for that work. The planned value of all the work completed (earned) to a point in time, usually the data date, without reference to actual costs. EV = sum of the planned value of completed work. AC Actual Cost The realized cost incurred for the work performed on an activity during a specific time period. The actual cost of all the work completed to a point in time, usually the data date. BAC Budget at Completion The sum of all budgets established for the work to be performed. The value of total planned work, the project cost baseline.
  • 17. Earned Value Calculation (PMBOK 5, page 224) !!! Abbreviation Name Lexicon Definition How Used Equation Interpretation of Result CV Cost Variance The amount of budget deficit or surplus at a givent point in time, expressed as the difference between the earned value and the actual cost. The difference between the value of work completed to a point in time, usually the data date, and the actual costs to the same point in time. CV = EV – AC Positive = Under planned cost Neutral = On planned cost Negative = Over planned cost SV Schedule Variance The amount by which the project is ahead or behind the planned delivery date, at a given point in time, expressed as the difference between the earned value and the planned value. The difference between the work completed to a pint in time, usually the data date, and the work planned to be completed to the same point in time. SV = EV – PV Positive = Ahead of Schedule Neutral = On Schedule Negative = Behind Schedule VAC Variance at Completion A projection of the amount of budget deficit or surplus, expressed as the difference between the budget at completion and the estimate at completion. The estimated difference in cost at the completion of the project. VAC = BAC – EAC Positive = Under planned cost Neutral = On planned cost Negative = Over planned cost
  • 18. Earned Value Calculation (PMBOK 5, page 224) !!! Abbreviation Name Lexicon Definition How Used Equation Interpretation of Result CPI Cost Performance Index A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost. A CPI of 1.0 means the project is exactly on budget, that the work actually done so far is exactly the same as the cost so far. Other values show the percentage of how much costs are over or under the budgeted amount for work accomplished. CPI = EV / AC Greater than 1.0 = Under planned cost Exactly 1.0 = On planned cost Less than 1.0 = Over planned cost SPI Schedule Performance Index A measure of schedule efficiency expressed as the ratio of earned value to planned value. An SPI of 1.0 means that the project is exactly on schedule, that the work actually done so far is exactly the same as the work planned to be done so far. Other values show the percentage of how much costs are over or under the budgeted amount for work planned. SPI = EV / PV Greater than 1.0 = Ahead of Schedule Exactly 1.0 = On Schedule Less than 1.0 = Behind schedule EAC Estimate at Completion The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete. If the CPI is expected to be the same for the remainder of the project, EAC can be calculated using: If future work will be accomplished at the planned rate, use: If the initial plan is no longer valid, use: If both the CPI and SPI influence the remaining work, use: EAC = BAC / CPI EAC = AC + BAC – EV EAC = AC + Bottom-up ETC EAC = AC + [(BAC – EV)/(CPI x SPI)]
  • 19. Earned Value Calculation (PMBOK 5, page 224) !!! Abbreviation Name Lexicon Definition How Used Equation Interpretation of Result ETC Extimate to Complete The expected cost to finish all the remaining project work. Assuming work is proceeding on plan, the cost of completing the remaining authorized work can be calculated using: Reestimate the remaining work from the bottom up: ETC = EAC – AC ETC = Reestimate TCPI To Complete Performance Index A measure of the cost performance that must be achieved with the remaining resources in order to meet a specified management goal, expressed as the ratio of the cost to finish the outstanding work to the budget available. The efficiency that must be maintained in order to complete on plan. The efficiency that must be maintained in order to complete the current EAC. TCPI = (BAC-EV)/(BAC-AC) TCPI = (BAC-EV)/(EAC-AC) Greater than 1.0 = Harder to complete Exactly 1.0 = Same to complete Less than 1.0 = Easier to complete Greater than 1.0 = Harder to complete Exactly 1.0 = Same to complete Less than 1.0 = Easier to complete
  • 20. • Analogous estimating: A. Uses bottom-up estimating techniques. B. Is used most frequently during the executing processes of the project. C. Uses top-down estimating techniques. D. Uses actual detailed historical costs. Sample question #1
  • 21. • Analogous estimating: A. Uses bottom-up estimating techniques. B. Is used most frequently during the executing processes of the project. C. Uses top-down estimating techniques. D. Uses actual detailed historical costs. Sample question #1
  • 22. • The main focus of life cycle costing is to: A. Estimate installation costs B. Estimate the cost of operations and maintenance C. Consider installation costs when planning the project costs D. Consider operations and maintenance costs in making project decisions Sample question #2
  • 23. • The main focus of life cycle costing is to: A. Estimate installation costs B. Estimate the cost of operations and maintenance C. Consider installation costs when planning the project costs D. Consider operations and maintenance costs in making project decisions Sample question #2
  • 24. • Cost performance measurement is BEST done through which of the following: A. Asking for a percent complete from each team member and reporting that in the monthly progress report B. Calculating earned value and using the indexes and other calculations to report past performance and forecast future performance C. Using the 50/50 rule and making sure the life cyde cost is less than the project cost D. Focusing on the amount expended last month and what will be expended the following month Sample question #3
  • 25. • Cost performance measurement is BEST done through which of the following: A. Asking for a percent complete from each team member and reporting that in the monthly progress report B. Calculating earned value and using the indexes and other calculations to report past performance and forecast future performance C. Using the 50/50 rule and making sure the life cyde cost is less than the project cost D. Focusing on the amount expended last month and what will be expended the following month Sample question #3
  • 26. • A cost performance index (CPI) of 0.89 means: A. At this time, we expect the total project to cost 89 percent more than planned B. When the project is completed we will have spent 89 percent more than planned C. The project is only progressing at 89 percent of the rate planned D. The project is only getting 89 cents out of every dollar invested Sample question #4
  • 27. • A cost performance index (CPI) of 0.89 means: A. At this time, we expect the total project to cost 89 percent more than planned B. When the project is completed we will have spent 89 percent more than planned C. The project is only progressing at 89 percent of the rate planned D. The project is only getting 89 cents out of every dollar invested Sample question #4
  • 28. • A schedule performance index (SPI) of 0.76 means: A. You are over budget B. You are ahead of schedule C. You are only progressing at 76 percent of the rate originally planned D. You are only progressing at 24 percent of the rate originally planned Sample question #5
  • 29. • A schedule performance index (SPI) of 0.76 means: A. You are over budget B. You are ahead of schedule C. You are only progressing at 76 percent of the rate originally planned D. You are only progressing at 24 percent of the rate originally planned Sample question #5
  • 30. • A cost baseline is an output of which cost management process? A. Estimate Activity Resources B. Estimate Costs C. Determine Budget D. Control Costs Sample question #6
  • 31. • A cost baseline is an output of which cost management process? A. Estimate Activity Resources B. Estimate Costs C. Determine Budget D. Control Costs Sample question #6
  • 32. • During which project management process group are budget forecasts created? A. Monitoring and controlling B. Planning C. Initiating D. Executing Sample question #7
  • 33. • During which project management process group are budget forecasts created? A. Monitoring and controlling B. Planning C. Initiating D. Executing Sample question #7
  • 34. • Which of the following represents the estimated value of the work actually accomplished? A. Earned value (EV) B. Planned value (PV) C. Actual cost (AC) D. Cost variance (CV) Sample question #8
  • 35. • Which of the following represents the estimated value of the work actually accomplished? A. Earned value (EV) B. Planned value (PV) C. Actual cost (AC) D. Cost variance (CV) Sample question #8
  • 36. • The cost contingency reserve should be: A. Hidden to prevent management from disallowing the reserve B. Added to each activity to provide the customer with a shorter critical path C. Maintained by management to cover cost overruns D. Added to the base costs of the project to account for risks Sample question #9
  • 37. • The cost contingency reserve should be: A. Hidden to prevent management from disallowing the reserve B. Added to each activity to provide the customer with a shorter critical path C. Maintained by management to cover cost overruns D. Added to the base costs of the project to account for risks Sample question #9
  • 38. • You are the project manager for a railroad construction project. Your Sponsor has asked you for a forecast for the cost of project completion. The project has a total budget of $80,000 and CPI of .95 . The project has spent $25,000 of its budget so far. How much more money do you plan to spend on the project? A. $59,210 B. $80,000 C. $84,210 D. $109,210 Sample question #10
  • 39. • You are the project manager for a railroad construction project. Your Sponsor has asked you for a forecast for the cost of project completion. The project has a total budget of $80,000 and CPI of .95 . The project has spent $25,000 of its budget so far. How much more money do you plan to spend on the project? A. $59,210 B. $80,000 C. $84,210 D. $109,210 Sample question #10 EAC = BAC/CPI. ETC = EAC - AC = BAC/CPI - AC = $80,000/0.95 - $25,000 = $59,210 (A)
  • 40. Vladimir VUJOVIĆ, PMP E-mail: vladimir.vujovic@gmail.com PMO and BCM Manager Delhaize Serbia Sources used: PMBOK Guide, 5th Edition Rita Mulcahy’s PMP Exam Prep, 8th Edition Good Luck!

Editor's Notes

  1. How presentation will benefit audience: Adult learners are more interested in a subject if they know how or why it is important to them. Presenter’s level of expertise in the subject: Briefly state your credentials in this area, or explain why participants should listen to you.
  2. Lesson descriptions should be brief.