DELAY ANALYSIS IN CONSTRUCTION OF REDEVELOPMENT
RESIDENTIAL PROJECT
Rashmi. M. Bijwar1, Prof. Dr. A. B. More2
1P.G. Scholar Department Civil Engineering TSSM’s PVPIT, SPPU Pune, Maharashtra, India
2Head of Department, Civil Engineering TSSM’s PVPIT, SPPU Pune, Maharashtra, India
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract - Delays of a developmentventure ischaracterized
as late fulfilment of the venture when contrasted with the
arranged timetable. Development delays are frequently after
effect of miscommunication between contractual workers,
subcontractors, proprietors and providers. These types of
unrealistic exceptions are usuallyavoidedby using acleanand
efficient planning mechanism, which clearlyspecifiesthework
and timetable to be used. Delays in construction projects are
quite expensive; sometimes they may result in severe damages
to the involved parties. This thesis concentrates on
investigation of centre components that are bringing about
deferrals and breaking down the everyday records to limit
delays. The current study is undertaken on Construction of
High rise residential building project in Andheri, Mumbai. The
project is reconstruction of G+13 floor High rise Residential
Building and is scheduled to complete in 47 Months including
all sanctioning and redevelopment processes. The study is
being conducted on various factors that were causing the
delays in project. The causes, resources and the discrete
methods on nonetheless to derogate the delays in
the ordering locality arenoteddownregularly. Theday-to-day
data is regularly collected from site. Beginning time,
completing time, Also span is recorded over misundertaking
differentiating undertaking Furthermore basic movement
alongside the delays brought about What's more purposes
behind those delays. A questionnaire may be arrangedposting
crazy Different variables helping to delay under diverse
classifications In light of perceptions In developmentwebpage
Furthermore from a few diary papers as reference. Thosesees
on the same starting with Different gatherings includedOnan
undertaking similar to those builder/developer, foreman
What's more consultants are moaning in the questionnaire.
Each component will be provided for An weight-age landed at
utilizing filled-up questionnaires, using, whichthose mossy cup
oak persuasive elements would recognized.
Key Words: Delays in construction project1,
Redevelopment2,causesfordelays3,impactofdelayson
Construction project4, RERA 2016 act5 Box plot6,
Demonetization7.
1. INTRODUCTION
Clinched alongside construction, the expression
―Delay alludes on something happening toward a after the
fact occasion when over planned, expected, specified
Previously, an agreement or pastthedatethatthegatherings
concurred for the conveyance of a venture. Delay will be
those abating down from claiming worth of effort without
ceasing development actually Furthermore that might
prompt run through overwhelmPossiblypasttheagreement
date or past the date that the gatherings bring concurred to
the conveyance of the project. Delays classified into non-
excusable delays, excusable non compensable delays,
excusable compensable delays and concurrent delays[1].
Non-excusable delays are delays, which those
foreman whichever reasons alternately accepts the hazard
for. Sensible non-compensable delays might delays initiated
Eventually Tom's perusing components that need aid not
foreseeable, previous those contractor‘s sensible control
likewise not attributable of the contractor‘s lack alternately
heedlessness. Compensable reasonable delays these are
compensable delays are reasonable delays, suspensions, or
interruptions should every last bit or and only the worth of
effort brought on Eventually Tom's perusing a
demonstration or disappointment to enactment by the
manager coming about because of owner‘s break for an
obligation, stated alternately implied, in the contract.
Concurrent delays occur when both owner and the
contractor are responsible for the delay.
There are three basic ways to categorize type of delays:
 Critical and noncritical
 Excusable and Non-excusable
 Compensable and non-compensable
Fig No. 1 Types of delays
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 38
This document is template. We ask that authors followsome
simple guidelines. In essence,weask youtomakeyourpaper
look exactly like this document. The easiest way to do this is
simply to download the template, and replace(copy-paste)
the content with your own material. Number the reference
items consecutively in square brackets (e.g. [1]). However
the authors name can be used along with the reference
number in the running text. The order of reference in the
running text should match with the list of references at the
end of the paper.
1.1Delay Analysis Techniques
If or not a delay will be compensable relies
principally on the money house under the agreement. In the
greater part cases, an agreement particularly notes the sorts
about delays that need aid non-compensable,forwhichthose
foreman doesn't accept any extra cash yet all the might make
permitted a period development.
DelayexaminationmaybeAnexplanatoryprocedure
that ought to a chance to be utilized for task documentation
alongside gathered information starting with one task site.
Those determinations aboutdelay Investigationreliesonthe
mixed bag about Components and the accessible records.
There are five commonly used delay techniques.
1. Impacted as-planned method
2. Time impact analysis method
3. Collapsed as-built or ‗but-for analysis method
4. Snapshot/windows/time slice analysis method
5. As-planned versus as-built windows analysis method
1.2 Cause Effects Relationship of Construction
Delays
Fig. No. 2 Cause Effects Relationship of Construction
Delays [6]
2. LITERATURE REVIEW
Construction industry is large, volatile and required
tremendous capital outlays. Delays are one of the major risk
factors in project. Bramble and Callahan(1987)havedefined
that “a delay is the time during which some part of the
construction projecthasbeenextendedornotperformeddue
to an unanticipated circumstance”[3].
Likewise a critical contribution, this investigation. Hails
crazy with experimental relationship the middle of makes
Also impacts of postponements Likewise the third
destinationas. Talked about in the dialogover.Trustthatthis
study might a chance to be an assistance of the professionals
(clients,. Consultants What's more contractors) and also
academicians will An finer see all the over the project.
Oversaw economy Furthermore aggravate deliberations to
decrease the development postponements. says Syahira
Nabilla Ahmad Hisham (2015)[11]
Delays in construction projects are a widely researched
area for which more researches are constantly being carried
out. Due to the wide coverage of construction
projects in terms of size, type, geography and so on, there
is still the need to investigatethe causes and assess the effect
of delays on various construction projects at various levels.
This may eventually lead to the muchneededdevelopmentin
the industry. For this reason, this researcher sought to
analyze the construction of government road projects in
Kurdistan Region to address the inefficiencies in the system
and prescribe some solutions to mitigate them. Studied by
Twana Ahmed Muhammed, 2015, [12]
As per Divya.R, S.Ramya, The objective of this study is to
identify the major causes of construction delays, its effects,
and minimizing delays in construction projects. This study is
carried out based on literature reviews and questionnaire
survey.2015, [13]
2.1 PROJECT DISCRIPTION
The project was carried out in a site which is in Andheri,
Mumbai, Maharashtra which is a construction of High rise
residential project by Westin Developers, which is planned
forconstruction of stilt +13 Floors for26 Units of Residential
Flats. WESTIN is a firm which deals with the construction
related projects. JAONITA project is handle by Westin
Developer itself. MCGM i.e. Municipal CorporationOfGreater
Mumbai is the sanctioned authority for above project.
This project is a part of redevelopment agreement
between land owner and the builder. Past days eight story
building was there in which each floor having two flats i.e,
there are total number sixteen tenants including land owner
are there in redevelopment agreement. This project was
scheduled for 40 months from the date of site clearance.
This project was schedules forAsthiswasredevelopment
project most of the time consumed by the project was
government sanctioning and commencement certification
approval. whichleads to lengthyprojectactivity andacapital
loss. One of the biggest issue was randomly changed in
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 39
government policiesinconstructionindustries.in2015-2016
there was a biggest issue regarding sand availability. Which
leads to delays in construction in all over Maharashtra. Not
only sand butalso differentmaterialwerelimitedinthatspan
of construction industries.
3. PROBLEM STATEMENT
Numerous development undertakings need faced
Different issues What's more delay for time may be a
standout amongst those real issues. The delay in debate
settlement need pronouncement impacts for example, such
that it will provideforimpeding of the associationthemiddle
of holder and foreman. Those foreman and the manager pay
for those additional accuse to the fruition of the venture
because of delay over vast development ventures. The point
when the fruition period of the development one task
surpasses those consented fruition time, it will be known as
development undertaking delay. It may be required to direct
nitty grittyexaminationAlsoIDnumberaboutdelayelements
et cetera selecting the straight activities with counter theses
delay elements insideexpense Also looking after nature. The
faults and errors due to the contractor cause delays and
waste of capital and time. Thosecurrentponderconcentrates
looking into Different Components bringing on those delays
especially for much off spots the place assets ought make
transportedstartingwithsignificantlyoffspotswhichrequire
All the more chance Also cash What's more the place new fill
in requirement to a chance to be carried out straight from
those uncovering such as evacuating trees Furthermore
impacting few puts which can't a chance to be excavated
Toward hardware. This study attempts to generalize.
4. AIM AND METHODOLOGY
Aim :- To find out causes in residential redevelopment
construction project in Mumbai and give methodologies to
minimize delays and its effects
Objective of Study
The current objectives of proposed project work are:
1. To identifyvariouscausesofdelayandtheir
effect on cited project
2. To Prepare and schedule the baseline
program and update using MS project.
3. To identify the delay duration of each
activity and estimate the extensiontimerequiredfor
the final completion of project.
4. To collect responsesfromClient,contractor
and consultant in construction industry for this site.
5. To analyze the collected responses by
conducting one-way ANOVAanalysis using Minitab.
6. Toidentifythemostresponsiblefactorsthat
cause and effect the delay and to propose methods
to minimize delay.
4.1 Methodology
Strategy of methodology was done step by step
which includes literature review, questionnaire and data
collection from all possible sources.
Fig. No. 3 Methodology flowchart
5. DATA COLLECTION AND ANALYSIS
Data collection for project details collected from
journals, internet, books and by experts interviews. The
owners, Contractors, Consultants, Labours, Tenants, Project
managers and involved people were targeted forsurvey.The
derails of various stakeholders and needed data were
collected from project manager of the site.
Fig. No. 4 Work done sequence
5.1Questionnaire Methodology
Those review may be planned built to utilize Likert scale
on the destination of the study shouldfigureoutthosereason
for delays Previously, development activities Furthermore
impact of the delays once generally project. The study is
encircled over such an approach that the particular
perspective fordistinctive individuals included in distinctive
tasks may be gathered Furthermore investigated. That
questionnaire essentially comprisesabout fourareasasnitty
gritty beneath.
1. Respondent foundation - thiswill be ongatherthose
fundamental data of the respondent.
2. Reason fordelays - this is usedtogatherinformation
those information on separate reason for the delays
happened in that specific venture.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 40
3. Impacts from claiming delays - utilizing these
inquiries those impacts of the delays on the project
would distinguish.
4. Measures to Minimizingdelays-themostrecentand
only those overview comprises of inquiries in
regards to the systems they used to decrease the
delays if At whatever.
The collected data is analyzed using Minitab software to
find out the major causes of delay, the effects of the delayand
how to minimize the delay of a construction project.
Fig. No. 5 Analysis programme
5.2 MSP, LIKERT SCALE, SCORING AND ANOVA
ANALYSIS
5.2.1MSP
Microsoft project, herein after MSP may be An product
device created Eventually Tom's perusing Microsoft should
deal with What's more examine schedules. Furthermore will
be client cordial permitting you to begin planning exercises
instantly. MSP will be fit from claiming handling OK reports
What's more graphs in a matter of moments.
Development activities oblige occasional plan
update, which goes about similar to an evaluation of the
venture status Furthermore prediction for how and when
those task will make finished.
Those real steps On overhauling a plan include.
1. Setting a benchmark.
2. Overhauling those plan.
3. Thinking about the calendar updates.
MSP need large portions interesting features
particularly intended with aggravate utilizing the product
basic.Nonetheless At it hailswithoverhaulingaplanutilizing
MSP, development schedules frequently Figure MSP greatly
befuddling. This is basically because of those MSP
straightforwardness to utilize obstruction What's more
features.
5.2.1 Likert Scale
After the questionnaire may be completed, everything
might be broke down independently alternately over some
instances thing reactions might make summed will make a
score to an aggregation for things. Hence, Likert scales are
frequently known as summer scales.
There need aid two elementary considerations in this
exchange. In Likert scales would discretionary. The quality
doled out should An Likert thing need no destination
numerical basis, Possibly As far as measure hypothesis or
scale (from which a separation metric camwood a chance to
be determined). The worth allocated should every Likert
thing will be essentially decided Eventually Tom's perusing
the analyst outlining the survey, who makes the choice
dependent upon a wanted level about point of interest.
However, Eventually Tom's perusing gathering Likert things
tend on make doled out progressive sure basic values. Likert
scales regularly go from 2 to 10 – with 5 or 7 constantlythose
The majority normal.
Further, this progressive structure of the scale will be
such-and-such each progressive Likert thing may be treated
as demonstrating An ‗better‘reaction over the first esteem.
(This might vary clinched alongside instances the place
opposite requesting of the Likert scale is needed).
The second, What's more potentially a greater amount
critical side of the point may be if those ‗distance‘ the middle
of each progressive thingclassisequivalent,whichisinferred
customarily. For example, in the over five-point Likert item,
those induction may be that those ‗distance‘between
classification 1 and 2 will be those same Concerning
illustration between class 3 Furthermore 4. As far as handy
Scrutinize practice, an equidistant presentation by those
analysts is important; generally a inclination in the
examination might result. For example, An four-point Likert
thing forclassifications "Poor", "Average","Good",Also"Very
Good" will be farfetched with have know equidistant Classes
since there is special case class that could get a underneath
Normal rating. This might seemingly inclination any bring
about shortages energetic about An sure Conclusion. On the
other hand, regardless of a analyst displays what he or she
accepts are equidistant categories, it might notachancetobe
translated all things considered Eventually Tom's perusing
the respondent.
A great Likert scale, Likewise above, will exhibit
symmetry of Classes something like a midpoint with plainly
characterized semantic qualifiers. Done such symmetric
scaling, equidistant qualities will regularly be a greater
amount plainly watched or, In least, inferred. It will be At
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 41
Likert scale will be symmetricWhat'smoreequidistantthatit
will act a greater amount similar to an interval-level
estimation. With the goal same time a Likert scale will be to
be sure ordinal, whether great exhibited it might All things
considered estimated a interval-level estimation. This could
make advantageous since, On it mighthavebeendealtwithin
the same way that a ordinal scale, At that point exactly
profitable majority of the data Might be lost Assuming that
those ‗distance‘ the middle of Likert things were not
accessible for thought.
Reactions on a few Likert inquiries might make summed
giving that the sum inquiries utilize the sameLikertscaleand
that those scale may be a solid close estimation should an
interim scale, to whichinstancethosenationalbreakingpoint
hypothesis permits medicine of the information Concerning
illustration interim information measuring An idle variable.
Whether those summed reactions satisfy these assumptions,
parametric Factual tests for example, the examination of
fluctuation might make connected. Commonplace cutoffs to
keeping in touch with you must be clear in your reasoning
that this close estimation will a chance to be adequate is a
least from claiming 4 Furthermore preferably 8 things in the
entirety of cash.
5.2.3 ANOVA Analysis
Analysis of Variance (ANOVA) is used to analyze the
differences between group mean. An analysis ofvariancecan
be used as an explanatory tool to explain observations.
ANOVA is relatively robust procedure with respect to
violations of the normality assumption.
The assumptions of one-way ANOVA analysis are
1. Response variable residuals are approximately
normally distributed.
2. The occurrence of one Sample doesn’t affect the
other.
3. The variance of same for each level
4. Responses of given group are independent and
identicallydistributed(notasimplerandomsample)
5.3 Questionnaire
The inquiries regarding the makes to delays would
separate under 7 segments holding 9 inquiries each. Those
respondents may be approached to rank each of the
accompanying inquiries. Following are two of them.
Group-A Owner Contributed Components.
1. Delay in advancement installments.
2. Delay to outfit Also convey the site.
3. Change requests Eventually Tom's perusing holder
Throughout development.
4. Latedonechangingandsanctioningplandocuments.
5. Delay done sanctioning shop drawing What's more
test materials.
6. Poor correspondence Also coordination.
7. Gradualness to choice making transform.
8. Clashes the middle of joint-ownership of the one
task.
9. Suspension from claiming worth of effort Toward
manager.
Group-B Contractor Contributed variables.
1. Challenges Previously, financing venture.
2. Clashes On sub-contractors calendar for execution
of task.
3. RevampbecauseoferrorsThroughoutdevelopment.
4. Clashes the middle of foreman Also different
gatherings.
5. Poor correspondence Also coordination.
6. Inadequate arranging What's more planning about
undertaking.
7. Shameful development systems execute.
8. Delays over sub-contractors fill in.
9. Insufficient contractor's worth of effort.
What's more open strikes. Respondents need aid
Additionally required to provide for their assessment on the
impacts from claimingdelays.6inquirieswereapproachedin
this segment.
1. Time overwhelm.
2. Average cost for basic items.
3. Question.
4. Mediation.
5. Downright abandonment.
6. Litigation
The most recent segment incorporates inquiries
regarding those steps that ought further bolstering a chance
to be taken to stay away from delays over development
project. This segment comprises for 12 inquiries.
1. Incessant Advance gathering.
2. Utilize upand coming engineering organizationuse.
3. Use correct What's more current development.
4. Utilize fitting development routines.
5. Compelling vital arranging.
6. Legitimate material acquisition.
7. Exact beginning expense estimates.
8. Reasonable majority of the data and
correspondence channels.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 42
9. Incessant coordination the middle of the gatherings
included.
10. Fitting stress with respect to previous background.
11. Fitting undertaking arranging and planning.
12. Finish and legitimate outline at the good occasion
when.
6. RESULTS AND DISCUSSION
6.1 Data Analysis and Its Results
The collected responses from different categories of
people involved in construction project. The mean of each
group of question is calculated using ANOVA analysis. The
final result showing the contribution of different factors on
the delay of a construction project is plotted on a pie chart.
From the pie chart the contribution of various
parties involved in the project are almost same while
contractor is more slightly more for delay.
6.1.1 Owner Contributed Factors
Respondents are asked to scale the 9 given questions
related to the contribution of owner towards the delay in
project. Questions are named as BA1 through BA9.
Following showing the box-plot for owner’s contribution
factor with respect to questionnaire.
Above graph showing higher to lower number of factors
responsible for days in owner’s view. Higher the number
showing good contribution in nullifying delay. And lowerthe
number showing factors most responsible.
Similarly, contractors, consultants, labours, material,
equipments and outercomponentsshooingboxplotsfortheir
contributions in delays in construction.
6.2 Factors that cause delays
1) 3. 8 which may be the delay for installments which
created delay in the undertaking Similarly as
responded from the respondents.
2) The most noteworthy intend in foreman reasons is
3. 9 which may be Poor correspondence and co-
ordination initiated a greater amount delay
Concerning illustration responded Toward those
respondents.
3) The most noteworthy imply On box plot may be 3.
86 which says that insufficient experience about
specialist may be those The majority helping make
for those delay.
4) Those most astounding reason for delay is late
acquisition about materials for those imply about 3.
56 and the following The greater part helping
component might make lack for development
materials over business.
5) Those most noteworthy mean quality may be 3. 86
which need two reasons to the same intend value, i.
E gear breakdown Also low level about supplies
operator’s ability are the major makes Similarly as
responded starting with the respondents.
6) Those most noteworthy intend starting with those
box plot will be 3. 9 which says low benefit from
claiming labors will be the real cause Likewise
responded Toward the respondents.
7) The followingmostelevatedfoundationwillbedelay
is performing last review and Confirmation which
need mean quality 3. 36.
6.3 Effects of Delays
Due to those Different factors the development venture
might a chance to be deferred and the effect will make
different contingent upon the states. For A large portion of
the activities a period extensions solves those issue same
time for exactly others necessity a greater amount cash over
evaluated. The place as to other circumstances it mightmake
important with suspend those fill in will fathom those issues
the middle of separategatheringsorconstantlyongatherings
included On venture can't attain aggregate abandonment of
the one task if a correct conclusion.
This segment's comprises about inquiries identified with
those effect of the postponements. The six inquiriesneedaid.
1. Time overrun
2. Cost overrun
3. Dispute
4. Arbitration
5. Total abandonment
6. Litigation
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 43
6.4 Steps to Avoid Delays
Following are some methods or steps to avoid time
overrun in construction of project.
1. Incessant Advance meeting.
2. Utilize up and coming engineering usage.
3. Use correct modern type construction to date
development.
4. Utilization suitable development systems.
5. Successful vital planning.
6. Best possible material acquisition.
7. Exact starting expense estimates.
8. Clear majority of the data and correspondence
channels.
9. Incessant coordination the middle of the gatherings
included.
10. Fitting accentuation for past work experience.
11.Proper project arranging and planning.
12. Finish and best possible configuration toward the
straight the long time.
13. Always planned for backup situations for 3M's i.e.
materials, man and machineries.
7. EFFECTS OF RERA AND DEMONETIZATION ON
CONSTRUCTION INDUSTRY
A) Delays done developmentgenerallyinfluencesthose
economy for contractor, holder and consultants. Which
specifically trouble fundamental money to task. However
these days delays not just influence three Classes Likewise
stated overaswellasthosepurchaserclinchedalongsidenew
structure.
A year ago administration for India made new go about
for development business and that is RERA (Real bequest
administrative power Act, 2016).
Land of land administrative power Also investigative
tribunal it will assistance with secure state-level land
administrative powers (RERAs) on control transactions
identified with both private What's more business ventures
Furthermore guarantee their auspicious fruition
Furthermorehandover.InvestigativeTribunalswillpresently
be required will settle instances On 60 days Similarly as
against the prior procurement for 90 days Also
administrative powers on discard objections for 60 days
same time no time allotment might have been shown
Previously, prior bill. If RERA is properly implemented on
construction work then automatically there will be less
percentage on construction delays as well as cost and time
overrun. Due to fear of giving penalty and extralossofcapital
builders has to work out fast for construction of any
structure. He will work properly, on time working process
B) Demonetization for Rs. 500 Also Rs. 1,000 notes
Toward those legislaturefromclaimingIndiamaybeastrong
act Also welcoming person. Those storing about cash
Eventually Tom's perusing corrupt individuals prompted
twofold pronged effect on the economy.
Those grade deals section will be generally impacted by
home fund players, Furthermore bargainshaveatendencyto
be encouraged clinched alongside An transparent way. This
section will thusly see best case scenario a constrained sway
in the bigger cities, however A percentage level 2 Also level 3
urban areas the place money segmentsneedbeenanelement
Significantly over elementarydeals willperceiveabenefitsof
the business crunch. The optional or resale advertise will,
however, absolutely make impacted, provided for the truth
that this section does view the inclusion of money part.
C) In construction with heavy use of Cement and
concretethere is high percentage of CO2 emissioneveryyear
which leads to make polluted air every time. If project
progress held for long lasting time it will create more
nuisance for near about locality and make Low immunity of
human as well as for animals.
Pollution like Noise Pollution,LandPollution,Segregation
also equally affect due to long construction period. So to
minimize environmental impacts, long term cost and time
overrun, and heavy capital losses we need to manage project
from its start to Decrease delays.
8. CONCLUSION
Those reactions gathered starting with the respondents
make it obvious that very nearly the sum parties holds
almost equivalent obligationto the delaysclinchedalongside
project. and from the above analysis I conclude following
conclusions:-
 Delays in instalments i.e,paymentsleadstodelaysin
construction.
 Poor Co-ordination from contractors side.
 Absence of qualified labour, supplies and material
when necessary.
 Overall timeoverrun foraboveprojectwas369days
from the planning of the project.
 From box plot analysis it shows most significant
delays from constructors for poor communication
and from low productivity labours i.e. 3.9.
 Maximum delays was appeared in government
sanctioning process i.e. receiving of commencement
certificates up to 4th floor and delay was 4 months,
for 6th floor delay was 4 months, for 7thfloor delay
was calculated as 4 monthsand for9th floor it was3
months.
Respondents communicated that incessant Advance
meeting, exact beginning expense estimation, powerful vital
arranging and legitimate acquisition need aid those
Components that ought further bolstering a chance to be
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 44
acknowledged Also controlled should minimize those
Generally speaking one task delays.
BIBLIOGRAPHY
[1] Zaki M. Kraiem And James E. Diekmann, ‘Concurrent
Delays In Construction Projects ‘,Journal Of Construction
Engineering And Management,Vol. 113, No. 4, December,
1987.
[2] Assaf, S.A., Al-Khalil, M. And Al-Hazmi, M, ‘Causes Of
Delay In Large Building Construction Projects’, Journal Of
Project Management In Engineering Asce, 2; 45-50, 1995.
[3] Stuart H. Bartholomew, ‘Concurrent Delays In
Construction Projects'’, J. Constr. Eng. Manage. 1989.
[4] J. K. Yates, ‘Construction Decision SupportSystemFor
Delay Analysis’, J. Constr. Eng. Manage. 1993
[5] SawsanRasheed Mohammed,’ Construction Delay
Analysis Using Daily Windows Technique’, Journal Of
Engineering, Volume 17 February 2011.
[6] Jonathan Jingsheng Shi And David Arditi,’
Construction Delay Computation Method,’ Journal Of
Construction Engineering And Management /
January/February 2001
[7] AradhanaRathod,’ Delays In Residential Building
Construction’,InternationalJournalOfInnovativeResearch&
Development, Vol 2 Issue 5, 2013.
[8] John Christian And Daniel Hachey,’ Effects Of Delay
Times On Production Rates In Construction’, Journal Of
Construction Engineering And Management, 1995
[9] M. Z. Abd. Majld1 And Ronald McCaffer, Factors Of
Non-Excusable Delays That Influence Contractors'
Performance,’JOURNALOFMANAGEMENTINENGINEERING,
1998
[10]Said Kartam , ‘Generic Methodology For Analyzing
Delay Claims’, JOURNAL OF CONSTRUCTION ENGINEERING
AND MANAGEMENT, 1999
[11] Syahira Nabilla Ahmad Hisham1, Dr Khairulzan
Yahya1, CAUSES AND EFFECTS OF DELAYS IN
CONSTRUCTION INDUSTRY,2015
[12]Twana Ahmed Muhammed, DELAYS IN
CONSTRUCTION PROJECTS, 2015
[13] Divya.R, S.Ramya, CAUSES, EFFECTS AND
MINIMIZATION OF DELAYS IN CONSTRUCTION PROJECTS,
ISSN: 2348 – 8352, 2015
[14] Mohamed Babikir Ibrahiem Mohamed, A STUDY OF
PROJECT DELAY IN SUDAN CONSTRUCTION INDUSTRY,
2015

More Related Content

What's hot

Management For Construction Project:-Various Aspects Of Delay
Management For Construction Project:-Various Aspects Of DelayManagement For Construction Project:-Various Aspects Of Delay
Management For Construction Project:-Various Aspects Of DelayIRJET Journal
 
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...Gaurav Verma
 
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsDELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsTwana Ahmad
 
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsExploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsIRJET Journal
 
Analysis of factors contributing delays and claims in
Analysis of factors contributing delays and claims inAnalysis of factors contributing delays and claims in
Analysis of factors contributing delays and claims ineSAT Publishing House
 
“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”IOSR Journals
 
Managing the Construction Claims Effectively
Managing the Construction Claims EffectivelyManaging the Construction Claims Effectively
Managing the Construction Claims EffectivelySHAZEBALIKHAN1
 
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )Engr_Emad Khan
 
IRJET- Review: Factors Affecting Scheduling of Multiple Projects
IRJET- 	  Review: Factors Affecting Scheduling of Multiple ProjectsIRJET- 	  Review: Factors Affecting Scheduling of Multiple Projects
IRJET- Review: Factors Affecting Scheduling of Multiple ProjectsIRJET Journal
 
1% AIMS Improving Construction productivity. November 30th 2015.
1% AIMS Improving Construction productivity.  November 30th 2015.1% AIMS Improving Construction productivity.  November 30th 2015.
1% AIMS Improving Construction productivity. November 30th 2015.kiebut
 
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...IJERA Editor
 
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTSFACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTSIAEME Publication
 
Delay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index MethodDelay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index MethodIRJET Journal
 
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTSISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTSIAEME Publication
 
A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...
A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...
A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...IRJET Journal
 
Implementation of Last Planner System and Challenges Encountered in an Indian...
Implementation of Last Planner System and Challenges Encountered in an Indian...Implementation of Last Planner System and Challenges Encountered in an Indian...
Implementation of Last Planner System and Challenges Encountered in an Indian...IRJET Journal
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET Journal
 
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time ManagementIRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time ManagementIRJET Journal
 

What's hot (20)

Time overruns
Time overrunsTime overruns
Time overruns
 
Management For Construction Project:-Various Aspects Of Delay
Management For Construction Project:-Various Aspects Of DelayManagement For Construction Project:-Various Aspects Of Delay
Management For Construction Project:-Various Aspects Of Delay
 
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
 
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsDELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
 
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsExploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
 
Analysis of factors contributing delays and claims in
Analysis of factors contributing delays and claims inAnalysis of factors contributing delays and claims in
Analysis of factors contributing delays and claims in
 
“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”
 
Managing the Construction Claims Effectively
Managing the Construction Claims EffectivelyManaging the Construction Claims Effectively
Managing the Construction Claims Effectively
 
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
 
IRJET- Review: Factors Affecting Scheduling of Multiple Projects
IRJET- 	  Review: Factors Affecting Scheduling of Multiple ProjectsIRJET- 	  Review: Factors Affecting Scheduling of Multiple Projects
IRJET- Review: Factors Affecting Scheduling of Multiple Projects
 
20320140503023
2032014050302320320140503023
20320140503023
 
1% AIMS Improving Construction productivity. November 30th 2015.
1% AIMS Improving Construction productivity.  November 30th 2015.1% AIMS Improving Construction productivity.  November 30th 2015.
1% AIMS Improving Construction productivity. November 30th 2015.
 
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
 
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTSFACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
 
Delay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index MethodDelay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index Method
 
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTSISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
 
A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...
A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...
A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...
 
Implementation of Last Planner System and Challenges Encountered in an Indian...
Implementation of Last Planner System and Challenges Encountered in an Indian...Implementation of Last Planner System and Challenges Encountered in an Indian...
Implementation of Last Planner System and Challenges Encountered in an Indian...
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
 
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time ManagementIRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
 

Similar to Delay Analysis in Construction of Redevelopment Residential Project

IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET-  	  Identification of Constraints and there Impact on Construction Pro...IRJET-  	  Identification of Constraints and there Impact on Construction Pro...
IRJET- Identification of Constraints and there Impact on Construction Pro...IRJET Journal
 
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTHOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTIRJET Journal
 
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET Journal
 
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET Journal
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsDr. Amarjeet Singh
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewIRJET Journal
 
Impact of delayness on construction projects
Impact of delayness on construction projectsImpact of delayness on construction projects
Impact of delayness on construction projectsIRJET Journal
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET Journal
 
Application of last planner system
Application of last planner systemApplication of last planner system
Application of last planner systemAnshi Verma
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...IRJET Journal
 
Delay Analysis for an On-Going Residential Project
Delay Analysis for an On-Going Residential ProjectDelay Analysis for an On-Going Residential Project
Delay Analysis for an On-Going Residential ProjectIRJET Journal
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET Journal
 
IRJET- Enhancement of Highway Project Performance using Lean Construction Method
IRJET- Enhancement of Highway Project Performance using Lean Construction MethodIRJET- Enhancement of Highway Project Performance using Lean Construction Method
IRJET- Enhancement of Highway Project Performance using Lean Construction MethodIRJET Journal
 
A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...IRJET Journal
 
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...IRJET Journal
 
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting InflationIRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting InflationIRJET Journal
 
IRJET- Delay in Construction its Causes and Mitigation: A Review
IRJET-  	  Delay in Construction its Causes and Mitigation: A ReviewIRJET-  	  Delay in Construction its Causes and Mitigation: A Review
IRJET- Delay in Construction its Causes and Mitigation: A ReviewIRJET Journal
 
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Sankalp Swarnkar
 
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTINVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTIRJET Journal
 
A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsRick Vogel
 

Similar to Delay Analysis in Construction of Redevelopment Residential Project (20)

IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET-  	  Identification of Constraints and there Impact on Construction Pro...IRJET-  	  Identification of Constraints and there Impact on Construction Pro...
IRJET- Identification of Constraints and there Impact on Construction Pro...
 
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTHOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
 
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
 
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure Projects
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A Review
 
Impact of delayness on construction projects
Impact of delayness on construction projectsImpact of delayness on construction projects
Impact of delayness on construction projects
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
 
Application of last planner system
Application of last planner systemApplication of last planner system
Application of last planner system
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
 
Delay Analysis for an On-Going Residential Project
Delay Analysis for an On-Going Residential ProjectDelay Analysis for an On-Going Residential Project
Delay Analysis for an On-Going Residential Project
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
 
IRJET- Enhancement of Highway Project Performance using Lean Construction Method
IRJET- Enhancement of Highway Project Performance using Lean Construction MethodIRJET- Enhancement of Highway Project Performance using Lean Construction Method
IRJET- Enhancement of Highway Project Performance using Lean Construction Method
 
A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...
 
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
 
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting InflationIRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
 
IRJET- Delay in Construction its Causes and Mitigation: A Review
IRJET-  	  Delay in Construction its Causes and Mitigation: A ReviewIRJET-  	  Delay in Construction its Causes and Mitigation: A Review
IRJET- Delay in Construction its Causes and Mitigation: A Review
 
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
 
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTINVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
 
A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction Projects
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGSIVASHANKAR N
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxfenichawla
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 

Recently uploaded (20)

MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 

Delay Analysis in Construction of Redevelopment Residential Project

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 37 DELAY ANALYSIS IN CONSTRUCTION OF REDEVELOPMENT RESIDENTIAL PROJECT Rashmi. M. Bijwar1, Prof. Dr. A. B. More2 1P.G. Scholar Department Civil Engineering TSSM’s PVPIT, SPPU Pune, Maharashtra, India 2Head of Department, Civil Engineering TSSM’s PVPIT, SPPU Pune, Maharashtra, India ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract - Delays of a developmentventure ischaracterized as late fulfilment of the venture when contrasted with the arranged timetable. Development delays are frequently after effect of miscommunication between contractual workers, subcontractors, proprietors and providers. These types of unrealistic exceptions are usuallyavoidedby using acleanand efficient planning mechanism, which clearlyspecifiesthework and timetable to be used. Delays in construction projects are quite expensive; sometimes they may result in severe damages to the involved parties. This thesis concentrates on investigation of centre components that are bringing about deferrals and breaking down the everyday records to limit delays. The current study is undertaken on Construction of High rise residential building project in Andheri, Mumbai. The project is reconstruction of G+13 floor High rise Residential Building and is scheduled to complete in 47 Months including all sanctioning and redevelopment processes. The study is being conducted on various factors that were causing the delays in project. The causes, resources and the discrete methods on nonetheless to derogate the delays in the ordering locality arenoteddownregularly. Theday-to-day data is regularly collected from site. Beginning time, completing time, Also span is recorded over misundertaking differentiating undertaking Furthermore basic movement alongside the delays brought about What's more purposes behind those delays. A questionnaire may be arrangedposting crazy Different variables helping to delay under diverse classifications In light of perceptions In developmentwebpage Furthermore from a few diary papers as reference. Thosesees on the same starting with Different gatherings includedOnan undertaking similar to those builder/developer, foreman What's more consultants are moaning in the questionnaire. Each component will be provided for An weight-age landed at utilizing filled-up questionnaires, using, whichthose mossy cup oak persuasive elements would recognized. Key Words: Delays in construction project1, Redevelopment2,causesfordelays3,impactofdelayson Construction project4, RERA 2016 act5 Box plot6, Demonetization7. 1. INTRODUCTION Clinched alongside construction, the expression ―Delay alludes on something happening toward a after the fact occasion when over planned, expected, specified Previously, an agreement or pastthedatethatthegatherings concurred for the conveyance of a venture. Delay will be those abating down from claiming worth of effort without ceasing development actually Furthermore that might prompt run through overwhelmPossiblypasttheagreement date or past the date that the gatherings bring concurred to the conveyance of the project. Delays classified into non- excusable delays, excusable non compensable delays, excusable compensable delays and concurrent delays[1]. Non-excusable delays are delays, which those foreman whichever reasons alternately accepts the hazard for. Sensible non-compensable delays might delays initiated Eventually Tom's perusing components that need aid not foreseeable, previous those contractor‘s sensible control likewise not attributable of the contractor‘s lack alternately heedlessness. Compensable reasonable delays these are compensable delays are reasonable delays, suspensions, or interruptions should every last bit or and only the worth of effort brought on Eventually Tom's perusing a demonstration or disappointment to enactment by the manager coming about because of owner‘s break for an obligation, stated alternately implied, in the contract. Concurrent delays occur when both owner and the contractor are responsible for the delay. There are three basic ways to categorize type of delays:  Critical and noncritical  Excusable and Non-excusable  Compensable and non-compensable Fig No. 1 Types of delays
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 38 This document is template. We ask that authors followsome simple guidelines. In essence,weask youtomakeyourpaper look exactly like this document. The easiest way to do this is simply to download the template, and replace(copy-paste) the content with your own material. Number the reference items consecutively in square brackets (e.g. [1]). However the authors name can be used along with the reference number in the running text. The order of reference in the running text should match with the list of references at the end of the paper. 1.1Delay Analysis Techniques If or not a delay will be compensable relies principally on the money house under the agreement. In the greater part cases, an agreement particularly notes the sorts about delays that need aid non-compensable,forwhichthose foreman doesn't accept any extra cash yet all the might make permitted a period development. DelayexaminationmaybeAnexplanatoryprocedure that ought to a chance to be utilized for task documentation alongside gathered information starting with one task site. Those determinations aboutdelay Investigationreliesonthe mixed bag about Components and the accessible records. There are five commonly used delay techniques. 1. Impacted as-planned method 2. Time impact analysis method 3. Collapsed as-built or ‗but-for analysis method 4. Snapshot/windows/time slice analysis method 5. As-planned versus as-built windows analysis method 1.2 Cause Effects Relationship of Construction Delays Fig. No. 2 Cause Effects Relationship of Construction Delays [6] 2. LITERATURE REVIEW Construction industry is large, volatile and required tremendous capital outlays. Delays are one of the major risk factors in project. Bramble and Callahan(1987)havedefined that “a delay is the time during which some part of the construction projecthasbeenextendedornotperformeddue to an unanticipated circumstance”[3]. Likewise a critical contribution, this investigation. Hails crazy with experimental relationship the middle of makes Also impacts of postponements Likewise the third destinationas. Talked about in the dialogover.Trustthatthis study might a chance to be an assistance of the professionals (clients,. Consultants What's more contractors) and also academicians will An finer see all the over the project. Oversaw economy Furthermore aggravate deliberations to decrease the development postponements. says Syahira Nabilla Ahmad Hisham (2015)[11] Delays in construction projects are a widely researched area for which more researches are constantly being carried out. Due to the wide coverage of construction projects in terms of size, type, geography and so on, there is still the need to investigatethe causes and assess the effect of delays on various construction projects at various levels. This may eventually lead to the muchneededdevelopmentin the industry. For this reason, this researcher sought to analyze the construction of government road projects in Kurdistan Region to address the inefficiencies in the system and prescribe some solutions to mitigate them. Studied by Twana Ahmed Muhammed, 2015, [12] As per Divya.R, S.Ramya, The objective of this study is to identify the major causes of construction delays, its effects, and minimizing delays in construction projects. This study is carried out based on literature reviews and questionnaire survey.2015, [13] 2.1 PROJECT DISCRIPTION The project was carried out in a site which is in Andheri, Mumbai, Maharashtra which is a construction of High rise residential project by Westin Developers, which is planned forconstruction of stilt +13 Floors for26 Units of Residential Flats. WESTIN is a firm which deals with the construction related projects. JAONITA project is handle by Westin Developer itself. MCGM i.e. Municipal CorporationOfGreater Mumbai is the sanctioned authority for above project. This project is a part of redevelopment agreement between land owner and the builder. Past days eight story building was there in which each floor having two flats i.e, there are total number sixteen tenants including land owner are there in redevelopment agreement. This project was scheduled for 40 months from the date of site clearance. This project was schedules forAsthiswasredevelopment project most of the time consumed by the project was government sanctioning and commencement certification approval. whichleads to lengthyprojectactivity andacapital loss. One of the biggest issue was randomly changed in
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 39 government policiesinconstructionindustries.in2015-2016 there was a biggest issue regarding sand availability. Which leads to delays in construction in all over Maharashtra. Not only sand butalso differentmaterialwerelimitedinthatspan of construction industries. 3. PROBLEM STATEMENT Numerous development undertakings need faced Different issues What's more delay for time may be a standout amongst those real issues. The delay in debate settlement need pronouncement impacts for example, such that it will provideforimpeding of the associationthemiddle of holder and foreman. Those foreman and the manager pay for those additional accuse to the fruition of the venture because of delay over vast development ventures. The point when the fruition period of the development one task surpasses those consented fruition time, it will be known as development undertaking delay. It may be required to direct nitty grittyexaminationAlsoIDnumberaboutdelayelements et cetera selecting the straight activities with counter theses delay elements insideexpense Also looking after nature. The faults and errors due to the contractor cause delays and waste of capital and time. Thosecurrentponderconcentrates looking into Different Components bringing on those delays especially for much off spots the place assets ought make transportedstartingwithsignificantlyoffspotswhichrequire All the more chance Also cash What's more the place new fill in requirement to a chance to be carried out straight from those uncovering such as evacuating trees Furthermore impacting few puts which can't a chance to be excavated Toward hardware. This study attempts to generalize. 4. AIM AND METHODOLOGY Aim :- To find out causes in residential redevelopment construction project in Mumbai and give methodologies to minimize delays and its effects Objective of Study The current objectives of proposed project work are: 1. To identifyvariouscausesofdelayandtheir effect on cited project 2. To Prepare and schedule the baseline program and update using MS project. 3. To identify the delay duration of each activity and estimate the extensiontimerequiredfor the final completion of project. 4. To collect responsesfromClient,contractor and consultant in construction industry for this site. 5. To analyze the collected responses by conducting one-way ANOVAanalysis using Minitab. 6. Toidentifythemostresponsiblefactorsthat cause and effect the delay and to propose methods to minimize delay. 4.1 Methodology Strategy of methodology was done step by step which includes literature review, questionnaire and data collection from all possible sources. Fig. No. 3 Methodology flowchart 5. DATA COLLECTION AND ANALYSIS Data collection for project details collected from journals, internet, books and by experts interviews. The owners, Contractors, Consultants, Labours, Tenants, Project managers and involved people were targeted forsurvey.The derails of various stakeholders and needed data were collected from project manager of the site. Fig. No. 4 Work done sequence 5.1Questionnaire Methodology Those review may be planned built to utilize Likert scale on the destination of the study shouldfigureoutthosereason for delays Previously, development activities Furthermore impact of the delays once generally project. The study is encircled over such an approach that the particular perspective fordistinctive individuals included in distinctive tasks may be gathered Furthermore investigated. That questionnaire essentially comprisesabout fourareasasnitty gritty beneath. 1. Respondent foundation - thiswill be ongatherthose fundamental data of the respondent. 2. Reason fordelays - this is usedtogatherinformation those information on separate reason for the delays happened in that specific venture.
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 40 3. Impacts from claiming delays - utilizing these inquiries those impacts of the delays on the project would distinguish. 4. Measures to Minimizingdelays-themostrecentand only those overview comprises of inquiries in regards to the systems they used to decrease the delays if At whatever. The collected data is analyzed using Minitab software to find out the major causes of delay, the effects of the delayand how to minimize the delay of a construction project. Fig. No. 5 Analysis programme 5.2 MSP, LIKERT SCALE, SCORING AND ANOVA ANALYSIS 5.2.1MSP Microsoft project, herein after MSP may be An product device created Eventually Tom's perusing Microsoft should deal with What's more examine schedules. Furthermore will be client cordial permitting you to begin planning exercises instantly. MSP will be fit from claiming handling OK reports What's more graphs in a matter of moments. Development activities oblige occasional plan update, which goes about similar to an evaluation of the venture status Furthermore prediction for how and when those task will make finished. Those real steps On overhauling a plan include. 1. Setting a benchmark. 2. Overhauling those plan. 3. Thinking about the calendar updates. MSP need large portions interesting features particularly intended with aggravate utilizing the product basic.Nonetheless At it hailswithoverhaulingaplanutilizing MSP, development schedules frequently Figure MSP greatly befuddling. This is basically because of those MSP straightforwardness to utilize obstruction What's more features. 5.2.1 Likert Scale After the questionnaire may be completed, everything might be broke down independently alternately over some instances thing reactions might make summed will make a score to an aggregation for things. Hence, Likert scales are frequently known as summer scales. There need aid two elementary considerations in this exchange. In Likert scales would discretionary. The quality doled out should An Likert thing need no destination numerical basis, Possibly As far as measure hypothesis or scale (from which a separation metric camwood a chance to be determined). The worth allocated should every Likert thing will be essentially decided Eventually Tom's perusing the analyst outlining the survey, who makes the choice dependent upon a wanted level about point of interest. However, Eventually Tom's perusing gathering Likert things tend on make doled out progressive sure basic values. Likert scales regularly go from 2 to 10 – with 5 or 7 constantlythose The majority normal. Further, this progressive structure of the scale will be such-and-such each progressive Likert thing may be treated as demonstrating An ‗better‘reaction over the first esteem. (This might vary clinched alongside instances the place opposite requesting of the Likert scale is needed). The second, What's more potentially a greater amount critical side of the point may be if those ‗distance‘ the middle of each progressive thingclassisequivalent,whichisinferred customarily. For example, in the over five-point Likert item, those induction may be that those ‗distance‘between classification 1 and 2 will be those same Concerning illustration between class 3 Furthermore 4. As far as handy Scrutinize practice, an equidistant presentation by those analysts is important; generally a inclination in the examination might result. For example, An four-point Likert thing forclassifications "Poor", "Average","Good",Also"Very Good" will be farfetched with have know equidistant Classes since there is special case class that could get a underneath Normal rating. This might seemingly inclination any bring about shortages energetic about An sure Conclusion. On the other hand, regardless of a analyst displays what he or she accepts are equidistant categories, it might notachancetobe translated all things considered Eventually Tom's perusing the respondent. A great Likert scale, Likewise above, will exhibit symmetry of Classes something like a midpoint with plainly characterized semantic qualifiers. Done such symmetric scaling, equidistant qualities will regularly be a greater amount plainly watched or, In least, inferred. It will be At
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 41 Likert scale will be symmetricWhat'smoreequidistantthatit will act a greater amount similar to an interval-level estimation. With the goal same time a Likert scale will be to be sure ordinal, whether great exhibited it might All things considered estimated a interval-level estimation. This could make advantageous since, On it mighthavebeendealtwithin the same way that a ordinal scale, At that point exactly profitable majority of the data Might be lost Assuming that those ‗distance‘ the middle of Likert things were not accessible for thought. Reactions on a few Likert inquiries might make summed giving that the sum inquiries utilize the sameLikertscaleand that those scale may be a solid close estimation should an interim scale, to whichinstancethosenationalbreakingpoint hypothesis permits medicine of the information Concerning illustration interim information measuring An idle variable. Whether those summed reactions satisfy these assumptions, parametric Factual tests for example, the examination of fluctuation might make connected. Commonplace cutoffs to keeping in touch with you must be clear in your reasoning that this close estimation will a chance to be adequate is a least from claiming 4 Furthermore preferably 8 things in the entirety of cash. 5.2.3 ANOVA Analysis Analysis of Variance (ANOVA) is used to analyze the differences between group mean. An analysis ofvariancecan be used as an explanatory tool to explain observations. ANOVA is relatively robust procedure with respect to violations of the normality assumption. The assumptions of one-way ANOVA analysis are 1. Response variable residuals are approximately normally distributed. 2. The occurrence of one Sample doesn’t affect the other. 3. The variance of same for each level 4. Responses of given group are independent and identicallydistributed(notasimplerandomsample) 5.3 Questionnaire The inquiries regarding the makes to delays would separate under 7 segments holding 9 inquiries each. Those respondents may be approached to rank each of the accompanying inquiries. Following are two of them. Group-A Owner Contributed Components. 1. Delay in advancement installments. 2. Delay to outfit Also convey the site. 3. Change requests Eventually Tom's perusing holder Throughout development. 4. Latedonechangingandsanctioningplandocuments. 5. Delay done sanctioning shop drawing What's more test materials. 6. Poor correspondence Also coordination. 7. Gradualness to choice making transform. 8. Clashes the middle of joint-ownership of the one task. 9. Suspension from claiming worth of effort Toward manager. Group-B Contractor Contributed variables. 1. Challenges Previously, financing venture. 2. Clashes On sub-contractors calendar for execution of task. 3. RevampbecauseoferrorsThroughoutdevelopment. 4. Clashes the middle of foreman Also different gatherings. 5. Poor correspondence Also coordination. 6. Inadequate arranging What's more planning about undertaking. 7. Shameful development systems execute. 8. Delays over sub-contractors fill in. 9. Insufficient contractor's worth of effort. What's more open strikes. Respondents need aid Additionally required to provide for their assessment on the impacts from claimingdelays.6inquirieswereapproachedin this segment. 1. Time overwhelm. 2. Average cost for basic items. 3. Question. 4. Mediation. 5. Downright abandonment. 6. Litigation The most recent segment incorporates inquiries regarding those steps that ought further bolstering a chance to be taken to stay away from delays over development project. This segment comprises for 12 inquiries. 1. Incessant Advance gathering. 2. Utilize upand coming engineering organizationuse. 3. Use correct What's more current development. 4. Utilize fitting development routines. 5. Compelling vital arranging. 6. Legitimate material acquisition. 7. Exact beginning expense estimates. 8. Reasonable majority of the data and correspondence channels.
  • 6. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 42 9. Incessant coordination the middle of the gatherings included. 10. Fitting stress with respect to previous background. 11. Fitting undertaking arranging and planning. 12. Finish and legitimate outline at the good occasion when. 6. RESULTS AND DISCUSSION 6.1 Data Analysis and Its Results The collected responses from different categories of people involved in construction project. The mean of each group of question is calculated using ANOVA analysis. The final result showing the contribution of different factors on the delay of a construction project is plotted on a pie chart. From the pie chart the contribution of various parties involved in the project are almost same while contractor is more slightly more for delay. 6.1.1 Owner Contributed Factors Respondents are asked to scale the 9 given questions related to the contribution of owner towards the delay in project. Questions are named as BA1 through BA9. Following showing the box-plot for owner’s contribution factor with respect to questionnaire. Above graph showing higher to lower number of factors responsible for days in owner’s view. Higher the number showing good contribution in nullifying delay. And lowerthe number showing factors most responsible. Similarly, contractors, consultants, labours, material, equipments and outercomponentsshooingboxplotsfortheir contributions in delays in construction. 6.2 Factors that cause delays 1) 3. 8 which may be the delay for installments which created delay in the undertaking Similarly as responded from the respondents. 2) The most noteworthy intend in foreman reasons is 3. 9 which may be Poor correspondence and co- ordination initiated a greater amount delay Concerning illustration responded Toward those respondents. 3) The most noteworthy imply On box plot may be 3. 86 which says that insufficient experience about specialist may be those The majority helping make for those delay. 4) Those most astounding reason for delay is late acquisition about materials for those imply about 3. 56 and the following The greater part helping component might make lack for development materials over business. 5) Those most noteworthy mean quality may be 3. 86 which need two reasons to the same intend value, i. E gear breakdown Also low level about supplies operator’s ability are the major makes Similarly as responded starting with the respondents. 6) Those most noteworthy intend starting with those box plot will be 3. 9 which says low benefit from claiming labors will be the real cause Likewise responded Toward the respondents. 7) The followingmostelevatedfoundationwillbedelay is performing last review and Confirmation which need mean quality 3. 36. 6.3 Effects of Delays Due to those Different factors the development venture might a chance to be deferred and the effect will make different contingent upon the states. For A large portion of the activities a period extensions solves those issue same time for exactly others necessity a greater amount cash over evaluated. The place as to other circumstances it mightmake important with suspend those fill in will fathom those issues the middle of separategatheringsorconstantlyongatherings included On venture can't attain aggregate abandonment of the one task if a correct conclusion. This segment's comprises about inquiries identified with those effect of the postponements. The six inquiriesneedaid. 1. Time overrun 2. Cost overrun 3. Dispute 4. Arbitration 5. Total abandonment 6. Litigation
  • 7. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 43 6.4 Steps to Avoid Delays Following are some methods or steps to avoid time overrun in construction of project. 1. Incessant Advance meeting. 2. Utilize up and coming engineering usage. 3. Use correct modern type construction to date development. 4. Utilization suitable development systems. 5. Successful vital planning. 6. Best possible material acquisition. 7. Exact starting expense estimates. 8. Clear majority of the data and correspondence channels. 9. Incessant coordination the middle of the gatherings included. 10. Fitting accentuation for past work experience. 11.Proper project arranging and planning. 12. Finish and best possible configuration toward the straight the long time. 13. Always planned for backup situations for 3M's i.e. materials, man and machineries. 7. EFFECTS OF RERA AND DEMONETIZATION ON CONSTRUCTION INDUSTRY A) Delays done developmentgenerallyinfluencesthose economy for contractor, holder and consultants. Which specifically trouble fundamental money to task. However these days delays not just influence three Classes Likewise stated overaswellasthosepurchaserclinchedalongsidenew structure. A year ago administration for India made new go about for development business and that is RERA (Real bequest administrative power Act, 2016). Land of land administrative power Also investigative tribunal it will assistance with secure state-level land administrative powers (RERAs) on control transactions identified with both private What's more business ventures Furthermore guarantee their auspicious fruition Furthermorehandover.InvestigativeTribunalswillpresently be required will settle instances On 60 days Similarly as against the prior procurement for 90 days Also administrative powers on discard objections for 60 days same time no time allotment might have been shown Previously, prior bill. If RERA is properly implemented on construction work then automatically there will be less percentage on construction delays as well as cost and time overrun. Due to fear of giving penalty and extralossofcapital builders has to work out fast for construction of any structure. He will work properly, on time working process B) Demonetization for Rs. 500 Also Rs. 1,000 notes Toward those legislaturefromclaimingIndiamaybeastrong act Also welcoming person. Those storing about cash Eventually Tom's perusing corrupt individuals prompted twofold pronged effect on the economy. Those grade deals section will be generally impacted by home fund players, Furthermore bargainshaveatendencyto be encouraged clinched alongside An transparent way. This section will thusly see best case scenario a constrained sway in the bigger cities, however A percentage level 2 Also level 3 urban areas the place money segmentsneedbeenanelement Significantly over elementarydeals willperceiveabenefitsof the business crunch. The optional or resale advertise will, however, absolutely make impacted, provided for the truth that this section does view the inclusion of money part. C) In construction with heavy use of Cement and concretethere is high percentage of CO2 emissioneveryyear which leads to make polluted air every time. If project progress held for long lasting time it will create more nuisance for near about locality and make Low immunity of human as well as for animals. Pollution like Noise Pollution,LandPollution,Segregation also equally affect due to long construction period. So to minimize environmental impacts, long term cost and time overrun, and heavy capital losses we need to manage project from its start to Decrease delays. 8. CONCLUSION Those reactions gathered starting with the respondents make it obvious that very nearly the sum parties holds almost equivalent obligationto the delaysclinchedalongside project. and from the above analysis I conclude following conclusions:-  Delays in instalments i.e,paymentsleadstodelaysin construction.  Poor Co-ordination from contractors side.  Absence of qualified labour, supplies and material when necessary.  Overall timeoverrun foraboveprojectwas369days from the planning of the project.  From box plot analysis it shows most significant delays from constructors for poor communication and from low productivity labours i.e. 3.9.  Maximum delays was appeared in government sanctioning process i.e. receiving of commencement certificates up to 4th floor and delay was 4 months, for 6th floor delay was 4 months, for 7thfloor delay was calculated as 4 monthsand for9th floor it was3 months. Respondents communicated that incessant Advance meeting, exact beginning expense estimation, powerful vital arranging and legitimate acquisition need aid those Components that ought further bolstering a chance to be
  • 8. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 44 acknowledged Also controlled should minimize those Generally speaking one task delays. BIBLIOGRAPHY [1] Zaki M. Kraiem And James E. Diekmann, ‘Concurrent Delays In Construction Projects ‘,Journal Of Construction Engineering And Management,Vol. 113, No. 4, December, 1987. [2] Assaf, S.A., Al-Khalil, M. And Al-Hazmi, M, ‘Causes Of Delay In Large Building Construction Projects’, Journal Of Project Management In Engineering Asce, 2; 45-50, 1995. [3] Stuart H. Bartholomew, ‘Concurrent Delays In Construction Projects'’, J. Constr. Eng. Manage. 1989. [4] J. K. Yates, ‘Construction Decision SupportSystemFor Delay Analysis’, J. Constr. Eng. Manage. 1993 [5] SawsanRasheed Mohammed,’ Construction Delay Analysis Using Daily Windows Technique’, Journal Of Engineering, Volume 17 February 2011. [6] Jonathan Jingsheng Shi And David Arditi,’ Construction Delay Computation Method,’ Journal Of Construction Engineering And Management / January/February 2001 [7] AradhanaRathod,’ Delays In Residential Building Construction’,InternationalJournalOfInnovativeResearch& Development, Vol 2 Issue 5, 2013. [8] John Christian And Daniel Hachey,’ Effects Of Delay Times On Production Rates In Construction’, Journal Of Construction Engineering And Management, 1995 [9] M. Z. Abd. Majld1 And Ronald McCaffer, Factors Of Non-Excusable Delays That Influence Contractors' Performance,’JOURNALOFMANAGEMENTINENGINEERING, 1998 [10]Said Kartam , ‘Generic Methodology For Analyzing Delay Claims’, JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 1999 [11] Syahira Nabilla Ahmad Hisham1, Dr Khairulzan Yahya1, CAUSES AND EFFECTS OF DELAYS IN CONSTRUCTION INDUSTRY,2015 [12]Twana Ahmed Muhammed, DELAYS IN CONSTRUCTION PROJECTS, 2015 [13] Divya.R, S.Ramya, CAUSES, EFFECTS AND MINIMIZATION OF DELAYS IN CONSTRUCTION PROJECTS, ISSN: 2348 – 8352, 2015 [14] Mohamed Babikir Ibrahiem Mohamed, A STUDY OF PROJECT DELAY IN SUDAN CONSTRUCTION INDUSTRY, 2015