TO TA L

P R O D U C T IV E

M A IN T E N A N C
        E
Maintenance   is defined as the
 management, control, execution and
 quality assurance of activities which
 ensure the achievement of optimum
 availability and performance of a
 plant in order to meet business
 objectives.
T: TOTAL  
 Participation of all Employees.
 Include all Departments, operation, equipment and
  process.
P: PRODUCTIVE
       Pursue the maximization of efficiency of the
  production system by making all loses zero.
   Zero accidents Zero defects Zero breakdowns.
M: MAINTENANCE
   To improve the efficiency of the equipment.
     Maintenance means the entire life cycle of the
  production system.
    Maintenance is not only to repair and maintain the
  machines.
1.   The major difference between TPM and
     other concepts is that the operators are
     also made to involve in the maintenance
     process.
2.   Avoid wastage in quickly changing
     environment.
3.   Reduce Cost of Manufacturing.
4.   Produce a low batch quantity at the earliest
     possible time.
5.   Goods send to Customers must be “ non –
     defective”
Increased Employee Morale
Increased Productivity
Improved Sharing & Working as a Team
Improved cleaning of the working place
Improved Product Quality
Improved Customer Satisfaction
Reduced Costs
Improved Delivery Time
Enhanced safety Records
Improved Image
Improved Reputation
TPM is a partnership between the
 maintenance      and    production
 organization to improve product
 quality, reduce waste, reduce cost,
 increase equipment availability
 and improve maintenance state.
First              Second Generation Third Generation
 Generation
 Fix it when it    Higher plant           Higher plant
 broke              availability            reliability and
                    Longer                 availability
                    equipment life          Greater safety

                    Lower Costs            Better quality

                                            Longer

                                            equipment life
                                            Cost

                                            Effectiveness
1940         1950   1960             1970   1980   1990   2000
 Corrective   (or) breakdown maintenance
 It implies that repairs are made after failure of
 machine or equipment

 Scheduled    (or) Routine maintenance
 It is a stitch-in-time procedure aimed to
 avoiding breakdowns
 Preventive   maintenance
 It is carried out before the failure arises (or)
 prior to the equipment actually
 breakdowns. E.g. Overhauling & Periodic
 upkeep.
 Predictivemaintenance
 Equipment Condition evaluated
 periodically and maintenance carried
 out.
Improve Equipment Effectiveness
Achieve Autonomous
Plan Maintenance
To Train all staff in maintenance
skills
To Zero Breakdowns
1 Breakdowns             Long interruptions,
.                        Costly Repairs
2 Setup and changeover   Taking Longer time than
.                        needed
3 Idling time and        Hard to quantify, add to
. stoppages              big losses
4 Reduced speed          Equipment cycle time
.                        reduces
5 Defects and reworks    Quality losses & Unhappy
.                        customer
 Increased productivity
 Equipment reliability
 Reduced down time
 Increased plant capacity
 Low production maintenance costs
 Team work Between Production &
  Maintenance People
 Improved safety & Profit
 Totalcommitment of upper level
  management.
 Employees must be empowered to initiate
  corrective action.
    Category              TQM                    TPM
                  Quality ( Output and   Equipment ( Input
 Object
                  effects )              and cause )
                  Systematize the        Employees
 Mains of
                  management. It is      participation and it is
 attaining goal
                  software oriented      hardware oriented
                                         Elimination of losses
 Target           Quality for PPM
                                         and wastes.
PILLARS OF TPM

                 JISHU HOZEN
              KOBETSU KAIZEN
            Planned Maintenance
             Quality Maintenance
                    Training
                   Office TPM
        Safety , Health & Environment
                   5S
SEIRI SEITON SEISO      SEIKETSU SHITSUKE
   FIRST STEP of improvement
    SEIRI – SORTOUT:  Keep only essential items and eliminate what is not
      required, prioritizing things as per requirements and keeping them in
      approachable places. Everything else is stored or discarded.
    SEITON – ORGANIZE:There should be a place for everything and
      everything should be in its place. Each tool, part, supply, or piece of
      equipment should be kept close to where it will be used – in other words,
      straightening the flow path.
    SEISO – SHINE THE WORKPLACE:Keep the workplace tidy and organized.
      At the end of each shift, clean the work area and be sure everything is
      restored to its place.
    SEIKETSU – STANDARDIZATION: Work practices should be consistent and
      standardized. Everyone should know exactly what his or her
      responsibilities are for adhering to the first 3 S's.
    SHITSUKE – SELF DISCIPLINE: When an issue arises such as a suggested
      improvement, a new way of working, a new tool or a new output
      requirement, review the first 4 S's and make changes as appropriate.
POLICY
3.  Uninterrupted operation of equipments
4.  Flexible operators to operate & maintain other
    equipments
5.  Eliminating the defects at source through active employee
    participation
6.  Stepwise implementation of JISHU HOZEN activities.
JH TARGETS
8.    Reduce process time by predicted values
9.    Reduce oil/ lubricants consumption by predicted valus
10.   Increase use of JH
JH STEPS
12.   Preparation of employees
13.   Initial cleanup of machines
14.   Take counter measures
15.   Fix tentative JH standards
16.   General inspection
17.   Autonomus inspection
18.   Standardization
19.   Autonomus management
KAI means change or improvement and ZEN
 means good (for the better). Kobetsu means
 focused. Basically Kobetsu Kaizen is for
 small adjustments and corrections but
 effects the whole process and carried out on
 a continual basis and involves all people in
 the organization.
The principal behind is that “ a very large
 number of small improvements are more
 effective in an organizational environment
 than a few improvements of large value.
With planned maintenance, we evolve an effort from a reactive to a
    proactive method and use trained maintenance staff to help
    train the operators to better maintain their equipment.

Policy:

    •     Achieve and sustains availability of machines
    •     Optimum maintenance cost.
    •     Reduce spares inventory.
    •     Improve reliability and maintainability of machines.
   It is aimed towards customer delight through highest
    quality through defect free manufacturing. Focus is on
    eliminating non-conformances in a systematic manner.

   Quality defects are classified as “CUSTOMER END
    defects” and “IN HOUSE defects”.
   For customer-end data, we have to get data on
    Customer-end line rejection and field complaints. In-
    house data include data related to products and data
    related to process.
It is aimed to have multi-skilled revitalized
   employees whose moral is high and who has eager
   to come to work and perform all required functions
   effectively and independently. Education is given
   to operators to upgrade their skill.
  The employees should be trained to achieve the
 form phase of skill which are as under:

PHASE 1: Do not know.
PHASE 2: Know the theory but cannot do.
PHASE 3: Can do but cannot teach.
PHASE 4: Can do and also teach.

    Office TPM should be started after activating from
    other pillars of TPM (JH, KK, and QM.PM). Office
    TPM must be established to improve productivity,
    efficiency in the administrative function and
    identify eliminate losses. This includes analyzing
    process and procedure towards increased office
    automation. Statistical analysis will give higher
    effectiveness to investigate the production and
    management departments simultaneously.Tpm
    office has responsibility to take the report of the
    losses and gainings then scheduling the traning
    hours professional trainers for the entire company.
   Downtime loss : A=(T/P)x100 where A = availability,
    T=operating time (P-D), P=planned operating time,
    D=Downtime
   Reduced speed loss : E= (CxN) x 100
                                 T
    E = perf efficiency, C= Theoticiacl cycle time, N=
    Processed amt quantity
   Poor quality Loss : R = = (N-Q) x 100
                                  N
    R=rate of quality pdts, N-processed amt, Q=non
    conformity
                      OEE = A x E x R

  6 major losses are need to be measures
1- PLANNED (startups, shift change, coffee&lunch
  break, planned maintenance shutdowns)
2-Unplanned Downtown ( Equipment breakdown,
  change over, Lack of material,
3-Idling and minor stoppage
4-Slow downs
5-Proces NC
6- Scrap
Trainer & Consultant




          https://sites.google.com/site/anubhawalia/
         www.prism-global.org, anubhawalia@gmail.com

TQM TPM

  • 1.
    TO TA L PR O D U C T IV E M A IN T E N A N C E
  • 2.
    Maintenance is defined as the management, control, execution and quality assurance of activities which ensure the achievement of optimum availability and performance of a plant in order to meet business objectives.
  • 3.
    T: TOTAL   Participation of all Employees.  Include all Departments, operation, equipment and process. P: PRODUCTIVE  Pursue the maximization of efficiency of the production system by making all loses zero.  Zero accidents Zero defects Zero breakdowns. M: MAINTENANCE  To improve the efficiency of the equipment.  Maintenance means the entire life cycle of the production system.  Maintenance is not only to repair and maintain the machines.
  • 4.
    1. The major difference between TPM and other concepts is that the operators are also made to involve in the maintenance process. 2. Avoid wastage in quickly changing environment. 3. Reduce Cost of Manufacturing. 4. Produce a low batch quantity at the earliest possible time. 5. Goods send to Customers must be “ non – defective”
  • 5.
    Increased Employee Morale IncreasedProductivity Improved Sharing & Working as a Team Improved cleaning of the working place Improved Product Quality Improved Customer Satisfaction Reduced Costs Improved Delivery Time Enhanced safety Records Improved Image Improved Reputation
  • 6.
    TPM is apartnership between the maintenance and production organization to improve product quality, reduce waste, reduce cost, increase equipment availability and improve maintenance state.
  • 7.
    First Second Generation Third Generation Generation Fix it when it Higher plant Higher plant broke availability reliability and Longer availability equipment life Greater safety Lower Costs Better quality Longer equipment life Cost Effectiveness 1940 1950 1960 1970 1980 1990 2000
  • 8.
     Corrective (or) breakdown maintenance It implies that repairs are made after failure of machine or equipment  Scheduled (or) Routine maintenance It is a stitch-in-time procedure aimed to avoiding breakdowns
  • 9.
     Preventive maintenance It is carried out before the failure arises (or) prior to the equipment actually breakdowns. E.g. Overhauling & Periodic upkeep.  Predictivemaintenance Equipment Condition evaluated periodically and maintenance carried out.
  • 10.
    Improve Equipment Effectiveness AchieveAutonomous Plan Maintenance To Train all staff in maintenance skills To Zero Breakdowns
  • 11.
    1 Breakdowns Long interruptions, . Costly Repairs 2 Setup and changeover Taking Longer time than . needed 3 Idling time and Hard to quantify, add to . stoppages big losses 4 Reduced speed Equipment cycle time . reduces 5 Defects and reworks Quality losses & Unhappy . customer
  • 12.
     Increased productivity Equipment reliability  Reduced down time  Increased plant capacity  Low production maintenance costs  Team work Between Production & Maintenance People  Improved safety & Profit
  • 13.
     Totalcommitment ofupper level management.  Employees must be empowered to initiate corrective action. Category TQM TPM Quality ( Output and Equipment ( Input Object effects ) and cause ) Systematize the Employees Mains of management. It is participation and it is attaining goal software oriented hardware oriented Elimination of losses Target Quality for PPM and wastes.
  • 14.
    PILLARS OF TPM JISHU HOZEN KOBETSU KAIZEN Planned Maintenance Quality Maintenance Training Office TPM Safety , Health & Environment 5S SEIRI SEITON SEISO SEIKETSU SHITSUKE
  • 15.
    FIRST STEP of improvement SEIRI – SORTOUT:  Keep only essential items and eliminate what is not required, prioritizing things as per requirements and keeping them in approachable places. Everything else is stored or discarded. SEITON – ORGANIZE:There should be a place for everything and everything should be in its place. Each tool, part, supply, or piece of equipment should be kept close to where it will be used – in other words, straightening the flow path. SEISO – SHINE THE WORKPLACE:Keep the workplace tidy and organized. At the end of each shift, clean the work area and be sure everything is restored to its place. SEIKETSU – STANDARDIZATION: Work practices should be consistent and standardized. Everyone should know exactly what his or her responsibilities are for adhering to the first 3 S's. SHITSUKE – SELF DISCIPLINE: When an issue arises such as a suggested improvement, a new way of working, a new tool or a new output requirement, review the first 4 S's and make changes as appropriate.
  • 16.
    POLICY 3. Uninterruptedoperation of equipments 4. Flexible operators to operate & maintain other equipments 5. Eliminating the defects at source through active employee participation 6. Stepwise implementation of JISHU HOZEN activities. JH TARGETS 8. Reduce process time by predicted values 9. Reduce oil/ lubricants consumption by predicted valus 10. Increase use of JH JH STEPS 12. Preparation of employees 13. Initial cleanup of machines 14. Take counter measures 15. Fix tentative JH standards 16. General inspection 17. Autonomus inspection 18. Standardization 19. Autonomus management
  • 17.
    KAI means changeor improvement and ZEN means good (for the better). Kobetsu means focused. Basically Kobetsu Kaizen is for small adjustments and corrections but effects the whole process and carried out on a continual basis and involves all people in the organization. The principal behind is that “ a very large number of small improvements are more effective in an organizational environment than a few improvements of large value.
  • 18.
    With planned maintenance,we evolve an effort from a reactive to a proactive method and use trained maintenance staff to help train the operators to better maintain their equipment. Policy: • Achieve and sustains availability of machines • Optimum maintenance cost. • Reduce spares inventory. • Improve reliability and maintainability of machines.
  • 19.
    It is aimed towards customer delight through highest quality through defect free manufacturing. Focus is on eliminating non-conformances in a systematic manner.  Quality defects are classified as “CUSTOMER END defects” and “IN HOUSE defects”.  For customer-end data, we have to get data on Customer-end line rejection and field complaints. In- house data include data related to products and data related to process.
  • 20.
    It is aimedto have multi-skilled revitalized employees whose moral is high and who has eager to come to work and perform all required functions effectively and independently. Education is given to operators to upgrade their skill. The employees should be trained to achieve the form phase of skill which are as under: PHASE 1: Do not know. PHASE 2: Know the theory but cannot do. PHASE 3: Can do but cannot teach. PHASE 4: Can do and also teach.
  • 21.
    Office TPM should be started after activating from other pillars of TPM (JH, KK, and QM.PM). Office TPM must be established to improve productivity, efficiency in the administrative function and identify eliminate losses. This includes analyzing process and procedure towards increased office automation. Statistical analysis will give higher effectiveness to investigate the production and management departments simultaneously.Tpm office has responsibility to take the report of the losses and gainings then scheduling the traning hours professional trainers for the entire company.
  • 22.
    Downtime loss : A=(T/P)x100 where A = availability, T=operating time (P-D), P=planned operating time, D=Downtime  Reduced speed loss : E= (CxN) x 100 T E = perf efficiency, C= Theoticiacl cycle time, N= Processed amt quantity  Poor quality Loss : R = = (N-Q) x 100 N R=rate of quality pdts, N-processed amt, Q=non conformity OEE = A x E x R
  • 23.
     6major losses are need to be measures 1- PLANNED (startups, shift change, coffee&lunch break, planned maintenance shutdowns) 2-Unplanned Downtown ( Equipment breakdown, change over, Lack of material, 3-Idling and minor stoppage 4-Slow downs 5-Proces NC 6- Scrap
  • 24.
    Trainer & Consultant https://sites.google.com/site/anubhawalia/ www.prism-global.org, anubhawalia@gmail.com