SlideShare a Scribd company logo
FROM PRODUCTIVITY BRIEFCASES HELP DESK
LABOUR
PRODUCTIVITY
LABOUR PRODUCTIVITY
 A large proportion of the high cost
in construction work is as a result of
excessive labour costs.
 These costs can be reduced if
productivity on site is increased by
improving labour efficiency.
LABOUR PRODUCTIVITY
 Labour productivity is determined by a
complexity of factors.
 One of these factors is the type and size
of the project.
 It includes the layout and complexity of the
project.
 A large construction site requiring a large
number of workers will be relatively harder
to manage than a smaller size.
LABOUR PRODUCTIVITY
 The difficulties in managing manpower on a
large scale may result in productivity loss
(Thomas and Jansma, 1985).
 There are four main factors that affect labour
productivity;
1. The duration of worker’s effort.
2. The intensity of worker’s effort.
3. The effectiveness of worker’s effort combined
with the technology used.
4. The efficiency of worker’s effort, which can be
described as a measure of how much the
worker is utilising his ability.
LABOUR PRODUCTIVITY
 Work on a complex project (e.g. such as the
construction of a major shopping centre)
becomes more difficult as the project advances.
 Off-site pre-fabrication units will reduce the
number of labour hours required.
Other factors such as:
 the level of skill amongst the workers;
 the length of the workday;
 Innovative work practices can increase
productivity.
LABOUR PRODUCTIVITY
 In view of Olomolaiye et al (1998):
 The personal attribution of workers contribute to
the factors that directly affect productivity.
These attributes as:
 worker’s skills
 experience
 training
 qualifications
 Innate (inborn) physical and mental ability.
 The intensity of the application of both skills and
innate ability to the production process.
LABOUR PRODUCTIVITY
Thomas et al (1992) investigated the level of labour
productivity for masonry activities from seven countries.
Case study showed that:
 little difference in productivity amongst the seven
countries.
 The aim of investigation was to show that productivity in
 Australia
 Canada
 England
 Finland,
 Scotland
 Sweden and the United State-was similar.
LABOUR PRODUCTIVITY
 The site with the highest level of
disruption will have the worse level of
productivity.
 Other investigations show that labour
disruption accounts for more than
50% of the variability in daily crew
productivity.
LABOUR PRODUCTIVITY
 An excessive number of staff can be disruptive.
 It also has the effect of reducing the level of
productivity.
The results of a model based survey of contractors
(planning engineers) in France, Germany and UK
Showed that :
 the working schedule of UK and German
contractors may be excessive;
 can have an impact on construction productivity
level.
LABOUR PRODUCTIVITY
 The survey also identified that in the UK the
labour force employed on site are:
 26% directly employed
 74% sub-contracted
 In France 93% of the labour force on site are
directly employed.
 In France 7% are sub-contractors.
 This trend goes back to year 2000 to 2003
and recently there has been some changes
to above figures.
LABOUR PRODUCTIVITY
 Employment practice has an impact on
the cohesiveness amongst the workforce.
Some of the Important contributors towards
Labour productivity are:
 a culture of cohesiveness
 common goal
 strong sense of a team working
 towards a common goal
LABOUR PRODUCTIVITY
 A culture of team working involving all
workers is to achieve a common goal.
 A common goal on construction site is to
achieve KPIs.
 Labour productivity can also be improved
if operatives on site avoid conflict.
 Conflict on site can hamper the progress
of work.
 Team working reduces conflict and will
greatly facilitate increased productivity.
LABOUR PRODUCTIVITY
 The importance of a directly or indirectly
employed workforce.
 and the effect on the dynamics of
productivity is reiterated in several
research work.
 The growth in the construction sector is
relatively stagnant.
 The job security can be very bad during
any recession for construction workforce.
LABOUR PRODUCTIVITY
 This is based on a number of observations.
 One such observation is the limited use of
mass production.
 The reasons for high productivity amongst
major contractors are:
 Scheduled overtime is avoided
 The labour force is directly employed
 They are a mainly skilled work force
LABOUR PRODUCTIVITY
 Maximum 40 hour per week is the norm
rather than the exception.
 There are also other factors such as:
 high salary
 job security
which are also important reasons for high
productivity amongst major construction
firms.
LABOUR PRODUCTIVITY
Impact of Changes on Labour
Productivity
 Any changes made to the original
scope of work are costly.
 They will have an effect on labour
productivity.
 Although some changes are inevitable,
the impact on site productivity is
nonetheless significant.
LABOUR PRODUCTIVITY
 The impact of changes in quantitative
terms has been measured by researchers.
 Changes impacts on the labour force’s
efficiency.
 The relationship between change and
various types of disruption would result in
productivity decline.
LABOUR PRODUCTIVITY
 The increase in the percentage of work
hours spent on changes will lead to a 10-
20% loss in productivity.
 Changes are considered an indirect factor
influencing productivity.
 It has also been realised that changes in
themselves do not decrease productivity
or efficiency.
 It is the manpower involved in the process.
LABOUR PRODUCTIVITY
 If a change occurs in the final stage of a
construction project:
 the crew must stop working until the
changes are carried out first.
 Also the work method may require
changes as well as more co-ordination
being required.
LABOUR PRODUCTIVITY
 If changes occur:
 routine work will change,
 processes will slow down
 the total work hours will be several times
greater.
 On average, there is a 30% loss of
efficiency when changes are being
performed, although it is possible to carry
out many changes without a loss of
efficiency.
LABOUR PRODUCTIVITY
 The variables affecting efficiency are
believed to be the time of the change.
 Productivity can decline if there are:
 repeat works
 disruption
 the presence of change
LABOUR PRODUCTIVITY
 The impact of change on the construction site
will often result in disputes.
 Changes should be kept to a minimum.
Improving Productivity by Training Methods
 Training is considered to be an influential factor
in high productivity on construction sites.
 The growth in labour only sub-contracting in UK
construction sector.
 The level and quality of training within the
industry.
LABOUR PRODUCTIVITY
 Productivity within the UK construction
industry compared with West Germany
and France is partly the result of low levels
of training labour force receive in UK
amongst small firms.
 Large UK firms have a good training
policy.
LABOUR PRODUCTIVITY
 Improving the knowledge and skill of
workers on construction sites.
 Motivated work force.
 Including the quality of management all
can improve the productivity.
 Site worker’s training is considered to be
an important factor in improving site
productivity.
LABOUR PRODUCTIVITY
 Therefore, organisational performance (P)
can be considered to be dependent on:
 the aggregate sums of performance of
each worker (F)
 and each manager (M)
 and the external factor (e)
 and the organisational performance is
shown as; P = f (F, M, e).
LABOUR PRODUCTIVITY
 The individual performance is dependent
on individual knowledge (K)
 skill (S)
 and the attitude to the work (a) of each
worker and manager
 P= f (K,S, a), M =f (K, S, a). Performance
of workers is linked to both quality
(qualitative) and output (quantitative) rate.
LABOUR PRODUCTIVITY
 Productivity and the quality of work can be
improved by:
 giving appropriate training to upgrade the:
 knowledge
 skills
 and attitude of workers and managers.
056 Labour Productivity
056 Labour Productivity

More Related Content

What's hot

093 Productivity Measurement
093 Productivity Measurement093 Productivity Measurement
093 Productivity Measurement
Dr Fereidoun Dejahang
 
Productivity concepts
Productivity conceptsProductivity concepts
Productivity concepts
Md Mosaruf Hossan
 
Factors affecting productivity
Factors affecting productivity Factors affecting productivity
Factors affecting productivity
Waleed Attalla
 
1. productivity concept and calculation.
1. productivity concept and calculation.1. productivity concept and calculation.
1. productivity concept and calculation.
Samir Potale-sylvester
 
Controling productivity in construction projects
Controling productivity in construction projectsControling productivity in construction projects
Controling productivity in construction projects
Essam Lotffy, PMP®, CCP®
 
Production Presentation
Production PresentationProduction Presentation
Production Presentation
ahmad bassiouny
 
Productivity management
Productivity management   Productivity management
Productivity management
Nikhil Nimbarte
 
Construction industry
Construction industryConstruction industry
Construction industry
anojan kanagarathnam
 
Construction planning & management
Construction planning & managementConstruction planning & management
Construction planning & management
Manit Agarwal
 
Line of balance in civil engineering
Line of balance in civil engineeringLine of balance in civil engineering
Line of balance in civil engineering
rathodjaydeep2
 
CAPACITY PLANNING
CAPACITY PLANNINGCAPACITY PLANNING
CAPACITY PLANNING
Shilpi Panchal
 
Production planning control ppt
Production planning control pptProduction planning control ppt
Production planning control ppt
sudhir pawar
 
UNIT 4 - PRODUCTION SCHEDULING
UNIT 4 - PRODUCTION SCHEDULINGUNIT 4 - PRODUCTION SCHEDULING
Man power management or labour management.
Man power management or labour management.Man power management or labour management.
Man power management or labour management.
Sumpi Tana
 
Labor management at construction site
Labor management at construction siteLabor management at construction site
Labor management at construction site
B.H.Gardi College of Engineering and Technology
 
Five ways to improve productivity at the construction site
Five ways to improve productivity at the construction siteFive ways to improve productivity at the construction site
Five ways to improve productivity at the construction siteVikaslal2006
 
Project cost stimating
Project cost stimatingProject cost stimating
Project cost stimating
hatim ahmed
 
02 Construction Projects
02 Construction Projects02 Construction Projects
02 Construction Projects
akashpadole
 

What's hot (20)

093 Productivity Measurement
093 Productivity Measurement093 Productivity Measurement
093 Productivity Measurement
 
Productivity concepts
Productivity conceptsProductivity concepts
Productivity concepts
 
Work measurement
Work measurementWork measurement
Work measurement
 
Factors affecting productivity
Factors affecting productivity Factors affecting productivity
Factors affecting productivity
 
1. productivity concept and calculation.
1. productivity concept and calculation.1. productivity concept and calculation.
1. productivity concept and calculation.
 
Controling productivity in construction projects
Controling productivity in construction projectsControling productivity in construction projects
Controling productivity in construction projects
 
Production Presentation
Production PresentationProduction Presentation
Production Presentation
 
Productivity management
Productivity management   Productivity management
Productivity management
 
Construction industry
Construction industryConstruction industry
Construction industry
 
Construction planning & management
Construction planning & managementConstruction planning & management
Construction planning & management
 
Line of balance in civil engineering
Line of balance in civil engineeringLine of balance in civil engineering
Line of balance in civil engineering
 
Capacity planning
Capacity planning Capacity planning
Capacity planning
 
CAPACITY PLANNING
CAPACITY PLANNINGCAPACITY PLANNING
CAPACITY PLANNING
 
Production planning control ppt
Production planning control pptProduction planning control ppt
Production planning control ppt
 
UNIT 4 - PRODUCTION SCHEDULING
UNIT 4 - PRODUCTION SCHEDULINGUNIT 4 - PRODUCTION SCHEDULING
UNIT 4 - PRODUCTION SCHEDULING
 
Man power management or labour management.
Man power management or labour management.Man power management or labour management.
Man power management or labour management.
 
Labor management at construction site
Labor management at construction siteLabor management at construction site
Labor management at construction site
 
Five ways to improve productivity at the construction site
Five ways to improve productivity at the construction siteFive ways to improve productivity at the construction site
Five ways to improve productivity at the construction site
 
Project cost stimating
Project cost stimatingProject cost stimating
Project cost stimating
 
02 Construction Projects
02 Construction Projects02 Construction Projects
02 Construction Projects
 

Viewers also liked

#MP2013 Presentation by the Minister of Labour and Productivity
#MP2013 Presentation by the Minister of Labour and Productivity#MP2013 Presentation by the Minister of Labour and Productivity
#MP2013 Presentation by the Minister of Labour and Productivity
FMINigeria
 
021 Construction Productivity (PART 1)
021 Construction Productivity (PART 1)021 Construction Productivity (PART 1)
021 Construction Productivity (PART 1)
Dr Fereidoun Dejahang
 
Labor productivity improvement in construction projects using wbs obs integra...
Labor productivity improvement in construction projects using wbs obs integra...Labor productivity improvement in construction projects using wbs obs integra...
Labor productivity improvement in construction projects using wbs obs integra...
Essam Lotffy, PMP®, CCP®
 
Human capital: Education and health in economic development egp
Human capital: Education and health in economic development egpHuman capital: Education and health in economic development egp
Human capital: Education and health in economic development egp
Shivani Baghel
 
Associação MTM Portugal
Associação MTM PortugalAssociação MTM Portugal
Associação MTM Portugal
Associação MTM Portugal
 
10. Nepal standard formulation process
10. Nepal standard formulation process10. Nepal standard formulation process
10. Nepal standard formulation process
Centre For Rural Technology, Nepal
 
02 cernic urban-rural%20-life%20setting%20as%20the%20explanatory%20factor%20of..
02 cernic urban-rural%20-life%20setting%20as%20the%20explanatory%20factor%20of..02 cernic urban-rural%20-life%20setting%20as%20the%20explanatory%20factor%20of..
02 cernic urban-rural%20-life%20setting%20as%20the%20explanatory%20factor%20of..
tuyagerel
 
Status of Hepatitis in Pakistam
Status of Hepatitis in PakistamStatus of Hepatitis in Pakistam
Status of Hepatitis in Pakistam
Hareem_syed
 
Gender and migration
Gender and migration Gender and migration
Gender and migration ysu1314
 
Economic determinants and female labour force participation an empirical anal...
Economic determinants and female labour force participation an empirical anal...Economic determinants and female labour force participation an empirical anal...
Economic determinants and female labour force participation an empirical anal...
Alexander Decker
 
MERIDIANOS ESTOMAGO-BAÇO PANCREAS MTC.PPT
MERIDIANOS ESTOMAGO-BAÇO PANCREAS MTC.PPTMERIDIANOS ESTOMAGO-BAÇO PANCREAS MTC.PPT
MERIDIANOS ESTOMAGO-BAÇO PANCREAS MTC.PPT
fabricio escudine
 
Gender Dimension of Migration
Gender Dimension of MigrationGender Dimension of Migration
Gender Dimension of Migrationguest7ebcc3
 
DETERMINANTS OF FEMALE LABOUR FORCE PARTICIPATION IN FAM AND NON FARM LIVELIH...
DETERMINANTS OF FEMALE LABOUR FORCE PARTICIPATION IN FAM AND NON FARM LIVELIH...DETERMINANTS OF FEMALE LABOUR FORCE PARTICIPATION IN FAM AND NON FARM LIVELIH...
DETERMINANTS OF FEMALE LABOUR FORCE PARTICIPATION IN FAM AND NON FARM LIVELIH...Hudu Zakaria
 
Women in the labour force 23 9-2004
Women in the labour force 23 9-2004Women in the labour force 23 9-2004
Women in the labour force 23 9-2004
VIBHUTI PATEL
 
Indian textile industry
Indian textile industryIndian textile industry
Indian textile industryAdane Nega
 
HEALTH & ECONOMIC DEVELOPMENT
HEALTH & ECONOMIC DEVELOPMENTHEALTH & ECONOMIC DEVELOPMENT
HEALTH & ECONOMIC DEVELOPMENT
Bobba Leeladhar
 
Presentation1 brain drain
Presentation1 brain drainPresentation1 brain drain
Presentation1 brain drainSujay Pal
 
Women Participation in Labour Market
Women Participation in Labour MarketWomen Participation in Labour Market
Women Participation in Labour MarketKeshab Giri
 

Viewers also liked (20)

#MP2013 Presentation by the Minister of Labour and Productivity
#MP2013 Presentation by the Minister of Labour and Productivity#MP2013 Presentation by the Minister of Labour and Productivity
#MP2013 Presentation by the Minister of Labour and Productivity
 
021 Construction Productivity (PART 1)
021 Construction Productivity (PART 1)021 Construction Productivity (PART 1)
021 Construction Productivity (PART 1)
 
Labor productivity improvement in construction projects using wbs obs integra...
Labor productivity improvement in construction projects using wbs obs integra...Labor productivity improvement in construction projects using wbs obs integra...
Labor productivity improvement in construction projects using wbs obs integra...
 
Human capital: Education and health in economic development egp
Human capital: Education and health in economic development egpHuman capital: Education and health in economic development egp
Human capital: Education and health in economic development egp
 
Productivity
ProductivityProductivity
Productivity
 
Associação MTM Portugal
Associação MTM PortugalAssociação MTM Portugal
Associação MTM Portugal
 
10. Nepal standard formulation process
10. Nepal standard formulation process10. Nepal standard formulation process
10. Nepal standard formulation process
 
02 cernic urban-rural%20-life%20setting%20as%20the%20explanatory%20factor%20of..
02 cernic urban-rural%20-life%20setting%20as%20the%20explanatory%20factor%20of..02 cernic urban-rural%20-life%20setting%20as%20the%20explanatory%20factor%20of..
02 cernic urban-rural%20-life%20setting%20as%20the%20explanatory%20factor%20of..
 
2 3
2 32 3
2 3
 
Status of Hepatitis in Pakistam
Status of Hepatitis in PakistamStatus of Hepatitis in Pakistam
Status of Hepatitis in Pakistam
 
Gender and migration
Gender and migration Gender and migration
Gender and migration
 
Economic determinants and female labour force participation an empirical anal...
Economic determinants and female labour force participation an empirical anal...Economic determinants and female labour force participation an empirical anal...
Economic determinants and female labour force participation an empirical anal...
 
MERIDIANOS ESTOMAGO-BAÇO PANCREAS MTC.PPT
MERIDIANOS ESTOMAGO-BAÇO PANCREAS MTC.PPTMERIDIANOS ESTOMAGO-BAÇO PANCREAS MTC.PPT
MERIDIANOS ESTOMAGO-BAÇO PANCREAS MTC.PPT
 
Gender Dimension of Migration
Gender Dimension of MigrationGender Dimension of Migration
Gender Dimension of Migration
 
DETERMINANTS OF FEMALE LABOUR FORCE PARTICIPATION IN FAM AND NON FARM LIVELIH...
DETERMINANTS OF FEMALE LABOUR FORCE PARTICIPATION IN FAM AND NON FARM LIVELIH...DETERMINANTS OF FEMALE LABOUR FORCE PARTICIPATION IN FAM AND NON FARM LIVELIH...
DETERMINANTS OF FEMALE LABOUR FORCE PARTICIPATION IN FAM AND NON FARM LIVELIH...
 
Women in the labour force 23 9-2004
Women in the labour force 23 9-2004Women in the labour force 23 9-2004
Women in the labour force 23 9-2004
 
Indian textile industry
Indian textile industryIndian textile industry
Indian textile industry
 
HEALTH & ECONOMIC DEVELOPMENT
HEALTH & ECONOMIC DEVELOPMENTHEALTH & ECONOMIC DEVELOPMENT
HEALTH & ECONOMIC DEVELOPMENT
 
Presentation1 brain drain
Presentation1 brain drainPresentation1 brain drain
Presentation1 brain drain
 
Women Participation in Labour Market
Women Participation in Labour MarketWomen Participation in Labour Market
Women Participation in Labour Market
 

Similar to 056 Labour Productivity

092 Productivity Improvement
092 Productivity Improvement092 Productivity Improvement
092 Productivity Improvement
Dr Fereidoun Dejahang
 
Critical Study, Analysis and Suggestion for Labor Productivity Improvement in...
Critical Study, Analysis and Suggestion for Labor Productivity Improvement in...Critical Study, Analysis and Suggestion for Labor Productivity Improvement in...
Critical Study, Analysis and Suggestion for Labor Productivity Improvement in...
IRJET Journal
 
Improvement of construction labor productivity in chambal region
Improvement of construction labor productivity in chambal regionImprovement of construction labor productivity in chambal region
Improvement of construction labor productivity in chambal region
eSAT Publishing House
 
Improvement of construction labor productivity in chambal region
Improvement of construction labor productivity in chambal regionImprovement of construction labor productivity in chambal region
Improvement of construction labor productivity in chambal region
eSAT Journals
 
A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...
A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...
A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...
IRJET Journal
 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)
IJERD Editor
 
Importance of labor productivity and its measurement
Importance of labor productivity and its measurementImportance of labor productivity and its measurement
Importance of labor productivity and its measurement
Siddharth Mantri
 
Productivity planning and management
Productivity planning and managementProductivity planning and management
Productivity planning and management
priyam141
 
Operations-Management-and-TQM_ESC-1LESSON-1 (1).pptx
Operations-Management-and-TQM_ESC-1LESSON-1 (1).pptxOperations-Management-and-TQM_ESC-1LESSON-1 (1).pptx
Operations-Management-and-TQM_ESC-1LESSON-1 (1).pptx
GebethBaadera
 
Limits+of+the+learning+curve
Limits+of+the+learning+curveLimits+of+the+learning+curve
Limits+of+the+learning+curve
reagan22
 
040 Integrating Financial Incentives
040 Integrating Financial Incentives040 Integrating Financial Incentives
040 Integrating Financial Incentives
Dr Fereidoun Dejahang
 
040 integrating financial incentives
040 integrating financial incentives040 integrating financial incentives
040 integrating financial incentives
drdej19
 
8. chapter 7 work study (time and motion study)
8. chapter 7   work study (time and motion study)8. chapter 7   work study (time and motion study)
8. chapter 7 work study (time and motion study)
sundar sivam
 
Factors Affecting Laborers’ Productivity in the Construction Companies
Factors Affecting Laborers’ Productivity in the Construction CompaniesFactors Affecting Laborers’ Productivity in the Construction Companies
Factors Affecting Laborers’ Productivity in the Construction Companies
IJAEMSJORNAL
 
cost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeriacost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeria
Newman Jonathan
 
Downsizing & Business Reorganisation
Downsizing & Business ReorganisationDownsizing & Business Reorganisation
Downsizing & Business ReorganisationRAHAYU TASNIM
 
downsizing & business reorganisation
downsizing & business reorganisationdownsizing & business reorganisation
downsizing & business reorganisationRAHAYU TASNIM
 
Overall Equipment Effectiveness in Construction Equipments
Overall Equipment Effectiveness in Construction EquipmentsOverall Equipment Effectiveness in Construction Equipments
Overall Equipment Effectiveness in Construction Equipments
IRJET Journal
 
IRJET-A Review of Impact on Labour Management in Construction Industry
IRJET-A Review of Impact on Labour Management in Construction IndustryIRJET-A Review of Impact on Labour Management in Construction Industry
IRJET-A Review of Impact on Labour Management in Construction Industry
IRJET Journal
 
Manufacturing differently
Manufacturing differentlyManufacturing differently
Manufacturing differently
Hendrik Lourens
 

Similar to 056 Labour Productivity (20)

092 Productivity Improvement
092 Productivity Improvement092 Productivity Improvement
092 Productivity Improvement
 
Critical Study, Analysis and Suggestion for Labor Productivity Improvement in...
Critical Study, Analysis and Suggestion for Labor Productivity Improvement in...Critical Study, Analysis and Suggestion for Labor Productivity Improvement in...
Critical Study, Analysis and Suggestion for Labor Productivity Improvement in...
 
Improvement of construction labor productivity in chambal region
Improvement of construction labor productivity in chambal regionImprovement of construction labor productivity in chambal region
Improvement of construction labor productivity in chambal region
 
Improvement of construction labor productivity in chambal region
Improvement of construction labor productivity in chambal regionImprovement of construction labor productivity in chambal region
Improvement of construction labor productivity in chambal region
 
A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...
A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...
A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...
 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)
 
Importance of labor productivity and its measurement
Importance of labor productivity and its measurementImportance of labor productivity and its measurement
Importance of labor productivity and its measurement
 
Productivity planning and management
Productivity planning and managementProductivity planning and management
Productivity planning and management
 
Operations-Management-and-TQM_ESC-1LESSON-1 (1).pptx
Operations-Management-and-TQM_ESC-1LESSON-1 (1).pptxOperations-Management-and-TQM_ESC-1LESSON-1 (1).pptx
Operations-Management-and-TQM_ESC-1LESSON-1 (1).pptx
 
Limits+of+the+learning+curve
Limits+of+the+learning+curveLimits+of+the+learning+curve
Limits+of+the+learning+curve
 
040 Integrating Financial Incentives
040 Integrating Financial Incentives040 Integrating Financial Incentives
040 Integrating Financial Incentives
 
040 integrating financial incentives
040 integrating financial incentives040 integrating financial incentives
040 integrating financial incentives
 
8. chapter 7 work study (time and motion study)
8. chapter 7   work study (time and motion study)8. chapter 7   work study (time and motion study)
8. chapter 7 work study (time and motion study)
 
Factors Affecting Laborers’ Productivity in the Construction Companies
Factors Affecting Laborers’ Productivity in the Construction CompaniesFactors Affecting Laborers’ Productivity in the Construction Companies
Factors Affecting Laborers’ Productivity in the Construction Companies
 
cost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeriacost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeria
 
Downsizing & Business Reorganisation
Downsizing & Business ReorganisationDownsizing & Business Reorganisation
Downsizing & Business Reorganisation
 
downsizing & business reorganisation
downsizing & business reorganisationdownsizing & business reorganisation
downsizing & business reorganisation
 
Overall Equipment Effectiveness in Construction Equipments
Overall Equipment Effectiveness in Construction EquipmentsOverall Equipment Effectiveness in Construction Equipments
Overall Equipment Effectiveness in Construction Equipments
 
IRJET-A Review of Impact on Labour Management in Construction Industry
IRJET-A Review of Impact on Labour Management in Construction IndustryIRJET-A Review of Impact on Labour Management in Construction Industry
IRJET-A Review of Impact on Labour Management in Construction Industry
 
Manufacturing differently
Manufacturing differentlyManufacturing differently
Manufacturing differently
 

More from Dr Fereidoun Dejahang

27 j20 my news punch -dr f dejahang 27-01-2020
27 j20 my news punch -dr f dejahang  27-01-202027 j20 my news punch -dr f dejahang  27-01-2020
27 j20 my news punch -dr f dejahang 27-01-2020
Dr Fereidoun Dejahang
 
28 dej my news punch rev 28-12-2019
28 dej my news punch rev 28-12-201928 dej my news punch rev 28-12-2019
28 dej my news punch rev 28-12-2019
Dr Fereidoun Dejahang
 
16 fd my news punch rev 16-12-2019
16 fd my news punch rev 16-12-201916 fd my news punch rev 16-12-2019
16 fd my news punch rev 16-12-2019
Dr Fereidoun Dejahang
 
029 fast-tracking projects
029 fast-tracking projects029 fast-tracking projects
029 fast-tracking projects
Dr Fereidoun Dejahang
 
028 fast-tracking projects & cost overrun
028 fast-tracking projects & cost overrun028 fast-tracking projects & cost overrun
028 fast-tracking projects & cost overrun
Dr Fereidoun Dejahang
 
027 fast-tracked projects-materials
027 fast-tracked projects-materials027 fast-tracked projects-materials
027 fast-tracked projects-materials
Dr Fereidoun Dejahang
 
026 fast react-productivity improvement
026 fast react-productivity improvement026 fast react-productivity improvement
026 fast react-productivity improvement
Dr Fereidoun Dejahang
 
025 enterprise resources management
025 enterprise resources management025 enterprise resources management
025 enterprise resources management
Dr Fereidoun Dejahang
 
022 b construction productivity-write
022 b construction productivity-write022 b construction productivity-write
022 b construction productivity-write
Dr Fereidoun Dejahang
 
022 a construction productivity (2)
022 a construction productivity (2)022 a construction productivity (2)
022 a construction productivity (2)
Dr Fereidoun Dejahang
 
021 construction productivity (1)
021 construction productivity (1)021 construction productivity (1)
021 construction productivity (1)
Dr Fereidoun Dejahang
 
019 competencies-managers
019 competencies-managers019 competencies-managers
019 competencies-managers
Dr Fereidoun Dejahang
 
018 company productivity
018 company productivity018 company productivity
018 company productivity
Dr Fereidoun Dejahang
 
017 communication
017 communication017 communication
017 communication
Dr Fereidoun Dejahang
 
016 communication in construction sector
016 communication in construction sector016 communication in construction sector
016 communication in construction sector
Dr Fereidoun Dejahang
 
015 changes-process model
015 changes-process model015 changes-process model
015 changes-process model
Dr Fereidoun Dejahang
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
Dr Fereidoun Dejahang
 
013 changes in construction projects
013 changes in construction projects013 changes in construction projects
013 changes in construction projects
Dr Fereidoun Dejahang
 
012 bussiness planning process
012 bussiness planning process012 bussiness planning process
012 bussiness planning process
Dr Fereidoun Dejahang
 
011 business performance management
011 business performance management011 business performance management
011 business performance management
Dr Fereidoun Dejahang
 

More from Dr Fereidoun Dejahang (20)

27 j20 my news punch -dr f dejahang 27-01-2020
27 j20 my news punch -dr f dejahang  27-01-202027 j20 my news punch -dr f dejahang  27-01-2020
27 j20 my news punch -dr f dejahang 27-01-2020
 
28 dej my news punch rev 28-12-2019
28 dej my news punch rev 28-12-201928 dej my news punch rev 28-12-2019
28 dej my news punch rev 28-12-2019
 
16 fd my news punch rev 16-12-2019
16 fd my news punch rev 16-12-201916 fd my news punch rev 16-12-2019
16 fd my news punch rev 16-12-2019
 
029 fast-tracking projects
029 fast-tracking projects029 fast-tracking projects
029 fast-tracking projects
 
028 fast-tracking projects & cost overrun
028 fast-tracking projects & cost overrun028 fast-tracking projects & cost overrun
028 fast-tracking projects & cost overrun
 
027 fast-tracked projects-materials
027 fast-tracked projects-materials027 fast-tracked projects-materials
027 fast-tracked projects-materials
 
026 fast react-productivity improvement
026 fast react-productivity improvement026 fast react-productivity improvement
026 fast react-productivity improvement
 
025 enterprise resources management
025 enterprise resources management025 enterprise resources management
025 enterprise resources management
 
022 b construction productivity-write
022 b construction productivity-write022 b construction productivity-write
022 b construction productivity-write
 
022 a construction productivity (2)
022 a construction productivity (2)022 a construction productivity (2)
022 a construction productivity (2)
 
021 construction productivity (1)
021 construction productivity (1)021 construction productivity (1)
021 construction productivity (1)
 
019 competencies-managers
019 competencies-managers019 competencies-managers
019 competencies-managers
 
018 company productivity
018 company productivity018 company productivity
018 company productivity
 
017 communication
017 communication017 communication
017 communication
 
016 communication in construction sector
016 communication in construction sector016 communication in construction sector
016 communication in construction sector
 
015 changes-process model
015 changes-process model015 changes-process model
015 changes-process model
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
 
013 changes in construction projects
013 changes in construction projects013 changes in construction projects
013 changes in construction projects
 
012 bussiness planning process
012 bussiness planning process012 bussiness planning process
012 bussiness planning process
 
011 business performance management
011 business performance management011 business performance management
011 business performance management
 

Recently uploaded

power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
Kamal Acharya
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
Kamal Acharya
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
Kamal Acharya
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 

Recently uploaded (20)

power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 

056 Labour Productivity

  • 1. FROM PRODUCTIVITY BRIEFCASES HELP DESK LABOUR PRODUCTIVITY
  • 2. LABOUR PRODUCTIVITY  A large proportion of the high cost in construction work is as a result of excessive labour costs.  These costs can be reduced if productivity on site is increased by improving labour efficiency.
  • 3. LABOUR PRODUCTIVITY  Labour productivity is determined by a complexity of factors.  One of these factors is the type and size of the project.  It includes the layout and complexity of the project.  A large construction site requiring a large number of workers will be relatively harder to manage than a smaller size.
  • 4. LABOUR PRODUCTIVITY  The difficulties in managing manpower on a large scale may result in productivity loss (Thomas and Jansma, 1985).  There are four main factors that affect labour productivity; 1. The duration of worker’s effort. 2. The intensity of worker’s effort. 3. The effectiveness of worker’s effort combined with the technology used. 4. The efficiency of worker’s effort, which can be described as a measure of how much the worker is utilising his ability.
  • 5. LABOUR PRODUCTIVITY  Work on a complex project (e.g. such as the construction of a major shopping centre) becomes more difficult as the project advances.  Off-site pre-fabrication units will reduce the number of labour hours required. Other factors such as:  the level of skill amongst the workers;  the length of the workday;  Innovative work practices can increase productivity.
  • 6. LABOUR PRODUCTIVITY  In view of Olomolaiye et al (1998):  The personal attribution of workers contribute to the factors that directly affect productivity. These attributes as:  worker’s skills  experience  training  qualifications  Innate (inborn) physical and mental ability.  The intensity of the application of both skills and innate ability to the production process.
  • 7. LABOUR PRODUCTIVITY Thomas et al (1992) investigated the level of labour productivity for masonry activities from seven countries. Case study showed that:  little difference in productivity amongst the seven countries.  The aim of investigation was to show that productivity in  Australia  Canada  England  Finland,  Scotland  Sweden and the United State-was similar.
  • 8. LABOUR PRODUCTIVITY  The site with the highest level of disruption will have the worse level of productivity.  Other investigations show that labour disruption accounts for more than 50% of the variability in daily crew productivity.
  • 9. LABOUR PRODUCTIVITY  An excessive number of staff can be disruptive.  It also has the effect of reducing the level of productivity. The results of a model based survey of contractors (planning engineers) in France, Germany and UK Showed that :  the working schedule of UK and German contractors may be excessive;  can have an impact on construction productivity level.
  • 10. LABOUR PRODUCTIVITY  The survey also identified that in the UK the labour force employed on site are:  26% directly employed  74% sub-contracted  In France 93% of the labour force on site are directly employed.  In France 7% are sub-contractors.  This trend goes back to year 2000 to 2003 and recently there has been some changes to above figures.
  • 11. LABOUR PRODUCTIVITY  Employment practice has an impact on the cohesiveness amongst the workforce. Some of the Important contributors towards Labour productivity are:  a culture of cohesiveness  common goal  strong sense of a team working  towards a common goal
  • 12. LABOUR PRODUCTIVITY  A culture of team working involving all workers is to achieve a common goal.  A common goal on construction site is to achieve KPIs.  Labour productivity can also be improved if operatives on site avoid conflict.  Conflict on site can hamper the progress of work.  Team working reduces conflict and will greatly facilitate increased productivity.
  • 13. LABOUR PRODUCTIVITY  The importance of a directly or indirectly employed workforce.  and the effect on the dynamics of productivity is reiterated in several research work.  The growth in the construction sector is relatively stagnant.  The job security can be very bad during any recession for construction workforce.
  • 14. LABOUR PRODUCTIVITY  This is based on a number of observations.  One such observation is the limited use of mass production.  The reasons for high productivity amongst major contractors are:  Scheduled overtime is avoided  The labour force is directly employed  They are a mainly skilled work force
  • 15. LABOUR PRODUCTIVITY  Maximum 40 hour per week is the norm rather than the exception.  There are also other factors such as:  high salary  job security which are also important reasons for high productivity amongst major construction firms.
  • 16. LABOUR PRODUCTIVITY Impact of Changes on Labour Productivity  Any changes made to the original scope of work are costly.  They will have an effect on labour productivity.  Although some changes are inevitable, the impact on site productivity is nonetheless significant.
  • 17. LABOUR PRODUCTIVITY  The impact of changes in quantitative terms has been measured by researchers.  Changes impacts on the labour force’s efficiency.  The relationship between change and various types of disruption would result in productivity decline.
  • 18. LABOUR PRODUCTIVITY  The increase in the percentage of work hours spent on changes will lead to a 10- 20% loss in productivity.  Changes are considered an indirect factor influencing productivity.  It has also been realised that changes in themselves do not decrease productivity or efficiency.  It is the manpower involved in the process.
  • 19. LABOUR PRODUCTIVITY  If a change occurs in the final stage of a construction project:  the crew must stop working until the changes are carried out first.  Also the work method may require changes as well as more co-ordination being required.
  • 20. LABOUR PRODUCTIVITY  If changes occur:  routine work will change,  processes will slow down  the total work hours will be several times greater.  On average, there is a 30% loss of efficiency when changes are being performed, although it is possible to carry out many changes without a loss of efficiency.
  • 21. LABOUR PRODUCTIVITY  The variables affecting efficiency are believed to be the time of the change.  Productivity can decline if there are:  repeat works  disruption  the presence of change
  • 22. LABOUR PRODUCTIVITY  The impact of change on the construction site will often result in disputes.  Changes should be kept to a minimum. Improving Productivity by Training Methods  Training is considered to be an influential factor in high productivity on construction sites.  The growth in labour only sub-contracting in UK construction sector.  The level and quality of training within the industry.
  • 23. LABOUR PRODUCTIVITY  Productivity within the UK construction industry compared with West Germany and France is partly the result of low levels of training labour force receive in UK amongst small firms.  Large UK firms have a good training policy.
  • 24. LABOUR PRODUCTIVITY  Improving the knowledge and skill of workers on construction sites.  Motivated work force.  Including the quality of management all can improve the productivity.  Site worker’s training is considered to be an important factor in improving site productivity.
  • 25. LABOUR PRODUCTIVITY  Therefore, organisational performance (P) can be considered to be dependent on:  the aggregate sums of performance of each worker (F)  and each manager (M)  and the external factor (e)  and the organisational performance is shown as; P = f (F, M, e).
  • 26. LABOUR PRODUCTIVITY  The individual performance is dependent on individual knowledge (K)  skill (S)  and the attitude to the work (a) of each worker and manager  P= f (K,S, a), M =f (K, S, a). Performance of workers is linked to both quality (qualitative) and output (quantitative) rate.
  • 27. LABOUR PRODUCTIVITY  Productivity and the quality of work can be improved by:  giving appropriate training to upgrade the:  knowledge  skills  and attitude of workers and managers.