International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 10 Issue: 05 | May 2023 www.irjet.net p-ISSN: 2395-0072
© 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 1749
FORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND
QUALITY ANALYSIS
Ar. Swetha. D1, Ar. Radhika2
1 Post Graduate Student, M. Arch – Construction Project Management, Faculty of Architecture, Dr. MGR
Educational and Research Institute, Maduravoyal, Chennai
2 Head of the department, M. Arch – Construction Project Management, Faculty of Architecture, Dr. MGR
Educational and Research Institute, Maduravoyal, Chennai
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract - This paper describes about the formwork
technology used in high- rise building suitable for Indian
construction. By utilizing new technologies in formwork,
construction can now achieve the casting oflargerelements in
a single pour. This advancement not only minimizes time and
labor needed but also outperforms conventional methods.
Formwork technology is based on the cost, time, andqualityof
project delivery. The study is about advantages of aluminium
formwork and tunnel formwork with conventional system in
terms of cost and quality analysis. Traditional approaches
can’t keep up the demand of infrastructuralfacilitieswith high
degree of quality control & assurance. Case studies with two
different technology is done, its cost and duration are
compared. This study is focusses on the two different
conducted on a construction site in Chennai. Further, the real
time cost duration and labor savings in the use of aluminium
formwork is demonstrated in a G+21, 8 tower building.
Key Words: Aluminium formwork, cost, tunnel formwork,
comparison of quality analysis, economy, time saving.
1. INTRODUCTION
Formwork in construction refers to the utilization of
supportive structures and molds to shape concrete into
desired structures. Concrete is poured into these molds,
which can be constructed from various materials such as
steel, wood, aluminum, or pre-made forms. A range of
material options is available for constructing the formwork.
The selection of formwork material is based on various
factors, including cost, project requirements, and the type of
structure involved. This study is to compare conventional
with aluminium and tunnel specifically related to high rise
building
1.1 TYPES OF FORMWORKS:
Timber has been the prevailing choice of material for
formwork thus far. Nonetheless, due to diminishing forest
reserves and escalating timber costs, the adoption of
alternative materials like plywood and steel has gained
prominence. Moreover, plastics and fiberglass haverecently
emerged as viable options for prefabricating formwork. The
selection of material depends on factors such as the
construction's characteristics, material availability,andcost.
Additionally, project constraints such as overall cost and
completion time significantlyinfluencethechoiceofmaterial
for formwork. Timber, Steel Aluminum, Plastics, Fabric are
common materials used in formwork. The formwork used in
high-rise construction are timber, aluminiumformwork and
tunnel formwork.
1.2 ALUMINIUM FORMWORK:
The utilization of an aluminum formwork system enhances
the construction's quality while simultaneously reducing
both time and costs. The cost-effectiveness of the formwork
becomes evident when it is utilized for numerous
construction cycles. As aluminium can be used around 250
repetations. The primary drawback of aluminum
forms is that once the formwork is manufactured, no
changes can be made. The system typically operates on a
four-day cycle, as outlined below:
Day 1 - The initial task involves erecting vertical
reinforcement bars and one side ofthevertical formwork for
either an entire floor or a portion of a floor.
Day 2 - The subsequent step entails erecting the secondside
of the vertical formwork and installing formwork for the
floor.
Day 3 - Involves the placement of reinforcementbarsforthe
floor slab and the casting of walls and the slab.
Day 4 - The vertical formwork panels are removed after 24
hours, while the support props remain in place for seven
days, and the floor slabs formwork remains in place for 2.5
days.
1.3 TUNNEL FORMWORK:
A tunnel is a specially fabricatedstructure madeofstructural
steel, designed in the shape of an L and resembling a half-
room in size. Its primary function is to facilitatetheseamless
pouring of reinforced concrete (RCC) walls and floor slabs,
allowing them to form a unifiedanduninterruptedstructure.
Two half tunnels are combined to create a full tunnel with
dimensions equivalent to that of a room. This innovative
approach ensures efficient construction with a focus on
speed, quality, and precision whileofferingtheadvantagesof
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 10 Issue: 05 | May 2023 www.irjet.net p-ISSN: 2395-0072
© 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 1750
on-site construction, flexibility, and cost-effectiveness. The
slab cycle for this system is 24 hours. However, it should be
noted that each tunnel is custom-made and highly modular,
limiting the possibility of design changes.
Figure 1 Tunnel Formwork Process
2. METHODOLOGY:
The study is to identify the different types of formworks
used in high-rise building. The literature and net study are
done to collect data about the most efficiently used
formwork in high-rise. Comparative study is done between
aluminium, tunnel and conventional formwork. For the
proposed site aluminium formwork is implemented,itscost,
quality and time schedule analysis are done and the end
results are compared with conventional formwork
technology.
3. LITERATURE REVIEW:
The review of journal papers involves a comparison of
different types of formwork for high-rise buildings. The
study suggests that, in terms of cost and availability,
aluminium formwork is well-suited for construction sites in
India. This is due to its design flexibility, minimal machinery
usage, and the ability to utilize unskilled labor, despite
having fewer repetitions compared to tunnel formwork. In
contrast, tunnel formwork necessitates heavy machinery, a
significant initial investment, and skilled labor.
Consequently, the aluminium formwork is economically
advantageous for high-rise building projects in India.
ACTIVITY CONVENTIONAL ALUMINIUM TUNNEL
Capital cost less
Cost of
shuttering
material is
high
Cost of
shuttering
material and
other related
machinery is
very high
Speed of
work
slow fast fast
Accuracy and
Quality of
construction
less Good
accuracy
Good
accuracy
Internal/exte
rnal
Plastering
required
required Not required Not required
Cycle time of
RCC work
20 days 10-15 days 1 day with
proper
infrastructur
e and other
ancillary
machineries
No of
repetition of
shuttering
material
12-15 200-250 500
Cost of
shuttering
Around Rs 400
to 500 / Sq.ft of
shuttering floor
area
Around Rs
8000 to
10000 /Sq.ft
of shuttering
floor area
Around Rs
12,000 to
14,000 / Sq.ft
of shuttering
floor area
3.1 CASE STUDY 1:
The project involves the construction of a high-rise
residential building on a 3.88-acre site, consisting of 6
towers, 2 basements, stilt, and G+21 floors. The total project
cost amounts to 218.72 crores, employing an aluminium
formwork system.
For this project, the shear walls are 200 mm thick, while the
non-shear walls are 10 mm thick.Theformwork isfilledwith
self-compacting concrete to fill the voids [4]. By utilizing
thinner wall sections, the usable area is increased by
approximately 5% through the adoption of shear wall
systems. Additionally, maintenance costs arereduceddueto
improved quality and the elimination of brickwork and
plaster [5]. All services are pre-planned, and the cost of
construction for one floor, includingtheprovisionandlaying
of RCC M-30, self-compacting concrete, steel reinforcement,
and aluminium formwork, amounts to 44,00,258
The construction time schedule for each floor using the
aluminium formwork system is 620 days. The floorcycle is4
days per floor, employing a box-type framework structure.
The dimensional accuracy is high, and the surface finish
allows for direct painting after putty application. From an
economic perspective, the fund flow associated with the
aluminium formwork system is favorable. The waste
production when using aluminium formwork is moderate,
and the formwork can be repeated up to 200 times.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 10 Issue: 05 | May 2023 www.irjet.net p-ISSN: 2395-0072
© 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 1751
Figure 2 Site Map
3.2 CASE STUDY 2:
The project entails the construction of a high-rise residential
building on a 3.88-acre site, comprising 3 towers with G+18
floors. The total project cost amounts to Rs. 117,32,17,750,
employing the tunnel formwork system.
Considering the project's location in the bustling premium
residential hub of Chennai metropolitan city, three distinct
unconventional formwork technologies have been adopted
to leverage their specific advantages [11]. While tunnel
formwork allows for the construction of large, multi-story,
and cellular structures [9],theproject'scostincreaseddueto
the utilization of expensive equipment and skilled labor.
However, tunnel formwork lacks the design flexibility
necessary for incorporating basement floors in the towers,
making it less preferable for efficient high-rise building
construction when compared to aluminium formwork.
4. PROJECT PROPOSAL: DOSHI RISINGTON:
The proposal for Phase 2 construction in DOSHI RISETON
suggests the utilization of aluminium formwork, as outlined
in the provided table. The conventional construction
approach for Phase 2 involves approximately 10 towers,
encompassing 2 basements, stilt, and G+21 floors.
By adopting the aluminium formwork system, different
design phases within each tower can be efficiently executed.
The estimated time duration for the conventional method is
around 3 years, whereasaluminiumformconstructionoffers
the advantagesofhigh-qualityconstruction,increasedspeed,
and reasonable cost [5]. This technology holds significant
potential for addressing India's growing population's need
for affordable housing.
Moreover, the number of repetitions with aluminium
formwork increases, making the initial investment more
profitable [5]. Unlike the conventional method where the
number of repetitions is lower, leading to an increase incost
per square meter after the 16th floor slab cycle. This
includes rising costs for shuttering formwork, brickwork,
and plastering. The break point forthe aluminiumformwork
occurs after the 16th floor of the tower, and repetitions
continue for the remaining part of the tower, ensuring a
profitable initial investment..
Figure 3 Cost Analysis
Time schedule for 1 floor using aluminum formwork:
INSTALLATION OF ALUMINIUM OF PRE-CONCRETE
ACTIVITIES
SI.NO PROCESS
DURATION
(HOURS)
1 level surveys 5
2 setting out data 5
3 control of deviations 5
4 enforcement wall panel 15
5
enforcement column
panel 5
6
enforcement staircase
panel 3
7 enforcement beam level 10
8 enforcement slab level 20
9 setting kickers 10
10
lay oil at the panel &
kickers 9
ERECTION OF ALUMINIUM OF POST-CONCRETE
ACTIVITIES
11
erection wall and column
panel 10
12
erection beam and slab
panel 15
13
clean, transport and stack
panel 10
14 erection of kickers 10
TOTAL DURATION 132
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 10 Issue: 05 | May 2023 www.irjet.net p-ISSN: 2395-0072
© 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 1752
The duration for 1 floor of 870 Sq.m is 132 hrs. using
aluminium formwork.Ittakesabout126daysapproximately
to complete tower A.
Time schedule for 1 floor using conventional formwork:
INSTALLATION OF CONVENTIONAL
FORMWORK OF PRE-CONCRETE ACTIVITIES
SI.NO PROCESS
DURATION
(HOURS)
1 level surveys 15
2 setting out data 5
3 control of deviations 10
4
enforcement wall
wood 150
5
enforcement column
wood 80
6
enforcement staircase
wood 60
7
enforcement beam
wood 75
8
enforcement slab
wood 75
9
setting- up other
components 100
10
lay oil at the panel &
kickers 25
ERECTION OF CONVENTIONAL FORMWORK OF
POST-CONCRETE ACTIVITIES
11
dismantle wood
column 15
12 dismantle wood wall 50
13 dismantle wood beam 20
14 dismantle wood slab 40
15
dismantle other
components 25
16 clean up leftovers 20
TOTAL DURATION 765
The duration for 1 floor of 870 Sq.m is 765 hrs. using
conventional formwork. It takes about 651 days
approximately to complete tower
5. CONCLUSIONS
The aluminium formwork presents a favorable option for
achieving timely completion of construction with maximum
efficiency. Gathering information from literature and case
studies will prove beneficial for selecting the appropriate
formwork in future projects. Additionally, this approach
helps minimize construction waste associated with
formwork usage.
Although the aluminium system formwork incurs a higher
initial cost, it demonstrates its cost-effectiveness when the
number of repetitions falls between 150 and 200 in the
construction of high-rise buildings. In contrast, employing
contemporary conventional formwork, which is the least
expensive type and requires moretime,resultsinthehighest
total expenditure. For the proposed site, utilizing
conventional formwork leads to a 25% reduction in both
cost and time.
6. REFERENCES
[1] Prof. Zen Raut, Mayur S. Meshram Analysis and
Comparison of Mivan Formwork System with Conventional
Formwork System
[2] Mayur Sanjay Lodha Comparative Analysis of
Conventional Formwork and Mivan Formwork based on
Duration and Cost
[3] Jaya Surya R Evaluation of Different Kinds of Formwork
Systems in Indian Construction Industry
[4] Danish Sadruddin Ansari, COMPARATIVE STUDIES OF
CONSTRUCTION TECHNIQUES (CONVENTIONAL
TECHNIQUE VS ALUMINIUM FORMWORK TECHNIQUES)
[5] Ar. Sowndharya ANALYISING ADVANCED FORMWORK
SYSTEM FOR HIGH RISE BUILDING CONSTRUCTION
[6] Loganathan ALUMINIUMFORMWORKSYSTEMUSINGIN
HIGHRISE BUILDINGS CONSTRUCTION
[7] Miss Manik Moholkar Productivity Analysis of Building
Construction Using Mivan Formwork June 2019 | IJIRT |
Volume 6 Issue 1 | ISSN: 2349-6002
[8] Miss. Renuka Hangarge Comparison of Conventional,
Aluminium and Tunnel Formwork
[9] Vallabhy .S Advanced Technology for Speedy
Construction (Tunnel Formwork)
[10] Asst. Prof. A. R. Chavan A REVIEW ON FAST TRACK
CONSTRUCTION USING MODERN FORMWORK SYSTEMS
[11] Mr. Manas A. Shalgar IntroductiontoadvancedTUNNEL
Formwork system: Case study of ‘Rohan - Abhilasha’

More Related Content

Similar to FORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSIS

Advance section properties_for_students
Advance section properties_for_studentsAdvance section properties_for_students
Advance section properties_for_studentsChhay Teng
 
Introduction to advanced TUNNEL Formwork system: Case study of ‘Rohan - Abhi...
Introduction to advanced TUNNEL Formwork system: Case study of  ‘Rohan - Abhi...Introduction to advanced TUNNEL Formwork system: Case study of  ‘Rohan - Abhi...
Introduction to advanced TUNNEL Formwork system: Case study of ‘Rohan - Abhi...IRJET Journal
 
Development OF Low Cost Durable Precast Compound Wall
Development OF Low Cost Durable Precast Compound WallDevelopment OF Low Cost Durable Precast Compound Wall
Development OF Low Cost Durable Precast Compound WallIRJET Journal
 
Advanced Tunnel Form Construction Technique, Case Study of Rohan-Abhilasha, ...
Advanced Tunnel Form Construction Technique, Case Study of  Rohan-Abhilasha, ...Advanced Tunnel Form Construction Technique, Case Study of  Rohan-Abhilasha, ...
Advanced Tunnel Form Construction Technique, Case Study of Rohan-Abhilasha, ...Mary Montoya
 
IRJET- Dynamic Wind Analysis of RC Bundled Tube in Tube Structure using E...
IRJET-  	  Dynamic Wind Analysis of RC Bundled Tube in Tube Structure using E...IRJET-  	  Dynamic Wind Analysis of RC Bundled Tube in Tube Structure using E...
IRJET- Dynamic Wind Analysis of RC Bundled Tube in Tube Structure using E...IRJET Journal
 
Application of Advanced formwork system for High rise buildings in Chennai, I...
Application of Advanced formwork system for High rise buildings in Chennai, I...Application of Advanced formwork system for High rise buildings in Chennai, I...
Application of Advanced formwork system for High rise buildings in Chennai, I...IRJET Journal
 
IRJET- Analytical Study of High Volume Fly Ash Concrete Bubble Deck Slab
IRJET- Analytical Study of High Volume Fly Ash Concrete Bubble Deck SlabIRJET- Analytical Study of High Volume Fly Ash Concrete Bubble Deck Slab
IRJET- Analytical Study of High Volume Fly Ash Concrete Bubble Deck SlabIRJET Journal
 
IRJET - Sesismic Analysis of Multistorey Building using ETABS
IRJET -  	  Sesismic Analysis of Multistorey Building using ETABSIRJET -  	  Sesismic Analysis of Multistorey Building using ETABS
IRJET - Sesismic Analysis of Multistorey Building using ETABSIRJET Journal
 
IRJET- Comparative Study of Rc Structure with Different Infill Materials
IRJET-  	  Comparative Study of Rc Structure with Different Infill MaterialsIRJET-  	  Comparative Study of Rc Structure with Different Infill Materials
IRJET- Comparative Study of Rc Structure with Different Infill MaterialsIRJET Journal
 
An Attempt of Green Building Construction Using GFRG Panels
An Attempt of Green Building Construction Using GFRG PanelsAn Attempt of Green Building Construction Using GFRG Panels
An Attempt of Green Building Construction Using GFRG PanelsIRJET Journal
 
“COMPARATIVE STUDY ANALYSIS OF MULTI STOREYED RC FRAMED BUILDINGS WITH AAC BL...
“COMPARATIVE STUDY ANALYSIS OF MULTI STOREYED RC FRAMED BUILDINGS WITH AAC BL...“COMPARATIVE STUDY ANALYSIS OF MULTI STOREYED RC FRAMED BUILDINGS WITH AAC BL...
“COMPARATIVE STUDY ANALYSIS OF MULTI STOREYED RC FRAMED BUILDINGS WITH AAC BL...IRJET Journal
 
“ANALYSIS AND DESIGN OF PRE ENGINEERED BUILDING FOR INDUSTRIAL SHED IN CHAKAN”
“ANALYSIS AND DESIGN OF PRE ENGINEERED BUILDING FOR INDUSTRIAL SHED IN CHAKAN”“ANALYSIS AND DESIGN OF PRE ENGINEERED BUILDING FOR INDUSTRIAL SHED IN CHAKAN”
“ANALYSIS AND DESIGN OF PRE ENGINEERED BUILDING FOR INDUSTRIAL SHED IN CHAKAN”IRJET Journal
 
IRJET- Comparative Study of Multi-Storey Multi-Span G+4 Building by PEB and C...
IRJET- Comparative Study of Multi-Storey Multi-Span G+4 Building by PEB and C...IRJET- Comparative Study of Multi-Storey Multi-Span G+4 Building by PEB and C...
IRJET- Comparative Study of Multi-Storey Multi-Span G+4 Building by PEB and C...IRJET Journal
 
Performance of ibs precast concrete beam column connections under earthquake ...
Performance of ibs precast concrete beam column connections under earthquake ...Performance of ibs precast concrete beam column connections under earthquake ...
Performance of ibs precast concrete beam column connections under earthquake ...Ramin Vaghei
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System ashleyyeap
 
IRJET- Study of Pre-Engineered Building
IRJET-  	  Study of Pre-Engineered BuildingIRJET-  	  Study of Pre-Engineered Building
IRJET- Study of Pre-Engineered BuildingIRJET Journal
 
SELECTION OF FORMWORKS FOR BUILDING CONSTRUCTION
SELECTION OF FORMWORKS FOR BUILDING CONSTRUCTIONSELECTION OF FORMWORKS FOR BUILDING CONSTRUCTION
SELECTION OF FORMWORKS FOR BUILDING CONSTRUCTIONIRJET Journal
 
Irjet v4 i73Cost and Time estimation for Conventional, Aluminium &Tunnel Form...
Irjet v4 i73Cost and Time estimation for Conventional, Aluminium &Tunnel Form...Irjet v4 i73Cost and Time estimation for Conventional, Aluminium &Tunnel Form...
Irjet v4 i73Cost and Time estimation for Conventional, Aluminium &Tunnel Form...IRJET Journal
 
IRJET- Composite Floors using Profiled Deck Sheet in Steel Structure
IRJET- Composite Floors using Profiled Deck Sheet in Steel StructureIRJET- Composite Floors using Profiled Deck Sheet in Steel Structure
IRJET- Composite Floors using Profiled Deck Sheet in Steel StructureIRJET Journal
 
Review Paper on Analysis and Design of Steel Truss by using Angle and Tube Se...
Review Paper on Analysis and Design of Steel Truss by using Angle and Tube Se...Review Paper on Analysis and Design of Steel Truss by using Angle and Tube Se...
Review Paper on Analysis and Design of Steel Truss by using Angle and Tube Se...IRJET Journal
 

Similar to FORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSIS (20)

Advance section properties_for_students
Advance section properties_for_studentsAdvance section properties_for_students
Advance section properties_for_students
 
Introduction to advanced TUNNEL Formwork system: Case study of ‘Rohan - Abhi...
Introduction to advanced TUNNEL Formwork system: Case study of  ‘Rohan - Abhi...Introduction to advanced TUNNEL Formwork system: Case study of  ‘Rohan - Abhi...
Introduction to advanced TUNNEL Formwork system: Case study of ‘Rohan - Abhi...
 
Development OF Low Cost Durable Precast Compound Wall
Development OF Low Cost Durable Precast Compound WallDevelopment OF Low Cost Durable Precast Compound Wall
Development OF Low Cost Durable Precast Compound Wall
 
Advanced Tunnel Form Construction Technique, Case Study of Rohan-Abhilasha, ...
Advanced Tunnel Form Construction Technique, Case Study of  Rohan-Abhilasha, ...Advanced Tunnel Form Construction Technique, Case Study of  Rohan-Abhilasha, ...
Advanced Tunnel Form Construction Technique, Case Study of Rohan-Abhilasha, ...
 
IRJET- Dynamic Wind Analysis of RC Bundled Tube in Tube Structure using E...
IRJET-  	  Dynamic Wind Analysis of RC Bundled Tube in Tube Structure using E...IRJET-  	  Dynamic Wind Analysis of RC Bundled Tube in Tube Structure using E...
IRJET- Dynamic Wind Analysis of RC Bundled Tube in Tube Structure using E...
 
Application of Advanced formwork system for High rise buildings in Chennai, I...
Application of Advanced formwork system for High rise buildings in Chennai, I...Application of Advanced formwork system for High rise buildings in Chennai, I...
Application of Advanced formwork system for High rise buildings in Chennai, I...
 
IRJET- Analytical Study of High Volume Fly Ash Concrete Bubble Deck Slab
IRJET- Analytical Study of High Volume Fly Ash Concrete Bubble Deck SlabIRJET- Analytical Study of High Volume Fly Ash Concrete Bubble Deck Slab
IRJET- Analytical Study of High Volume Fly Ash Concrete Bubble Deck Slab
 
IRJET - Sesismic Analysis of Multistorey Building using ETABS
IRJET -  	  Sesismic Analysis of Multistorey Building using ETABSIRJET -  	  Sesismic Analysis of Multistorey Building using ETABS
IRJET - Sesismic Analysis of Multistorey Building using ETABS
 
IRJET- Comparative Study of Rc Structure with Different Infill Materials
IRJET-  	  Comparative Study of Rc Structure with Different Infill MaterialsIRJET-  	  Comparative Study of Rc Structure with Different Infill Materials
IRJET- Comparative Study of Rc Structure with Different Infill Materials
 
An Attempt of Green Building Construction Using GFRG Panels
An Attempt of Green Building Construction Using GFRG PanelsAn Attempt of Green Building Construction Using GFRG Panels
An Attempt of Green Building Construction Using GFRG Panels
 
“COMPARATIVE STUDY ANALYSIS OF MULTI STOREYED RC FRAMED BUILDINGS WITH AAC BL...
“COMPARATIVE STUDY ANALYSIS OF MULTI STOREYED RC FRAMED BUILDINGS WITH AAC BL...“COMPARATIVE STUDY ANALYSIS OF MULTI STOREYED RC FRAMED BUILDINGS WITH AAC BL...
“COMPARATIVE STUDY ANALYSIS OF MULTI STOREYED RC FRAMED BUILDINGS WITH AAC BL...
 
“ANALYSIS AND DESIGN OF PRE ENGINEERED BUILDING FOR INDUSTRIAL SHED IN CHAKAN”
“ANALYSIS AND DESIGN OF PRE ENGINEERED BUILDING FOR INDUSTRIAL SHED IN CHAKAN”“ANALYSIS AND DESIGN OF PRE ENGINEERED BUILDING FOR INDUSTRIAL SHED IN CHAKAN”
“ANALYSIS AND DESIGN OF PRE ENGINEERED BUILDING FOR INDUSTRIAL SHED IN CHAKAN”
 
IRJET- Comparative Study of Multi-Storey Multi-Span G+4 Building by PEB and C...
IRJET- Comparative Study of Multi-Storey Multi-Span G+4 Building by PEB and C...IRJET- Comparative Study of Multi-Storey Multi-Span G+4 Building by PEB and C...
IRJET- Comparative Study of Multi-Storey Multi-Span G+4 Building by PEB and C...
 
Performance of ibs precast concrete beam column connections under earthquake ...
Performance of ibs precast concrete beam column connections under earthquake ...Performance of ibs precast concrete beam column connections under earthquake ...
Performance of ibs precast concrete beam column connections under earthquake ...
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System
 
IRJET- Study of Pre-Engineered Building
IRJET-  	  Study of Pre-Engineered BuildingIRJET-  	  Study of Pre-Engineered Building
IRJET- Study of Pre-Engineered Building
 
SELECTION OF FORMWORKS FOR BUILDING CONSTRUCTION
SELECTION OF FORMWORKS FOR BUILDING CONSTRUCTIONSELECTION OF FORMWORKS FOR BUILDING CONSTRUCTION
SELECTION OF FORMWORKS FOR BUILDING CONSTRUCTION
 
Irjet v4 i73Cost and Time estimation for Conventional, Aluminium &Tunnel Form...
Irjet v4 i73Cost and Time estimation for Conventional, Aluminium &Tunnel Form...Irjet v4 i73Cost and Time estimation for Conventional, Aluminium &Tunnel Form...
Irjet v4 i73Cost and Time estimation for Conventional, Aluminium &Tunnel Form...
 
IRJET- Composite Floors using Profiled Deck Sheet in Steel Structure
IRJET- Composite Floors using Profiled Deck Sheet in Steel StructureIRJET- Composite Floors using Profiled Deck Sheet in Steel Structure
IRJET- Composite Floors using Profiled Deck Sheet in Steel Structure
 
Review Paper on Analysis and Design of Steel Truss by using Angle and Tube Se...
Review Paper on Analysis and Design of Steel Truss by using Angle and Tube Se...Review Paper on Analysis and Design of Steel Truss by using Angle and Tube Se...
Review Paper on Analysis and Design of Steel Truss by using Angle and Tube Se...
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 

Recently uploaded (20)

What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 

FORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSIS

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 10 Issue: 05 | May 2023 www.irjet.net p-ISSN: 2395-0072 © 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 1749 FORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSIS Ar. Swetha. D1, Ar. Radhika2 1 Post Graduate Student, M. Arch – Construction Project Management, Faculty of Architecture, Dr. MGR Educational and Research Institute, Maduravoyal, Chennai 2 Head of the department, M. Arch – Construction Project Management, Faculty of Architecture, Dr. MGR Educational and Research Institute, Maduravoyal, Chennai ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract - This paper describes about the formwork technology used in high- rise building suitable for Indian construction. By utilizing new technologies in formwork, construction can now achieve the casting oflargerelements in a single pour. This advancement not only minimizes time and labor needed but also outperforms conventional methods. Formwork technology is based on the cost, time, andqualityof project delivery. The study is about advantages of aluminium formwork and tunnel formwork with conventional system in terms of cost and quality analysis. Traditional approaches can’t keep up the demand of infrastructuralfacilitieswith high degree of quality control & assurance. Case studies with two different technology is done, its cost and duration are compared. This study is focusses on the two different conducted on a construction site in Chennai. Further, the real time cost duration and labor savings in the use of aluminium formwork is demonstrated in a G+21, 8 tower building. Key Words: Aluminium formwork, cost, tunnel formwork, comparison of quality analysis, economy, time saving. 1. INTRODUCTION Formwork in construction refers to the utilization of supportive structures and molds to shape concrete into desired structures. Concrete is poured into these molds, which can be constructed from various materials such as steel, wood, aluminum, or pre-made forms. A range of material options is available for constructing the formwork. The selection of formwork material is based on various factors, including cost, project requirements, and the type of structure involved. This study is to compare conventional with aluminium and tunnel specifically related to high rise building 1.1 TYPES OF FORMWORKS: Timber has been the prevailing choice of material for formwork thus far. Nonetheless, due to diminishing forest reserves and escalating timber costs, the adoption of alternative materials like plywood and steel has gained prominence. Moreover, plastics and fiberglass haverecently emerged as viable options for prefabricating formwork. The selection of material depends on factors such as the construction's characteristics, material availability,andcost. Additionally, project constraints such as overall cost and completion time significantlyinfluencethechoiceofmaterial for formwork. Timber, Steel Aluminum, Plastics, Fabric are common materials used in formwork. The formwork used in high-rise construction are timber, aluminiumformwork and tunnel formwork. 1.2 ALUMINIUM FORMWORK: The utilization of an aluminum formwork system enhances the construction's quality while simultaneously reducing both time and costs. The cost-effectiveness of the formwork becomes evident when it is utilized for numerous construction cycles. As aluminium can be used around 250 repetations. The primary drawback of aluminum forms is that once the formwork is manufactured, no changes can be made. The system typically operates on a four-day cycle, as outlined below: Day 1 - The initial task involves erecting vertical reinforcement bars and one side ofthevertical formwork for either an entire floor or a portion of a floor. Day 2 - The subsequent step entails erecting the secondside of the vertical formwork and installing formwork for the floor. Day 3 - Involves the placement of reinforcementbarsforthe floor slab and the casting of walls and the slab. Day 4 - The vertical formwork panels are removed after 24 hours, while the support props remain in place for seven days, and the floor slabs formwork remains in place for 2.5 days. 1.3 TUNNEL FORMWORK: A tunnel is a specially fabricatedstructure madeofstructural steel, designed in the shape of an L and resembling a half- room in size. Its primary function is to facilitatetheseamless pouring of reinforced concrete (RCC) walls and floor slabs, allowing them to form a unifiedanduninterruptedstructure. Two half tunnels are combined to create a full tunnel with dimensions equivalent to that of a room. This innovative approach ensures efficient construction with a focus on speed, quality, and precision whileofferingtheadvantagesof
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 10 Issue: 05 | May 2023 www.irjet.net p-ISSN: 2395-0072 © 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 1750 on-site construction, flexibility, and cost-effectiveness. The slab cycle for this system is 24 hours. However, it should be noted that each tunnel is custom-made and highly modular, limiting the possibility of design changes. Figure 1 Tunnel Formwork Process 2. METHODOLOGY: The study is to identify the different types of formworks used in high-rise building. The literature and net study are done to collect data about the most efficiently used formwork in high-rise. Comparative study is done between aluminium, tunnel and conventional formwork. For the proposed site aluminium formwork is implemented,itscost, quality and time schedule analysis are done and the end results are compared with conventional formwork technology. 3. LITERATURE REVIEW: The review of journal papers involves a comparison of different types of formwork for high-rise buildings. The study suggests that, in terms of cost and availability, aluminium formwork is well-suited for construction sites in India. This is due to its design flexibility, minimal machinery usage, and the ability to utilize unskilled labor, despite having fewer repetitions compared to tunnel formwork. In contrast, tunnel formwork necessitates heavy machinery, a significant initial investment, and skilled labor. Consequently, the aluminium formwork is economically advantageous for high-rise building projects in India. ACTIVITY CONVENTIONAL ALUMINIUM TUNNEL Capital cost less Cost of shuttering material is high Cost of shuttering material and other related machinery is very high Speed of work slow fast fast Accuracy and Quality of construction less Good accuracy Good accuracy Internal/exte rnal Plastering required required Not required Not required Cycle time of RCC work 20 days 10-15 days 1 day with proper infrastructur e and other ancillary machineries No of repetition of shuttering material 12-15 200-250 500 Cost of shuttering Around Rs 400 to 500 / Sq.ft of shuttering floor area Around Rs 8000 to 10000 /Sq.ft of shuttering floor area Around Rs 12,000 to 14,000 / Sq.ft of shuttering floor area 3.1 CASE STUDY 1: The project involves the construction of a high-rise residential building on a 3.88-acre site, consisting of 6 towers, 2 basements, stilt, and G+21 floors. The total project cost amounts to 218.72 crores, employing an aluminium formwork system. For this project, the shear walls are 200 mm thick, while the non-shear walls are 10 mm thick.Theformwork isfilledwith self-compacting concrete to fill the voids [4]. By utilizing thinner wall sections, the usable area is increased by approximately 5% through the adoption of shear wall systems. Additionally, maintenance costs arereduceddueto improved quality and the elimination of brickwork and plaster [5]. All services are pre-planned, and the cost of construction for one floor, includingtheprovisionandlaying of RCC M-30, self-compacting concrete, steel reinforcement, and aluminium formwork, amounts to 44,00,258 The construction time schedule for each floor using the aluminium formwork system is 620 days. The floorcycle is4 days per floor, employing a box-type framework structure. The dimensional accuracy is high, and the surface finish allows for direct painting after putty application. From an economic perspective, the fund flow associated with the aluminium formwork system is favorable. The waste production when using aluminium formwork is moderate, and the formwork can be repeated up to 200 times.
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 10 Issue: 05 | May 2023 www.irjet.net p-ISSN: 2395-0072 © 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 1751 Figure 2 Site Map 3.2 CASE STUDY 2: The project entails the construction of a high-rise residential building on a 3.88-acre site, comprising 3 towers with G+18 floors. The total project cost amounts to Rs. 117,32,17,750, employing the tunnel formwork system. Considering the project's location in the bustling premium residential hub of Chennai metropolitan city, three distinct unconventional formwork technologies have been adopted to leverage their specific advantages [11]. While tunnel formwork allows for the construction of large, multi-story, and cellular structures [9],theproject'scostincreaseddueto the utilization of expensive equipment and skilled labor. However, tunnel formwork lacks the design flexibility necessary for incorporating basement floors in the towers, making it less preferable for efficient high-rise building construction when compared to aluminium formwork. 4. PROJECT PROPOSAL: DOSHI RISINGTON: The proposal for Phase 2 construction in DOSHI RISETON suggests the utilization of aluminium formwork, as outlined in the provided table. The conventional construction approach for Phase 2 involves approximately 10 towers, encompassing 2 basements, stilt, and G+21 floors. By adopting the aluminium formwork system, different design phases within each tower can be efficiently executed. The estimated time duration for the conventional method is around 3 years, whereasaluminiumformconstructionoffers the advantagesofhigh-qualityconstruction,increasedspeed, and reasonable cost [5]. This technology holds significant potential for addressing India's growing population's need for affordable housing. Moreover, the number of repetitions with aluminium formwork increases, making the initial investment more profitable [5]. Unlike the conventional method where the number of repetitions is lower, leading to an increase incost per square meter after the 16th floor slab cycle. This includes rising costs for shuttering formwork, brickwork, and plastering. The break point forthe aluminiumformwork occurs after the 16th floor of the tower, and repetitions continue for the remaining part of the tower, ensuring a profitable initial investment.. Figure 3 Cost Analysis Time schedule for 1 floor using aluminum formwork: INSTALLATION OF ALUMINIUM OF PRE-CONCRETE ACTIVITIES SI.NO PROCESS DURATION (HOURS) 1 level surveys 5 2 setting out data 5 3 control of deviations 5 4 enforcement wall panel 15 5 enforcement column panel 5 6 enforcement staircase panel 3 7 enforcement beam level 10 8 enforcement slab level 20 9 setting kickers 10 10 lay oil at the panel & kickers 9 ERECTION OF ALUMINIUM OF POST-CONCRETE ACTIVITIES 11 erection wall and column panel 10 12 erection beam and slab panel 15 13 clean, transport and stack panel 10 14 erection of kickers 10 TOTAL DURATION 132
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 10 Issue: 05 | May 2023 www.irjet.net p-ISSN: 2395-0072 © 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 1752 The duration for 1 floor of 870 Sq.m is 132 hrs. using aluminium formwork.Ittakesabout126daysapproximately to complete tower A. Time schedule for 1 floor using conventional formwork: INSTALLATION OF CONVENTIONAL FORMWORK OF PRE-CONCRETE ACTIVITIES SI.NO PROCESS DURATION (HOURS) 1 level surveys 15 2 setting out data 5 3 control of deviations 10 4 enforcement wall wood 150 5 enforcement column wood 80 6 enforcement staircase wood 60 7 enforcement beam wood 75 8 enforcement slab wood 75 9 setting- up other components 100 10 lay oil at the panel & kickers 25 ERECTION OF CONVENTIONAL FORMWORK OF POST-CONCRETE ACTIVITIES 11 dismantle wood column 15 12 dismantle wood wall 50 13 dismantle wood beam 20 14 dismantle wood slab 40 15 dismantle other components 25 16 clean up leftovers 20 TOTAL DURATION 765 The duration for 1 floor of 870 Sq.m is 765 hrs. using conventional formwork. It takes about 651 days approximately to complete tower 5. CONCLUSIONS The aluminium formwork presents a favorable option for achieving timely completion of construction with maximum efficiency. Gathering information from literature and case studies will prove beneficial for selecting the appropriate formwork in future projects. Additionally, this approach helps minimize construction waste associated with formwork usage. Although the aluminium system formwork incurs a higher initial cost, it demonstrates its cost-effectiveness when the number of repetitions falls between 150 and 200 in the construction of high-rise buildings. In contrast, employing contemporary conventional formwork, which is the least expensive type and requires moretime,resultsinthehighest total expenditure. For the proposed site, utilizing conventional formwork leads to a 25% reduction in both cost and time. 6. REFERENCES [1] Prof. Zen Raut, Mayur S. Meshram Analysis and Comparison of Mivan Formwork System with Conventional Formwork System [2] Mayur Sanjay Lodha Comparative Analysis of Conventional Formwork and Mivan Formwork based on Duration and Cost [3] Jaya Surya R Evaluation of Different Kinds of Formwork Systems in Indian Construction Industry [4] Danish Sadruddin Ansari, COMPARATIVE STUDIES OF CONSTRUCTION TECHNIQUES (CONVENTIONAL TECHNIQUE VS ALUMINIUM FORMWORK TECHNIQUES) [5] Ar. Sowndharya ANALYISING ADVANCED FORMWORK SYSTEM FOR HIGH RISE BUILDING CONSTRUCTION [6] Loganathan ALUMINIUMFORMWORKSYSTEMUSINGIN HIGHRISE BUILDINGS CONSTRUCTION [7] Miss Manik Moholkar Productivity Analysis of Building Construction Using Mivan Formwork June 2019 | IJIRT | Volume 6 Issue 1 | ISSN: 2349-6002 [8] Miss. Renuka Hangarge Comparison of Conventional, Aluminium and Tunnel Formwork [9] Vallabhy .S Advanced Technology for Speedy Construction (Tunnel Formwork) [10] Asst. Prof. A. R. Chavan A REVIEW ON FAST TRACK CONSTRUCTION USING MODERN FORMWORK SYSTEMS [11] Mr. Manas A. Shalgar IntroductiontoadvancedTUNNEL Formwork system: Case study of ‘Rohan - Abhilasha’