SlideShare a Scribd company logo
4
Project Management
Day (4)
4
Course Outline
Day 1: Introduction + Project Integration Management.
Day 2: Project Scope Management.
Day 3: Project Schedule Management.
Day 4: Project Cost Management.
Day 5: Project Risk Management.
Day 6: Scrum.
Day 7: Final Presentation Day!
4
Project Cost Management
Rev.221102
3
4
Processes
Orientation
4
Dr Mohamed Elfarran
4
Project Cost Management
● Project Cost Management includes the processes involved
in Planning, Estimating, Budgeting, Financing, Funding,
Managing, And Controlling Costs so that the project can be
completed within the approved budget.
4
Project Cost Management Overview :
Control Costs
Determine
Budget
Estimate
Costs
4
Definitions
1. Estimate Costs-The process of developing an approximation of the monetary
resources needed to complete project activates.
2. Determining Budget-The process of aggregating the estimated costs of
individual activates or work packages to establish an authorized cost baseline.
3. Control Costs: The process on monitoring the status of the project to update
the project budget and managing changes to the cost baseline.
4
Planning the
Project under
Triple
Constraints
4
Planning
Process
Costs/Budget
4
Using Gantt
Chart for
Project
Control
http://en.wikipedia.org/wiki/File:GanttChartAnatomy.svg
4
Performance
Measurement
Baseline
Plan Cost Management
21102
12
4
Plan Cost Management
The process of how the project costs will be estimated,
budgeted, managed, monitored, and controlled. The key benefit
of this process is to provide guidance and direction on how the
project costs will be managed throughout the project.
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®
Guide) – Fifth Edition, Project Management Institute, Inc., 2013, Page 195.
4
Plan Cost Management
4
Plan Cost Management, Output
Plan Cost Management can establish:
● Unites of measure (Hrs – Days - $ - SAR)
● Level of precision (995.59$ to 1000$)
● Level of accuracy (+- 10%)
● Organization procedures links
● Control thresholds
● Rules of performance measurement
● Reporting format
● Additional details such as Funding & Fluctuation
Estimate Costs
21102
16
4
Estimate Costs
Estimate Costs is Process of developing an approximation of the cost of
the resources needed to complete the project work. The key benefit of
this process is that it determines the monetary resources required for the
project.
○ Cost estimating: Assessing how much it will cost the organization
to provide the product or service.
○ Pricing: Assessing how much the organization will charge for the
product or service.
4
Estimate Costs
4
Estimate costs, Inputs
● Enterprise Environmental Factors (EEFs)
○ Marketplace conditions
○ Published Commercial Information
○ Exchange rates and inflation
● Organizational Process Assets (OPAs)
○ Cost estimating policies
○ Cost estimating templates
○ Historical information and Lessons learned repository
4
Estimate costs: Tools & Tech.
● Analogous estimating (Expert judgment)
○ Used to estimate total project costs if there is a limited amount of detailed
information
● Parametric estimating
○ Using project characteristics (or parameters) in a mathematical model to predict
costs (e.g., price per square foot)
● Bottom-up estimating
○ Estimating the cost of individual work items and then rolling up the costs to arrive
at a project total
4
Estimate costs: Tools & Tech.
● Three Point Estimate
- Most likely (cM): the cost of the activity based on realistic effort assessment for the
required work and any predicted expenses.
- Optimistic (cO): The cost based on analysis of the best case scenario for the activity.
- Pessimistic (cP): The cost based on analysis of the worst case scenario for the activity.
Two commonly used formulas:
Triangular distribution cE = (cO + cM + cP)/ 3
Beta distribution cE = (cO + 4 cM + cP)/ 6
4
Estimate Cost, Outputs
● Activity Cost estimates:
Quantitative assessments of the probable cost required to complete project works, as well as contingency
amount.
Types of estimates
➢ Order of magnitude (-25% to + 75%)
(It's usually performed during the selection and approval stage of a project. Generally, it’s used for estimating a project budget that doesn’t have
a lot of detail.)
➢ Budget estimate (-10% to + 25%)
(This type of estimate is useful when a project proceeds in its planning or when budgets need to be allocated across the
work breakdown structure.)
➢ Definitive estimate (-5% to + 10%)
(This high level of accuracy can normally only be achieved when the project has been planned in detail and the information
relevant for a reliable estimation of the work is available.)
4
● Resource Cost
Estimation
● Activity Cost
Estimation
23
Dr Mohamed Elfarran
Determine Budget
21102
24
4
Determine Budget
Determine Budget is the process of aggregating the estimated cost of
the individual activities or work packages, to establish an authorized
baseline. The key benefit of this process is that it determines the cost
baseline against which performance can be monitored and controlled.
4
Budget
http://pm-foundations.com/tag/project-budgeting/
4
Determine Budget
4
Determine Budget, Outputs
Cost baseline
The cost baseline is the approved version of the time-phased project
budget at, excluding any management reserves, which can only be
changed through formal change control procedures. It is used as a basis
for comparison.
4
Project Cost Management
SN Activity List Cost EGP 1 2 3 4 5 6 7 8 9 10 11
A1
A2
A3
A4
A5
A6
A7
A8
A9
A10
A11
A12
Start
BBB
CCC
DDD
EEE
FFF
GGG
HHH
III
JJJ
KKK
LLL
0
100
1600
600
200
330
50
200
900
50
250
80
50 50
400 400 400 400
150 150 150 150
100 100
110
110
110
50
100 100
300 300 300
50
250
80
4
● Resource Cost
Estimation
● Activity Cost
Estimation
30
Dr Mohamed Elfarran
Control Costs
21102
31
4
Control costs
Cost control is the process of monitoring the status of the project to update
the project costs and managing changes to the cost baseline.
The key benefit of this process is that the cast baseline is maintained
throughout the project.
32
*This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management
Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017.
4
Control costs
● Project Cost Control includes:
○ Influencing the factors that create changes to the authorized cost baseline.
○ Ensuring that all change requests are acted on in a timely manner.
○ Managing the actual changes when and as they occur.
○ Ensuring that cost expenditure do not exceed the authorized funding by
period, by WAS, by activity, and in total for the project.
33
4
Control costs
● Monitoring cost performance to isolate and understand variances from the
approved cost baseline.
● Monitor work performance against funds expended.
● Preventing unapproved changed from being included in the reported cost or
resources usage.
● Informing appropriate stakeholders of all approved changes and associated cost.
● Bring expected cost overruns within acceptable limits.
34
4
Earned Value
Rev.221102
35
4
Acronym Name Formula
AC Actual Cost
AC = actual cost of the
project up to the
measurement period
BAC Budget at Completion BAC = total budgeted cost
of the project
EV Earned Value EV = Actual % complete x
BAC
PV Planned Value PV = Planned % complete x
BAC
CV Cost Variance CV = EV - AC
Control Costs Formulas:
4
Acronym Name Formula
SV Schedule Variance SV = EV - PV
CPI Cost Performance Index CPI = EV / AC
SPI Schedule Performance Index SPI = EV / PV
EAC Estimate at Completion EAC = BAC / CPI
ETC Estimate to Complete ETC = EAC - AC
VAR Variance at Completion VAR = BAC - EAC
Control Costs Formulas:
4
Earned Value
● Earned Value (EV)
A method of measuring project performance by comparing
the amount of work planned with that actually accomplished,
in order to determine if cost and schedule performance are
as planned.
4
Example
4
Example
4
Example:
•4-month project: Total budget $1,000,000 = Budget at completion (BAC)
•Project cost at end of month three: $950,000 = Actual cost (AC)
•Estimated work complete at end of month three: 80%
•Actual work complete at end month three: 75%
4-month project (BAC) =
1,000,000
M 1 M 2 M 3 M 4
Planned work complete = 80%
Actual work complete = 75%
Control Costs Formulas:
4
Planned value
PV = Planned % Complete x BAC
PV = 80% x $1,000,000 = $800,000
Earned value
EV = Actual % Complete x BAC
EV = 75% x $1000,000 = $750,500
Cost variance
CV = EV – AC
CV = $750,000 - $950,000 = -$200,000
Planned Value (PV) is how much
work was expected to be completed
Earned Value (EV) is how much
work has actually been completed
Cost Variance (CV) is how the cost
of the project is comparing to the
value of work completed
Control Costs Formulas:
4
Cost performance index
CPI = EV / AC
CPI = $750,500 / $950,000 = 0.79
For every $1 input (cost) , we are earning only $0.8 in work output
Cost Performance Index (CPI)
shows how much work is being
completed for every unit of cost
spent (Output/Input)
Control Costs Formulas:
4
Schedule performance index
SPI = EV / PV
SPI = $750,500 / $800,000 = 0.94
For every hour we planned , we are completing only 0.94 hours.
Schedule Performance Index
(SPI) shows how close the actual
completed work compared to the
schedule
Control Costs Formulas:
4
Estimate at completion
EAC = BAC / CPI
EAC = $1000,000 / 0.94 = $1,063,829
Based on current performance, the project
will be completed at cost = $1,063,829.
Estimate to complete
ETC = EAC - AC
ETC = $1,063,829 - 950,000 = $113,829
Based on current performance, the project
requires $113,829 to get it finished
Estimate At Completion (EAC)
forecasts the total cost of the
project based on current project
performance
Estimate To Complete (ETC)
forecasts how much more money
will be required to finish the project
Control Costs Formulas:
4
Variance at completion
VAR = BAC – EAC
VAR = $1,000,000 - $1,063,829 = -$63,829
Based on current performance, the project will
run about $63,829 over budget
Variance At Completion (VAR)
predicts difference between the
budgeted and actual project cost at
the end of the project
Control Costs Formulas:
4
Planned Value
Using the example above, let’s calculate the planned value.
1. After 2 months
*As you can see in the graphic, the project is scheduled for four months. Meaning, after two months,
you should have completed 50% of the work.
Given:
● Project duration: 4 months
● Project budget (BAC): $4,000
● Elapsed time: 2 months
● % complete (planned): 50%
PV = % complete (planned) x BAC
PV = 50% x $4,000
PV = $2,000
4
Earned Value
1. You spent $750 after the first month and you only completed 20% of the project.
Given:
● Project duration: 4 months
● Project budget (BAC): $4,000
● Elapsed time: 1 month
● Planned value: $1,000
● Actual cost: $750
● % complete (planned): 25%
● % complete (actual): 20%
EV = % complete (actual) x BAC
EV = 20% x $4,000
EV = $800
*The value of the work done is $800 even when you only spent $750.
4
Cost Variance (CV)
● Comparing EV to AC:
○ EV: the amount originally budgeted for the work completed or in-
process
○ AC: the actual costs of that work
● CV = EV – AC
● A negative CV means more dollars were spent to accomplish the
work than was planned
4
Cost Variance
CV = EV - AC
CV = $800 - $750
CV = $50
*Because the cost variance is positive, this project is under budget.
Cost Performance Index = EV/AC
CPI = $800/$750
CPI = 1.067
*Because the CPI is greater than 1, this project is under budget.
4
Schedule Variance (SV)
● Comparing EV to PV:
○ EV, the amount originally budgeted for the work that has been
completed or is in-process
○ PV, the amount budgeted for the work that was planned to have
been accomplished
● SV = EV – PV
● A negative result means less work has been performed than was
planned
4
Schedule Variance
SV = EV - PV
SV = $800 - $1,000
SV = -$200
*Because the schedule variance is negative, this project is behind schedule
Schedule Performance Index (SPI) = EV/PV
SPI = $800/$1,000
SPI = 0.8
*Because the SPI is less than 1, this project is behind schedule.
4
Quick Revision
Rev.221102
63
4
Performance Measurement
Cost
Time
VAC
EAC
Data Date
AC
ETC
CV
SV
PV
EV
Schedule Slippage
(to date)
Project Schedule Slippage
(at completion)
BAC
4
Earned Value
AC
EV
PV
On cost
On Schedule
$1
$1
$1
Under cost
On Schedule
$1
$2
$2
Over cost
On Schedule
$2
$1
$1
On cost
Ahead of Schedule
$2
$2
$1
Over cost
Ahead of Schedule
$3
$2
$1
Under cost
Ahead of Schedule
$1
$2
$1
Under cost
Behind Schedule
$1
$2
$3
Over cost
Behind Schedule
$3
$1
$2
On cost
Behind Schedule
$1
$1
$2
4
Earned Value example
● PV= $ 3000, EV= $ 2500, AC= $ 2800, BAC= $ 4000
● Find: CV, CPI, SV, SPI, EAC, ETC & VAC
4
Earned Value Example
● CV= EV – AC = 2500 – 2800 = - 300
○ we are over budget by $ 300
● CPI= EV / AC = 2500 / 2800 = 0.893
○ we are getting 89 cents out of every dollar we put in the project
● SV= EV – PV = 2500 – 3000 = - 500
○ we are behind schedule
● SPI= EV / PV = 2500 / 3000 = 0.833
○ we are only progressing at 83% of the rate of the planned
4
Earned Value Example
● EAC= BAC / CPI = 4000 / 0.893 = 4479
○ we are currently estimate that the total project will cost $ 4479
● ETC= EAC – AC = 4479 – 2800 = 1679
○ we need to spend $ 1679 to finish the project
● VAC= BAC - EAC = 4000 - 4479 = - 479
○ we are currently expect to be $ 479 over budget, when the project is
completed
70

More Related Content

Similar to Project Management Day 4 Cost ٌ R02.pdf

L06 cost management
L06 cost managementL06 cost management
L06 cost management
Asa Chan
 
Day 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdfDay 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdf
Madhusha15
 
Chapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxChapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptx
ssusercf695b
 
L03 integration management
L03 integration managementL03 integration management
L03 integration management
Asa Chan
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
BECM, RUET, Bangladesh
 
7 cost managmenet
7 cost managmenet7 cost managmenet
7 cost managmenet
Ala Ibrahim
 
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSISPROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
G K, BE,MS,ISTQB Certified Expert
 
An introduction to project accounting
An introduction to project accountingAn introduction to project accounting
An introduction to project accounting
Association for Project Management
 
COST MANAGEMENT REPORT
COST MANAGEMENT REPORT COST MANAGEMENT REPORT
COST MANAGEMENT REPORT
Jo Balucanag - Bitonio
 
Group 12 - Progress and Performance Measurement and Evaluation.pdf
Group 12 - Progress and Performance Measurement and Evaluation.pdfGroup 12 - Progress and Performance Measurement and Evaluation.pdf
Group 12 - Progress and Performance Measurement and Evaluation.pdf
alvieramada23
 
PMP-Cost Management area
PMP-Cost Management areaPMP-Cost Management area
PMP-Cost Management area
Zaur Ahmadov, PMP
 
Project Management C8 -cost_estimation_and_budgeting
Project Management C8  -cost_estimation_and_budgetingProject Management C8  -cost_estimation_and_budgeting
Project Management C8 -cost_estimation_and_budgeting
Izah Asmadi
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updated
Shraddha PMP
 
Project Planning and Excution chapter 4.ppt
Project Planning and Excution chapter 4.pptProject Planning and Excution chapter 4.ppt
Project Planning and Excution chapter 4.ppt
adabotor7
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
Ahmed Elshaboury,PMP,LEED GA
 
P ex cost management-1
P ex cost management-1P ex cost management-1
P ex cost management-1
AHMED NADIM JILANI
 
PMP Exam Preparation Course: 06 Project Cost Management
PMP Exam Preparation Course: 06 Project Cost ManagementPMP Exam Preparation Course: 06 Project Cost Management
PMP Exam Preparation Course: 06 Project Cost Management
B M Shahrier Majumder, PMP, CSM
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
Serdar Temiz
 
Project Cost Management - PMP preparation course
Project Cost Management - PMP preparation courseProject Cost Management - PMP preparation course
Project Cost Management - PMP preparation course
Vladimir Vujovic
 
Using Earned Value Management Concepts to Improve Commercial Project Performance
Using Earned Value Management Concepts to Improve Commercial Project PerformanceUsing Earned Value Management Concepts to Improve Commercial Project Performance
Using Earned Value Management Concepts to Improve Commercial Project Performance
LewisFowlerLLC
 

Similar to Project Management Day 4 Cost ٌ R02.pdf (20)

L06 cost management
L06 cost managementL06 cost management
L06 cost management
 
Day 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdfDay 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdf
 
Chapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxChapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptx
 
L03 integration management
L03 integration managementL03 integration management
L03 integration management
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
7 cost managmenet
7 cost managmenet7 cost managmenet
7 cost managmenet
 
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSISPROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
 
An introduction to project accounting
An introduction to project accountingAn introduction to project accounting
An introduction to project accounting
 
COST MANAGEMENT REPORT
COST MANAGEMENT REPORT COST MANAGEMENT REPORT
COST MANAGEMENT REPORT
 
Group 12 - Progress and Performance Measurement and Evaluation.pdf
Group 12 - Progress and Performance Measurement and Evaluation.pdfGroup 12 - Progress and Performance Measurement and Evaluation.pdf
Group 12 - Progress and Performance Measurement and Evaluation.pdf
 
PMP-Cost Management area
PMP-Cost Management areaPMP-Cost Management area
PMP-Cost Management area
 
Project Management C8 -cost_estimation_and_budgeting
Project Management C8  -cost_estimation_and_budgetingProject Management C8  -cost_estimation_and_budgeting
Project Management C8 -cost_estimation_and_budgeting
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updated
 
Project Planning and Excution chapter 4.ppt
Project Planning and Excution chapter 4.pptProject Planning and Excution chapter 4.ppt
Project Planning and Excution chapter 4.ppt
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
P ex cost management-1
P ex cost management-1P ex cost management-1
P ex cost management-1
 
PMP Exam Preparation Course: 06 Project Cost Management
PMP Exam Preparation Course: 06 Project Cost ManagementPMP Exam Preparation Course: 06 Project Cost Management
PMP Exam Preparation Course: 06 Project Cost Management
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Project Cost Management - PMP preparation course
Project Cost Management - PMP preparation courseProject Cost Management - PMP preparation course
Project Cost Management - PMP preparation course
 
Using Earned Value Management Concepts to Improve Commercial Project Performance
Using Earned Value Management Concepts to Improve Commercial Project PerformanceUsing Earned Value Management Concepts to Improve Commercial Project Performance
Using Earned Value Management Concepts to Improve Commercial Project Performance
 

More from Dr Mohamed Elfarran

SCRUM Day 1 Rev03.pdf
SCRUM Day 1 Rev03.pdfSCRUM Day 1 Rev03.pdf
SCRUM Day 1 Rev03.pdf
Dr Mohamed Elfarran
 
Project Management Day 5 Risk R02.pdf
Project Management Day 5 Risk  R02.pdfProject Management Day 5 Risk  R02.pdf
Project Management Day 5 Risk R02.pdf
Dr Mohamed Elfarran
 
Day 3 Schedule R02.pdf
Day 3 Schedule R02.pdfDay 3 Schedule R02.pdf
Day 3 Schedule R02.pdf
Dr Mohamed Elfarran
 
Day 1 Framework R03.pdf
Day 1 Framework R03.pdfDay 1 Framework R03.pdf
Day 1 Framework R03.pdf
Dr Mohamed Elfarran
 
Day 2 Scope R02.pdf
Day 2 Scope R02.pdfDay 2 Scope R02.pdf
Day 2 Scope R02.pdf
Dr Mohamed Elfarran
 
how to write a business plan
how to write a business planhow to write a business plan
how to write a business plan
Dr Mohamed Elfarran
 
Industry 4.0 and Cyber physical systems Intro
Industry 4.0 and Cyber physical systems IntroIndustry 4.0 and Cyber physical systems Intro
Industry 4.0 and Cyber physical systems Intro
Dr Mohamed Elfarran
 
Ace 402 lec 12 fueslage shear flow
Ace 402 lec 12 fueslage shear flowAce 402 lec 12 fueslage shear flow
Ace 402 lec 12 fueslage shear flow
Dr Mohamed Elfarran
 
Ace 402 lec 7 unsymmetrical
Ace 402 lec 7 unsymmetrical Ace 402 lec 7 unsymmetrical
Ace 402 lec 7 unsymmetrical
Dr Mohamed Elfarran
 
Ace 402 lec 8 max stress
Ace 402 lec 8 max stressAce 402 lec 8 max stress
Ace 402 lec 8 max stress
Dr Mohamed Elfarran
 
Ace 402 lec 12 fueslage shear flow2
Ace 402 lec 12 fueslage shear flow2Ace 402 lec 12 fueslage shear flow2
Ace 402 lec 12 fueslage shear flow2
Dr Mohamed Elfarran
 
Ace 402 lec 13 max stress unsymetric
Ace 402 lec 13 max stress unsymetricAce 402 lec 13 max stress unsymetric
Ace 402 lec 13 max stress unsymetric
Dr Mohamed Elfarran
 
Ace 402 lec 3 bending
Ace 402 lec 3  bendingAce 402 lec 3  bending
Ace 402 lec 3 bending
Dr Mohamed Elfarran
 
Ace 402 lec 1&2
Ace 402 lec 1&2Ace 402 lec 1&2
Ace 402 lec 1&2
Dr Mohamed Elfarran
 
Ace 402 lec 5 effective
Ace 402 lec 5 effectiveAce 402 lec 5 effective
Ace 402 lec 5 effective
Dr Mohamed Elfarran
 
Ace 402 lec 6 ultimate bending
Ace 402 lec 6 ultimate bending Ace 402 lec 6 ultimate bending
Ace 402 lec 6 ultimate bending
Dr Mohamed Elfarran
 
Ace 402 lec 4 buckling
Ace 402 lec 4 buckling Ace 402 lec 4 buckling
Ace 402 lec 4 buckling
Dr Mohamed Elfarran
 
Mpe 209 lec 9 Pressized Vessels
Mpe 209 lec 9 Pressized Vessels Mpe 209 lec 9 Pressized Vessels
Mpe 209 lec 9 Pressized Vessels
Dr Mohamed Elfarran
 
Mpe 209 lec gear Design
Mpe 209 lec gear DesignMpe 209 lec gear Design
Mpe 209 lec gear Design
Dr Mohamed Elfarran
 
Mpe 209 lec 11 springs
Mpe 209 lec 11 springs Mpe 209 lec 11 springs
Mpe 209 lec 11 springs
Dr Mohamed Elfarran
 

More from Dr Mohamed Elfarran (20)

SCRUM Day 1 Rev03.pdf
SCRUM Day 1 Rev03.pdfSCRUM Day 1 Rev03.pdf
SCRUM Day 1 Rev03.pdf
 
Project Management Day 5 Risk R02.pdf
Project Management Day 5 Risk  R02.pdfProject Management Day 5 Risk  R02.pdf
Project Management Day 5 Risk R02.pdf
 
Day 3 Schedule R02.pdf
Day 3 Schedule R02.pdfDay 3 Schedule R02.pdf
Day 3 Schedule R02.pdf
 
Day 1 Framework R03.pdf
Day 1 Framework R03.pdfDay 1 Framework R03.pdf
Day 1 Framework R03.pdf
 
Day 2 Scope R02.pdf
Day 2 Scope R02.pdfDay 2 Scope R02.pdf
Day 2 Scope R02.pdf
 
how to write a business plan
how to write a business planhow to write a business plan
how to write a business plan
 
Industry 4.0 and Cyber physical systems Intro
Industry 4.0 and Cyber physical systems IntroIndustry 4.0 and Cyber physical systems Intro
Industry 4.0 and Cyber physical systems Intro
 
Ace 402 lec 12 fueslage shear flow
Ace 402 lec 12 fueslage shear flowAce 402 lec 12 fueslage shear flow
Ace 402 lec 12 fueslage shear flow
 
Ace 402 lec 7 unsymmetrical
Ace 402 lec 7 unsymmetrical Ace 402 lec 7 unsymmetrical
Ace 402 lec 7 unsymmetrical
 
Ace 402 lec 8 max stress
Ace 402 lec 8 max stressAce 402 lec 8 max stress
Ace 402 lec 8 max stress
 
Ace 402 lec 12 fueslage shear flow2
Ace 402 lec 12 fueslage shear flow2Ace 402 lec 12 fueslage shear flow2
Ace 402 lec 12 fueslage shear flow2
 
Ace 402 lec 13 max stress unsymetric
Ace 402 lec 13 max stress unsymetricAce 402 lec 13 max stress unsymetric
Ace 402 lec 13 max stress unsymetric
 
Ace 402 lec 3 bending
Ace 402 lec 3  bendingAce 402 lec 3  bending
Ace 402 lec 3 bending
 
Ace 402 lec 1&2
Ace 402 lec 1&2Ace 402 lec 1&2
Ace 402 lec 1&2
 
Ace 402 lec 5 effective
Ace 402 lec 5 effectiveAce 402 lec 5 effective
Ace 402 lec 5 effective
 
Ace 402 lec 6 ultimate bending
Ace 402 lec 6 ultimate bending Ace 402 lec 6 ultimate bending
Ace 402 lec 6 ultimate bending
 
Ace 402 lec 4 buckling
Ace 402 lec 4 buckling Ace 402 lec 4 buckling
Ace 402 lec 4 buckling
 
Mpe 209 lec 9 Pressized Vessels
Mpe 209 lec 9 Pressized Vessels Mpe 209 lec 9 Pressized Vessels
Mpe 209 lec 9 Pressized Vessels
 
Mpe 209 lec gear Design
Mpe 209 lec gear DesignMpe 209 lec gear Design
Mpe 209 lec gear Design
 
Mpe 209 lec 11 springs
Mpe 209 lec 11 springs Mpe 209 lec 11 springs
Mpe 209 lec 11 springs
 

Recently uploaded

Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
mahammadsalmanmech
 
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
RadiNasr
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
IJNSA Journal
 
Wearable antenna for antenna applications
Wearable antenna for antenna applicationsWearable antenna for antenna applications
Wearable antenna for antenna applications
Madhumitha Jayaram
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
mamunhossenbd75
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
NidhalKahouli2
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
JamalHussainArman
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
KrishnaveniKrishnara1
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
IJECEIAES
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
jpsjournal1
 
Swimming pool mechanical components design.pptx
Swimming pool  mechanical components design.pptxSwimming pool  mechanical components design.pptx
Swimming pool mechanical components design.pptx
yokeleetan1
 
bank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdfbank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdf
Divyam548318
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
MIGUELANGEL966976
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
ssuser36d3051
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
Hitesh Mohapatra
 

Recently uploaded (20)

Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
 
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
 
Wearable antenna for antenna applications
Wearable antenna for antenna applicationsWearable antenna for antenna applications
Wearable antenna for antenna applications
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
 
Swimming pool mechanical components design.pptx
Swimming pool  mechanical components design.pptxSwimming pool  mechanical components design.pptx
Swimming pool mechanical components design.pptx
 
bank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdfbank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdf
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
 

Project Management Day 4 Cost ٌ R02.pdf

  • 2. 4 Course Outline Day 1: Introduction + Project Integration Management. Day 2: Project Scope Management. Day 3: Project Schedule Management. Day 4: Project Cost Management. Day 5: Project Risk Management. Day 6: Scrum. Day 7: Final Presentation Day!
  • 5. 4 Project Cost Management ● Project Cost Management includes the processes involved in Planning, Estimating, Budgeting, Financing, Funding, Managing, And Controlling Costs so that the project can be completed within the approved budget.
  • 6. 4 Project Cost Management Overview : Control Costs Determine Budget Estimate Costs
  • 7. 4 Definitions 1. Estimate Costs-The process of developing an approximation of the monetary resources needed to complete project activates. 2. Determining Budget-The process of aggregating the estimated costs of individual activates or work packages to establish an authorized cost baseline. 3. Control Costs: The process on monitoring the status of the project to update the project budget and managing changes to the cost baseline.
  • 13. 4 Plan Cost Management The process of how the project costs will be estimated, budgeted, managed, monitored, and controlled. The key benefit of this process is to provide guidance and direction on how the project costs will be managed throughout the project. Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fifth Edition, Project Management Institute, Inc., 2013, Page 195.
  • 15. 4 Plan Cost Management, Output Plan Cost Management can establish: ● Unites of measure (Hrs – Days - $ - SAR) ● Level of precision (995.59$ to 1000$) ● Level of accuracy (+- 10%) ● Organization procedures links ● Control thresholds ● Rules of performance measurement ● Reporting format ● Additional details such as Funding & Fluctuation
  • 17. 4 Estimate Costs Estimate Costs is Process of developing an approximation of the cost of the resources needed to complete the project work. The key benefit of this process is that it determines the monetary resources required for the project. ○ Cost estimating: Assessing how much it will cost the organization to provide the product or service. ○ Pricing: Assessing how much the organization will charge for the product or service.
  • 19. 4 Estimate costs, Inputs ● Enterprise Environmental Factors (EEFs) ○ Marketplace conditions ○ Published Commercial Information ○ Exchange rates and inflation ● Organizational Process Assets (OPAs) ○ Cost estimating policies ○ Cost estimating templates ○ Historical information and Lessons learned repository
  • 20. 4 Estimate costs: Tools & Tech. ● Analogous estimating (Expert judgment) ○ Used to estimate total project costs if there is a limited amount of detailed information ● Parametric estimating ○ Using project characteristics (or parameters) in a mathematical model to predict costs (e.g., price per square foot) ● Bottom-up estimating ○ Estimating the cost of individual work items and then rolling up the costs to arrive at a project total
  • 21. 4 Estimate costs: Tools & Tech. ● Three Point Estimate - Most likely (cM): the cost of the activity based on realistic effort assessment for the required work and any predicted expenses. - Optimistic (cO): The cost based on analysis of the best case scenario for the activity. - Pessimistic (cP): The cost based on analysis of the worst case scenario for the activity. Two commonly used formulas: Triangular distribution cE = (cO + cM + cP)/ 3 Beta distribution cE = (cO + 4 cM + cP)/ 6
  • 22. 4 Estimate Cost, Outputs ● Activity Cost estimates: Quantitative assessments of the probable cost required to complete project works, as well as contingency amount. Types of estimates ➢ Order of magnitude (-25% to + 75%) (It's usually performed during the selection and approval stage of a project. Generally, it’s used for estimating a project budget that doesn’t have a lot of detail.) ➢ Budget estimate (-10% to + 25%) (This type of estimate is useful when a project proceeds in its planning or when budgets need to be allocated across the work breakdown structure.) ➢ Definitive estimate (-5% to + 10%) (This high level of accuracy can normally only be achieved when the project has been planned in detail and the information relevant for a reliable estimation of the work is available.)
  • 23. 4 ● Resource Cost Estimation ● Activity Cost Estimation 23 Dr Mohamed Elfarran
  • 25. 4 Determine Budget Determine Budget is the process of aggregating the estimated cost of the individual activities or work packages, to establish an authorized baseline. The key benefit of this process is that it determines the cost baseline against which performance can be monitored and controlled.
  • 28. 4 Determine Budget, Outputs Cost baseline The cost baseline is the approved version of the time-phased project budget at, excluding any management reserves, which can only be changed through formal change control procedures. It is used as a basis for comparison.
  • 29. 4 Project Cost Management SN Activity List Cost EGP 1 2 3 4 5 6 7 8 9 10 11 A1 A2 A3 A4 A5 A6 A7 A8 A9 A10 A11 A12 Start BBB CCC DDD EEE FFF GGG HHH III JJJ KKK LLL 0 100 1600 600 200 330 50 200 900 50 250 80 50 50 400 400 400 400 150 150 150 150 100 100 110 110 110 50 100 100 300 300 300 50 250 80
  • 30. 4 ● Resource Cost Estimation ● Activity Cost Estimation 30 Dr Mohamed Elfarran
  • 32. 4 Control costs Cost control is the process of monitoring the status of the project to update the project costs and managing changes to the cost baseline. The key benefit of this process is that the cast baseline is maintained throughout the project. 32 *This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017.
  • 33. 4 Control costs ● Project Cost Control includes: ○ Influencing the factors that create changes to the authorized cost baseline. ○ Ensuring that all change requests are acted on in a timely manner. ○ Managing the actual changes when and as they occur. ○ Ensuring that cost expenditure do not exceed the authorized funding by period, by WAS, by activity, and in total for the project. 33
  • 34. 4 Control costs ● Monitoring cost performance to isolate and understand variances from the approved cost baseline. ● Monitor work performance against funds expended. ● Preventing unapproved changed from being included in the reported cost or resources usage. ● Informing appropriate stakeholders of all approved changes and associated cost. ● Bring expected cost overruns within acceptable limits. 34
  • 36. 4 Acronym Name Formula AC Actual Cost AC = actual cost of the project up to the measurement period BAC Budget at Completion BAC = total budgeted cost of the project EV Earned Value EV = Actual % complete x BAC PV Planned Value PV = Planned % complete x BAC CV Cost Variance CV = EV - AC Control Costs Formulas:
  • 37. 4 Acronym Name Formula SV Schedule Variance SV = EV - PV CPI Cost Performance Index CPI = EV / AC SPI Schedule Performance Index SPI = EV / PV EAC Estimate at Completion EAC = BAC / CPI ETC Estimate to Complete ETC = EAC - AC VAR Variance at Completion VAR = BAC - EAC Control Costs Formulas:
  • 38. 4 Earned Value ● Earned Value (EV) A method of measuring project performance by comparing the amount of work planned with that actually accomplished, in order to determine if cost and schedule performance are as planned.
  • 41. 4 Example: •4-month project: Total budget $1,000,000 = Budget at completion (BAC) •Project cost at end of month three: $950,000 = Actual cost (AC) •Estimated work complete at end of month three: 80% •Actual work complete at end month three: 75% 4-month project (BAC) = 1,000,000 M 1 M 2 M 3 M 4 Planned work complete = 80% Actual work complete = 75% Control Costs Formulas:
  • 42. 4 Planned value PV = Planned % Complete x BAC PV = 80% x $1,000,000 = $800,000 Earned value EV = Actual % Complete x BAC EV = 75% x $1000,000 = $750,500 Cost variance CV = EV – AC CV = $750,000 - $950,000 = -$200,000 Planned Value (PV) is how much work was expected to be completed Earned Value (EV) is how much work has actually been completed Cost Variance (CV) is how the cost of the project is comparing to the value of work completed Control Costs Formulas:
  • 43. 4 Cost performance index CPI = EV / AC CPI = $750,500 / $950,000 = 0.79 For every $1 input (cost) , we are earning only $0.8 in work output Cost Performance Index (CPI) shows how much work is being completed for every unit of cost spent (Output/Input) Control Costs Formulas:
  • 44. 4 Schedule performance index SPI = EV / PV SPI = $750,500 / $800,000 = 0.94 For every hour we planned , we are completing only 0.94 hours. Schedule Performance Index (SPI) shows how close the actual completed work compared to the schedule Control Costs Formulas:
  • 45. 4 Estimate at completion EAC = BAC / CPI EAC = $1000,000 / 0.94 = $1,063,829 Based on current performance, the project will be completed at cost = $1,063,829. Estimate to complete ETC = EAC - AC ETC = $1,063,829 - 950,000 = $113,829 Based on current performance, the project requires $113,829 to get it finished Estimate At Completion (EAC) forecasts the total cost of the project based on current project performance Estimate To Complete (ETC) forecasts how much more money will be required to finish the project Control Costs Formulas:
  • 46. 4 Variance at completion VAR = BAC – EAC VAR = $1,000,000 - $1,063,829 = -$63,829 Based on current performance, the project will run about $63,829 over budget Variance At Completion (VAR) predicts difference between the budgeted and actual project cost at the end of the project Control Costs Formulas:
  • 47. 4 Planned Value Using the example above, let’s calculate the planned value. 1. After 2 months *As you can see in the graphic, the project is scheduled for four months. Meaning, after two months, you should have completed 50% of the work. Given: ● Project duration: 4 months ● Project budget (BAC): $4,000 ● Elapsed time: 2 months ● % complete (planned): 50% PV = % complete (planned) x BAC PV = 50% x $4,000 PV = $2,000
  • 48. 4 Earned Value 1. You spent $750 after the first month and you only completed 20% of the project. Given: ● Project duration: 4 months ● Project budget (BAC): $4,000 ● Elapsed time: 1 month ● Planned value: $1,000 ● Actual cost: $750 ● % complete (planned): 25% ● % complete (actual): 20% EV = % complete (actual) x BAC EV = 20% x $4,000 EV = $800 *The value of the work done is $800 even when you only spent $750.
  • 49. 4 Cost Variance (CV) ● Comparing EV to AC: ○ EV: the amount originally budgeted for the work completed or in- process ○ AC: the actual costs of that work ● CV = EV – AC ● A negative CV means more dollars were spent to accomplish the work than was planned
  • 50. 4 Cost Variance CV = EV - AC CV = $800 - $750 CV = $50 *Because the cost variance is positive, this project is under budget. Cost Performance Index = EV/AC CPI = $800/$750 CPI = 1.067 *Because the CPI is greater than 1, this project is under budget.
  • 51. 4 Schedule Variance (SV) ● Comparing EV to PV: ○ EV, the amount originally budgeted for the work that has been completed or is in-process ○ PV, the amount budgeted for the work that was planned to have been accomplished ● SV = EV – PV ● A negative result means less work has been performed than was planned
  • 52. 4 Schedule Variance SV = EV - PV SV = $800 - $1,000 SV = -$200 *Because the schedule variance is negative, this project is behind schedule Schedule Performance Index (SPI) = EV/PV SPI = $800/$1,000 SPI = 0.8 *Because the SPI is less than 1, this project is behind schedule.
  • 54. 4 Performance Measurement Cost Time VAC EAC Data Date AC ETC CV SV PV EV Schedule Slippage (to date) Project Schedule Slippage (at completion) BAC
  • 55. 4 Earned Value AC EV PV On cost On Schedule $1 $1 $1 Under cost On Schedule $1 $2 $2 Over cost On Schedule $2 $1 $1 On cost Ahead of Schedule $2 $2 $1 Over cost Ahead of Schedule $3 $2 $1 Under cost Ahead of Schedule $1 $2 $1 Under cost Behind Schedule $1 $2 $3 Over cost Behind Schedule $3 $1 $2 On cost Behind Schedule $1 $1 $2
  • 56. 4 Earned Value example ● PV= $ 3000, EV= $ 2500, AC= $ 2800, BAC= $ 4000 ● Find: CV, CPI, SV, SPI, EAC, ETC & VAC
  • 57. 4 Earned Value Example ● CV= EV – AC = 2500 – 2800 = - 300 ○ we are over budget by $ 300 ● CPI= EV / AC = 2500 / 2800 = 0.893 ○ we are getting 89 cents out of every dollar we put in the project ● SV= EV – PV = 2500 – 3000 = - 500 ○ we are behind schedule ● SPI= EV / PV = 2500 / 3000 = 0.833 ○ we are only progressing at 83% of the rate of the planned
  • 58. 4 Earned Value Example ● EAC= BAC / CPI = 4000 / 0.893 = 4479 ○ we are currently estimate that the total project will cost $ 4479 ● ETC= EAC – AC = 4479 – 2800 = 1679 ○ we need to spend $ 1679 to finish the project ● VAC= BAC - EAC = 4000 - 4479 = - 479 ○ we are currently expect to be $ 479 over budget, when the project is completed
  • 59.
  • 60. 70