SlideShare a Scribd company logo
A Presentation on

PRINTED CIRCUIT BOARD
ASSEMBLY
KIRAN HANJAR

1
Aim of the Presentation
• Understanding PCB assembly using simulation with
DOE approach
• To assess the feasibility of process flow logic and
relative impact of changing line configurations
• It is aimed to identify constraints or bottlenecks and
development of improvement strategies accordingly
• By using DOE, the factors that are affecting the system’s
efficiency are identified
• Finally to improve the system’s overall performance

2
Introduction
Printed circuit board (PCB) assembly
•Printed circuit board (PCB) assembly lines fall under the general
category of serial production lines
•Common problems faced in these lines include designing
configuration of existing or future lines to meet target production
rates
•Simulation modeling can capture the complex behaviour and
interaction between various components of PCB assembly lines
•This is very much important to analyze and help to make better
decisions

3
Introduction
Printed Circuit Board Manufacturing
•PCB can be classified into two categories based on the type
of components placed on the board
– Surface Mount Technology (SMT)
– Insertion Mount Technology (IMT)

Six steps involved in SMT manufacturing are explained as
follows:
• Attachment Media Dispensing
•Component Placement
•Curing
•Soldering
•Cleaning
•Testing
4
General steps involved in SMT process for PCB
assembly
SOLDER
PASTE
APPLICATION

INVERT
BOARD

REFLOW
OVEN

COMPONENT
PLACEMENT

YES

OTHER
SIDE
NEEDED
SMC’s

NO

TEST

CLEAN

PASS?

NO
REPAIR

YES

SHIP

FINISHED
Source: (Hollomon,
BOARD

5
1989) and (Capillo,
With the help of Cause and Effect Diagram factors which are affecting
throughput are identified
PERSONNEL

MATERIALS
Paste Type

Handling
Rework

Components
Board

Setup
THROUGHPUT

In-Circuit Testing

TESTING

Board
Functional
Testing

Screen
Printing

Component
Placing

MACHINE

Cause and Effect Diagram for PCB assembly line

Generally in PCBA solder paste, Component placement, ICT, BFT ,
Rework creates variability in process time

6
DOE
• Systematic Plan of investigation using principles of statistics
wherein response or output value is obtained by varying factors/
levels or a combination of factor level
• 5 factors , 2 levels (high and low) are considered , 25 full factorial
design is made to anlayse the model
PARAMETERS
SOLDER PASTE
COMPONENT PLACING
ICT
BFT
REPAIR

FACTOR LEVEL
( LOW )
5
7
5
15
5

FACTOR LEVEL
(HIGH)
7
12
15
40
20

C.V for low level and high level are 0.1 and 0.4 respectively

7
Simulation Modeling and Analysis
The steps involved in a simulation
•Input analysis: involves collection and analysis of data, and
definition as well as validation of conceptual model
•Model development: involves simulation model development
followed by verification and validation of the simulation model
•Output analysis: where performance metrics of the system are
determined and analysed

Some of the advantages of simulation are:
•Simulation offers better control over experimental conditions
•Animation provided by simulation enables better understanding of
the system
•Alternative proposed system configurations can be compared
using simulation
8
Model Building
It involves six steps as shown in the figure
Collect i/p
data

Develop static
model

Validate
simulation
model

Run current
configuration
Yes
Analyse the
system

Potential
improvements

Modify
configuratio
n

No
Stop
Source :(Mukkamala, Smith & Valenzuela, 2003)

9
Step 1 : Collect input data
This data may be extracted from historical databases of the line
under consideration (if the manufacturing line already exists) or
a similar line (if line is non-existent, i.e. proposed).
•Machine Data
•Operator data
•Inspection and rework data
•Oven data
•Buffer data
•Conveyor data
•Traverser/shuttle data
For a PCB that has to get shipped it has to start from Solder paste
assembly then to component placement, Reflow oven, Pin through
holes, Wave soldering, In-circuit testing, Final mechanical assembly,
Board functional testing, Repair if any and finally to packing.
10
Reflow Oven

Cooling

Solder paste
Assembly
Component
placing

Yes

PTH

Wave Soldering

ICT

No

Final
Mechanical
assembly

Repair

Yes
BFT

Ship
No

Disassemble

The simulation model of Printed Board
Circuit Assembly

Rework
11
Process carried out in each Section
Solder Paste Assembly
•In PCBA the paste printing process accounts for the majority of
assembly defects
•Over sixty percent of all soldering defects are due to problems
associated with the screening process
•Parameters such as squeegee pressure, squeegee speed, stencil
separation speed, snap-off and stencil cleaning interval are the most
important factors in the process to achieve a better yield
•The set up time taken is around five to seven minutes, two minutes
is required to paste on stencil to get completed, Board printing
takes one minute and visual inspection takes around two minutes
and vary depending on the complexity of the board
• So the time taken for the entire process is around six minutes
12
Component Placing
• In the pick & place station, only one components is taken
from the component feeder by means of a vacuum pipette,
and is placed on the PCB
• Based on the complexity of the PCB the process time varies
between seven and twelve minutes

13
Reflow oven
• A reflow oven is a machine used primarily for reflow
soldering of surface mount electronic components to printed
circuit boards
• The oven contains multiple zones, which can be individually
controlled for temperature
• The PCB moves through the oven on a conveyor and is therefore
subjected to a controlled time-temperature profile
• Some ovens are designed to reflow PCBs in an oxygen-free
atmosphere. Nitrogen (N2) is a common gas used for this purpose.
This minimizes oxidation of the surfaces to be soldered

14
In-Circuit Test (ICT)
•

Here, checking for shorts, opens,
resistance, capacitance, and other
basic quantities which will show
whether the assembly was correctly
fabricated
• It may be performed with a bed of
nails type test fixture and specialist
test equipment
• Based on the design of the circuit
and complexity it takes around five
to fifteen minutes to undergo this
process
Industrial printed circuit board being tested with a
modern digital oscilloscope an oscilloscope
15
Board Functional Test (BFT)
• Functional test (FCT) is used as a final manufacturing step
providing a pass/fail determination on finished PCBs before they
are shipped
• To validate that product hardware is free of defects that could,
otherwise, adversely affect the product’s correct functioning in a
system application
• Requirements of a functional test, its development, and procedures
vary widely from PCB to PCB and system to system
• The most common form of functional test, known as “hot mock-up”
simply verifies that the PCB is functioning properly
• Generally time taken to undergo functional test is between fifteen
and forty minutes

16
Step 2 : Develop Static Model of the
Process Line
• Based on the input data collected, a static model is prepared for
the validation and benchmarking of the simulation model
• Static model is a spreadsheet based model developed using the
mean values of cycle times, utilization time and failure
• Then, the throughput which is the least among all the machines or
processes is identified as the throughput of the whole line

In doing so, these things are should be ignored:
• The inherent interdependence between the processes (induced by
the capacitated buffers).
• The variability (induced by the unpredictable breakdowns and
component part exhaustions)
17
Input Datasheet
Sl no

Process

Time distribution in min

1

Solder paste assembly

NORM (6. 1.2)

2

Component placement

BETA (12, 7)

3

Reflow oven

NORM ( 4, 0.1)

4

Cooling

NORM (1, .05)

5

Pin through hole

NORM ( 4 , 0.5)

6

Wave Soldering

NORM ( 3.5, 0.5)

7

ICT

BETA ( 15, 5)

8

Repair(ICT)

BETA ( 20, 5)

9

Final mechanical assembly

NORM ( 4, 0.5)

10

BFT

BETA ( 40, 15)

11

Disassemble

NORM ( 2, .05)

12

Rework (BFT)

BETA (20, 5)

By using Arena software PCB Assembly line is built and respected
inputs are tabulated at every section and Run simulation. From the
result obtained analysis is done

18
Run Current Configuration
Arriv e

Arrive 1

Serv er

Serv er

Serv er 1

Serv er

Server 2

Server 3

?
In s p ec t

Inspect 1

Serv er

Serv er

Serv er

Serv er 6

Server 5

Server 4

?
Serv er

In s p ec t

Server 8

Inspect 2

Dep a rt

Depart 1

Serv er

Serv er

Server 9

Server 7

Si m u la te

PCb assembly
500

It took 252 min to complete the assembly process for a batch of 10 PCB

Serv er

Serv er 10

19
Analysing the variability using DOE
• To understand the behaviour of the system to a next level the factors
(process) that are creating the variables are identified
• For the current model five factors are taken into account they are:
– Solder paste assembly
– Component Placing
– ICT
– BFT and
– Rework
• By taking low level and high level concentration 25 factorial design is
made
• To eliminate the bias randomization is done as shown in the following
table
• In the table below : A- Solder paste assembly process time, Bcomponent Placement process time, C – ICT Processing time, D- BFT
Processing time, E- time taken to repair, I- process time taken for ten
20
batches.
The simulation model is run accordingly to the random number assigned to the
order number and the obtained results are analysed using MINITAB software 21
Main Effects Plots

From the Main Effects plot for Time , Factor D i.e., Board
Functional Test is one which is causing delay in process time
than the other factors
22
Estimated Effects and Coefficients for
TIME(min) (coded units)

23
Analysis of Variance for TIME(min)
(coded units)
Source
Main Effects
2-Way Interactions
3-Way Interactions
4-Way Interactions
5-Way Interactions
Residual Error
Total

DF
5
10
10
5
1
0
31

Seq SS
688160
2496
746
187
55
*
691644

Adj SS
688160
2496
746
187
55
*

Adj MS
137632
250
75
37
55
*

F P
* *
* *
* *
* *
* *

• From the Main effects plots and ANOVA table it is found that BFT
plays a significant role in process. Simulation showed that the
Bottleneck created in this section and there were queue of PCB
that has to wait.
• In order to improve the system it is better to provide a one more
BFT section (parallel).

24
Conclusion
•
•

•
•

•
•

These topics help us to know the problem of simulation modeling and analysis of
PCB assembly lines
This is an important problem as line managers and decision makers of PCB
assembly lines often face situations like designing configuration of entire line for
new product etc, by using simulation concepts and software one can take a
quantitative decisions but it is left to the line managers ability and experience to
take the qualitative decisions
By the help of Simulation one can understand visualise some more things such as
buffer, bottleneck etc.
By using Design of experiments, the factors that are affecting the model flow and
also provide valid information whether to add a new line in the production to
meet the demand or remove the parallel lines if the demands are not so good,
without affecting the actual flow line.
As in this case it clearly stated there is need for adding another line for BFT
section in order to avoid blocking, bottlenecks etc.
Hence with help of quantitative results and qualitative aspects optimal solution for
any kind of problems can be found out
25
References
•
•
•
•
•
•
•
•
•
•
•
•
•

Law, A. M. and Kelton, D. W. (2000). Simulation Modeling and Analysis. McGraw-Hill Companies, Inc.
Papadopoulos, H.T. and Heavy, C. (1996). Queuing theory in manufacturing systems analysis and design: a
classification of models of production and transfer lines. European Journal of Operations Research,92, 1-27.
Heavy, C., Papadopoulos, H.T., and Browne, J. (1993). The throughput rate of multistation unreliable production
lines.European Journal of Operational Research68(1), 69-89.
Hollomon, James K. Jr. (1989). Surface mount technology for PC board design.Indianapolis: Howard W. Sams &
Company.
Goss, G.B. (2000). Measuring machine interference to evaluate an operator cross-training program. M.S. thesis.
Massachusetts, MA: Massachusetts Institute of Technology.
D’Souza, R.C. (2004) A throughput-based technique for identifying production system bottlenecks. M.S. thesis.
Mississippi, MI: Mississippi State University.
Capillo, C. (1990). Surface Mount Technology: materials, processes, and equipment. McGraw-Hill Publishing
Company.
Kamath, M. (1999). Recent development in modeling and performance analysis tools for manufacturing systems. In:
S. B. Joshi and J. S. Smith, Computer Control of Flexible Manufacturing Systems, (pp.231-263). Chapman and Hall.
Law, A.M. and McComas, M.G. (1997). Simulation of manufacturing systems. Proc. of 1997 Winter Simulation Conf.,
86-89
Kotcher, R.C. (2001). How “overstaffing” atbottleneck machines can unleash extra capacity. Proc. of the 2001 Winter
Simulation Conference, 1163-1169.
Conway, R., Maxwell, M., McClain, J.O., and Thomas, J.L. (1988). The role of work-in process inventory in serial
production lines. Operations Research,36(2), 229-241.
Simulation modeling and analysis of printed circuit board assembly lines: Pradip Dinkarrao Jadhav
Design and Analysis of Experiments. 5th edition, Douglas C.Montgomery, Wiley student edition .

26
Thank you

Kiran Hanjar S
1MS12MIA03
II Sem, IE M.TECH
MSRIT
27

More Related Content

What's hot

pcb
pcbpcb
Package fabrication technolog ynew
Package fabrication technolog ynewPackage fabrication technolog ynew
Package fabrication technolog ynew
prashant singh
 
Pcb manufacturing
Pcb manufacturingPcb manufacturing
Pcb manufacturing
Clement Ang
 
Pcb design guidelines
Pcb design guidelinesPcb design guidelines
Pcb design guidelines
eddyboadu
 
Double sided PCB manufacturing
Double sided PCB manufacturingDouble sided PCB manufacturing
Double sided PCB manufacturing
Aditya Todi
 
IC Packaging
IC PackagingIC Packaging
IC Packaging
santoshnimbal
 
Physical Verification Design.pdf
Physical Verification Design.pdfPhysical Verification Design.pdf
Physical Verification Design.pdf
Ahmed Abdelazeem
 
Three dimensional integrated circuit
Three dimensional integrated circuitThree dimensional integrated circuit
Three dimensional integrated circuit
Arqam Mirza
 
Surface mount technology (smt) and smd packages
Surface mount technology (smt) and smd packagesSurface mount technology (smt) and smd packages
Surface mount technology (smt) and smd packages
karen zou
 
Flip Chip technology
Flip Chip technologyFlip Chip technology
Flip Chip technology
Mantra VLSI
 
PCB Designing
PCB Designing PCB Designing
WelcomePCB
WelcomePCBWelcomePCB
PCB
PCB PCB
Smt notes
Smt notesSmt notes
Smt notes
abishus
 
How to find defects in SMT electronics manufacturing
How to find defects in SMT electronics manufacturingHow to find defects in SMT electronics manufacturing
How to find defects in SMT electronics manufacturing
Bill Cardoso
 
Flipchip bonding.
Flipchip bonding.Flipchip bonding.
Flipchip bonding.
venkata016
 
2.5D/3D IC Market Challenges & Opportunities
2.5D/3D IC MarketChallenges & Opportunities2.5D/3D IC MarketChallenges & Opportunities
2.5D/3D IC Market Challenges & Opportunities
Rohan Hubli
 
Why (and how) to switch to KiCad
Why (and how) to switch to KiCadWhy (and how) to switch to KiCad
Why (and how) to switch to KiCad
Baoshi Zhu
 
Matching concept in Microelectronics
Matching concept in MicroelectronicsMatching concept in Microelectronics
Matching concept in Microelectronics
Tallinn University of Technology
 
Surface Mount Technology
 Surface Mount Technology Surface Mount Technology
Surface Mount Technology
SABBULA NAVYA PRAVALIKA
 

What's hot (20)

pcb
pcbpcb
pcb
 
Package fabrication technolog ynew
Package fabrication technolog ynewPackage fabrication technolog ynew
Package fabrication technolog ynew
 
Pcb manufacturing
Pcb manufacturingPcb manufacturing
Pcb manufacturing
 
Pcb design guidelines
Pcb design guidelinesPcb design guidelines
Pcb design guidelines
 
Double sided PCB manufacturing
Double sided PCB manufacturingDouble sided PCB manufacturing
Double sided PCB manufacturing
 
IC Packaging
IC PackagingIC Packaging
IC Packaging
 
Physical Verification Design.pdf
Physical Verification Design.pdfPhysical Verification Design.pdf
Physical Verification Design.pdf
 
Three dimensional integrated circuit
Three dimensional integrated circuitThree dimensional integrated circuit
Three dimensional integrated circuit
 
Surface mount technology (smt) and smd packages
Surface mount technology (smt) and smd packagesSurface mount technology (smt) and smd packages
Surface mount technology (smt) and smd packages
 
Flip Chip technology
Flip Chip technologyFlip Chip technology
Flip Chip technology
 
PCB Designing
PCB Designing PCB Designing
PCB Designing
 
WelcomePCB
WelcomePCBWelcomePCB
WelcomePCB
 
PCB
PCB PCB
PCB
 
Smt notes
Smt notesSmt notes
Smt notes
 
How to find defects in SMT electronics manufacturing
How to find defects in SMT electronics manufacturingHow to find defects in SMT electronics manufacturing
How to find defects in SMT electronics manufacturing
 
Flipchip bonding.
Flipchip bonding.Flipchip bonding.
Flipchip bonding.
 
2.5D/3D IC Market Challenges & Opportunities
2.5D/3D IC MarketChallenges & Opportunities2.5D/3D IC MarketChallenges & Opportunities
2.5D/3D IC Market Challenges & Opportunities
 
Why (and how) to switch to KiCad
Why (and how) to switch to KiCadWhy (and how) to switch to KiCad
Why (and how) to switch to KiCad
 
Matching concept in Microelectronics
Matching concept in MicroelectronicsMatching concept in Microelectronics
Matching concept in Microelectronics
 
Surface Mount Technology
 Surface Mount Technology Surface Mount Technology
Surface Mount Technology
 

Viewers also liked

Manufacturing of PCB
Manufacturing of PCBManufacturing of PCB
Manufacturing of PCB
Sujith J S
 
PCBA Assembly Process Flow / PCB Assembly Manufacturing
PCBA Assembly Process Flow / PCB Assembly ManufacturingPCBA Assembly Process Flow / PCB Assembly Manufacturing
PCBA Assembly Process Flow / PCB Assembly Manufacturing
Agile Circuit Co., Ltd
 
PCB Process Flow Multilayer Manufacturing Flowchart
PCB Process Flow Multilayer Manufacturing FlowchartPCB Process Flow Multilayer Manufacturing Flowchart
PCB Process Flow Multilayer Manufacturing Flowchart
Domestic PCB Fabrication
 
Printed circuit Board Description
Printed circuit Board DescriptionPrinted circuit Board Description
Printed circuit Board Description
RUBY DIKSHIT
 
Pcb design
Pcb designPcb design
Pcb design
Abu Bakker
 
Seminar report on national instruments electronics workbench
Seminar report on national instruments electronics workbenchSeminar report on national instruments electronics workbench
Seminar report on national instruments electronics workbench
Trishan Jaiswal
 
Electrical and Electronics Engineering (EEE) Research Methodology Presentation
Electrical and Electronics Engineering (EEE) Research Methodology PresentationElectrical and Electronics Engineering (EEE) Research Methodology Presentation
Electrical and Electronics Engineering (EEE) Research Methodology Presentation
Engr. Md. Ashikur Rahman Ashik
 
Solder Paste Screen Printing
Solder Paste Screen PrintingSolder Paste Screen Printing
Solder Paste Screen Printing
Rockwell Automation
 
Microfluidics
MicrofluidicsMicrofluidics
Microfluidics
tabirsir
 
Power System Modelling And Simulation Lab
Power System Modelling And Simulation LabPower System Modelling And Simulation Lab
Power System Modelling And Simulation Lab
Sachin Airan
 
FUZZY LOGIC CONTROLLER ON DC/DC BOOST CONVERTER
FUZZY LOGIC CONTROLLER ON DC/DC BOOST CONVERTERFUZZY LOGIC CONTROLLER ON DC/DC BOOST CONVERTER
FUZZY LOGIC CONTROLLER ON DC/DC BOOST CONVERTER
RAGHVENDRA KUMAR PANDIT
 
5S: презентация без картинок
5S: презентация без картинок5S: презентация без картинок
5S: презентация без картинок
SixSigmaOnline
 
Surface Mount Manufacturing Basics
Surface Mount Manufacturing BasicsSurface Mount Manufacturing Basics
Surface Mount Manufacturing Basics
SIM
 
Solar powered automatic street light controller report
Solar powered automatic street light controller reportSolar powered automatic street light controller report
Solar powered automatic street light controller report
Amar Gupta
 
electrical distribution system ppt/13b61a0221
electrical distribution system ppt/13b61a0221electrical distribution system ppt/13b61a0221
electrical distribution system ppt/13b61a0221
saikrishna kandhikatla
 
automatic-street-light-controller
automatic-street-light-controllerautomatic-street-light-controller
automatic-street-light-controller
Amit Singh
 
Presentation on Over-/under-voltage protection of electrical appliance
Presentation on Over-/under-voltage protection of electrical appliancePresentation on Over-/under-voltage protection of electrical appliance
Presentation on Over-/under-voltage protection of electrical appliance
Nishant Kumar
 
Artificial Intelligence in Power Systems
Artificial Intelligence in Power SystemsArtificial Intelligence in Power Systems
Artificial Intelligence in Power Systems
Sowmya T
 
Ppt on automatic street light control using ir sensors
Ppt on automatic street light control using ir sensorsPpt on automatic street light control using ir sensors
Ppt on automatic street light control using ir sensors
Vikram Emmidi
 
Automatic control of street light using LDR
Automatic control of street light using LDRAutomatic control of street light using LDR
Automatic control of street light using LDR
Devang Loharikar
 

Viewers also liked (20)

Manufacturing of PCB
Manufacturing of PCBManufacturing of PCB
Manufacturing of PCB
 
PCBA Assembly Process Flow / PCB Assembly Manufacturing
PCBA Assembly Process Flow / PCB Assembly ManufacturingPCBA Assembly Process Flow / PCB Assembly Manufacturing
PCBA Assembly Process Flow / PCB Assembly Manufacturing
 
PCB Process Flow Multilayer Manufacturing Flowchart
PCB Process Flow Multilayer Manufacturing FlowchartPCB Process Flow Multilayer Manufacturing Flowchart
PCB Process Flow Multilayer Manufacturing Flowchart
 
Printed circuit Board Description
Printed circuit Board DescriptionPrinted circuit Board Description
Printed circuit Board Description
 
Pcb design
Pcb designPcb design
Pcb design
 
Seminar report on national instruments electronics workbench
Seminar report on national instruments electronics workbenchSeminar report on national instruments electronics workbench
Seminar report on national instruments electronics workbench
 
Electrical and Electronics Engineering (EEE) Research Methodology Presentation
Electrical and Electronics Engineering (EEE) Research Methodology PresentationElectrical and Electronics Engineering (EEE) Research Methodology Presentation
Electrical and Electronics Engineering (EEE) Research Methodology Presentation
 
Solder Paste Screen Printing
Solder Paste Screen PrintingSolder Paste Screen Printing
Solder Paste Screen Printing
 
Microfluidics
MicrofluidicsMicrofluidics
Microfluidics
 
Power System Modelling And Simulation Lab
Power System Modelling And Simulation LabPower System Modelling And Simulation Lab
Power System Modelling And Simulation Lab
 
FUZZY LOGIC CONTROLLER ON DC/DC BOOST CONVERTER
FUZZY LOGIC CONTROLLER ON DC/DC BOOST CONVERTERFUZZY LOGIC CONTROLLER ON DC/DC BOOST CONVERTER
FUZZY LOGIC CONTROLLER ON DC/DC BOOST CONVERTER
 
5S: презентация без картинок
5S: презентация без картинок5S: презентация без картинок
5S: презентация без картинок
 
Surface Mount Manufacturing Basics
Surface Mount Manufacturing BasicsSurface Mount Manufacturing Basics
Surface Mount Manufacturing Basics
 
Solar powered automatic street light controller report
Solar powered automatic street light controller reportSolar powered automatic street light controller report
Solar powered automatic street light controller report
 
electrical distribution system ppt/13b61a0221
electrical distribution system ppt/13b61a0221electrical distribution system ppt/13b61a0221
electrical distribution system ppt/13b61a0221
 
automatic-street-light-controller
automatic-street-light-controllerautomatic-street-light-controller
automatic-street-light-controller
 
Presentation on Over-/under-voltage protection of electrical appliance
Presentation on Over-/under-voltage protection of electrical appliancePresentation on Over-/under-voltage protection of electrical appliance
Presentation on Over-/under-voltage protection of electrical appliance
 
Artificial Intelligence in Power Systems
Artificial Intelligence in Power SystemsArtificial Intelligence in Power Systems
Artificial Intelligence in Power Systems
 
Ppt on automatic street light control using ir sensors
Ppt on automatic street light control using ir sensorsPpt on automatic street light control using ir sensors
Ppt on automatic street light control using ir sensors
 
Automatic control of street light using LDR
Automatic control of street light using LDRAutomatic control of street light using LDR
Automatic control of street light using LDR
 

Similar to Understanding printed board assembly using simulation with design of experiments approach

Making of an Application Specific Integrated Circuit
Making of an Application Specific Integrated CircuitMaking of an Application Specific Integrated Circuit
Making of an Application Specific Integrated Circuit
SWINDONSilicon
 
ASIC design verification
ASIC design verificationASIC design verification
ASIC design verification
Gireesh Kallihal
 
Chromatography Data system: Process your Data
Chromatography Data system: Process your Data Chromatography Data system: Process your Data
Chromatography Data system: Process your Data
Chromatography & Mass Spectrometry Solutions
 
Predictive Analytics in Manufacturing
Predictive Analytics in ManufacturingPredictive Analytics in Manufacturing
Predictive Analytics in Manufacturing
Data Science Thailand
 
SOC Chip Basics
SOC Chip BasicsSOC Chip Basics
SOC Chip Basics
A B Shinde
 
PCBA Testing--Hitech Circuits Co., Limited
PCBA Testing--Hitech Circuits Co., LimitedPCBA Testing--Hitech Circuits Co., Limited
PCBA Testing--Hitech Circuits Co., Limited
Hitech Circuits Co.,Ltd.
 
2019 2 testing and verification of vlsi design_verification
2019 2 testing and verification of vlsi design_verification2019 2 testing and verification of vlsi design_verification
2019 2 testing and verification of vlsi design_verification
Usha Mehta
 
Ncerc rlmca202 adm m3 ssm
Ncerc rlmca202  adm m3 ssmNcerc rlmca202  adm m3 ssm
Ncerc rlmca202 adm m3 ssm
ssmarar
 
Unit II- Hardware design & testing methods1 - Electronic Product Design
Unit II- Hardware design & testing methods1 - Electronic Product DesignUnit II- Hardware design & testing methods1 - Electronic Product Design
Unit II- Hardware design & testing methods1 - Electronic Product Design
Centre for Electronics, Computer, Self development
 
PCB Assembly Testing and Inspection, from Hitech Circuits Co., Limited.pdf
PCB Assembly Testing and Inspection, from Hitech Circuits Co., Limited.pdfPCB Assembly Testing and Inspection, from Hitech Circuits Co., Limited.pdf
PCB Assembly Testing and Inspection, from Hitech Circuits Co., Limited.pdf
Cynthia HitechPCB
 
System design techniques and networks
System design techniques and networksSystem design techniques and networks
System design techniques and networks
RAMPRAKASHT1
 
3 test economic_test_equipments_yield
3 test economic_test_equipments_yield3 test economic_test_equipments_yield
3 test economic_test_equipments_yield
Usha Mehta
 
ABC of developer test
ABC of developer testABC of developer test
ABC of developer test
Dr. Anish Cheriyan (PhD)
 
sairam_CV
sairam_CVsairam_CV
Pipelining And Vector Processing
Pipelining And Vector ProcessingPipelining And Vector Processing
Pipelining And Vector Processing
TheInnocentTuber
 
Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006
Chris Baichoo
 
Vlsi physical design-notes
Vlsi physical design-notesVlsi physical design-notes
Vlsi physical design-notes
Dr.YNM
 
Cim presentation (1)
Cim presentation (1)Cim presentation (1)
Cim presentation (1)
rajnitj19
 
Mineral processing plant design and optimisation
Mineral processing plant design and optimisation Mineral processing plant design and optimisation
Mineral processing plant design and optimisation
Basdew Rooplal
 
Scan insertion
Scan insertionScan insertion
Scan insertion
kumar gavanurmath
 

Similar to Understanding printed board assembly using simulation with design of experiments approach (20)

Making of an Application Specific Integrated Circuit
Making of an Application Specific Integrated CircuitMaking of an Application Specific Integrated Circuit
Making of an Application Specific Integrated Circuit
 
ASIC design verification
ASIC design verificationASIC design verification
ASIC design verification
 
Chromatography Data system: Process your Data
Chromatography Data system: Process your Data Chromatography Data system: Process your Data
Chromatography Data system: Process your Data
 
Predictive Analytics in Manufacturing
Predictive Analytics in ManufacturingPredictive Analytics in Manufacturing
Predictive Analytics in Manufacturing
 
SOC Chip Basics
SOC Chip BasicsSOC Chip Basics
SOC Chip Basics
 
PCBA Testing--Hitech Circuits Co., Limited
PCBA Testing--Hitech Circuits Co., LimitedPCBA Testing--Hitech Circuits Co., Limited
PCBA Testing--Hitech Circuits Co., Limited
 
2019 2 testing and verification of vlsi design_verification
2019 2 testing and verification of vlsi design_verification2019 2 testing and verification of vlsi design_verification
2019 2 testing and verification of vlsi design_verification
 
Ncerc rlmca202 adm m3 ssm
Ncerc rlmca202  adm m3 ssmNcerc rlmca202  adm m3 ssm
Ncerc rlmca202 adm m3 ssm
 
Unit II- Hardware design & testing methods1 - Electronic Product Design
Unit II- Hardware design & testing methods1 - Electronic Product DesignUnit II- Hardware design & testing methods1 - Electronic Product Design
Unit II- Hardware design & testing methods1 - Electronic Product Design
 
PCB Assembly Testing and Inspection, from Hitech Circuits Co., Limited.pdf
PCB Assembly Testing and Inspection, from Hitech Circuits Co., Limited.pdfPCB Assembly Testing and Inspection, from Hitech Circuits Co., Limited.pdf
PCB Assembly Testing and Inspection, from Hitech Circuits Co., Limited.pdf
 
System design techniques and networks
System design techniques and networksSystem design techniques and networks
System design techniques and networks
 
3 test economic_test_equipments_yield
3 test economic_test_equipments_yield3 test economic_test_equipments_yield
3 test economic_test_equipments_yield
 
ABC of developer test
ABC of developer testABC of developer test
ABC of developer test
 
sairam_CV
sairam_CVsairam_CV
sairam_CV
 
Pipelining And Vector Processing
Pipelining And Vector ProcessingPipelining And Vector Processing
Pipelining And Vector Processing
 
Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006
 
Vlsi physical design-notes
Vlsi physical design-notesVlsi physical design-notes
Vlsi physical design-notes
 
Cim presentation (1)
Cim presentation (1)Cim presentation (1)
Cim presentation (1)
 
Mineral processing plant design and optimisation
Mineral processing plant design and optimisation Mineral processing plant design and optimisation
Mineral processing plant design and optimisation
 
Scan insertion
Scan insertionScan insertion
Scan insertion
 

More from Kiran Hanjar

Manufacturing systems design
Manufacturing systems designManufacturing systems design
Manufacturing systems design
Kiran Hanjar
 
Throughput Accounting (Management Accounting and Finance)
Throughput Accounting (Management Accounting and Finance)Throughput Accounting (Management Accounting and Finance)
Throughput Accounting (Management Accounting and Finance)
Kiran Hanjar
 
Trend adjusted exponential smoothing forecasting metho ds
Trend adjusted exponential smoothing forecasting metho dsTrend adjusted exponential smoothing forecasting metho ds
Trend adjusted exponential smoothing forecasting metho ds
Kiran Hanjar
 
Cost of software quality ( software quality assurance )
Cost of software quality ( software quality assurance )Cost of software quality ( software quality assurance )
Cost of software quality ( software quality assurance )
Kiran Hanjar
 
Quality and reliability in health care
Quality and reliability in health careQuality and reliability in health care
Quality and reliability in health care
Kiran Hanjar
 
Measuring work by physiological methods
Measuring work by physiological methodsMeasuring work by physiological methods
Measuring work by physiological methods
Kiran Hanjar
 
AUTHORSHIP AND THE ALLOCATION OF CREDIT ( Design of Research )
AUTHORSHIP AND THE ALLOCATION OF CREDIT ( Design of Research )AUTHORSHIP AND THE ALLOCATION OF CREDIT ( Design of Research )
AUTHORSHIP AND THE ALLOCATION OF CREDIT ( Design of Research )
Kiran Hanjar
 
Time allowances
Time allowancesTime allowances
Time allowances
Kiran Hanjar
 
Joint venture - Case study
Joint venture - Case studyJoint venture - Case study
Joint venture - Case study
Kiran Hanjar
 
Factories of Future
Factories of FutureFactories of Future
Factories of Future
Kiran Hanjar
 
Indian aerospace since independence
Indian aerospace since independenceIndian aerospace since independence
Indian aerospace since independence
Kiran Hanjar
 

More from Kiran Hanjar (11)

Manufacturing systems design
Manufacturing systems designManufacturing systems design
Manufacturing systems design
 
Throughput Accounting (Management Accounting and Finance)
Throughput Accounting (Management Accounting and Finance)Throughput Accounting (Management Accounting and Finance)
Throughput Accounting (Management Accounting and Finance)
 
Trend adjusted exponential smoothing forecasting metho ds
Trend adjusted exponential smoothing forecasting metho dsTrend adjusted exponential smoothing forecasting metho ds
Trend adjusted exponential smoothing forecasting metho ds
 
Cost of software quality ( software quality assurance )
Cost of software quality ( software quality assurance )Cost of software quality ( software quality assurance )
Cost of software quality ( software quality assurance )
 
Quality and reliability in health care
Quality and reliability in health careQuality and reliability in health care
Quality and reliability in health care
 
Measuring work by physiological methods
Measuring work by physiological methodsMeasuring work by physiological methods
Measuring work by physiological methods
 
AUTHORSHIP AND THE ALLOCATION OF CREDIT ( Design of Research )
AUTHORSHIP AND THE ALLOCATION OF CREDIT ( Design of Research )AUTHORSHIP AND THE ALLOCATION OF CREDIT ( Design of Research )
AUTHORSHIP AND THE ALLOCATION OF CREDIT ( Design of Research )
 
Time allowances
Time allowancesTime allowances
Time allowances
 
Joint venture - Case study
Joint venture - Case studyJoint venture - Case study
Joint venture - Case study
 
Factories of Future
Factories of FutureFactories of Future
Factories of Future
 
Indian aerospace since independence
Indian aerospace since independenceIndian aerospace since independence
Indian aerospace since independence
 

Recently uploaded

CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
camakaiclarkmusic
 
A Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdfA Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdf
Jean Carlos Nunes Paixão
 
Types of Herbal Cosmetics its standardization.
Types of Herbal Cosmetics its standardization.Types of Herbal Cosmetics its standardization.
Types of Herbal Cosmetics its standardization.
Ashokrao Mane college of Pharmacy Peth-Vadgaon
 
How to Build a Module in Odoo 17 Using the Scaffold Method
How to Build a Module in Odoo 17 Using the Scaffold MethodHow to Build a Module in Odoo 17 Using the Scaffold Method
How to Build a Module in Odoo 17 Using the Scaffold Method
Celine George
 
clinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdfclinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdf
Priyankaranawat4
 
Top five deadliest dog breeds in America
Top five deadliest dog breeds in AmericaTop five deadliest dog breeds in America
Top five deadliest dog breeds in America
Bisnar Chase Personal Injury Attorneys
 
A Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptxA Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptx
thanhdowork
 
Film vocab for eal 3 students: Australia the movie
Film vocab for eal 3 students: Australia the movieFilm vocab for eal 3 students: Australia the movie
Film vocab for eal 3 students: Australia the movie
Nicholas Montgomery
 
The basics of sentences session 6pptx.pptx
The basics of sentences session 6pptx.pptxThe basics of sentences session 6pptx.pptx
The basics of sentences session 6pptx.pptx
heathfieldcps1
 
Assessment and Planning in Educational technology.pptx
Assessment and Planning in Educational technology.pptxAssessment and Planning in Educational technology.pptx
Assessment and Planning in Educational technology.pptx
Kavitha Krishnan
 
South African Journal of Science: Writing with integrity workshop (2024)
South African Journal of Science: Writing with integrity workshop (2024)South African Journal of Science: Writing with integrity workshop (2024)
South African Journal of Science: Writing with integrity workshop (2024)
Academy of Science of South Africa
 
The History of Stoke Newington Street Names
The History of Stoke Newington Street NamesThe History of Stoke Newington Street Names
The History of Stoke Newington Street Names
History of Stoke Newington
 
Hindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdfHindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdf
Dr. Mulla Adam Ali
 
Chapter 4 - Islamic Financial Institutions in Malaysia.pptx
Chapter 4 - Islamic Financial Institutions in Malaysia.pptxChapter 4 - Islamic Financial Institutions in Malaysia.pptx
Chapter 4 - Islamic Financial Institutions in Malaysia.pptx
Mohd Adib Abd Muin, Senior Lecturer at Universiti Utara Malaysia
 
Digital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments UnitDigital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments Unit
chanes7
 
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
Nguyen Thanh Tu Collection
 
RPMS TEMPLATE FOR SCHOOL YEAR 2023-2024 FOR TEACHER 1 TO TEACHER 3
RPMS TEMPLATE FOR SCHOOL YEAR 2023-2024 FOR TEACHER 1 TO TEACHER 3RPMS TEMPLATE FOR SCHOOL YEAR 2023-2024 FOR TEACHER 1 TO TEACHER 3
RPMS TEMPLATE FOR SCHOOL YEAR 2023-2024 FOR TEACHER 1 TO TEACHER 3
IreneSebastianRueco1
 
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
PECB
 
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
National Information Standards Organization (NISO)
 
PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.
Dr. Shivangi Singh Parihar
 

Recently uploaded (20)

CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
 
A Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdfA Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdf
 
Types of Herbal Cosmetics its standardization.
Types of Herbal Cosmetics its standardization.Types of Herbal Cosmetics its standardization.
Types of Herbal Cosmetics its standardization.
 
How to Build a Module in Odoo 17 Using the Scaffold Method
How to Build a Module in Odoo 17 Using the Scaffold MethodHow to Build a Module in Odoo 17 Using the Scaffold Method
How to Build a Module in Odoo 17 Using the Scaffold Method
 
clinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdfclinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdf
 
Top five deadliest dog breeds in America
Top five deadliest dog breeds in AmericaTop five deadliest dog breeds in America
Top five deadliest dog breeds in America
 
A Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptxA Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptx
 
Film vocab for eal 3 students: Australia the movie
Film vocab for eal 3 students: Australia the movieFilm vocab for eal 3 students: Australia the movie
Film vocab for eal 3 students: Australia the movie
 
The basics of sentences session 6pptx.pptx
The basics of sentences session 6pptx.pptxThe basics of sentences session 6pptx.pptx
The basics of sentences session 6pptx.pptx
 
Assessment and Planning in Educational technology.pptx
Assessment and Planning in Educational technology.pptxAssessment and Planning in Educational technology.pptx
Assessment and Planning in Educational technology.pptx
 
South African Journal of Science: Writing with integrity workshop (2024)
South African Journal of Science: Writing with integrity workshop (2024)South African Journal of Science: Writing with integrity workshop (2024)
South African Journal of Science: Writing with integrity workshop (2024)
 
The History of Stoke Newington Street Names
The History of Stoke Newington Street NamesThe History of Stoke Newington Street Names
The History of Stoke Newington Street Names
 
Hindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdfHindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdf
 
Chapter 4 - Islamic Financial Institutions in Malaysia.pptx
Chapter 4 - Islamic Financial Institutions in Malaysia.pptxChapter 4 - Islamic Financial Institutions in Malaysia.pptx
Chapter 4 - Islamic Financial Institutions in Malaysia.pptx
 
Digital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments UnitDigital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments Unit
 
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
 
RPMS TEMPLATE FOR SCHOOL YEAR 2023-2024 FOR TEACHER 1 TO TEACHER 3
RPMS TEMPLATE FOR SCHOOL YEAR 2023-2024 FOR TEACHER 1 TO TEACHER 3RPMS TEMPLATE FOR SCHOOL YEAR 2023-2024 FOR TEACHER 1 TO TEACHER 3
RPMS TEMPLATE FOR SCHOOL YEAR 2023-2024 FOR TEACHER 1 TO TEACHER 3
 
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
 
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
 
PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.
 

Understanding printed board assembly using simulation with design of experiments approach

  • 1. A Presentation on PRINTED CIRCUIT BOARD ASSEMBLY KIRAN HANJAR 1
  • 2. Aim of the Presentation • Understanding PCB assembly using simulation with DOE approach • To assess the feasibility of process flow logic and relative impact of changing line configurations • It is aimed to identify constraints or bottlenecks and development of improvement strategies accordingly • By using DOE, the factors that are affecting the system’s efficiency are identified • Finally to improve the system’s overall performance 2
  • 3. Introduction Printed circuit board (PCB) assembly •Printed circuit board (PCB) assembly lines fall under the general category of serial production lines •Common problems faced in these lines include designing configuration of existing or future lines to meet target production rates •Simulation modeling can capture the complex behaviour and interaction between various components of PCB assembly lines •This is very much important to analyze and help to make better decisions 3
  • 4. Introduction Printed Circuit Board Manufacturing •PCB can be classified into two categories based on the type of components placed on the board – Surface Mount Technology (SMT) – Insertion Mount Technology (IMT) Six steps involved in SMT manufacturing are explained as follows: • Attachment Media Dispensing •Component Placement •Curing •Soldering •Cleaning •Testing 4
  • 5. General steps involved in SMT process for PCB assembly SOLDER PASTE APPLICATION INVERT BOARD REFLOW OVEN COMPONENT PLACEMENT YES OTHER SIDE NEEDED SMC’s NO TEST CLEAN PASS? NO REPAIR YES SHIP FINISHED Source: (Hollomon, BOARD 5 1989) and (Capillo,
  • 6. With the help of Cause and Effect Diagram factors which are affecting throughput are identified PERSONNEL MATERIALS Paste Type Handling Rework Components Board Setup THROUGHPUT In-Circuit Testing TESTING Board Functional Testing Screen Printing Component Placing MACHINE Cause and Effect Diagram for PCB assembly line Generally in PCBA solder paste, Component placement, ICT, BFT , Rework creates variability in process time 6
  • 7. DOE • Systematic Plan of investigation using principles of statistics wherein response or output value is obtained by varying factors/ levels or a combination of factor level • 5 factors , 2 levels (high and low) are considered , 25 full factorial design is made to anlayse the model PARAMETERS SOLDER PASTE COMPONENT PLACING ICT BFT REPAIR FACTOR LEVEL ( LOW ) 5 7 5 15 5 FACTOR LEVEL (HIGH) 7 12 15 40 20 C.V for low level and high level are 0.1 and 0.4 respectively 7
  • 8. Simulation Modeling and Analysis The steps involved in a simulation •Input analysis: involves collection and analysis of data, and definition as well as validation of conceptual model •Model development: involves simulation model development followed by verification and validation of the simulation model •Output analysis: where performance metrics of the system are determined and analysed Some of the advantages of simulation are: •Simulation offers better control over experimental conditions •Animation provided by simulation enables better understanding of the system •Alternative proposed system configurations can be compared using simulation 8
  • 9. Model Building It involves six steps as shown in the figure Collect i/p data Develop static model Validate simulation model Run current configuration Yes Analyse the system Potential improvements Modify configuratio n No Stop Source :(Mukkamala, Smith & Valenzuela, 2003) 9
  • 10. Step 1 : Collect input data This data may be extracted from historical databases of the line under consideration (if the manufacturing line already exists) or a similar line (if line is non-existent, i.e. proposed). •Machine Data •Operator data •Inspection and rework data •Oven data •Buffer data •Conveyor data •Traverser/shuttle data For a PCB that has to get shipped it has to start from Solder paste assembly then to component placement, Reflow oven, Pin through holes, Wave soldering, In-circuit testing, Final mechanical assembly, Board functional testing, Repair if any and finally to packing. 10
  • 11. Reflow Oven Cooling Solder paste Assembly Component placing Yes PTH Wave Soldering ICT No Final Mechanical assembly Repair Yes BFT Ship No Disassemble The simulation model of Printed Board Circuit Assembly Rework 11
  • 12. Process carried out in each Section Solder Paste Assembly •In PCBA the paste printing process accounts for the majority of assembly defects •Over sixty percent of all soldering defects are due to problems associated with the screening process •Parameters such as squeegee pressure, squeegee speed, stencil separation speed, snap-off and stencil cleaning interval are the most important factors in the process to achieve a better yield •The set up time taken is around five to seven minutes, two minutes is required to paste on stencil to get completed, Board printing takes one minute and visual inspection takes around two minutes and vary depending on the complexity of the board • So the time taken for the entire process is around six minutes 12
  • 13. Component Placing • In the pick & place station, only one components is taken from the component feeder by means of a vacuum pipette, and is placed on the PCB • Based on the complexity of the PCB the process time varies between seven and twelve minutes 13
  • 14. Reflow oven • A reflow oven is a machine used primarily for reflow soldering of surface mount electronic components to printed circuit boards • The oven contains multiple zones, which can be individually controlled for temperature • The PCB moves through the oven on a conveyor and is therefore subjected to a controlled time-temperature profile • Some ovens are designed to reflow PCBs in an oxygen-free atmosphere. Nitrogen (N2) is a common gas used for this purpose. This minimizes oxidation of the surfaces to be soldered 14
  • 15. In-Circuit Test (ICT) • Here, checking for shorts, opens, resistance, capacitance, and other basic quantities which will show whether the assembly was correctly fabricated • It may be performed with a bed of nails type test fixture and specialist test equipment • Based on the design of the circuit and complexity it takes around five to fifteen minutes to undergo this process Industrial printed circuit board being tested with a modern digital oscilloscope an oscilloscope 15
  • 16. Board Functional Test (BFT) • Functional test (FCT) is used as a final manufacturing step providing a pass/fail determination on finished PCBs before they are shipped • To validate that product hardware is free of defects that could, otherwise, adversely affect the product’s correct functioning in a system application • Requirements of a functional test, its development, and procedures vary widely from PCB to PCB and system to system • The most common form of functional test, known as “hot mock-up” simply verifies that the PCB is functioning properly • Generally time taken to undergo functional test is between fifteen and forty minutes 16
  • 17. Step 2 : Develop Static Model of the Process Line • Based on the input data collected, a static model is prepared for the validation and benchmarking of the simulation model • Static model is a spreadsheet based model developed using the mean values of cycle times, utilization time and failure • Then, the throughput which is the least among all the machines or processes is identified as the throughput of the whole line In doing so, these things are should be ignored: • The inherent interdependence between the processes (induced by the capacitated buffers). • The variability (induced by the unpredictable breakdowns and component part exhaustions) 17
  • 18. Input Datasheet Sl no Process Time distribution in min 1 Solder paste assembly NORM (6. 1.2) 2 Component placement BETA (12, 7) 3 Reflow oven NORM ( 4, 0.1) 4 Cooling NORM (1, .05) 5 Pin through hole NORM ( 4 , 0.5) 6 Wave Soldering NORM ( 3.5, 0.5) 7 ICT BETA ( 15, 5) 8 Repair(ICT) BETA ( 20, 5) 9 Final mechanical assembly NORM ( 4, 0.5) 10 BFT BETA ( 40, 15) 11 Disassemble NORM ( 2, .05) 12 Rework (BFT) BETA (20, 5) By using Arena software PCB Assembly line is built and respected inputs are tabulated at every section and Run simulation. From the result obtained analysis is done 18
  • 19. Run Current Configuration Arriv e Arrive 1 Serv er Serv er Serv er 1 Serv er Server 2 Server 3 ? In s p ec t Inspect 1 Serv er Serv er Serv er Serv er 6 Server 5 Server 4 ? Serv er In s p ec t Server 8 Inspect 2 Dep a rt Depart 1 Serv er Serv er Server 9 Server 7 Si m u la te PCb assembly 500 It took 252 min to complete the assembly process for a batch of 10 PCB Serv er Serv er 10 19
  • 20. Analysing the variability using DOE • To understand the behaviour of the system to a next level the factors (process) that are creating the variables are identified • For the current model five factors are taken into account they are: – Solder paste assembly – Component Placing – ICT – BFT and – Rework • By taking low level and high level concentration 25 factorial design is made • To eliminate the bias randomization is done as shown in the following table • In the table below : A- Solder paste assembly process time, Bcomponent Placement process time, C – ICT Processing time, D- BFT Processing time, E- time taken to repair, I- process time taken for ten 20 batches.
  • 21. The simulation model is run accordingly to the random number assigned to the order number and the obtained results are analysed using MINITAB software 21
  • 22. Main Effects Plots From the Main Effects plot for Time , Factor D i.e., Board Functional Test is one which is causing delay in process time than the other factors 22
  • 23. Estimated Effects and Coefficients for TIME(min) (coded units) 23
  • 24. Analysis of Variance for TIME(min) (coded units) Source Main Effects 2-Way Interactions 3-Way Interactions 4-Way Interactions 5-Way Interactions Residual Error Total DF 5 10 10 5 1 0 31 Seq SS 688160 2496 746 187 55 * 691644 Adj SS 688160 2496 746 187 55 * Adj MS 137632 250 75 37 55 * F P * * * * * * * * * * • From the Main effects plots and ANOVA table it is found that BFT plays a significant role in process. Simulation showed that the Bottleneck created in this section and there were queue of PCB that has to wait. • In order to improve the system it is better to provide a one more BFT section (parallel). 24
  • 25. Conclusion • • • • • • These topics help us to know the problem of simulation modeling and analysis of PCB assembly lines This is an important problem as line managers and decision makers of PCB assembly lines often face situations like designing configuration of entire line for new product etc, by using simulation concepts and software one can take a quantitative decisions but it is left to the line managers ability and experience to take the qualitative decisions By the help of Simulation one can understand visualise some more things such as buffer, bottleneck etc. By using Design of experiments, the factors that are affecting the model flow and also provide valid information whether to add a new line in the production to meet the demand or remove the parallel lines if the demands are not so good, without affecting the actual flow line. As in this case it clearly stated there is need for adding another line for BFT section in order to avoid blocking, bottlenecks etc. Hence with help of quantitative results and qualitative aspects optimal solution for any kind of problems can be found out 25
  • 26. References • • • • • • • • • • • • • Law, A. M. and Kelton, D. W. (2000). Simulation Modeling and Analysis. McGraw-Hill Companies, Inc. Papadopoulos, H.T. and Heavy, C. (1996). Queuing theory in manufacturing systems analysis and design: a classification of models of production and transfer lines. European Journal of Operations Research,92, 1-27. Heavy, C., Papadopoulos, H.T., and Browne, J. (1993). The throughput rate of multistation unreliable production lines.European Journal of Operational Research68(1), 69-89. Hollomon, James K. Jr. (1989). Surface mount technology for PC board design.Indianapolis: Howard W. Sams & Company. Goss, G.B. (2000). Measuring machine interference to evaluate an operator cross-training program. M.S. thesis. Massachusetts, MA: Massachusetts Institute of Technology. D’Souza, R.C. (2004) A throughput-based technique for identifying production system bottlenecks. M.S. thesis. Mississippi, MI: Mississippi State University. Capillo, C. (1990). Surface Mount Technology: materials, processes, and equipment. McGraw-Hill Publishing Company. Kamath, M. (1999). Recent development in modeling and performance analysis tools for manufacturing systems. In: S. B. Joshi and J. S. Smith, Computer Control of Flexible Manufacturing Systems, (pp.231-263). Chapman and Hall. Law, A.M. and McComas, M.G. (1997). Simulation of manufacturing systems. Proc. of 1997 Winter Simulation Conf., 86-89 Kotcher, R.C. (2001). How “overstaffing” atbottleneck machines can unleash extra capacity. Proc. of the 2001 Winter Simulation Conference, 1163-1169. Conway, R., Maxwell, M., McClain, J.O., and Thomas, J.L. (1988). The role of work-in process inventory in serial production lines. Operations Research,36(2), 229-241. Simulation modeling and analysis of printed circuit board assembly lines: Pradip Dinkarrao Jadhav Design and Analysis of Experiments. 5th edition, Douglas C.Montgomery, Wiley student edition . 26
  • 27. Thank you Kiran Hanjar S 1MS12MIA03 II Sem, IE M.TECH MSRIT 27

Editor's Notes

  1. Source: (Hollomon, 1989) and (Capillo, 1990)
  2. Note: Server 1 : Solderpaste Assembly, Server 2: Component placing, Server 3: Reflow oven, Server 4: Cooling, Server 5: PTH, Server 6: Wave soldering, Server 7 : Repair, Server 8 : Final Mechanical assembly, Server 9 : Disassemble , Server 10 : Rework, Inspect 1 : ICT, Inspect 2 : BFT.