The document provides an outline for a project management course. It includes details on the topics that will be covered each day, including project integration management, scope management, schedule management, cost management, risk management, and Scrum. The focus of the specific section summarized is on project cost management. It defines key processes involved in project cost management like planning, estimating, budgeting, controlling, and managing costs. Formulas for earned value management are also provided to measure project performance and forecast estimates.
A brief introduction on various concepts of Project Cost, covering various types of Project Costs, Processes to be followed for developing project budget, project budget components, contingency and management reserves, earned value management
This document provides an overview of project cost management. It discusses estimating, budgeting, and controlling costs so the project can be completed within the approved budget. Key aspects covered include developing cost estimates using various techniques, determining an authorized cost baseline by aggregating estimates, and monitoring costs against the baseline using earned value management. Formulas for calculating important metrics like cost and schedule variance, cost performance index, and estimate at completion are also presented to aid in cost control.
Control Costs is the process of monitoring project costs and managing changes to the cost baseline. It involves analyzing variances, forecasting costs, and updating cost estimates and budgets as needed. Key inputs include the cost management plan, cost baseline, and work performance data. Tools like earned value analysis, variance analysis, and forecasting are used. Outputs include updated cost forecasts, change requests, and revisions to cost documents and plans. The goal is to maintain an accurate cost baseline throughout the project.
The document discusses project cost management, which involves planning, estimating, budgeting, financing, funding, managing and controlling costs to complete a project within an approved budget. It outlines the four main processes: 1) plan cost management, 2) estimate costs, 3) determine budget, and 4) control costs. Earned value management is a key technique for monitoring project performance and progress against the cost baseline.
This document discusses project cost management. It explains that cost management includes planning, estimating, budgeting, and controlling costs to complete a project within the approved budget. Estimating involves developing cost estimates for project resources. Budgeting aggregates these estimates to establish a cost baseline. Controlling costs involves managing the baseline and variances using tools like earned value management. A surveyor plays a key role by supporting cost planning, estimating, monitoring budgets, and other cost control activities. Effective cost control is important for project success and company profitability.
This document discusses project cost management processes including:
1. Estimating costs, developing budgets, and controlling costs to complete projects within approved budgets. This involves estimating types of costs, quality of estimates, and determining authorized cost baselines.
2. Monitoring project status to update budgets and manage cost changes using earned value management techniques like tracking schedule and cost performance indexes.
3. Forecasting estimated costs at completion using data on past performance to predict future costs and variances. Interpreting earned value metrics is key to understanding project performance and risks.
Tools and Techniques of Capital Expenditure ControlSheetal Wagh
This document discusses tools and techniques for controlling capital expenditures. It defines capital expenditures as funds used to obtain physical assets used for over a year to expand a business. The four main tools discussed are: 1) performance indexes like schedule and cost performance indexes to measure efficiency, 2) technical performance measurements to monitor project requirements, 3) post-completion audits to evaluate final costs/benefits, and 4) earned value management which integrates measurements of scope, time and costs to provide accurate forecasts of project performance problems. The objectives of capital expenditure control are also outlined.
A brief introduction on various concepts of Project Cost, covering various types of Project Costs, Processes to be followed for developing project budget, project budget components, contingency and management reserves, earned value management
This document provides an overview of project cost management. It discusses estimating, budgeting, and controlling costs so the project can be completed within the approved budget. Key aspects covered include developing cost estimates using various techniques, determining an authorized cost baseline by aggregating estimates, and monitoring costs against the baseline using earned value management. Formulas for calculating important metrics like cost and schedule variance, cost performance index, and estimate at completion are also presented to aid in cost control.
Control Costs is the process of monitoring project costs and managing changes to the cost baseline. It involves analyzing variances, forecasting costs, and updating cost estimates and budgets as needed. Key inputs include the cost management plan, cost baseline, and work performance data. Tools like earned value analysis, variance analysis, and forecasting are used. Outputs include updated cost forecasts, change requests, and revisions to cost documents and plans. The goal is to maintain an accurate cost baseline throughout the project.
The document discusses project cost management, which involves planning, estimating, budgeting, financing, funding, managing and controlling costs to complete a project within an approved budget. It outlines the four main processes: 1) plan cost management, 2) estimate costs, 3) determine budget, and 4) control costs. Earned value management is a key technique for monitoring project performance and progress against the cost baseline.
This document discusses project cost management. It explains that cost management includes planning, estimating, budgeting, and controlling costs to complete a project within the approved budget. Estimating involves developing cost estimates for project resources. Budgeting aggregates these estimates to establish a cost baseline. Controlling costs involves managing the baseline and variances using tools like earned value management. A surveyor plays a key role by supporting cost planning, estimating, monitoring budgets, and other cost control activities. Effective cost control is important for project success and company profitability.
This document discusses project cost management processes including:
1. Estimating costs, developing budgets, and controlling costs to complete projects within approved budgets. This involves estimating types of costs, quality of estimates, and determining authorized cost baselines.
2. Monitoring project status to update budgets and manage cost changes using earned value management techniques like tracking schedule and cost performance indexes.
3. Forecasting estimated costs at completion using data on past performance to predict future costs and variances. Interpreting earned value metrics is key to understanding project performance and risks.
Tools and Techniques of Capital Expenditure ControlSheetal Wagh
This document discusses tools and techniques for controlling capital expenditures. It defines capital expenditures as funds used to obtain physical assets used for over a year to expand a business. The four main tools discussed are: 1) performance indexes like schedule and cost performance indexes to measure efficiency, 2) technical performance measurements to monitor project requirements, 3) post-completion audits to evaluate final costs/benefits, and 4) earned value management which integrates measurements of scope, time and costs to provide accurate forecasts of project performance problems. The objectives of capital expenditure control are also outlined.
This document discusses project cost management principles and processes. It explains that IT projects often experience cost overruns and provides examples. The key processes for managing costs are estimating costs, determining budgets, and controlling costs. Estimating involves developing cost approximations, while determining budgets allocates the estimate to work items to establish a baseline. Controlling costs involves monitoring performance against the baseline and approving changes. Earned value management is presented as a technique to integrate scope, time and cost data to track project performance.
This document provides an overview of project cost management processes including plan cost management, estimate costs, determine budget, and control costs. Key concepts such as earned value management, cost estimating techniques like three-point estimating, and terms like cost baseline and management reserve are defined. The document also discusses trends in project cost management like expanding earned value management to include earned schedule. Sample formulas for calculating earned value metrics like cost variance, schedule variance, and estimate at completion are provided.
Chapter 3 Project Cost Control and Monitoring.pptxssusercf695b
This document discusses various tools and techniques for project cost control and monitoring. It describes key inputs like the project management plan, work performance data, and funding requirements. Outputs include updated cost baselines, estimates, and lessons learned. Earned value management is discussed as a technique to integrate scope, time, and cost. Other techniques include forecasting using EAC, performance reviews, project management software, and reserve analysis.
The document discusses key aspects of project integration management including:
1) The importance of project integration management and coordinating all project knowledge areas.
2) How the Airbus A380 project faced integration issues due to software version mismatches.
3) Key project integration processes like developing plans, directing execution, monitoring, and change control.
4) Methods for project selection like NPV, ROI, weighted scoring, and how a project charter and management plan are used.
Project monitoring refers to tracking project metrics like team performance, task duration, and identifying potential problems to ensure a project is on schedule, budget, and scope. It clarifies objectives, links activities to objectives, reports progress to management, and alerts managers to issues. Project monitoring assesses results, improves planning, promotes learning, ensures accountability, and answers questions about task progress, unforeseen consequences, team performance, needed changes, and impact on results. Earned value analysis is a monitoring tool that compares planned, actual, and earned values to measure progress and performance through metrics like schedule and cost variances, and indexes. Regular reporting keeps stakeholders informed of project status.
The document discusses project cost management. It covers the importance of cost management for IT projects, which often experience large cost overruns. It then defines project costs and describes the key processes of cost estimating, cost budgeting, and cost control. Cost estimating involves developing cost estimates for project activities. Cost budgeting aggregates these estimates to establish a total cost baseline. Cost control monitors actual costs against the baseline and manages changes to keep the project within budget. The document provides details on the inputs, tools, techniques and outputs for each cost management process.
Abstract— Execution of engineering projects are tracked against critical metrics such as safety, quality,
delivery cost and inventory. Earned value is a key parameter that helps in assessing delivery (schedule) and cost.
Static shows that 70% of projects are over budget behind schedule, 52% of all projects finish at 189% of their
initial budget and some, after huge investments of time and money, are simply never completed. The rest of this
paper gives a perspective on monitoring project health by Earned value analysis.
In defining a project accounting system for an organisation, the needs of both project management and the finance function have to be met. However their needs differ. By combining project and programme management techniques with financial and management accounting methods, a more holistic approach to capturing metrics is possible. Analysis of this will enable focused effort to improve project efficiency and effectiveness.
This document discusses cost management in project planning and development. It defines cost management as estimating, budgeting, and controlling costs throughout a project's life cycle to keep expenses within the approved budget. It explains that cost management is vital for effective project planning and prevention of overruns. The types of costs include direct, indirect, labor, materials, equipment, and expenses. Key steps in cost management are project resource planning, cost estimation, cost budgeting, cost control, and using earned value management to measure performance. Formulas are provided to calculate cost variance, cost performance index, and schedule performance index. An example calculation is also included.
This document provides an overview of project cost management based on the PMBOK Guide. It discusses the key processes involved, including plan cost management, estimate costs, determine budget, and control costs. For each process, it outlines the typical inputs, tools and techniques, and outputs. It also discusses important concepts like the cost management plan, cost baselines, earned value management, variance analysis, and estimating techniques. The overall purpose is to plan, estimate, budget, and control costs throughout the project life cycle.
The document discusses the importance of project cost management. It notes that projects historically have poor track records for meeting cost goals, with average cost overruns found in various CHAOS studies from 1995 to 2003. Proper project cost management, including processes like resource planning, cost estimating, cost budgeting and cost control, can help reduce cost overruns. The basic principles of cost management, such as distinguishing different types of costs and using techniques like activity-based costing and reserves, are also covered.
The document provides information about cost management processes according to PMBOK 5. It includes definitions and explanations of processes for planning cost management, estimating costs, determining budgets, and controlling costs. Key aspects covered are cost estimation techniques, calculating estimates at completion, variance analysis using earned value management, and establishing cost baselines and performance measurement.
Project Planning and Excution chapter 4.pptadabotor7
undamental business information systems concepts including: trends, components, and roles of information systems and competitive advantage concepts and applications
This document provides an overview of project cost management. It defines key processes for planning, estimating, determining budgets, and controlling costs on a project. Section 7.1 discusses planning cost management by establishing policies and documentation for managing project costs. Section 7.2 covers estimating costs by developing approximations for completing project activities. Section 7.3 involves determining the project budget by aggregating activity cost estimates. Finally, section 7.4 is about controlling costs by monitoring project spending and updating the cost baseline.
This document discusses project cost management. It defines cost management as planning, estimating, budgeting, and controlling costs to complete a project within budget. Key aspects of cost management covered include cost estimating, budgeting, and control. Cost estimating techniques include analogous, bottom-up, parametric, and vendor bid analysis. Budgeting involves aggregating estimates and establishing contingency reserves. Control includes monitoring for cost variances, performance reviews, and change control. The overall goal of cost management is to inform stakeholders and take actions to prevent or address any expected cost overruns.
The document discusses key aspects of project cost management for PMP exam preparation. It describes the processes of estimate cost, determine budget, and control costs. For each process, it outlines the inputs, tools and techniques, and outputs. It also provides examples of tools like bottom-up estimating, earned value management, and variance analysis that are used to estimate costs, set the budget baseline, and monitor project performance against the budget. Definitions of important cost management terms like net present value, internal rate of return, and payback period are also included.
Project cost management involves planning, estimating, budgeting, and controlling costs to complete a project within an approved budget. Key terms include planned value, earned value, actual costs, budget at completion, estimate at completion, and estimate to complete. There are three main processes: 1) estimate costs using methods like analogous, bottom-up, and parametric estimating, 2) determine the budget by aggregating costs and establishing a cost baseline, and 3) control costs using earned value management, variance analysis, and forecasting estimates to complete. Earned value, schedule and cost variances, and performance indexes are calculated and monitored to assess performance and get projects back on track if over budget or behind schedule.
Using Earned Value Management Concepts to Improve Commercial Project PerformanceLewisFowlerLLC
Lewis Fowler Principal Consultant Scott Brunton presented this deck at the 2015 Houston PMI Conference & Expo. Scott explores the historical roots of EVM and offers practical advice for implementing EVM practices to maximize the business value of projects.
The document discusses project management methodologies, specifically comparing traditional waterfall and agile approaches. It provides details on waterfall, including its sequential phases of requirements, design, implementation, and test. Agile methodologies are described as iterative with short development cycles. The Scrum framework is then explained in depth, covering its roles of Product Owner, Scrum Master, and team, along with artifacts like the Product Backlog, Sprint Backlog, and burndown chart. Key Scrum meetings like the Sprint Planning, daily standup, and Sprint Review meetings are also outlined.
The document discusses project risk management over 7 days. Day 5 focuses on project risk management and includes discussions of identifying risks, qualitative and quantitative risk analysis, and planning risk responses. Key topics covered are the importance of risk management, types of risks, tools for risk identification like brainstorming, risk breakdown structures, and risk registers to document risks.
More Related Content
Similar to Project Management Day 4 Cost ٌ R02.pdf
This document discusses project cost management principles and processes. It explains that IT projects often experience cost overruns and provides examples. The key processes for managing costs are estimating costs, determining budgets, and controlling costs. Estimating involves developing cost approximations, while determining budgets allocates the estimate to work items to establish a baseline. Controlling costs involves monitoring performance against the baseline and approving changes. Earned value management is presented as a technique to integrate scope, time and cost data to track project performance.
This document provides an overview of project cost management processes including plan cost management, estimate costs, determine budget, and control costs. Key concepts such as earned value management, cost estimating techniques like three-point estimating, and terms like cost baseline and management reserve are defined. The document also discusses trends in project cost management like expanding earned value management to include earned schedule. Sample formulas for calculating earned value metrics like cost variance, schedule variance, and estimate at completion are provided.
Chapter 3 Project Cost Control and Monitoring.pptxssusercf695b
This document discusses various tools and techniques for project cost control and monitoring. It describes key inputs like the project management plan, work performance data, and funding requirements. Outputs include updated cost baselines, estimates, and lessons learned. Earned value management is discussed as a technique to integrate scope, time, and cost. Other techniques include forecasting using EAC, performance reviews, project management software, and reserve analysis.
The document discusses key aspects of project integration management including:
1) The importance of project integration management and coordinating all project knowledge areas.
2) How the Airbus A380 project faced integration issues due to software version mismatches.
3) Key project integration processes like developing plans, directing execution, monitoring, and change control.
4) Methods for project selection like NPV, ROI, weighted scoring, and how a project charter and management plan are used.
Project monitoring refers to tracking project metrics like team performance, task duration, and identifying potential problems to ensure a project is on schedule, budget, and scope. It clarifies objectives, links activities to objectives, reports progress to management, and alerts managers to issues. Project monitoring assesses results, improves planning, promotes learning, ensures accountability, and answers questions about task progress, unforeseen consequences, team performance, needed changes, and impact on results. Earned value analysis is a monitoring tool that compares planned, actual, and earned values to measure progress and performance through metrics like schedule and cost variances, and indexes. Regular reporting keeps stakeholders informed of project status.
The document discusses project cost management. It covers the importance of cost management for IT projects, which often experience large cost overruns. It then defines project costs and describes the key processes of cost estimating, cost budgeting, and cost control. Cost estimating involves developing cost estimates for project activities. Cost budgeting aggregates these estimates to establish a total cost baseline. Cost control monitors actual costs against the baseline and manages changes to keep the project within budget. The document provides details on the inputs, tools, techniques and outputs for each cost management process.
Abstract— Execution of engineering projects are tracked against critical metrics such as safety, quality,
delivery cost and inventory. Earned value is a key parameter that helps in assessing delivery (schedule) and cost.
Static shows that 70% of projects are over budget behind schedule, 52% of all projects finish at 189% of their
initial budget and some, after huge investments of time and money, are simply never completed. The rest of this
paper gives a perspective on monitoring project health by Earned value analysis.
In defining a project accounting system for an organisation, the needs of both project management and the finance function have to be met. However their needs differ. By combining project and programme management techniques with financial and management accounting methods, a more holistic approach to capturing metrics is possible. Analysis of this will enable focused effort to improve project efficiency and effectiveness.
This document discusses cost management in project planning and development. It defines cost management as estimating, budgeting, and controlling costs throughout a project's life cycle to keep expenses within the approved budget. It explains that cost management is vital for effective project planning and prevention of overruns. The types of costs include direct, indirect, labor, materials, equipment, and expenses. Key steps in cost management are project resource planning, cost estimation, cost budgeting, cost control, and using earned value management to measure performance. Formulas are provided to calculate cost variance, cost performance index, and schedule performance index. An example calculation is also included.
This document provides an overview of project cost management based on the PMBOK Guide. It discusses the key processes involved, including plan cost management, estimate costs, determine budget, and control costs. For each process, it outlines the typical inputs, tools and techniques, and outputs. It also discusses important concepts like the cost management plan, cost baselines, earned value management, variance analysis, and estimating techniques. The overall purpose is to plan, estimate, budget, and control costs throughout the project life cycle.
The document discusses the importance of project cost management. It notes that projects historically have poor track records for meeting cost goals, with average cost overruns found in various CHAOS studies from 1995 to 2003. Proper project cost management, including processes like resource planning, cost estimating, cost budgeting and cost control, can help reduce cost overruns. The basic principles of cost management, such as distinguishing different types of costs and using techniques like activity-based costing and reserves, are also covered.
The document provides information about cost management processes according to PMBOK 5. It includes definitions and explanations of processes for planning cost management, estimating costs, determining budgets, and controlling costs. Key aspects covered are cost estimation techniques, calculating estimates at completion, variance analysis using earned value management, and establishing cost baselines and performance measurement.
Project Planning and Excution chapter 4.pptadabotor7
undamental business information systems concepts including: trends, components, and roles of information systems and competitive advantage concepts and applications
This document provides an overview of project cost management. It defines key processes for planning, estimating, determining budgets, and controlling costs on a project. Section 7.1 discusses planning cost management by establishing policies and documentation for managing project costs. Section 7.2 covers estimating costs by developing approximations for completing project activities. Section 7.3 involves determining the project budget by aggregating activity cost estimates. Finally, section 7.4 is about controlling costs by monitoring project spending and updating the cost baseline.
This document discusses project cost management. It defines cost management as planning, estimating, budgeting, and controlling costs to complete a project within budget. Key aspects of cost management covered include cost estimating, budgeting, and control. Cost estimating techniques include analogous, bottom-up, parametric, and vendor bid analysis. Budgeting involves aggregating estimates and establishing contingency reserves. Control includes monitoring for cost variances, performance reviews, and change control. The overall goal of cost management is to inform stakeholders and take actions to prevent or address any expected cost overruns.
The document discusses key aspects of project cost management for PMP exam preparation. It describes the processes of estimate cost, determine budget, and control costs. For each process, it outlines the inputs, tools and techniques, and outputs. It also provides examples of tools like bottom-up estimating, earned value management, and variance analysis that are used to estimate costs, set the budget baseline, and monitor project performance against the budget. Definitions of important cost management terms like net present value, internal rate of return, and payback period are also included.
Project cost management involves planning, estimating, budgeting, and controlling costs to complete a project within an approved budget. Key terms include planned value, earned value, actual costs, budget at completion, estimate at completion, and estimate to complete. There are three main processes: 1) estimate costs using methods like analogous, bottom-up, and parametric estimating, 2) determine the budget by aggregating costs and establishing a cost baseline, and 3) control costs using earned value management, variance analysis, and forecasting estimates to complete. Earned value, schedule and cost variances, and performance indexes are calculated and monitored to assess performance and get projects back on track if over budget or behind schedule.
Using Earned Value Management Concepts to Improve Commercial Project PerformanceLewisFowlerLLC
Lewis Fowler Principal Consultant Scott Brunton presented this deck at the 2015 Houston PMI Conference & Expo. Scott explores the historical roots of EVM and offers practical advice for implementing EVM practices to maximize the business value of projects.
Similar to Project Management Day 4 Cost ٌ R02.pdf (20)
The document discusses project management methodologies, specifically comparing traditional waterfall and agile approaches. It provides details on waterfall, including its sequential phases of requirements, design, implementation, and test. Agile methodologies are described as iterative with short development cycles. The Scrum framework is then explained in depth, covering its roles of Product Owner, Scrum Master, and team, along with artifacts like the Product Backlog, Sprint Backlog, and burndown chart. Key Scrum meetings like the Sprint Planning, daily standup, and Sprint Review meetings are also outlined.
The document discusses project risk management over 7 days. Day 5 focuses on project risk management and includes discussions of identifying risks, qualitative and quantitative risk analysis, and planning risk responses. Key topics covered are the importance of risk management, types of risks, tools for risk identification like brainstorming, risk breakdown structures, and risk registers to document risks.
The document discusses project schedule management processes including plan schedule management, define activities, sequence activities, estimate activity resources, and estimate activity durations. It provides details on each process, including inputs, tools and techniques, and outputs. The key steps are decomposing work into activities, defining relationships between activities, estimating resource needs and duration of each activity, and developing a project schedule network diagram.
The document outlines a 7-day project management training course. Day 1 covers an introduction to project integration management. Later days cover additional topics like scope, schedule, cost, risk management and Scrum. The course aims to help participants understand key project management principles, processes, knowledge areas and the role of the project manager. It emphasizes the importance of integrating all project efforts, balancing scope, time and cost constraints, and addressing stakeholder needs.
The document outlines the course schedule for a 7-day project management training. Day 2 focuses on project scope management. It defines key scope management terms and processes. The presentation covers planning scope management, collecting requirements, defining the scope statement, creating the work breakdown structure (WBS), and validating scope. Tools for collecting requirements and creating the WBS are also discussed.
This document provides guidance on writing a business plan. It explains that a business plan clarifies the feasibility of a business idea by evaluating the potential market, management team, and profitability. It also communicates the idea to investors and provides the basis for securing financing. The document outlines the typical sections of a business plan, including executive summary, business description, products/services, sales and marketing plan, operations plan, and financial projections. It emphasizes that a well-written business plan is important for gaining investor confidence and improving the chances of business success.
This document appears to be a presentation about cyber-physical systems and Industry 4.0. It includes definitions of cyber-physical systems and Industry 4.0, examples of companies implementing Industry 4.0 solutions, discussions of the Internet of Things, impacts of new technologies on the economy, business, society and individuals, and slides on various related topics without titles like applications, history, and use cases. The presentation touches on many aspects of emerging digital technologies and their integration with physical systems and processes.
This document discusses shear flow in aircraft structural design. It covers governing equations for shear flow calculations, case studies of shear flow in aircraft fuselages, and methods for calculating moments of inertia and shear flow. The document is a lecture on shear flow given by Dr. Mohamed Elfarran of Cairo University's Aerospace Engineering Department.
The document discusses analyzing the ultimate bending strength of an aircraft fuselage structure. It provides an example problem to calculate the ultimate bending moment of a fuselage cross section considering shear lag and inter-rivet buckling effects. The solution involves determining the effective area of structural elements through an iterative process accounting for stresses, strains, and shear lag factors. The example provides details of the fuselage geometry, materials, and step-by-step working to arrive at the ultimate bending moment and stringer forces.
This document discusses calculating the ultimate bending strength of a fuselage structure. It provides an example problem of determining stresses in the stringers and skin of a fuselage cross-section due to an applied bending moment. The solution involves iteratively calculating the neutral axis position and effective area through trial and error, starting with an initial assumption that all materials are effective in tension. The results of the first trial are then used to refine the model for a second trial. Comparing the results shows an error of 14% in the neutral axis position between the first and second trials.
The document discusses three cases of aircraft structural loading and the resulting stresses: 1) Pressurization of the fuselage shell, which induces longitudinal and circumferential stresses that depend on the material properties and geometry, 2) Torsional loading of the fuselage shell, which causes shear stresses proportional to the applied torque and cross-sectional properties, and 3) Bending loads on wing spars, which are resisted by shear stresses in the spar webs and normal stresses in the spar caps that depend on the bending moment and section properties.
This document discusses analyzing stresses on an unsymmetrical tapered fuselage structure due to applied loads. It provides an example problem to determine stringer stresses and forces at two stations, section 0 and section 30, given loads applied at station 150. The solution strategy is outlined, which involves using the general bending stresses equation and calculating the centroid position with respect to the Z and Y axes. Steps are shown for calculating stresses at each section.
This document discusses material properties and bending stresses. It defines key terms like modulus of elasticity, Poisson's ratio, yield stress, and ultimate tensile stress. It explains that plane sections remain plane after bending but rotate, and that the neutral axis experiences no deformation or stress. The location of the neutral axis depends on the material properties and loading conditions. Equations are provided to calculate bending stresses based on the neutral axis location and applied moment. An example problem calculates bending stresses at different points on an airplanes wing. The document also notes that for very high loads above the elastic range, stresses become nonlinear and the neutral axis must be determined through trial and error.
The document outlines a lecture on fuselage structural design. It discusses iterative methods for calculating effective width and radius of gyration of thin-walled structures. It also covers loads acting on the fuselage, fuselage structure components like stringers and frames, and examples of analyzing stresses in circular fuselage sections. The document concludes by mentioning that stress analysis of wings will be covered next.
This document discusses effective sheet width and inter-rivet buckling in aerospace structures. It explains that stringers stiffen wing and fuselage skins, and skins provide stiffness to stringers even when buckling. An effective width calculation accounts for this effect. The document also describes how inter-rivet buckling can occur if rivet spacing is too long, and provides equations to calculate the effective rivet spacing to prevent this issue.
The document discusses the design of aircraft fuselages. It notes that fuselages must house passengers and luggage with proper strength and light weight. Fuselages experience both distributed and concentrated loads from various sources. A circular cross-section is commonly used as it efficiently handles these loads. Fuselage structures typically consist of a thin-walled tube with transverse frames, stringers, and cutouts. The document provides an example problem calculating the ultimate bending strength of a circular fuselage cross-section made of aluminum with stringers of different sizes. It considers linear and nonlinear stress distributions to determine the maximum moment the fuselage can withstand before failure.
- The fuselage skin consists of curved sheet panels that can buckle if no stiffeners are present. Stiffener elements are needed to calculate and compare the buckling loads to the aircraft's ultimate loads.
- Buckling of aircraft structures like fuselage skins must be analyzed and prevented. Curved sheets and cylinders can buckle under compression, bending, shear, torsion and combined loads. Internal pressure increases the buckling strength.
- Design examples are provided to calculate buckling loads of circular cylinders and curved-stiffened sheets under various loading conditions and determine if panels would buckle. Buckling analysis ensures the structure can withstand required loads.
1. The document discusses stresses in thin-walled and thick-walled cylinders. For thin-walled cylinders, the stress is assumed to be uniform throughout the wall. For thick-walled cylinders, the stresses depend on the radius and include circumferential (hoop), radial, and longitudinal stresses.
2. Internally pressurized thick-walled cylinders experience maximum hoop stress and compressive radial stress at the inner surface. The hoop stress decreases and radial stress increases towards zero at the outer surface. Longitudinal stress is uniform across the wall.
3. Externally pressurized thick-walled cylinders experience minimum hoop stress and compressive radial stress at the outer surface
This document provides an overview of various gear types and gear terminology. It discusses spur gears, helical gears, bevel gears, worm gears, and compares their basic configurations. Key gear concepts covered include involute tooth profiles, conjugate action, pressure angle, pitch circle, circular pitch, diametral pitch, addendum, dedendum, interference, contact ratio, and gear forming/cutting methods. Standard tooth systems and proportions are also presented in tables.
This document provides an overview of helical spring design and analysis. It discusses stresses in helical springs, deflection calculations, compression spring types, stability, materials selection, static design considerations, critical frequencies, and examples. The chapters cover key topics like curvature effects, stresses from torsion and shear, deflection-force relationships, buckling analysis, material properties, recommended design ranges, and the wave equation for vibrational frequency.
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSIJNSA Journal
The smart irrigation system represents an innovative approach to optimize water usage in agricultural and landscaping practices. The integration of cutting-edge technologies, including sensors, actuators, and data analysis, empowers this system to provide accurate monitoring and control of irrigation processes by leveraging real-time environmental conditions. The main objective of a smart irrigation system is to optimize water efficiency, minimize expenses, and foster the adoption of sustainable water management methods. This paper conducts a systematic risk assessment by exploring the key components/assets and their functionalities in the smart irrigation system. The crucial role of sensors in gathering data on soil moisture, weather patterns, and plant well-being is emphasized in this system. These sensors enable intelligent decision-making in irrigation scheduling and water distribution, leading to enhanced water efficiency and sustainable water management practices. Actuators enable automated control of irrigation devices, ensuring precise and targeted water delivery to plants. Additionally, the paper addresses the potential threat and vulnerabilities associated with smart irrigation systems. It discusses limitations of the system, such as power constraints and computational capabilities, and calculates the potential security risks. The paper suggests possible risk treatment methods for effective secure system operation. In conclusion, the paper emphasizes the significant benefits of implementing smart irrigation systems, including improved water conservation, increased crop yield, and reduced environmental impact. Additionally, based on the security analysis conducted, the paper recommends the implementation of countermeasures and security approaches to address vulnerabilities and ensure the integrity and reliability of the system. By incorporating these measures, smart irrigation technology can revolutionize water management practices in agriculture, promoting sustainability, resource efficiency, and safeguarding against potential security threats.
Understanding Inductive Bias in Machine LearningSUTEJAS
This presentation explores the concept of inductive bias in machine learning. It explains how algorithms come with built-in assumptions and preferences that guide the learning process. You'll learn about the different types of inductive bias and how they can impact the performance and generalizability of machine learning models.
The presentation also covers the positive and negative aspects of inductive bias, along with strategies for mitigating potential drawbacks. We'll explore examples of how bias manifests in algorithms like neural networks and decision trees.
By understanding inductive bias, you can gain valuable insights into how machine learning models work and make informed decisions when building and deploying them.
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesChristina Lin
Traditionally, dealing with real-time data pipelines has involved significant overhead, even for straightforward tasks like data transformation or masking. However, in this talk, we’ll venture into the dynamic realm of WebAssembly (WASM) and discover how it can revolutionize the creation of stateless streaming pipelines within a Kafka (Redpanda) broker. These pipelines are adept at managing low-latency, high-data-volume scenarios.
Introduction- e - waste – definition - sources of e-waste– hazardous substances in e-waste - effects of e-waste on environment and human health- need for e-waste management– e-waste handling rules - waste minimization techniques for managing e-waste – recycling of e-waste - disposal treatment methods of e- waste – mechanism of extraction of precious metal from leaching solution-global Scenario of E-waste – E-waste in India- case studies.
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...IJECEIAES
Climate change's impact on the planet forced the United Nations and governments to promote green energies and electric transportation. The deployments of photovoltaic (PV) and electric vehicle (EV) systems gained stronger momentum due to their numerous advantages over fossil fuel types. The advantages go beyond sustainability to reach financial support and stability. The work in this paper introduces the hybrid system between PV and EV to support industrial and commercial plants. This paper covers the theoretical framework of the proposed hybrid system including the required equation to complete the cost analysis when PV and EV are present. In addition, the proposed design diagram which sets the priorities and requirements of the system is presented. The proposed approach allows setup to advance their power stability, especially during power outages. The presented information supports researchers and plant owners to complete the necessary analysis while promoting the deployment of clean energy. The result of a case study that represents a dairy milk farmer supports the theoretical works and highlights its advanced benefits to existing plants. The short return on investment of the proposed approach supports the paper's novelty approach for the sustainable electrical system. In addition, the proposed system allows for an isolated power setup without the need for a transmission line which enhances the safety of the electrical network
Embedded machine learning-based road conditions and driving behavior monitoringIJECEIAES
Car accident rates have increased in recent years, resulting in losses in human lives, properties, and other financial costs. An embedded machine learning-based system is developed to address this critical issue. The system can monitor road conditions, detect driving patterns, and identify aggressive driving behaviors. The system is based on neural networks trained on a comprehensive dataset of driving events, driving styles, and road conditions. The system effectively detects potential risks and helps mitigate the frequency and impact of accidents. The primary goal is to ensure the safety of drivers and vehicles. Collecting data involved gathering information on three key road events: normal street and normal drive, speed bumps, circular yellow speed bumps, and three aggressive driving actions: sudden start, sudden stop, and sudden entry. The gathered data is processed and analyzed using a machine learning system designed for limited power and memory devices. The developed system resulted in 91.9% accuracy, 93.6% precision, and 92% recall. The achieved inference time on an Arduino Nano 33 BLE Sense with a 32-bit CPU running at 64 MHz is 34 ms and requires 2.6 kB peak RAM and 139.9 kB program flash memory, making it suitable for resource-constrained embedded systems.
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTjpsjournal1
The rivalry between prominent international actors for dominance over Central Asia's hydrocarbon
reserves and the ancient silk trade route, along with China's diplomatic endeavours in the area, has been
referred to as the "New Great Game." This research centres on the power struggle, considering
geopolitical, geostrategic, and geoeconomic variables. Topics including trade, political hegemony, oil
politics, and conventional and nontraditional security are all explored and explained by the researcher.
Using Mackinder's Heartland, Spykman Rimland, and Hegemonic Stability theories, examines China's role
in Central Asia. This study adheres to the empirical epistemological method and has taken care of
objectivity. This study analyze primary and secondary research documents critically to elaborate role of
china’s geo economic outreach in central Asian countries and its future prospect. China is thriving in trade,
pipeline politics, and winning states, according to this study, thanks to important instruments like the
Shanghai Cooperation Organisation and the Belt and Road Economic Initiative. According to this study,
China is seeing significant success in commerce, pipeline politics, and gaining influence on other
governments. This success may be attributed to the effective utilisation of key tools such as the Shanghai
Cooperation Organisation and the Belt and Road Economic Initiative.
2. 4
Course Outline
Day 1: Introduction + Project Integration Management.
Day 2: Project Scope Management.
Day 3: Project Schedule Management.
Day 4: Project Cost Management.
Day 5: Project Risk Management.
Day 6: Scrum.
Day 7: Final Presentation Day!
5. 4
Project Cost Management
● Project Cost Management includes the processes involved
in Planning, Estimating, Budgeting, Financing, Funding,
Managing, And Controlling Costs so that the project can be
completed within the approved budget.
7. 4
Definitions
1. Estimate Costs-The process of developing an approximation of the monetary
resources needed to complete project activates.
2. Determining Budget-The process of aggregating the estimated costs of
individual activates or work packages to establish an authorized cost baseline.
3. Control Costs: The process on monitoring the status of the project to update
the project budget and managing changes to the cost baseline.
13. 4
Plan Cost Management
The process of how the project costs will be estimated,
budgeted, managed, monitored, and controlled. The key benefit
of this process is to provide guidance and direction on how the
project costs will be managed throughout the project.
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®
Guide) – Fifth Edition, Project Management Institute, Inc., 2013, Page 195.
15. 4
Plan Cost Management, Output
Plan Cost Management can establish:
● Unites of measure (Hrs – Days - $ - SAR)
● Level of precision (995.59$ to 1000$)
● Level of accuracy (+- 10%)
● Organization procedures links
● Control thresholds
● Rules of performance measurement
● Reporting format
● Additional details such as Funding & Fluctuation
17. 4
Estimate Costs
Estimate Costs is Process of developing an approximation of the cost of
the resources needed to complete the project work. The key benefit of
this process is that it determines the monetary resources required for the
project.
○ Cost estimating: Assessing how much it will cost the organization
to provide the product or service.
○ Pricing: Assessing how much the organization will charge for the
product or service.
19. 4
Estimate costs, Inputs
● Enterprise Environmental Factors (EEFs)
○ Marketplace conditions
○ Published Commercial Information
○ Exchange rates and inflation
● Organizational Process Assets (OPAs)
○ Cost estimating policies
○ Cost estimating templates
○ Historical information and Lessons learned repository
20. 4
Estimate costs: Tools & Tech.
● Analogous estimating (Expert judgment)
○ Used to estimate total project costs if there is a limited amount of detailed
information
● Parametric estimating
○ Using project characteristics (or parameters) in a mathematical model to predict
costs (e.g., price per square foot)
● Bottom-up estimating
○ Estimating the cost of individual work items and then rolling up the costs to arrive
at a project total
21. 4
Estimate costs: Tools & Tech.
● Three Point Estimate
- Most likely (cM): the cost of the activity based on realistic effort assessment for the
required work and any predicted expenses.
- Optimistic (cO): The cost based on analysis of the best case scenario for the activity.
- Pessimistic (cP): The cost based on analysis of the worst case scenario for the activity.
Two commonly used formulas:
Triangular distribution cE = (cO + cM + cP)/ 3
Beta distribution cE = (cO + 4 cM + cP)/ 6
22. 4
Estimate Cost, Outputs
● Activity Cost estimates:
Quantitative assessments of the probable cost required to complete project works, as well as contingency
amount.
Types of estimates
➢ Order of magnitude (-25% to + 75%)
(It's usually performed during the selection and approval stage of a project. Generally, it’s used for estimating a project budget that doesn’t have
a lot of detail.)
➢ Budget estimate (-10% to + 25%)
(This type of estimate is useful when a project proceeds in its planning or when budgets need to be allocated across the
work breakdown structure.)
➢ Definitive estimate (-5% to + 10%)
(This high level of accuracy can normally only be achieved when the project has been planned in detail and the information
relevant for a reliable estimation of the work is available.)
25. 4
Determine Budget
Determine Budget is the process of aggregating the estimated cost of
the individual activities or work packages, to establish an authorized
baseline. The key benefit of this process is that it determines the cost
baseline against which performance can be monitored and controlled.
28. 4
Determine Budget, Outputs
Cost baseline
The cost baseline is the approved version of the time-phased project
budget at, excluding any management reserves, which can only be
changed through formal change control procedures. It is used as a basis
for comparison.
32. 4
Control costs
Cost control is the process of monitoring the status of the project to update
the project costs and managing changes to the cost baseline.
The key benefit of this process is that the cast baseline is maintained
throughout the project.
32
*This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management
Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017.
33. 4
Control costs
● Project Cost Control includes:
○ Influencing the factors that create changes to the authorized cost baseline.
○ Ensuring that all change requests are acted on in a timely manner.
○ Managing the actual changes when and as they occur.
○ Ensuring that cost expenditure do not exceed the authorized funding by
period, by WAS, by activity, and in total for the project.
33
34. 4
Control costs
● Monitoring cost performance to isolate and understand variances from the
approved cost baseline.
● Monitor work performance against funds expended.
● Preventing unapproved changed from being included in the reported cost or
resources usage.
● Informing appropriate stakeholders of all approved changes and associated cost.
● Bring expected cost overruns within acceptable limits.
34
36. 4
Acronym Name Formula
AC Actual Cost
AC = actual cost of the
project up to the
measurement period
BAC Budget at Completion BAC = total budgeted cost
of the project
EV Earned Value EV = Actual % complete x
BAC
PV Planned Value PV = Planned % complete x
BAC
CV Cost Variance CV = EV - AC
Control Costs Formulas:
37. 4
Acronym Name Formula
SV Schedule Variance SV = EV - PV
CPI Cost Performance Index CPI = EV / AC
SPI Schedule Performance Index SPI = EV / PV
EAC Estimate at Completion EAC = BAC / CPI
ETC Estimate to Complete ETC = EAC - AC
VAR Variance at Completion VAR = BAC - EAC
Control Costs Formulas:
38. 4
Earned Value
● Earned Value (EV)
A method of measuring project performance by comparing
the amount of work planned with that actually accomplished,
in order to determine if cost and schedule performance are
as planned.
41. 4
Example:
•4-month project: Total budget $1,000,000 = Budget at completion (BAC)
•Project cost at end of month three: $950,000 = Actual cost (AC)
•Estimated work complete at end of month three: 80%
•Actual work complete at end month three: 75%
4-month project (BAC) =
1,000,000
M 1 M 2 M 3 M 4
Planned work complete = 80%
Actual work complete = 75%
Control Costs Formulas:
42. 4
Planned value
PV = Planned % Complete x BAC
PV = 80% x $1,000,000 = $800,000
Earned value
EV = Actual % Complete x BAC
EV = 75% x $1000,000 = $750,500
Cost variance
CV = EV – AC
CV = $750,000 - $950,000 = -$200,000
Planned Value (PV) is how much
work was expected to be completed
Earned Value (EV) is how much
work has actually been completed
Cost Variance (CV) is how the cost
of the project is comparing to the
value of work completed
Control Costs Formulas:
43. 4
Cost performance index
CPI = EV / AC
CPI = $750,500 / $950,000 = 0.79
For every $1 input (cost) , we are earning only $0.8 in work output
Cost Performance Index (CPI)
shows how much work is being
completed for every unit of cost
spent (Output/Input)
Control Costs Formulas:
44. 4
Schedule performance index
SPI = EV / PV
SPI = $750,500 / $800,000 = 0.94
For every hour we planned , we are completing only 0.94 hours.
Schedule Performance Index
(SPI) shows how close the actual
completed work compared to the
schedule
Control Costs Formulas:
45. 4
Estimate at completion
EAC = BAC / CPI
EAC = $1000,000 / 0.94 = $1,063,829
Based on current performance, the project
will be completed at cost = $1,063,829.
Estimate to complete
ETC = EAC - AC
ETC = $1,063,829 - 950,000 = $113,829
Based on current performance, the project
requires $113,829 to get it finished
Estimate At Completion (EAC)
forecasts the total cost of the
project based on current project
performance
Estimate To Complete (ETC)
forecasts how much more money
will be required to finish the project
Control Costs Formulas:
46. 4
Variance at completion
VAR = BAC – EAC
VAR = $1,000,000 - $1,063,829 = -$63,829
Based on current performance, the project will
run about $63,829 over budget
Variance At Completion (VAR)
predicts difference between the
budgeted and actual project cost at
the end of the project
Control Costs Formulas:
47. 4
Planned Value
Using the example above, let’s calculate the planned value.
1. After 2 months
*As you can see in the graphic, the project is scheduled for four months. Meaning, after two months,
you should have completed 50% of the work.
Given:
● Project duration: 4 months
● Project budget (BAC): $4,000
● Elapsed time: 2 months
● % complete (planned): 50%
PV = % complete (planned) x BAC
PV = 50% x $4,000
PV = $2,000
48. 4
Earned Value
1. You spent $750 after the first month and you only completed 20% of the project.
Given:
● Project duration: 4 months
● Project budget (BAC): $4,000
● Elapsed time: 1 month
● Planned value: $1,000
● Actual cost: $750
● % complete (planned): 25%
● % complete (actual): 20%
EV = % complete (actual) x BAC
EV = 20% x $4,000
EV = $800
*The value of the work done is $800 even when you only spent $750.
49. 4
Cost Variance (CV)
● Comparing EV to AC:
○ EV: the amount originally budgeted for the work completed or in-
process
○ AC: the actual costs of that work
● CV = EV – AC
● A negative CV means more dollars were spent to accomplish the
work than was planned
50. 4
Cost Variance
CV = EV - AC
CV = $800 - $750
CV = $50
*Because the cost variance is positive, this project is under budget.
Cost Performance Index = EV/AC
CPI = $800/$750
CPI = 1.067
*Because the CPI is greater than 1, this project is under budget.
51. 4
Schedule Variance (SV)
● Comparing EV to PV:
○ EV, the amount originally budgeted for the work that has been
completed or is in-process
○ PV, the amount budgeted for the work that was planned to have
been accomplished
● SV = EV – PV
● A negative result means less work has been performed than was
planned
52. 4
Schedule Variance
SV = EV - PV
SV = $800 - $1,000
SV = -$200
*Because the schedule variance is negative, this project is behind schedule
Schedule Performance Index (SPI) = EV/PV
SPI = $800/$1,000
SPI = 0.8
*Because the SPI is less than 1, this project is behind schedule.
55. 4
Earned Value
AC
EV
PV
On cost
On Schedule
$1
$1
$1
Under cost
On Schedule
$1
$2
$2
Over cost
On Schedule
$2
$1
$1
On cost
Ahead of Schedule
$2
$2
$1
Over cost
Ahead of Schedule
$3
$2
$1
Under cost
Ahead of Schedule
$1
$2
$1
Under cost
Behind Schedule
$1
$2
$3
Over cost
Behind Schedule
$3
$1
$2
On cost
Behind Schedule
$1
$1
$2
57. 4
Earned Value Example
● CV= EV – AC = 2500 – 2800 = - 300
○ we are over budget by $ 300
● CPI= EV / AC = 2500 / 2800 = 0.893
○ we are getting 89 cents out of every dollar we put in the project
● SV= EV – PV = 2500 – 3000 = - 500
○ we are behind schedule
● SPI= EV / PV = 2500 / 3000 = 0.833
○ we are only progressing at 83% of the rate of the planned
58. 4
Earned Value Example
● EAC= BAC / CPI = 4000 / 0.893 = 4479
○ we are currently estimate that the total project will cost $ 4479
● ETC= EAC – AC = 4479 – 2800 = 1679
○ we need to spend $ 1679 to finish the project
● VAC= BAC - EAC = 4000 - 4479 = - 479
○ we are currently expect to be $ 479 over budget, when the project is
completed