Cost and Time estimation for Conventional, Aluminium &Tunnel
Formwork
1Prof. Ashish P. Waghmare, 2 Renuka S. Hangarge
1 Prof & PG Co-ordinator, Dept. Of Civil Engineering, Dr. D Y Patil SOET, Lohgaon, Pune 412105
2 Student M.E., (C&M) Civil Department, Dr. D Y Patil SOET, Lohgaon, Pune 412105
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract - Due to increase in inhabitants, people started to
construct the dwelling buildings. At the early days buildings
were constructed using conventional type form work system
where wooden planks, runners, poles were used for the form
work. With the development of technology, man tend to use
plywood in its place of planks, steel jacks forsupportinstead of
wooden poles. The below study is carried out to compare
different Formwork systems on the basis of Time & Cost.
Key Words: Conventional Formwork, Tunnel Formwork,
Aluminium Formwork, Construction Cost, time
1. INTRODUCTION
The expenditure on formwork is occupyinga majorpart in
the total cost of construction. Therefore the selection and
proper planning the system of form work will reduce the
cost of construction, time of construction, the wastages and
labour requirement which reduces the total cost of
construction.
Formwork systems are among the key factors
determining the success of a construction projectinterms of
speed, quality, cost and safety of the works. Construction
industry is seen to be able to play a bigger role into a
sustainable society by offering sustainable construction.
Formwork system is one of the important construction
methods in building construction
2. DATA COLLECTION
PhotographatTunnelFormworksiteduringtheconstruction.
Conventional Building during construction is as below
Aluminium Formwork during construction is as below
Case study1: Residential building with G+12 floors
(Aluminium Formwork is used)
Case study2: Residential building with G+12 floors
(Conventional Formwork is used)
Case Study3: Residential building with G+12 floors (Tunnel
Formwork is used)
Case study 1 & 2 are of same site & each case study contains
four buildings of G+12 floors.
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1704
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072
Table 3.1: Al-Formwork 1st Building cost
Item Amount
Concrete Quantity 16625986.2
Steel Quantity 26773524
Formwork Quantity 18449026.2
Gypsum 8674220.16
Labour Rate
Concrete rate 4835298
Steel 8924508
Shuttering 9056794.68
Deshuttering 402524.208
Gypsum 4486665.6
Total 94228547.05
Table 3.2: Conventional Formwork 1st Building cost
Item Amount
Concrete Quantity 11552673.19
Steel Quantity 19178505
Formwork Quantity 2375319.8
Brickwork 12199804.2
Internal Plaster 8674220.16
External Plaster 1380380.4
Labour Charges
Concrete casting 2938492.8
Steel 6392835
Shuttering 7125959.4
Deshuttering 244318.608
Brickwork 4267870.64
Internal Plaster 4539043.328
External Plaster 1060860.82
81930283.34
3 .DATA ANALYSIS
Total Cost of four Conventional formwork building =
327721133.4 Rs
Total Cost of four Al-Formwork building = 321567109.6 Rs
Total Difference = 6154023.768 Rs
This is the cost with 48 repetitions of AluminiumFormwork.
With proper use and handling these can be used up to 120
repetitions. So, out of 120 only 48 repetitions are used.
Hence cost savings for remaining life of Aluminium
Formwork is = (120-48)* Initial Investment in
Formwork/120 =1,10,69,415.3 Rs.
Currently cost of Al-Formwork building =321567109.6-
11069415.3= 31,04,97,693.4 Rs.
Cost of Conventional Formwork Building= 327721133.4 Rs.
Cost of Conventional Formwork for 81439 m² Skin area
construction = 32,77,21,133.4 Rs.
Currently cost of Al-Formwork for 134174.736 m² Skinarea
construction= 31,04,97,693.4 Rs.
Cost of Tunnel Formwork for 81721 m² Skin area
construction = 13,12,58,400 Rs.
Cost for 10000 m² Skin area construction for Conventional
FW= 40,24,130.12 Rs.
Cost for 10000 m² Skin area construction for Aluminium FW
= 23,14,129.34 Rs.
Cost for 10000 m² Skin area construction for Tunnel FW=
16,06,177.11 Rs.
Total Days required forConventionalFormworkBuilding
construction=816
Total Days required for Aluminium Formwork Building
construction=484
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1705
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072
Total Days difference = 332 Days
Time for Conventional Formwork for 81439 m² Skin area
construction = 816 Days.
Time for Al-Formwork for 134174.736 m² Skin area
construction= 484 Days
Time for Tunnel Formwork for 81721 m² Skin area
construction = 220 Days
Time for 10000 m² Skin area construction for
Conventional FW= 100.2 Days
Timefor10000 m² Skin areaconstruction forAluminium
FW= 36.07 Days
Timefor10000m²SkinareaconstructionforTunnelFW=
26.92 Days
4. CONCLUSIONS
Following Table gives the idea about the cost & time taken by Conventional, Aluminium & Tunnel Formwork system for
construction of 10,000 m² of skin area.
Item
Conventional
Formwork
Aluminium Formwork Tunnel formwork
Cost for construction of 10,000 m² of
Concrete area in INR
40,24,130.12 23,14,129.34 16,06,177.11
Time for construction of 10,000 m² of
Concrete area in Days
100.2 36.07 26.92
 From the results obtained we can conclude that, Aluminium formwork is Cost effective in comparison with
Conventional Formwork.
 Aluminium formwork is better for use in the constructions, where Time effective formwork is necessary, than
Conventional Formwork.
 Tunnel Formwork is the most time & cost effective formwork among Conventional, Aluminium & Tunnel Formwork.
 Also, the duration of the project can be reduced largely with the use of Tunnel formwork where 1-4 days cycle is
possible. So this is the fastest formwork system compared to conventional & Aluminium formwork.
 Time saving is equal to money saving. So, even though initial investment is large, Tunnel Formwork can be suggested
for faster construction.
 If the number of repetitions are more for residential buildings, then Aluminium formwork is suggested as it savesthe
time & cost of finishing & shuttering.
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1706
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072
REFERENCES
[1] Miss. Patil Dhanashri Suryakant1, Prof. Desai D B2 1
(Student, Civil Department, Dr .J Magdum College Of
Engineering Jaysingpur, Maharashtra) 2 (HOD, Department
Of Civil Engg, Dr. J Magdum College Of Engineering
Jaysingpur, Maharashtra)
“Emerging Trends in Formwork - Cost Analysis &
Effectiveness of Mivan Formwork over the Conventional
Formwork”
[2] NINJAL M PAREKH 1, 2BHUPENDRA M MARVADI,
3UMANG PATEL “COMPARATIVE STUDIES OF
CONSTRUCTION TECHNIQUES”
(CONVENTIONAL TECHNIQUEVSALUMINIUMFORMWORK
TECHNIQUES)
1 Student, M.E. Infrastructure Engineering, Dept. of Civil
Engineering, L.D.R.P. Institute of Technology and Research,
Gandhinagar-382015, Gujarat. 2,3Assistant Professor, Dept.
of Civil Engineering, L.D.R.P. Institute of Technology and
Research, Gandhinagar-382015, Gujarat.
[4] Prathul U1 , 2Leeladhar Pammar1PGstudent,2Assistant
Professor 1, 2Department of Civil Engineering, NMAMIT,
Nitte
“Analysis of Productivity by Comparing Mivan and
Conventional Formwork “
[5] Sandip.P.Pawar1 , P.M.Atterde2 1P.G. Student Dept. of
civil Engineering SSGBCOET Bhusawal Maharashtra 2Guide,
dept. of civil Engineering SSGBCOET Bhusawal Maharashtra
“COMPARATIVE ANALYSIS OF FORMWORK IN
MULTISTORY BUILDING”
IJRET: International Journal of Research in Engineeringand
Technology eISSN: 2319-1163 | pISSN: 2321-7308 Volume:
03 Special Issue: 09 | NCETCE-2014|June-2014,Available@
http://www.ijret.org 22
[6] Tejas D. Aradhye1 , Emeritus M. R. Apte2
“STUDY OF ADVANCED TUNNEL FORMWORK SYSTEM IN
HIGH RISE BUILDING”
IJRET: International Journal of Research in Engineeringand
Technology eISSN: 2319-1163 | pISSN: 2321-7308
[7] The Canadian Society for Civil Engineering 5th
International/11th Construction Specialty Conference, At
Vancouver
“Role of Formwork Systems in High-Rise Construction”
July2015 DOI:0.13140/RG.2.3386.6083 Conference:
ICSC15:
BIOGRAPHIES
Prof Ashish P. Waghmare ,
Prof & PG Co-ordinator,
Dept. Of Civil Engineering,
Dr. D Y Patil SOET, Lohgaon, Pune 412105
Student M.E., (C&M)
Civil Department,
Dr. D Y Patil SOET, Lohgaon, Pune 412105
Renuka S. Hangarge,
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1707

More Related Content

What's hot

Experimental Analysis of Material Removal Rate in Drilling of 41Cr4 by a Tagu...
Experimental Analysis of Material Removal Rate in Drilling of 41Cr4 by a Tagu...Experimental Analysis of Material Removal Rate in Drilling of 41Cr4 by a Tagu...
Experimental Analysis of Material Removal Rate in Drilling of 41Cr4 by a Tagu...
IJERA Editor
 
Optimization of input parameters of cnc turning operation for the given comp
Optimization of input parameters of cnc turning operation for the given compOptimization of input parameters of cnc turning operation for the given comp
Optimization of input parameters of cnc turning operation for the given comp
IAEME Publication
 

What's hot (18)

Experimental Analysis of Material Removal Rate in Drilling of 41Cr4 by a Tagu...
Experimental Analysis of Material Removal Rate in Drilling of 41Cr4 by a Tagu...Experimental Analysis of Material Removal Rate in Drilling of 41Cr4 by a Tagu...
Experimental Analysis of Material Removal Rate in Drilling of 41Cr4 by a Tagu...
 
Optimization of machining parameters in edm of cfrp composite using taguchi t...
Optimization of machining parameters in edm of cfrp composite using taguchi t...Optimization of machining parameters in edm of cfrp composite using taguchi t...
Optimization of machining parameters in edm of cfrp composite using taguchi t...
 
Assignment of weights method for the optimization of ti n coated carbide reaming
Assignment of weights method for the optimization of ti n coated carbide reamingAssignment of weights method for the optimization of ti n coated carbide reaming
Assignment of weights method for the optimization of ti n coated carbide reaming
 
IRJET- Review Paper Optimization of Machining Parameters by using of Taguchi'...
IRJET- Review Paper Optimization of Machining Parameters by using of Taguchi'...IRJET- Review Paper Optimization of Machining Parameters by using of Taguchi'...
IRJET- Review Paper Optimization of Machining Parameters by using of Taguchi'...
 
IRJET- Design and Analysis of Clutch Liner using Polymer Fibre
IRJET- Design and Analysis of Clutch Liner using Polymer FibreIRJET- Design and Analysis of Clutch Liner using Polymer Fibre
IRJET- Design and Analysis of Clutch Liner using Polymer Fibre
 
IRJET- Manufacturing Technology: Optimization of Machining Performance in...
IRJET-  	  Manufacturing Technology: Optimization of Machining Performance in...IRJET-  	  Manufacturing Technology: Optimization of Machining Performance in...
IRJET- Manufacturing Technology: Optimization of Machining Performance in...
 
Optimization of CNC Machining
Optimization of CNC MachiningOptimization of CNC Machining
Optimization of CNC Machining
 
IRJET- Analysis of Ceiling Cable Holder Base
IRJET- Analysis of Ceiling Cable Holder BaseIRJET- Analysis of Ceiling Cable Holder Base
IRJET- Analysis of Ceiling Cable Holder Base
 
EXPERIMENTAL STUDY OF TURNING OPERATION AND OPTIMIZATION OF MRR AND SURFACE R...
EXPERIMENTAL STUDY OF TURNING OPERATION AND OPTIMIZATION OF MRR AND SURFACE R...EXPERIMENTAL STUDY OF TURNING OPERATION AND OPTIMIZATION OF MRR AND SURFACE R...
EXPERIMENTAL STUDY OF TURNING OPERATION AND OPTIMIZATION OF MRR AND SURFACE R...
 
Optimization of input parameters of cnc turning operation for the given comp
Optimization of input parameters of cnc turning operation for the given compOptimization of input parameters of cnc turning operation for the given comp
Optimization of input parameters of cnc turning operation for the given comp
 
IRJET- Studies on Drilling Characteristics of Heat Treated Aluminium A356/Sil...
IRJET- Studies on Drilling Characteristics of Heat Treated Aluminium A356/Sil...IRJET- Studies on Drilling Characteristics of Heat Treated Aluminium A356/Sil...
IRJET- Studies on Drilling Characteristics of Heat Treated Aluminium A356/Sil...
 
IRJET- Static and Thermal Analysis of Piston with Different Thermal Coatings
IRJET- Static and Thermal Analysis of Piston with Different Thermal CoatingsIRJET- Static and Thermal Analysis of Piston with Different Thermal Coatings
IRJET- Static and Thermal Analysis of Piston with Different Thermal Coatings
 
Optimization of Precast Post-tensioned Concrete I-Girder Bridge
Optimization of Precast Post-tensioned Concrete I-Girder BridgeOptimization of Precast Post-tensioned Concrete I-Girder Bridge
Optimization of Precast Post-tensioned Concrete I-Girder Bridge
 
IRJET-V3I5313
IRJET-V3I5313IRJET-V3I5313
IRJET-V3I5313
 
IRJET - Mathematical Analysis of Angular Distortion on GTA Welded Hot Rolled ...
IRJET - Mathematical Analysis of Angular Distortion on GTA Welded Hot Rolled ...IRJET - Mathematical Analysis of Angular Distortion on GTA Welded Hot Rolled ...
IRJET - Mathematical Analysis of Angular Distortion on GTA Welded Hot Rolled ...
 
Analysis of Surface Roughness for Cylindrical Stainless Steel Pipe (Ss 3163) ...
Analysis of Surface Roughness for Cylindrical Stainless Steel Pipe (Ss 3163) ...Analysis of Surface Roughness for Cylindrical Stainless Steel Pipe (Ss 3163) ...
Analysis of Surface Roughness for Cylindrical Stainless Steel Pipe (Ss 3163) ...
 
20320140507005
2032014050700520320140507005
20320140507005
 
Fo33988994
Fo33988994Fo33988994
Fo33988994
 

Similar to Irjet v4 i73Cost and Time estimation for Conventional, Aluminium &Tunnel Formwork63

Similar to Irjet v4 i73Cost and Time estimation for Conventional, Aluminium &Tunnel Formwork63 (20)

IRJET- Comparative Analysis for High Rise Building of Tunnel Formwork System ...
IRJET- Comparative Analysis for High Rise Building of Tunnel Formwork System ...IRJET- Comparative Analysis for High Rise Building of Tunnel Formwork System ...
IRJET- Comparative Analysis for High Rise Building of Tunnel Formwork System ...
 
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
 
“ANALYSIS AND DESIGN OF PRE ENGINEERED BUILDING FOR INDUSTRIAL SHED IN CHAKAN”
“ANALYSIS AND DESIGN OF PRE ENGINEERED BUILDING FOR INDUSTRIAL SHED IN CHAKAN”“ANALYSIS AND DESIGN OF PRE ENGINEERED BUILDING FOR INDUSTRIAL SHED IN CHAKAN”
“ANALYSIS AND DESIGN OF PRE ENGINEERED BUILDING FOR INDUSTRIAL SHED IN CHAKAN”
 
IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...
IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...
IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...
 
Comparative analysis of formwork in multistory buildin gv
Comparative analysis of formwork in multistory buildin gvComparative analysis of formwork in multistory buildin gv
Comparative analysis of formwork in multistory buildin gv
 
FORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSIS
FORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSISFORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSIS
FORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSIS
 
RENOVATION OF OLD LIME STONE PORTICO SLAB AT ST THOMAS MOUNT WITH FILLER BLOC...
RENOVATION OF OLD LIME STONE PORTICO SLAB AT ST THOMAS MOUNT WITH FILLER BLOC...RENOVATION OF OLD LIME STONE PORTICO SLAB AT ST THOMAS MOUNT WITH FILLER BLOC...
RENOVATION OF OLD LIME STONE PORTICO SLAB AT ST THOMAS MOUNT WITH FILLER BLOC...
 
Time, Cost , Productivity and Quality Analysis of Precast Buildings
Time, Cost , Productivity and Quality Analysis of Precast BuildingsTime, Cost , Productivity and Quality Analysis of Precast Buildings
Time, Cost , Productivity and Quality Analysis of Precast Buildings
 
IRJET- Ultra High Performance Concrete on Bridges
IRJET- Ultra High Performance Concrete on BridgesIRJET- Ultra High Performance Concrete on Bridges
IRJET- Ultra High Performance Concrete on Bridges
 
IRJET- U-Boot Technology
IRJET-  	  U-Boot TechnologyIRJET-  	  U-Boot Technology
IRJET- U-Boot Technology
 
IRJET- Retrofitting of Reinforced Concrete Structures
IRJET-  	  Retrofitting of Reinforced Concrete StructuresIRJET-  	  Retrofitting of Reinforced Concrete Structures
IRJET- Retrofitting of Reinforced Concrete Structures
 
IRJET- Optimization of Industrial Truss
IRJET- Optimization of Industrial TrussIRJET- Optimization of Industrial Truss
IRJET- Optimization of Industrial Truss
 
IRJET- Comparative Study of Multi-Storey Multi-Span G+4 Building by PEB and C...
IRJET- Comparative Study of Multi-Storey Multi-Span G+4 Building by PEB and C...IRJET- Comparative Study of Multi-Storey Multi-Span G+4 Building by PEB and C...
IRJET- Comparative Study of Multi-Storey Multi-Span G+4 Building by PEB and C...
 
Cost Optimization of R.C Multistory Building
Cost Optimization of R.C Multistory BuildingCost Optimization of R.C Multistory Building
Cost Optimization of R.C Multistory Building
 
Befitting of Natural Fine Aggregate with Waste Slag in Concrete
Befitting of Natural Fine Aggregate with Waste Slag in ConcreteBefitting of Natural Fine Aggregate with Waste Slag in Concrete
Befitting of Natural Fine Aggregate with Waste Slag in Concrete
 
COST EFFECTIVENESS OF HIGH PERFORMANCE CONCRETE
COST EFFECTIVENESS OF HIGH PERFORMANCE CONCRETECOST EFFECTIVENESS OF HIGH PERFORMANCE CONCRETE
COST EFFECTIVENESS OF HIGH PERFORMANCE CONCRETE
 
IRJET- A Review on Design and Development of Circumferential Welding Machine
IRJET- A Review on Design and Development of Circumferential Welding MachineIRJET- A Review on Design and Development of Circumferential Welding Machine
IRJET- A Review on Design and Development of Circumferential Welding Machine
 
Analysis of Formwork in Multistory Building
Analysis of Formwork in Multistory BuildingAnalysis of Formwork in Multistory Building
Analysis of Formwork in Multistory Building
 
Introduction to advanced TUNNEL Formwork system: Case study of ‘Rohan - Abhi...
Introduction to advanced TUNNEL Formwork system: Case study of  ‘Rohan - Abhi...Introduction to advanced TUNNEL Formwork system: Case study of  ‘Rohan - Abhi...
Introduction to advanced TUNNEL Formwork system: Case study of ‘Rohan - Abhi...
 
PARAMETRIC STUDY OF INDUSTRIAL CHIMNEYS
PARAMETRIC STUDY OF INDUSTRIAL CHIMNEYSPARAMETRIC STUDY OF INDUSTRIAL CHIMNEYS
PARAMETRIC STUDY OF INDUSTRIAL CHIMNEYS
 

More from IRJET Journal

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

Artificial intelligence presentation2-171219131633.pdf
Artificial intelligence presentation2-171219131633.pdfArtificial intelligence presentation2-171219131633.pdf
Artificial intelligence presentation2-171219131633.pdf
Kira Dess
 
Final DBMS Manual (2).pdf final lab manual
Final DBMS Manual (2).pdf final lab manualFinal DBMS Manual (2).pdf final lab manual
Final DBMS Manual (2).pdf final lab manual
BalamuruganV28
 
Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...
Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...
Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...
drjose256
 
21P35A0312 Internship eccccccReport.docx
21P35A0312 Internship eccccccReport.docx21P35A0312 Internship eccccccReport.docx
21P35A0312 Internship eccccccReport.docx
rahulmanepalli02
 

Recently uploaded (20)

analog-vs-digital-communication (concept of analog and digital).pptx
analog-vs-digital-communication (concept of analog and digital).pptxanalog-vs-digital-communication (concept of analog and digital).pptx
analog-vs-digital-communication (concept of analog and digital).pptx
 
Artificial intelligence presentation2-171219131633.pdf
Artificial intelligence presentation2-171219131633.pdfArtificial intelligence presentation2-171219131633.pdf
Artificial intelligence presentation2-171219131633.pdf
 
The Entity-Relationship Model(ER Diagram).pptx
The Entity-Relationship Model(ER Diagram).pptxThe Entity-Relationship Model(ER Diagram).pptx
The Entity-Relationship Model(ER Diagram).pptx
 
litvinenko_Henry_Intrusion_Hong-Kong_2024.pdf
litvinenko_Henry_Intrusion_Hong-Kong_2024.pdflitvinenko_Henry_Intrusion_Hong-Kong_2024.pdf
litvinenko_Henry_Intrusion_Hong-Kong_2024.pdf
 
Final DBMS Manual (2).pdf final lab manual
Final DBMS Manual (2).pdf final lab manualFinal DBMS Manual (2).pdf final lab manual
Final DBMS Manual (2).pdf final lab manual
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptx
 
Autodesk Construction Cloud (Autodesk Build).pptx
Autodesk Construction Cloud (Autodesk Build).pptxAutodesk Construction Cloud (Autodesk Build).pptx
Autodesk Construction Cloud (Autodesk Build).pptx
 
Circuit Breakers for Engineering Students
Circuit Breakers for Engineering StudentsCircuit Breakers for Engineering Students
Circuit Breakers for Engineering Students
 
Basics of Relay for Engineering Students
Basics of Relay for Engineering StudentsBasics of Relay for Engineering Students
Basics of Relay for Engineering Students
 
Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...
Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...
Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...
 
21P35A0312 Internship eccccccReport.docx
21P35A0312 Internship eccccccReport.docx21P35A0312 Internship eccccccReport.docx
21P35A0312 Internship eccccccReport.docx
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)
 
Independent Solar-Powered Electric Vehicle Charging Station
Independent Solar-Powered Electric Vehicle Charging StationIndependent Solar-Powered Electric Vehicle Charging Station
Independent Solar-Powered Electric Vehicle Charging Station
 
Raashid final report on Embedded Systems
Raashid final report on Embedded SystemsRaashid final report on Embedded Systems
Raashid final report on Embedded Systems
 
Diploma Engineering Drawing Qp-2024 Ece .pdf
Diploma Engineering Drawing Qp-2024 Ece .pdfDiploma Engineering Drawing Qp-2024 Ece .pdf
Diploma Engineering Drawing Qp-2024 Ece .pdf
 
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024
 
Developing a smart system for infant incubators using the internet of things ...
Developing a smart system for infant incubators using the internet of things ...Developing a smart system for infant incubators using the internet of things ...
Developing a smart system for infant incubators using the internet of things ...
 
CLOUD COMPUTING SERVICES - Cloud Reference Modal
CLOUD COMPUTING SERVICES - Cloud Reference ModalCLOUD COMPUTING SERVICES - Cloud Reference Modal
CLOUD COMPUTING SERVICES - Cloud Reference Modal
 
Instruct Nirmaana 24-Smart and Lean Construction Through Technology.pdf
Instruct Nirmaana 24-Smart and Lean Construction Through Technology.pdfInstruct Nirmaana 24-Smart and Lean Construction Through Technology.pdf
Instruct Nirmaana 24-Smart and Lean Construction Through Technology.pdf
 
History of Indian Railways - the story of Growth & Modernization
History of Indian Railways - the story of Growth & ModernizationHistory of Indian Railways - the story of Growth & Modernization
History of Indian Railways - the story of Growth & Modernization
 

Irjet v4 i73Cost and Time estimation for Conventional, Aluminium &Tunnel Formwork63

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072 Cost and Time estimation for Conventional, Aluminium &Tunnel Formwork 1Prof. Ashish P. Waghmare, 2 Renuka S. Hangarge 1 Prof & PG Co-ordinator, Dept. Of Civil Engineering, Dr. D Y Patil SOET, Lohgaon, Pune 412105 2 Student M.E., (C&M) Civil Department, Dr. D Y Patil SOET, Lohgaon, Pune 412105 ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract - Due to increase in inhabitants, people started to construct the dwelling buildings. At the early days buildings were constructed using conventional type form work system where wooden planks, runners, poles were used for the form work. With the development of technology, man tend to use plywood in its place of planks, steel jacks forsupportinstead of wooden poles. The below study is carried out to compare different Formwork systems on the basis of Time & Cost. Key Words: Conventional Formwork, Tunnel Formwork, Aluminium Formwork, Construction Cost, time 1. INTRODUCTION The expenditure on formwork is occupyinga majorpart in the total cost of construction. Therefore the selection and proper planning the system of form work will reduce the cost of construction, time of construction, the wastages and labour requirement which reduces the total cost of construction. Formwork systems are among the key factors determining the success of a construction projectinterms of speed, quality, cost and safety of the works. Construction industry is seen to be able to play a bigger role into a sustainable society by offering sustainable construction. Formwork system is one of the important construction methods in building construction 2. DATA COLLECTION PhotographatTunnelFormworksiteduringtheconstruction. Conventional Building during construction is as below Aluminium Formwork during construction is as below Case study1: Residential building with G+12 floors (Aluminium Formwork is used) Case study2: Residential building with G+12 floors (Conventional Formwork is used) Case Study3: Residential building with G+12 floors (Tunnel Formwork is used) Case study 1 & 2 are of same site & each case study contains four buildings of G+12 floors. © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1704
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072 Table 3.1: Al-Formwork 1st Building cost Item Amount Concrete Quantity 16625986.2 Steel Quantity 26773524 Formwork Quantity 18449026.2 Gypsum 8674220.16 Labour Rate Concrete rate 4835298 Steel 8924508 Shuttering 9056794.68 Deshuttering 402524.208 Gypsum 4486665.6 Total 94228547.05 Table 3.2: Conventional Formwork 1st Building cost Item Amount Concrete Quantity 11552673.19 Steel Quantity 19178505 Formwork Quantity 2375319.8 Brickwork 12199804.2 Internal Plaster 8674220.16 External Plaster 1380380.4 Labour Charges Concrete casting 2938492.8 Steel 6392835 Shuttering 7125959.4 Deshuttering 244318.608 Brickwork 4267870.64 Internal Plaster 4539043.328 External Plaster 1060860.82 81930283.34 3 .DATA ANALYSIS Total Cost of four Conventional formwork building = 327721133.4 Rs Total Cost of four Al-Formwork building = 321567109.6 Rs Total Difference = 6154023.768 Rs This is the cost with 48 repetitions of AluminiumFormwork. With proper use and handling these can be used up to 120 repetitions. So, out of 120 only 48 repetitions are used. Hence cost savings for remaining life of Aluminium Formwork is = (120-48)* Initial Investment in Formwork/120 =1,10,69,415.3 Rs. Currently cost of Al-Formwork building =321567109.6- 11069415.3= 31,04,97,693.4 Rs. Cost of Conventional Formwork Building= 327721133.4 Rs. Cost of Conventional Formwork for 81439 m² Skin area construction = 32,77,21,133.4 Rs. Currently cost of Al-Formwork for 134174.736 m² Skinarea construction= 31,04,97,693.4 Rs. Cost of Tunnel Formwork for 81721 m² Skin area construction = 13,12,58,400 Rs. Cost for 10000 m² Skin area construction for Conventional FW= 40,24,130.12 Rs. Cost for 10000 m² Skin area construction for Aluminium FW = 23,14,129.34 Rs. Cost for 10000 m² Skin area construction for Tunnel FW= 16,06,177.11 Rs. Total Days required forConventionalFormworkBuilding construction=816 Total Days required for Aluminium Formwork Building construction=484 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1705
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072 Total Days difference = 332 Days Time for Conventional Formwork for 81439 m² Skin area construction = 816 Days. Time for Al-Formwork for 134174.736 m² Skin area construction= 484 Days Time for Tunnel Formwork for 81721 m² Skin area construction = 220 Days Time for 10000 m² Skin area construction for Conventional FW= 100.2 Days Timefor10000 m² Skin areaconstruction forAluminium FW= 36.07 Days Timefor10000m²SkinareaconstructionforTunnelFW= 26.92 Days 4. CONCLUSIONS Following Table gives the idea about the cost & time taken by Conventional, Aluminium & Tunnel Formwork system for construction of 10,000 m² of skin area. Item Conventional Formwork Aluminium Formwork Tunnel formwork Cost for construction of 10,000 m² of Concrete area in INR 40,24,130.12 23,14,129.34 16,06,177.11 Time for construction of 10,000 m² of Concrete area in Days 100.2 36.07 26.92  From the results obtained we can conclude that, Aluminium formwork is Cost effective in comparison with Conventional Formwork.  Aluminium formwork is better for use in the constructions, where Time effective formwork is necessary, than Conventional Formwork.  Tunnel Formwork is the most time & cost effective formwork among Conventional, Aluminium & Tunnel Formwork.  Also, the duration of the project can be reduced largely with the use of Tunnel formwork where 1-4 days cycle is possible. So this is the fastest formwork system compared to conventional & Aluminium formwork.  Time saving is equal to money saving. So, even though initial investment is large, Tunnel Formwork can be suggested for faster construction.  If the number of repetitions are more for residential buildings, then Aluminium formwork is suggested as it savesthe time & cost of finishing & shuttering. © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1706
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072 REFERENCES [1] Miss. Patil Dhanashri Suryakant1, Prof. Desai D B2 1 (Student, Civil Department, Dr .J Magdum College Of Engineering Jaysingpur, Maharashtra) 2 (HOD, Department Of Civil Engg, Dr. J Magdum College Of Engineering Jaysingpur, Maharashtra) “Emerging Trends in Formwork - Cost Analysis & Effectiveness of Mivan Formwork over the Conventional Formwork” [2] NINJAL M PAREKH 1, 2BHUPENDRA M MARVADI, 3UMANG PATEL “COMPARATIVE STUDIES OF CONSTRUCTION TECHNIQUES” (CONVENTIONAL TECHNIQUEVSALUMINIUMFORMWORK TECHNIQUES) 1 Student, M.E. Infrastructure Engineering, Dept. of Civil Engineering, L.D.R.P. Institute of Technology and Research, Gandhinagar-382015, Gujarat. 2,3Assistant Professor, Dept. of Civil Engineering, L.D.R.P. Institute of Technology and Research, Gandhinagar-382015, Gujarat. [4] Prathul U1 , 2Leeladhar Pammar1PGstudent,2Assistant Professor 1, 2Department of Civil Engineering, NMAMIT, Nitte “Analysis of Productivity by Comparing Mivan and Conventional Formwork “ [5] Sandip.P.Pawar1 , P.M.Atterde2 1P.G. Student Dept. of civil Engineering SSGBCOET Bhusawal Maharashtra 2Guide, dept. of civil Engineering SSGBCOET Bhusawal Maharashtra “COMPARATIVE ANALYSIS OF FORMWORK IN MULTISTORY BUILDING” IJRET: International Journal of Research in Engineeringand Technology eISSN: 2319-1163 | pISSN: 2321-7308 Volume: 03 Special Issue: 09 | NCETCE-2014|June-2014,Available@ http://www.ijret.org 22 [6] Tejas D. Aradhye1 , Emeritus M. R. Apte2 “STUDY OF ADVANCED TUNNEL FORMWORK SYSTEM IN HIGH RISE BUILDING” IJRET: International Journal of Research in Engineeringand Technology eISSN: 2319-1163 | pISSN: 2321-7308 [7] The Canadian Society for Civil Engineering 5th International/11th Construction Specialty Conference, At Vancouver “Role of Formwork Systems in High-Rise Construction” July2015 DOI:0.13140/RG.2.3386.6083 Conference: ICSC15: BIOGRAPHIES Prof Ashish P. Waghmare , Prof & PG Co-ordinator, Dept. Of Civil Engineering, Dr. D Y Patil SOET, Lohgaon, Pune 412105 Student M.E., (C&M) Civil Department, Dr. D Y Patil SOET, Lohgaon, Pune 412105 Renuka S. Hangarge, © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1707