SlideShare a Scribd company logo
1 of 23
CHAPTER 5
PROJECT COST
CONTROL &
MONITORING
GROUP 3
LIEW WEI LEONG 820767
YEO SEE CHEE 820766
5.2 INPUT AND OUTPUTS
TO/FROM COST
CONTROL
INPUTS AND OUTPUTS
• The key benefit of this process is that it provides the
means to recognize variance from the plan in order to
take corrective action and minimize risk.
• E.g. The project funding requirements are also an
input. The outputs will deal directly with work
performance information
INPUTS
• To determine project performance, one of the common
practise is by measuring the percentage of the project
progress.
• 2 problems with this approach: -
• it’s subjective and can be abused;
• for short-term activities, it’s time consuming.
• One way to reduce the time associated with recording
progress is to set up a fixed formula for short-term
activities, short-term being defined as spanning one to
two reporting periods.
INPUTS
• One way to reduce the time associated with recording
progress is to set up a fixed formula for short-term
activities, short-term being defined as spanning one to
two reporting periods.
• E.g. with the selection ratio with total of 100%, E.g. 50/50,
25/75, or 20/80. When an activity starts, the first
percentage is credited. When the activity is done, the
remainder is credited.
• Using a 50/50 measure is the most aggressive, and 20/80
is the most conservative.
TYPES OF INPUTS
Project
Management
Plan
Work
Performance
Data
Project
Funding
Requirement
Organization
l Process
Asset
TYPES OF INPUTS
• Project management plan: There are two
components you will use in this process.
• Cost baseline: planned expenditures vs actual costs.
• Cost management plan: Identify the acceptable variances for
cost performance based on:-
• Budget Constraint
• Progress Variance
• Reverse Engineering with Backwards and Forwards
Scheduling
• Cost Performance Measurement in Progress Report.
TYPES OF INPUTS
• Work performance data: This includes which
activities have started and finished, which costs have
been authorized, and which have been incurred.
• Project funding requirements: The periodic required
funds for expenditures and reserves.
• Organizational process assets
(OPAs): Organizational policies, templates, and
procedures you need to manage and report project
costs.
OUPUTS
• The outcome of this process is the actual work
performance information, E.g.:-
• Cumulative Cost & Schedule Variances
• Cumulative Cost & Schedule Performance Indexes.
• Forecasts is required and the associated data to justify
the assumptions made.
• From time to time, the project may required change
requests and update various project management plan
components, project documents, and organizational
process assets.
TYPES OF OUTPUTS
Outputs
Cost
management
plan
Cost baseline
Cost
estimates
Basis of
estimates
Causes of
variances
Lessons
learned
TYPES OF OUTPUTS
• Cost management plan: If there are significant cost
variances, you may need to revisit estimating
techniques as well as levels of accuracy needed for
estimating and reporting.
• Cost baseline: If changes have occurred or risk events
have materialized, the baseline may be updated (but
only after going through the formal change control
process).
• Cost estimates: Cost estimates may be updated to
reflect the most current information.
TYPES OF OUTPUTS
• Basis of estimates: As cost estimates are adjusted, the
underlying basis of the estimates are also updated.
• Causes of variances: Make sure to also catalog the
corrective actions taken to address the variances.
• Lessons learned: Record information that can be used
later in the project and by other projects.
EARNED VALUE
STATUS REPORT
SAMPLE
5.4 TOOLS AND
TECHNIQUES FOR COST
CONTROL
TYPES OF OUTPUTS
• Basis of estimates: As cost estimates are adjusted, the
underlying basis of the estimates are also updated.
• Causes of variances: Make sure to also catalog the
corrective actions taken to address the variances.
• Lessons learned: Record information that can be used
later in the project and by other projects.
TOOLS AND TECHNIQUES OF COST
CONTROL
• Earned Value Management
• Forecasting
• Rate of performance (RP)
• Performance Reviews
• Project Management Software
• Reserve Analysis
EARNED VALUE MANAGEMENT
(EVM)
• EVM is a project performance measurement technique
that integrates scope, time, and cost data.
• Given a baseline (original plan plus approved
changes), you can determine how well the project is
meeting its goals.
• You must enter actual information periodically to use
EVM.
• More and more organizations around the world are
using EVM to help control project costs.
EARNED VALUE MANAGEMENT
(EVM)
• The planned value (PV), formerly called the budgeted cost of
work scheduled (BCWS), also called the budget, is that portion
of the approved total cost estimate planned to be spent on an
activity during a given period
• Actual cost (AC), formerly called actual cost of work performed
(ACWP), is the total of direct and indirect costs incurred in
accomplishing work on an activity during a given period
• RM20,000 AC to accomplish task over two weeks - RM15K AC week
1and RM5K week 2
• The earned value (EV), formerly called the budgeted cost of
work performed (BCWP), is an estimate of the value of the
physical work actually completed
• EV is based on the original planned costs for the project or activity
and the rate at which the team is completing work on the project
or activity to date
FORECASTING
• EAC (Estimate At Completion) is determined based on
a calculated value or a bottom-up estimation based on
the remaining work
RATE OF PERFORMANCE (RP)
• Rate of performance (RP) is the ratio of actual
work completed to the percentage of work
planned to have been completed at any given
time during the life of the project or activity
• Brenda Taylor, Senior Project Manager in South
Africa, suggests this term and approach for
estimating earned value
• For example, suppose the server installation was
halfway completed by the end of week 1; the rate of
performance would be 50% because by the end of
week 1, the planned schedule reflects that the task
should be 100% complete and only 50% of that work
has been completed
• The EV would thus be $5,000 after week 1
($10,000*50%)
PERFORMANCE REVIEW
• Performance reviews in projects are required to check
the health of a project. This usually involves Cost and
Schedule as the main parameters to assess. However,
other parameters, such as Scope, Quality, and Team
Morale may be used. Reviews may include the
client, Owner, or other Project Managers
PROJECT MANAGEMENT
SOFTWARE
• Spreadsheets are a common tool for resource planning,
cost estimating, cost budgeting, and cost control
• Many companies use more sophisticated and centralized
financial applications software for cost information
• Project management software has many cost-related
features, especially enterprise PM software
• Several companies have developed methods to link data between
their project management software and their main accounting
systems
RESERVE ANALYSIS
• Reserve Analysis is one of the techniques used to
determine a project budget.
• During Reserve Analysis, a project is analyzed from a
cost overruns point of view and buffers are placed in
appropriate place.
• These buffers are called Contingency and
Management Reserves.

More Related Content

Similar to Chapter 3 Project Cost Control and Monitoring.pptx

CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptx
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptxCCM821S _ Contract Management _ 8. Monitoring Project Performance.pptx
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptxMariaNambahu
 
9-180307064518 (1).pptx
9-180307064518 (1).pptx9-180307064518 (1).pptx
9-180307064518 (1).pptxRenvic
 
7 Project planning for software engineering.pptx
7 Project planning for software engineering.pptx7 Project planning for software engineering.pptx
7 Project planning for software engineering.pptxgezaegebre1
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..pptPedadaSaikumar
 
Tools and Techniques of Capital Expenditure Control
Tools and Techniques of Capital Expenditure ControlTools and Techniques of Capital Expenditure Control
Tools and Techniques of Capital Expenditure ControlSheetal Wagh
 
cost Management V4
cost Management V4cost Management V4
cost Management V4Qussay Karam
 
Preparing cost estimation
Preparing cost estimationPreparing cost estimation
Preparing cost estimationSomashekar S.M
 
Project Cost Managementttttttttttt .pdf
Project Cost Managementttttttttttt   .pdfProject Cost Managementttttttttttt   .pdf
Project Cost Managementttttttttttt .pdfAliaaAl4
 
4- Project Cost Management.ppt
4- Project Cost Management.ppt4- Project Cost Management.ppt
4- Project Cost Management.pptMohamadAGhareb
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagementDhamo daran
 
Project management master class karin rheeder
Project management master class   karin rheederProject management master class   karin rheeder
Project management master class karin rheederKarin Rheeder
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueChris Carson
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueChris Carson
 
Monitor and control process group part two
Monitor and control process group part twoMonitor and control process group part two
Monitor and control process group part twoHossam Maghrabi
 
Project Management Ch 14.ppt
Project Management Ch 14.pptProject Management Ch 14.ppt
Project Management Ch 14.pptUjalaBatool7
 
Project control and process instrumentation
Project control and process instrumentationProject control and process instrumentation
Project control and process instrumentationKuppusamy P
 
Project Management C8 -cost_estimation_and_budgeting
Project Management C8  -cost_estimation_and_budgetingProject Management C8  -cost_estimation_and_budgeting
Project Management C8 -cost_estimation_and_budgetingIzah Asmadi
 

Similar to Chapter 3 Project Cost Control and Monitoring.pptx (20)

CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptx
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptxCCM821S _ Contract Management _ 8. Monitoring Project Performance.pptx
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptx
 
9-180307064518 (1).pptx
9-180307064518 (1).pptx9-180307064518 (1).pptx
9-180307064518 (1).pptx
 
7 Project planning for software engineering.pptx
7 Project planning for software engineering.pptx7 Project planning for software engineering.pptx
7 Project planning for software engineering.pptx
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
 
test
testtest
test
 
Tools and Techniques of Capital Expenditure Control
Tools and Techniques of Capital Expenditure ControlTools and Techniques of Capital Expenditure Control
Tools and Techniques of Capital Expenditure Control
 
cost Management V4
cost Management V4cost Management V4
cost Management V4
 
Preparing cost estimation
Preparing cost estimationPreparing cost estimation
Preparing cost estimation
 
Project Cost Managementttttttttttt .pdf
Project Cost Managementttttttttttt   .pdfProject Cost Managementttttttttttt   .pdf
Project Cost Managementttttttttttt .pdf
 
4- Project Cost Management.ppt
4- Project Cost Management.ppt4- Project Cost Management.ppt
4- Project Cost Management.ppt
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
 
Project management master class karin rheeder
Project management master class   karin rheederProject management master class   karin rheeder
Project management master class karin rheeder
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned Value
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned Value
 
Project cost management
Project cost managementProject cost management
Project cost management
 
Monitor and control process group part two
Monitor and control process group part twoMonitor and control process group part two
Monitor and control process group part two
 
Project Management Ch 14.ppt
Project Management Ch 14.pptProject Management Ch 14.ppt
Project Management Ch 14.ppt
 
Project control and process instrumentation
Project control and process instrumentationProject control and process instrumentation
Project control and process instrumentation
 
Project Management C8 -cost_estimation_and_budgeting
Project Management C8  -cost_estimation_and_budgetingProject Management C8  -cost_estimation_and_budgeting
Project Management C8 -cost_estimation_and_budgeting
 
Project Cost Management for IEM talk on 13 January 2018.
Project Cost Management  for IEM talk on 13 January 2018.Project Cost Management  for IEM talk on 13 January 2018.
Project Cost Management for IEM talk on 13 January 2018.
 

Recently uploaded

Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfSumit Tiwari
 
Science lesson Moon for 4th quarter lesson
Science lesson Moon for 4th quarter lessonScience lesson Moon for 4th quarter lesson
Science lesson Moon for 4th quarter lessonJericReyAuditor
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerunnathinaik
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxRaymartEstabillo3
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaVirag Sontakke
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
Biting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfBiting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfadityarao40181
 
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxsocialsciencegdgrohi
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfakmcokerachita
 
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptxENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptxAnaBeatriceAblay2
 

Recently uploaded (20)

Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
 
Science lesson Moon for 4th quarter lesson
Science lesson Moon for 4th quarter lessonScience lesson Moon for 4th quarter lesson
Science lesson Moon for 4th quarter lesson
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developer
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of India
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
Biting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfBiting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdf
 
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdf
 
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptxENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
 

Chapter 3 Project Cost Control and Monitoring.pptx

  • 1. CHAPTER 5 PROJECT COST CONTROL & MONITORING GROUP 3 LIEW WEI LEONG 820767 YEO SEE CHEE 820766
  • 2. 5.2 INPUT AND OUTPUTS TO/FROM COST CONTROL
  • 3. INPUTS AND OUTPUTS • The key benefit of this process is that it provides the means to recognize variance from the plan in order to take corrective action and minimize risk. • E.g. The project funding requirements are also an input. The outputs will deal directly with work performance information
  • 4. INPUTS • To determine project performance, one of the common practise is by measuring the percentage of the project progress. • 2 problems with this approach: - • it’s subjective and can be abused; • for short-term activities, it’s time consuming. • One way to reduce the time associated with recording progress is to set up a fixed formula for short-term activities, short-term being defined as spanning one to two reporting periods.
  • 5. INPUTS • One way to reduce the time associated with recording progress is to set up a fixed formula for short-term activities, short-term being defined as spanning one to two reporting periods. • E.g. with the selection ratio with total of 100%, E.g. 50/50, 25/75, or 20/80. When an activity starts, the first percentage is credited. When the activity is done, the remainder is credited. • Using a 50/50 measure is the most aggressive, and 20/80 is the most conservative.
  • 7. TYPES OF INPUTS • Project management plan: There are two components you will use in this process. • Cost baseline: planned expenditures vs actual costs. • Cost management plan: Identify the acceptable variances for cost performance based on:- • Budget Constraint • Progress Variance • Reverse Engineering with Backwards and Forwards Scheduling • Cost Performance Measurement in Progress Report.
  • 8. TYPES OF INPUTS • Work performance data: This includes which activities have started and finished, which costs have been authorized, and which have been incurred. • Project funding requirements: The periodic required funds for expenditures and reserves. • Organizational process assets (OPAs): Organizational policies, templates, and procedures you need to manage and report project costs.
  • 9. OUPUTS • The outcome of this process is the actual work performance information, E.g.:- • Cumulative Cost & Schedule Variances • Cumulative Cost & Schedule Performance Indexes. • Forecasts is required and the associated data to justify the assumptions made. • From time to time, the project may required change requests and update various project management plan components, project documents, and organizational process assets.
  • 10. TYPES OF OUTPUTS Outputs Cost management plan Cost baseline Cost estimates Basis of estimates Causes of variances Lessons learned
  • 11. TYPES OF OUTPUTS • Cost management plan: If there are significant cost variances, you may need to revisit estimating techniques as well as levels of accuracy needed for estimating and reporting. • Cost baseline: If changes have occurred or risk events have materialized, the baseline may be updated (but only after going through the formal change control process). • Cost estimates: Cost estimates may be updated to reflect the most current information.
  • 12. TYPES OF OUTPUTS • Basis of estimates: As cost estimates are adjusted, the underlying basis of the estimates are also updated. • Causes of variances: Make sure to also catalog the corrective actions taken to address the variances. • Lessons learned: Record information that can be used later in the project and by other projects.
  • 14. 5.4 TOOLS AND TECHNIQUES FOR COST CONTROL
  • 15. TYPES OF OUTPUTS • Basis of estimates: As cost estimates are adjusted, the underlying basis of the estimates are also updated. • Causes of variances: Make sure to also catalog the corrective actions taken to address the variances. • Lessons learned: Record information that can be used later in the project and by other projects.
  • 16. TOOLS AND TECHNIQUES OF COST CONTROL • Earned Value Management • Forecasting • Rate of performance (RP) • Performance Reviews • Project Management Software • Reserve Analysis
  • 17. EARNED VALUE MANAGEMENT (EVM) • EVM is a project performance measurement technique that integrates scope, time, and cost data. • Given a baseline (original plan plus approved changes), you can determine how well the project is meeting its goals. • You must enter actual information periodically to use EVM. • More and more organizations around the world are using EVM to help control project costs.
  • 18. EARNED VALUE MANAGEMENT (EVM) • The planned value (PV), formerly called the budgeted cost of work scheduled (BCWS), also called the budget, is that portion of the approved total cost estimate planned to be spent on an activity during a given period • Actual cost (AC), formerly called actual cost of work performed (ACWP), is the total of direct and indirect costs incurred in accomplishing work on an activity during a given period • RM20,000 AC to accomplish task over two weeks - RM15K AC week 1and RM5K week 2 • The earned value (EV), formerly called the budgeted cost of work performed (BCWP), is an estimate of the value of the physical work actually completed • EV is based on the original planned costs for the project or activity and the rate at which the team is completing work on the project or activity to date
  • 19. FORECASTING • EAC (Estimate At Completion) is determined based on a calculated value or a bottom-up estimation based on the remaining work
  • 20. RATE OF PERFORMANCE (RP) • Rate of performance (RP) is the ratio of actual work completed to the percentage of work planned to have been completed at any given time during the life of the project or activity • Brenda Taylor, Senior Project Manager in South Africa, suggests this term and approach for estimating earned value • For example, suppose the server installation was halfway completed by the end of week 1; the rate of performance would be 50% because by the end of week 1, the planned schedule reflects that the task should be 100% complete and only 50% of that work has been completed • The EV would thus be $5,000 after week 1 ($10,000*50%)
  • 21. PERFORMANCE REVIEW • Performance reviews in projects are required to check the health of a project. This usually involves Cost and Schedule as the main parameters to assess. However, other parameters, such as Scope, Quality, and Team Morale may be used. Reviews may include the client, Owner, or other Project Managers
  • 22. PROJECT MANAGEMENT SOFTWARE • Spreadsheets are a common tool for resource planning, cost estimating, cost budgeting, and cost control • Many companies use more sophisticated and centralized financial applications software for cost information • Project management software has many cost-related features, especially enterprise PM software • Several companies have developed methods to link data between their project management software and their main accounting systems
  • 23. RESERVE ANALYSIS • Reserve Analysis is one of the techniques used to determine a project budget. • During Reserve Analysis, a project is analyzed from a cost overruns point of view and buffers are placed in appropriate place. • These buffers are called Contingency and Management Reserves.