International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 11 | Nov -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 1592
Comparative Study of Mivan Formwork with Tunnel Form System for
High Rise Building
Mayur Sanjay Lodha1 ,Kiran Anil Tambe2
1, 2Final Year Student of MBA In Project And Construction Management , Department of Project and construction
management , MIT Art Design And Technology University, Pune, Maharashtra , India.
---------------------------------------------------------------------***--------------------------------------------------------------------
Abstract -Real estateconstructionindustryhasareputation
of not begin very technologically sophisticated, generally
lagging in innovation, construction techniques &
management. But now a day’s lot of research is carried out in
this sector, advanced TUNNEL form-work& ALUFORM system
are good examples of this innovation. The high rise building
construction consist of number of repetitive activities andalso
have same identical floors. The increase in duration of
construction greatly affects the construction cost. Selection of
best formwork system gives best result in cost saving.
Formwork consist of 20-25% of total cost of project. So that
used advanced formwork system helps in cost saving as
reduction slab cycle time. This study is done for comparative
analysis of tunnel formwork system and aluminum formwork
used for high rise building construction. this paper
aimedatstudyingadvancedtunnelformworksysteminhighrisebui
lding,tocomparethissystemwith MIVANsystemandtofindbest
formwork in terms of economy and rapid construction.
Key Words: Formwork, High Rise Building, Tunnel
Formwork , Cost , economy , Aluform.
1.INTRODUCTION
The high rise building involves high cost investment which is
increased day by day as delay in execution is occurred
formwork systems are key factors in determiningthesuccess
of a building construction project in terms of cost, speed,
quality and safety of work. Formwork constitutes 30% of the
cost and 60% of the time in concrete construction. Quality of
concretefinishandsoundnessofconcretedependsverymuch
on the formwork system. Formwork should be properly
designed, fabricated, and erected to receive fresh concrete. If
formwork is not done properly the desired shape of concrete
is not possible. When concrete is compacted, it exerts
pressureand the formworkmust be strong andstable totake
this pressure. The form should be leak proof to retain the
concrete &slurry.
Advanced Tunnel formwork identified to be suitable for
Indian conditions for mass construction, where quality and
speed can be achieved at highlevel.Thespeedofconstruction
by this system will surpass speed of most of the other
construction systems. The labour in coordination with heavy
machineries(eg. towercrane)handlesthismethodeffectively
to speed up the construction, to assure quality control and
durability. Adoption of thissystem reduces overallcostofthe
structure. This paper mainly focuses on advanced tunnel
formwork systems, its components, working cycle and its
benefits based on speed and economy.
1.1 TUNNEL FORMWORKSYSTEM
The tunnel formwork is room formwork in which
RCC slab and walls are casted in continuous pour. Then By
Using hot air blows thermal curing is used for accelerate the
concrete. The cycle Time for tunnel formwork system is 1-
3days only, The tunnel form work system is very useful for
repetitive room design.
1.2ALUMINIUM FORMWORK SYSTEM
Aluminium form work also known as MIVAN technology..
MIVAN system is formwork construction, cast – in situ
concrete wall and floor slabs cast monolithic provides the
structural system in one continuous pour. Large room sized
forms for walls and floors slabs are erected at site. These
forms are made strong and sturdy, fabricated with accuracy
and easy to handle. They afford large number of repetitions
(around 250).
2. OBJECTIVES
Objective of this paper is to introduce Indian construction
industry to advanced TUNNEL formwork systems which is
rapid and if used effectively ultimately economical based on,
a. Components
b. Working cycle
c. Economy.
d. Benefits and disadvantages.
2.1 Objective
1] Collection of primary and secondary data
2] Comparison of Tunnel formwork system and aluminum
formwork system used forhigh rise building construction
on time cost quality and its characteristics parameters.
3] Techno-Economical analysis of both formwork system.
4] study Components , Working cycle , Economy , Benefits
and disadvantages of Both Tunnel form and aluform
Technique.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 11 | Nov -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 1593
3. METHODOLOGY-
Formwork planning process is divided in 3 stages.
Stage 1: Information, data collection and examination of
limiting conditions.
Stage 2: Analysis of system & choice of system based on
information collected
Stage 3: Use of system in construction.
3.1 Slab cycle of ALUFORM system.
3.1.1 Aluminum formwork system/ALUFORMsystem
The System is fast, simple, adaptable and very cost
effective.
Aluform isadvanced form work system in whichcastinplace
concrete structured building can be constructed. The system
is fast (7-10 days slab cycle), simple to use easily adaptable
and very cost effective as number of reuses are more i.e.
about 150-200. As we can construct all building components
such as slabs, beams, columns, walls, stairs, window hoods
etc.
3.2 Slab cycle of TUNNEL FORM system.
The tunnel formwork is room sized steel formwork by
which monolithic structures i.e. RCC walls and slabs are
constructed in continuous pour. Thermal curing technique is
used to accelerate curing of concrete for which tunnel forms
are heated by means of hot air blows. This system is
economical only for large number of identical units and for
tall structures or skyscrapers. The sequence of construction
involves placing of reinforcement followed by electrical and
sanitary conduits fittings along with tunnel forms.
4. CASESTUDY
For project work two different sites were studied, Rohan
Builders India Pvt Ltd is using advanced TUNNEL formwork
system (1-3 days slab cycle) and marathon Reality’s ,
nexazone , panvel (Slab cycle of 8-14 days).
4.1 General Comparative statement
Sr.No Description Tunnel Aluminium
formwork Formwork
1 Initial
Investment(for
Project)
High High
2 Average
cost/sq.m
25000rs 8500rs
3 Labour cost /
sq.m
175-200/slab 170
4 Maintenance
cost
15
5 Storage cost 4
6 Cycle time 24hours 14 days
7 Size of panel 1 to 4 m 650*2400
8 Weight of panel 2-4 tonne 9.25kg/sq.m
9 Salvage value 40% of cost
10 Number of
repetitions
500nos 110Nos
11 De-shuttering
time
10hrs 22 hrs
12 Additional
Equipment
requirement
Tower crane &
boom placer
Staff and material
13 Manpower 55-60nos
/slab
3labour/day/sq.m
15 Durability High High
16 Finishing Paint finish Fine
17 % wastage 0 0%
18 Accuracy +-3mm +-5mm
19 Curing method Thermal
curing
Curing compound
20 Casting System RCC RccFramed
monolithic
4.2 Initial Cost/m2
Type Unit Rate
Tunnel Formwork Sq. mt 25000 Rs
Aluminium Formwork Sq. mt 8500 Rs
Case Study 1 Case study2
RohanAbhilasha,wagholi Nexazone, panvel
Residential Residential
Tunnel Formwork System Aluminium Formwork
System
MESA Imalat Marathon Reality
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 11 | Nov -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 1594
4.3 Cycle Time (days)
Type Days
Tunnel Formwork 3 days
Aluminium Formwork 14 days
Fig 1- Cycle time required for formwork
4.4 Cost Analysis for Numbers of repetitions
Type Nos.
Tunnel Formwork 450
Aluminium Formwork 150
Fig 2- No of Repetition with each formwork
5. CONCLUSIONS
From Data analysis and study of both formwork system it is
concluded
1] initial cost/sq.m for tunnel formwork is high But as the
numbers of repetations increasestunnelformworksystem
is best suitable after 450 nos repetations. So that
Aluminium formwork can be used for 150 repetations.
2] Heavy machinery and on site management are critical
factors in implementing tunnel formwork. Also high cash
flow management is essential to carry out work properly.
3]Coordination problemcauseremarkabledelayinschedule.
Also after studying the tunnel formwork system.
4] it can be concluded that, though initial investmentandper
day operational cost in TUNNEL formwork is more, due to
more reuses and reduced slab cycle time TUNNEL
formwork works out ultimately economical.
REFERANCES-
[1] ArbazKazi and Fauwaz Parkar (Dec 2015) “
Comparative study and decision making forformwork
technique to be adopted on construction site in
Mumbai” IJRET Volume; 04 Issue; 12 Dec 2015.
[2] Hisham A. Abou Ibrahim and Farook R. Hamzeh (April
2016) “Role of Formwork system in HighRisebuilding
construction” The master builder April 2016.
[3] K. Loganathan and K.E. Viswanathan ( April 2016) “A
study on Cost, Duration and Quality analysis of
different formworks in high rise building” IJSER
Volume 7; Issue 4 April2016.
[4] Larson & turbo building structurecompetencycentre,
“Hand Book on Foundation, Formwork, Rebar &
Concrete.
[5] Tejas D. Aradhye and Emeritus M.R.Apte ( May 2016)
“Study of Advanced tunnel formwork system in high
rise building IJRET Volume; 05 Issue; 05 May 2016.

More Related Content

What's hot

Low Cost Housing Concept
Low Cost Housing ConceptLow Cost Housing Concept
Low Cost Housing ConceptDr K M SONI
 
automation in construction
automation in constructionautomation in construction
automation in constructionAnand Khare
 
2.1 growth pattern of towns
2.1 growth pattern of towns2.1 growth pattern of towns
2.1 growth pattern of townsSachin PatiL
 
Lease term, rent, outgoings and other property management_MUWONGE RAPHAEL
Lease term, rent, outgoings and other property management_MUWONGE RAPHAELLease term, rent, outgoings and other property management_MUWONGE RAPHAEL
Lease term, rent, outgoings and other property management_MUWONGE RAPHAELMuwonge Land Ted
 
Curitiba 3
Curitiba 3Curitiba 3
Curitiba 3ce4710
 
2.4 town planning surveys
2.4 town planning surveys2.4 town planning surveys
2.4 town planning surveysSachin PatiL
 
Design of residential building
Design of residential buildingDesign of residential building
Design of residential buildingK.MAHESH KUMAR
 
Role of architect in city planning
Role of architect in city planningRole of architect in city planning
Role of architect in city planningArchitectureCrossing
 
comparitive analysis between Andhra Pradesh and Karnataka housing policy.pptx
comparitive analysis between Andhra Pradesh and Karnataka housing policy.pptxcomparitive analysis between Andhra Pradesh and Karnataka housing policy.pptx
comparitive analysis between Andhra Pradesh and Karnataka housing policy.pptxJanhviGupta22
 
Precast Construction technology
Precast Construction technologyPrecast Construction technology
Precast Construction technologyGedalaJairam
 
B.arch Estimation and Costing
B.arch  Estimation and CostingB.arch  Estimation and Costing
B.arch Estimation and CostingSamreenFatima29
 
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDING
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDINGPROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDING
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDINGAmritpal Singh
 

What's hot (20)

Low Cost Housing Concept
Low Cost Housing ConceptLow Cost Housing Concept
Low Cost Housing Concept
 
automation in construction
automation in constructionautomation in construction
automation in construction
 
2.1 growth pattern of towns
2.1 growth pattern of towns2.1 growth pattern of towns
2.1 growth pattern of towns
 
Lease term, rent, outgoings and other property management_MUWONGE RAPHAEL
Lease term, rent, outgoings and other property management_MUWONGE RAPHAELLease term, rent, outgoings and other property management_MUWONGE RAPHAEL
Lease term, rent, outgoings and other property management_MUWONGE RAPHAEL
 
Curitiba 3
Curitiba 3Curitiba 3
Curitiba 3
 
TOD Presentation-PDF_-part-I
TOD Presentation-PDF_-part-ITOD Presentation-PDF_-part-I
TOD Presentation-PDF_-part-I
 
2.4 town planning surveys
2.4 town planning surveys2.4 town planning surveys
2.4 town planning surveys
 
Design of residential building
Design of residential buildingDesign of residential building
Design of residential building
 
Town Planning
Town Planning Town Planning
Town Planning
 
Neighbourhood Planning
Neighbourhood PlanningNeighbourhood Planning
Neighbourhood Planning
 
Udpfistandards
UdpfistandardsUdpfistandards
Udpfistandards
 
Role of architect in city planning
Role of architect in city planningRole of architect in city planning
Role of architect in city planning
 
comparitive analysis between Andhra Pradesh and Karnataka housing policy.pptx
comparitive analysis between Andhra Pradesh and Karnataka housing policy.pptxcomparitive analysis between Andhra Pradesh and Karnataka housing policy.pptx
comparitive analysis between Andhra Pradesh and Karnataka housing policy.pptx
 
Prefabricated
PrefabricatedPrefabricated
Prefabricated
 
Precast Construction technology
Precast Construction technologyPrecast Construction technology
Precast Construction technology
 
Mivan tech
Mivan techMivan tech
Mivan tech
 
B.arch Estimation and Costing
B.arch  Estimation and CostingB.arch  Estimation and Costing
B.arch Estimation and Costing
 
Ai in civil
Ai in civilAi in civil
Ai in civil
 
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDING
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDINGPROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDING
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDING
 
Jan Gehl-An Urbanist
Jan Gehl-An UrbanistJan Gehl-An Urbanist
Jan Gehl-An Urbanist
 

Similar to Comparative Study of Tunnel and Aluminium Formwork Systems

Introduction to advanced TUNNEL Formwork system: Case study of ‘Rohan - Abhi...
Introduction to advanced TUNNEL Formwork system: Case study of  ‘Rohan - Abhi...Introduction to advanced TUNNEL Formwork system: Case study of  ‘Rohan - Abhi...
Introduction to advanced TUNNEL Formwork system: Case study of ‘Rohan - Abhi...IRJET Journal
 
IRJET- Comparative Analysis for High Rise Building of Tunnel Formwork System ...
IRJET- Comparative Analysis for High Rise Building of Tunnel Formwork System ...IRJET- Comparative Analysis for High Rise Building of Tunnel Formwork System ...
IRJET- Comparative Analysis for High Rise Building of Tunnel Formwork System ...IRJET Journal
 
FORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSIS
FORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSISFORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSIS
FORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSISIRJET Journal
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System ashleyyeap
 
Irjet v4 i73Cost and Time estimation for Conventional, Aluminium &Tunnel Form...
Irjet v4 i73Cost and Time estimation for Conventional, Aluminium &Tunnel Form...Irjet v4 i73Cost and Time estimation for Conventional, Aluminium &Tunnel Form...
Irjet v4 i73Cost and Time estimation for Conventional, Aluminium &Tunnel Form...IRJET Journal
 
Application of Advanced formwork system for High rise buildings in Chennai, I...
Application of Advanced formwork system for High rise buildings in Chennai, I...Application of Advanced formwork system for High rise buildings in Chennai, I...
Application of Advanced formwork system for High rise buildings in Chennai, I...IRJET Journal
 
Time, Cost , Productivity and Quality Analysis of Precast Buildings
Time, Cost , Productivity and Quality Analysis of Precast BuildingsTime, Cost , Productivity and Quality Analysis of Precast Buildings
Time, Cost , Productivity and Quality Analysis of Precast BuildingsIRJET Journal
 
Advanced Tunnel Form Construction Technique, Case Study of Rohan-Abhilasha, ...
Advanced Tunnel Form Construction Technique, Case Study of  Rohan-Abhilasha, ...Advanced Tunnel Form Construction Technique, Case Study of  Rohan-Abhilasha, ...
Advanced Tunnel Form Construction Technique, Case Study of Rohan-Abhilasha, ...Mary Montoya
 
Aluminium Formwork Vs Conventional Formwork
Aluminium Formwork Vs  Conventional  FormworkAluminium Formwork Vs  Conventional  Formwork
Aluminium Formwork Vs Conventional Formworkchaitanyakrsk
 
IRJET- Temperature Effect on Concrete Bridge
IRJET-  	  Temperature Effect on Concrete BridgeIRJET-  	  Temperature Effect on Concrete Bridge
IRJET- Temperature Effect on Concrete BridgeIRJET Journal
 
IRJET- U-Boot Technology
IRJET-  	  U-Boot TechnologyIRJET-  	  U-Boot Technology
IRJET- U-Boot TechnologyIRJET Journal
 
Comparative analysis of formwork in multistory buildin gv
Comparative analysis of formwork in multistory buildin gvComparative analysis of formwork in multistory buildin gv
Comparative analysis of formwork in multistory buildin gveSAT Publishing House
 
IRJET - Repair and Rehabilitation of Reinforced Concrete Bridge
IRJET - Repair and Rehabilitation of Reinforced Concrete BridgeIRJET - Repair and Rehabilitation of Reinforced Concrete Bridge
IRJET - Repair and Rehabilitation of Reinforced Concrete BridgeIRJET Journal
 
IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...
IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...
IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...IRJET Journal
 
Selection of Roof Casting Formwork Systems for the Bird Island Project: Case ...
Selection of Roof Casting Formwork Systems for the Bird Island Project: Case ...Selection of Roof Casting Formwork Systems for the Bird Island Project: Case ...
Selection of Roof Casting Formwork Systems for the Bird Island Project: Case ...Muhammad Umar
 
Mivan Formwork in Construction
Mivan Formwork in ConstructionMivan Formwork in Construction
Mivan Formwork in ConstructionIRJET Journal
 
Non linear analysis of reinforced concrete chimney
Non linear analysis of reinforced concrete chimneyNon linear analysis of reinforced concrete chimney
Non linear analysis of reinforced concrete chimneyIAEME Publication
 
IRJET- Static and Dynamic Analysis of Wind Energy Building under the Action o...
IRJET- Static and Dynamic Analysis of Wind Energy Building under the Action o...IRJET- Static and Dynamic Analysis of Wind Energy Building under the Action o...
IRJET- Static and Dynamic Analysis of Wind Energy Building under the Action o...IRJET Journal
 
Analyze Time-Cost Required for Conventional and Prefabricated Building Compon...
Analyze Time-Cost Required for Conventional and Prefabricated Building Compon...Analyze Time-Cost Required for Conventional and Prefabricated Building Compon...
Analyze Time-Cost Required for Conventional and Prefabricated Building Compon...IRJET Journal
 
IRJET- Planning and Selection of Heavy Construction Equipments in Civil En...
IRJET- 	  Planning and Selection of Heavy Construction Equipments in Civil En...IRJET- 	  Planning and Selection of Heavy Construction Equipments in Civil En...
IRJET- Planning and Selection of Heavy Construction Equipments in Civil En...IRJET Journal
 

Similar to Comparative Study of Tunnel and Aluminium Formwork Systems (20)

Introduction to advanced TUNNEL Formwork system: Case study of ‘Rohan - Abhi...
Introduction to advanced TUNNEL Formwork system: Case study of  ‘Rohan - Abhi...Introduction to advanced TUNNEL Formwork system: Case study of  ‘Rohan - Abhi...
Introduction to advanced TUNNEL Formwork system: Case study of ‘Rohan - Abhi...
 
IRJET- Comparative Analysis for High Rise Building of Tunnel Formwork System ...
IRJET- Comparative Analysis for High Rise Building of Tunnel Formwork System ...IRJET- Comparative Analysis for High Rise Building of Tunnel Formwork System ...
IRJET- Comparative Analysis for High Rise Building of Tunnel Formwork System ...
 
FORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSIS
FORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSISFORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSIS
FORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSIS
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System
 
Irjet v4 i73Cost and Time estimation for Conventional, Aluminium &Tunnel Form...
Irjet v4 i73Cost and Time estimation for Conventional, Aluminium &Tunnel Form...Irjet v4 i73Cost and Time estimation for Conventional, Aluminium &Tunnel Form...
Irjet v4 i73Cost and Time estimation for Conventional, Aluminium &Tunnel Form...
 
Application of Advanced formwork system for High rise buildings in Chennai, I...
Application of Advanced formwork system for High rise buildings in Chennai, I...Application of Advanced formwork system for High rise buildings in Chennai, I...
Application of Advanced formwork system for High rise buildings in Chennai, I...
 
Time, Cost , Productivity and Quality Analysis of Precast Buildings
Time, Cost , Productivity and Quality Analysis of Precast BuildingsTime, Cost , Productivity and Quality Analysis of Precast Buildings
Time, Cost , Productivity and Quality Analysis of Precast Buildings
 
Advanced Tunnel Form Construction Technique, Case Study of Rohan-Abhilasha, ...
Advanced Tunnel Form Construction Technique, Case Study of  Rohan-Abhilasha, ...Advanced Tunnel Form Construction Technique, Case Study of  Rohan-Abhilasha, ...
Advanced Tunnel Form Construction Technique, Case Study of Rohan-Abhilasha, ...
 
Aluminium Formwork Vs Conventional Formwork
Aluminium Formwork Vs  Conventional  FormworkAluminium Formwork Vs  Conventional  Formwork
Aluminium Formwork Vs Conventional Formwork
 
IRJET- Temperature Effect on Concrete Bridge
IRJET-  	  Temperature Effect on Concrete BridgeIRJET-  	  Temperature Effect on Concrete Bridge
IRJET- Temperature Effect on Concrete Bridge
 
IRJET- U-Boot Technology
IRJET-  	  U-Boot TechnologyIRJET-  	  U-Boot Technology
IRJET- U-Boot Technology
 
Comparative analysis of formwork in multistory buildin gv
Comparative analysis of formwork in multistory buildin gvComparative analysis of formwork in multistory buildin gv
Comparative analysis of formwork in multistory buildin gv
 
IRJET - Repair and Rehabilitation of Reinforced Concrete Bridge
IRJET - Repair and Rehabilitation of Reinforced Concrete BridgeIRJET - Repair and Rehabilitation of Reinforced Concrete Bridge
IRJET - Repair and Rehabilitation of Reinforced Concrete Bridge
 
IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...
IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...
IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...
 
Selection of Roof Casting Formwork Systems for the Bird Island Project: Case ...
Selection of Roof Casting Formwork Systems for the Bird Island Project: Case ...Selection of Roof Casting Formwork Systems for the Bird Island Project: Case ...
Selection of Roof Casting Formwork Systems for the Bird Island Project: Case ...
 
Mivan Formwork in Construction
Mivan Formwork in ConstructionMivan Formwork in Construction
Mivan Formwork in Construction
 
Non linear analysis of reinforced concrete chimney
Non linear analysis of reinforced concrete chimneyNon linear analysis of reinforced concrete chimney
Non linear analysis of reinforced concrete chimney
 
IRJET- Static and Dynamic Analysis of Wind Energy Building under the Action o...
IRJET- Static and Dynamic Analysis of Wind Energy Building under the Action o...IRJET- Static and Dynamic Analysis of Wind Energy Building under the Action o...
IRJET- Static and Dynamic Analysis of Wind Energy Building under the Action o...
 
Analyze Time-Cost Required for Conventional and Prefabricated Building Compon...
Analyze Time-Cost Required for Conventional and Prefabricated Building Compon...Analyze Time-Cost Required for Conventional and Prefabricated Building Compon...
Analyze Time-Cost Required for Conventional and Prefabricated Building Compon...
 
IRJET- Planning and Selection of Heavy Construction Equipments in Civil En...
IRJET- 	  Planning and Selection of Heavy Construction Equipments in Civil En...IRJET- 	  Planning and Selection of Heavy Construction Equipments in Civil En...
IRJET- Planning and Selection of Heavy Construction Equipments in Civil En...
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 

Recently uploaded (20)

Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 

Comparative Study of Tunnel and Aluminium Formwork Systems

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 11 | Nov -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 1592 Comparative Study of Mivan Formwork with Tunnel Form System for High Rise Building Mayur Sanjay Lodha1 ,Kiran Anil Tambe2 1, 2Final Year Student of MBA In Project And Construction Management , Department of Project and construction management , MIT Art Design And Technology University, Pune, Maharashtra , India. ---------------------------------------------------------------------***-------------------------------------------------------------------- Abstract -Real estateconstructionindustryhasareputation of not begin very technologically sophisticated, generally lagging in innovation, construction techniques & management. But now a day’s lot of research is carried out in this sector, advanced TUNNEL form-work& ALUFORM system are good examples of this innovation. The high rise building construction consist of number of repetitive activities andalso have same identical floors. The increase in duration of construction greatly affects the construction cost. Selection of best formwork system gives best result in cost saving. Formwork consist of 20-25% of total cost of project. So that used advanced formwork system helps in cost saving as reduction slab cycle time. This study is done for comparative analysis of tunnel formwork system and aluminum formwork used for high rise building construction. this paper aimedatstudyingadvancedtunnelformworksysteminhighrisebui lding,tocomparethissystemwith MIVANsystemandtofindbest formwork in terms of economy and rapid construction. Key Words: Formwork, High Rise Building, Tunnel Formwork , Cost , economy , Aluform. 1.INTRODUCTION The high rise building involves high cost investment which is increased day by day as delay in execution is occurred formwork systems are key factors in determiningthesuccess of a building construction project in terms of cost, speed, quality and safety of work. Formwork constitutes 30% of the cost and 60% of the time in concrete construction. Quality of concretefinishandsoundnessofconcretedependsverymuch on the formwork system. Formwork should be properly designed, fabricated, and erected to receive fresh concrete. If formwork is not done properly the desired shape of concrete is not possible. When concrete is compacted, it exerts pressureand the formworkmust be strong andstable totake this pressure. The form should be leak proof to retain the concrete &slurry. Advanced Tunnel formwork identified to be suitable for Indian conditions for mass construction, where quality and speed can be achieved at highlevel.Thespeedofconstruction by this system will surpass speed of most of the other construction systems. The labour in coordination with heavy machineries(eg. towercrane)handlesthismethodeffectively to speed up the construction, to assure quality control and durability. Adoption of thissystem reduces overallcostofthe structure. This paper mainly focuses on advanced tunnel formwork systems, its components, working cycle and its benefits based on speed and economy. 1.1 TUNNEL FORMWORKSYSTEM The tunnel formwork is room formwork in which RCC slab and walls are casted in continuous pour. Then By Using hot air blows thermal curing is used for accelerate the concrete. The cycle Time for tunnel formwork system is 1- 3days only, The tunnel form work system is very useful for repetitive room design. 1.2ALUMINIUM FORMWORK SYSTEM Aluminium form work also known as MIVAN technology.. MIVAN system is formwork construction, cast – in situ concrete wall and floor slabs cast monolithic provides the structural system in one continuous pour. Large room sized forms for walls and floors slabs are erected at site. These forms are made strong and sturdy, fabricated with accuracy and easy to handle. They afford large number of repetitions (around 250). 2. OBJECTIVES Objective of this paper is to introduce Indian construction industry to advanced TUNNEL formwork systems which is rapid and if used effectively ultimately economical based on, a. Components b. Working cycle c. Economy. d. Benefits and disadvantages. 2.1 Objective 1] Collection of primary and secondary data 2] Comparison of Tunnel formwork system and aluminum formwork system used forhigh rise building construction on time cost quality and its characteristics parameters. 3] Techno-Economical analysis of both formwork system. 4] study Components , Working cycle , Economy , Benefits and disadvantages of Both Tunnel form and aluform Technique.
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 11 | Nov -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 1593 3. METHODOLOGY- Formwork planning process is divided in 3 stages. Stage 1: Information, data collection and examination of limiting conditions. Stage 2: Analysis of system & choice of system based on information collected Stage 3: Use of system in construction. 3.1 Slab cycle of ALUFORM system. 3.1.1 Aluminum formwork system/ALUFORMsystem The System is fast, simple, adaptable and very cost effective. Aluform isadvanced form work system in whichcastinplace concrete structured building can be constructed. The system is fast (7-10 days slab cycle), simple to use easily adaptable and very cost effective as number of reuses are more i.e. about 150-200. As we can construct all building components such as slabs, beams, columns, walls, stairs, window hoods etc. 3.2 Slab cycle of TUNNEL FORM system. The tunnel formwork is room sized steel formwork by which monolithic structures i.e. RCC walls and slabs are constructed in continuous pour. Thermal curing technique is used to accelerate curing of concrete for which tunnel forms are heated by means of hot air blows. This system is economical only for large number of identical units and for tall structures or skyscrapers. The sequence of construction involves placing of reinforcement followed by electrical and sanitary conduits fittings along with tunnel forms. 4. CASESTUDY For project work two different sites were studied, Rohan Builders India Pvt Ltd is using advanced TUNNEL formwork system (1-3 days slab cycle) and marathon Reality’s , nexazone , panvel (Slab cycle of 8-14 days). 4.1 General Comparative statement Sr.No Description Tunnel Aluminium formwork Formwork 1 Initial Investment(for Project) High High 2 Average cost/sq.m 25000rs 8500rs 3 Labour cost / sq.m 175-200/slab 170 4 Maintenance cost 15 5 Storage cost 4 6 Cycle time 24hours 14 days 7 Size of panel 1 to 4 m 650*2400 8 Weight of panel 2-4 tonne 9.25kg/sq.m 9 Salvage value 40% of cost 10 Number of repetitions 500nos 110Nos 11 De-shuttering time 10hrs 22 hrs 12 Additional Equipment requirement Tower crane & boom placer Staff and material 13 Manpower 55-60nos /slab 3labour/day/sq.m 15 Durability High High 16 Finishing Paint finish Fine 17 % wastage 0 0% 18 Accuracy +-3mm +-5mm 19 Curing method Thermal curing Curing compound 20 Casting System RCC RccFramed monolithic 4.2 Initial Cost/m2 Type Unit Rate Tunnel Formwork Sq. mt 25000 Rs Aluminium Formwork Sq. mt 8500 Rs Case Study 1 Case study2 RohanAbhilasha,wagholi Nexazone, panvel Residential Residential Tunnel Formwork System Aluminium Formwork System MESA Imalat Marathon Reality
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 11 | Nov -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 1594 4.3 Cycle Time (days) Type Days Tunnel Formwork 3 days Aluminium Formwork 14 days Fig 1- Cycle time required for formwork 4.4 Cost Analysis for Numbers of repetitions Type Nos. Tunnel Formwork 450 Aluminium Formwork 150 Fig 2- No of Repetition with each formwork 5. CONCLUSIONS From Data analysis and study of both formwork system it is concluded 1] initial cost/sq.m for tunnel formwork is high But as the numbers of repetations increasestunnelformworksystem is best suitable after 450 nos repetations. So that Aluminium formwork can be used for 150 repetations. 2] Heavy machinery and on site management are critical factors in implementing tunnel formwork. Also high cash flow management is essential to carry out work properly. 3]Coordination problemcauseremarkabledelayinschedule. Also after studying the tunnel formwork system. 4] it can be concluded that, though initial investmentandper day operational cost in TUNNEL formwork is more, due to more reuses and reduced slab cycle time TUNNEL formwork works out ultimately economical. REFERANCES- [1] ArbazKazi and Fauwaz Parkar (Dec 2015) “ Comparative study and decision making forformwork technique to be adopted on construction site in Mumbai” IJRET Volume; 04 Issue; 12 Dec 2015. [2] Hisham A. Abou Ibrahim and Farook R. Hamzeh (April 2016) “Role of Formwork system in HighRisebuilding construction” The master builder April 2016. [3] K. Loganathan and K.E. Viswanathan ( April 2016) “A study on Cost, Duration and Quality analysis of different formworks in high rise building” IJSER Volume 7; Issue 4 April2016. [4] Larson & turbo building structurecompetencycentre, “Hand Book on Foundation, Formwork, Rebar & Concrete. [5] Tejas D. Aradhye and Emeritus M.R.Apte ( May 2016) “Study of Advanced tunnel formwork system in high rise building IJRET Volume; 05 Issue; 05 May 2016.