This document provides an overview of past and present tunnelling projects and challenges. It discusses the stuck Bertha tunnel boring machine in Seattle which has been stuck since 2013 due to overheating. It also discusses cost overruns and litigation on the Seymour-Capilano Twin Tunnels project in BC. Finally, it provides details on the course topics, lectures, and assignments for an introduction to tunnelling class.
A Review Study on Methods of Tunneling in Hard Rocksijsrd.com
This article presents a review on the different methodologies that are used for tunnels excavations in hard rocks in present era. Growing needs for modern transportation and utility networks have increased the demand for a more extensive and elaborate use of underground space or through high mountains / hills. As a result, more projects have to be completed in various ground conditions and one of which is more challenging is to carry out excavation work in hard rocks. Significant technological advances have rendered these projects possible, but have also given rise to new challenges as many of these projects have to be completed in difficult conditions, with very strict environmental constraints, particularly in urban areas where the potential impact of tunneling on existing structures is a major concern. This paper addresses the main aspects of tunneling and underground works performed in hard rocks. A summary is presented of the more recent advances and widely adopted techniques in these regards.
A Review Study on Methods of Tunneling in Hard Rocksijsrd.com
This article presents a review on the different methodologies that are used for tunnels excavations in hard rocks in present era. Growing needs for modern transportation and utility networks have increased the demand for a more extensive and elaborate use of underground space or through high mountains / hills. As a result, more projects have to be completed in various ground conditions and one of which is more challenging is to carry out excavation work in hard rocks. Significant technological advances have rendered these projects possible, but have also given rise to new challenges as many of these projects have to be completed in difficult conditions, with very strict environmental constraints, particularly in urban areas where the potential impact of tunneling on existing structures is a major concern. This paper addresses the main aspects of tunneling and underground works performed in hard rocks. A summary is presented of the more recent advances and widely adopted techniques in these regards.
Tunnel is an artificially constructed underground passage to by- pass obstacles safely without disturbing the over burden. This module explains about tunnels, their parts, types and importance.
Underground Construction provides construction, technical and management services to its customers. The company specializes in power, communications, airport fueling and heavy engineering. Since laying its first pipe in 1936, Underground Construction has completed thousands of projects throughout the United States.
interesting civil engineering topics
civil engineering topics for presentation
underground construction magazine
underground construction contractors
underground construction az
underground construction company
underground construction safety
underground construction company california
underground construction technology 2019
push underground construction llc
seminar topics pdf
best seminar topics for civil engineering
civil seminar topics ppt
civil engineering seminar topics 2019
seminar topics for mechanical engineers
mechanical engineering seminar topics 2018
tunnel lining may be permanent or temporary based upon their use and requirement. design of lining is done in two parts one is temporary or initial lining design and other is permanent design of the lining. empirical and theoretical methods are major design methods.
Tunnel is an artificially constructed underground passage to by- pass obstacles safely without disturbing the over burden. This module explains about tunnels, their parts, types and importance.
Underground Construction provides construction, technical and management services to its customers. The company specializes in power, communications, airport fueling and heavy engineering. Since laying its first pipe in 1936, Underground Construction has completed thousands of projects throughout the United States.
interesting civil engineering topics
civil engineering topics for presentation
underground construction magazine
underground construction contractors
underground construction az
underground construction company
underground construction safety
underground construction company california
underground construction technology 2019
push underground construction llc
seminar topics pdf
best seminar topics for civil engineering
civil seminar topics ppt
civil engineering seminar topics 2019
seminar topics for mechanical engineers
mechanical engineering seminar topics 2018
tunnel lining may be permanent or temporary based upon their use and requirement. design of lining is done in two parts one is temporary or initial lining design and other is permanent design of the lining. empirical and theoretical methods are major design methods.
This construction job story, "Deep Foundations Drill to Keep TBMs Crawling on Canada's Largest Transit Expansion," ran on the cover of Foundation Drilling Magazine. It also ran in several American, Canadian, and European construction magazines.
This construction job story, "Keep on Boring," ran in the November 2017 issue of Foundation Drilling Magazine. It also ran in several American, Canadian, and European construction magazines.
Immersed tube tunnel is an alternative to bridges and bored tunnels for the crossing of harbors/rivers. Different strategies were considered for the construction of the immersed tunnels in India from different projects around the world during the project.
Evaluating the application limits of Unreinforced & Steel Fiber Reinforced Co...MECandPMV
OUTLINE OF THE PRESENTATION
1. Recent tunnel cases with unreinforced and Steel Fiber Reinforced Concrete tunnel linings
2. Existing Design Codes and Design Recommendations framework
3. Numerical analyses of the unreinforced concrete tunnel linings under static and seismic loading conditions. T1 & T2 tunnels of Maliakos - Kleidi Motorway and T26 tunnel of Athens - Patras Motorway in Greece.
4. Numerical analyses of SFRC tunnel linings under static loading conditions.
5. Some critical thoughts about the geostatic loads on to the tunnel final linings.
6. Some critical thoughts about the ground elastic modulus for the design of tunnel linings
7. Conclusions
Detailed outlineResearch question What happened to th.docxsimonithomas47935
Detailed outline
Research question:
What happened to the Tacoma Narrows Bridge and what steps can engineer take to avoid this situation from happening again?
Thesis statement:
There are important lessons that engineers can learn from studying the design and the collapse of the Tacoma Narrows Bridge so they can avoid this from happening again in the future.
I. Introduction
II. Design
A. As the Tacoma Narrows Bridge was being designed, engineers were not expecting wind that hits at 42 miles per hour.
B. The Tacoma Narrows Bridge was too weak to hold because the bridge was too light, too shallow and too long.
III. Cause of collapse
How could a modern bridge with advanced design suffer failure from wind?
A. the main reason of the failure of Tacoma Narrows bridge was it’s great flexibility, while the bridge was moving it acted like aerofoil, creating drag and lift.
B. aerodynamic were a bit understood, engineers were supposed to test bring modals and suspension.
IV. For avoiding future problems
A. Engineers must utilise computer simulations that makes them better understand design and pressure of wind flow.
B.
Detailed outline
Research question:
What happened to the Tacoma Narrows Bridge and what steps can engineer take to avoid this situation from happening again?
Thesis statement:
There are important lessons that engineers can learn from studying the design and the collapse of the Tacoma Narrows Bridge so they can avoid this from happening again in the future.
I. Introduction
II. Design
A. As the Tacoma Narrows Bridge was being designed, engineers were not expecting wind that hits at 42 miles per hour.
B. The Tacoma Narrows Bridge was too weak to hold because the bridge was too light, too shallow and too long.
III. Cause of collapse
How could a modern bridge with advanced design suffer failure from wind?
A. the main reason of the failure of Tacoma Narrows bridge was it’s great flexibility, while the bridge was moving it acted like aerofoil, creating drag and lift.
B. aerodynamic were a bit understood, engineers were supposed to test bring modals and suspension.
IV. For avoiding future problems
A. Engineers must utilise computer simulations that makes them better understand design and pressure of wind flow.
B.
The Tacoma Narrows Collapse
March, 2017
Imagine yourself driving through the third longest bridge with your beloved Golden Retriever on a hot sunny day. However, you suddenly feel the bridge kneeling towards the right and left. Seeing everyone in front of you vacating their cars and running away from the bridge before it collapses. Most likely, you would do the same even maybe 3 times faster before it’s too late. But sadly, when it’s too late and the bridge has collapsed you will eventually realize that you have left your beloved dog behind. The First Tacoma Narrows Bridge was being completed and designed in the state of Washington, Tacoma. The Tacoma Narrows bridge was constructed .
Cosmetic shop management system project report.pdfKamal Acharya
Buying new cosmetic products is difficult. It can even be scary for those who have sensitive skin and are prone to skin trouble. The information needed to alleviate this problem is on the back of each product, but it's thought to interpret those ingredient lists unless you have a background in chemistry.
Instead of buying and hoping for the best, we can use data science to help us predict which products may be good fits for us. It includes various function programs to do the above mentioned tasks.
Data file handling has been effectively used in the program.
The automated cosmetic shop management system should deal with the automation of general workflow and administration process of the shop. The main processes of the system focus on customer's request where the system is able to search the most appropriate products and deliver it to the customers. It should help the employees to quickly identify the list of cosmetic product that have reached the minimum quantity and also keep a track of expired date for each cosmetic product. It should help the employees to find the rack number in which the product is placed.It is also Faster and more efficient way.
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Dr.Costas Sachpazis
Terzaghi's soil bearing capacity theory, developed by Karl Terzaghi, is a fundamental principle in geotechnical engineering used to determine the bearing capacity of shallow foundations. This theory provides a method to calculate the ultimate bearing capacity of soil, which is the maximum load per unit area that the soil can support without undergoing shear failure. The Calculation HTML Code included.
Forklift Classes Overview by Intella PartsIntella Parts
Discover the different forklift classes and their specific applications. Learn how to choose the right forklift for your needs to ensure safety, efficiency, and compliance in your operations.
For more technical information, visit our website https://intellaparts.com
Saudi Arabia stands as a titan in the global energy landscape, renowned for its abundant oil and gas resources. It's the largest exporter of petroleum and holds some of the world's most significant reserves. Let's delve into the top 10 oil and gas projects shaping Saudi Arabia's energy future in 2024.
Welcome to WIPAC Monthly the magazine brought to you by the LinkedIn Group Water Industry Process Automation & Control.
In this month's edition, along with this month's industry news to celebrate the 13 years since the group was created we have articles including
A case study of the used of Advanced Process Control at the Wastewater Treatment works at Lleida in Spain
A look back on an article on smart wastewater networks in order to see how the industry has measured up in the interim around the adoption of Digital Transformation in the Water Industry.
Hierarchical Digital Twin of a Naval Power SystemKerry Sado
A hierarchical digital twin of a Naval DC power system has been developed and experimentally verified. Similar to other state-of-the-art digital twins, this technology creates a digital replica of the physical system executed in real-time or faster, which can modify hardware controls. However, its advantage stems from distributing computational efforts by utilizing a hierarchical structure composed of lower-level digital twin blocks and a higher-level system digital twin. Each digital twin block is associated with a physical subsystem of the hardware and communicates with a singular system digital twin, which creates a system-level response. By extracting information from each level of the hierarchy, power system controls of the hardware were reconfigured autonomously. This hierarchical digital twin development offers several advantages over other digital twins, particularly in the field of naval power systems. The hierarchical structure allows for greater computational efficiency and scalability while the ability to autonomously reconfigure hardware controls offers increased flexibility and responsiveness. The hierarchical decomposition and models utilized were well aligned with the physical twin, as indicated by the maximum deviations between the developed digital twin hierarchy and the hardware.
We have compiled the most important slides from each speaker's presentation. This year’s compilation, available for free, captures the key insights and contributions shared during the DfMAy 2024 conference.
Tunnelling & underground design (Topic1-introduction to the tunnelling industry)
1. 1
1 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
EOSC547:
Tunnelling &
Underground Design
Topic 1:
Introduction –
Tunnelling Past &
Present
2 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
Tunnelling Challenges: Bertha
Seattle is undertaking the replacement of the
Alaskan Way Viaduct with a 3.2 km tunnel. The
project is estimated to cost US$4.25 billion.
The $80 million TBM - Bertha - created for
this project by Hitachi Zosen Corporation is a
record-breaking 17.5 m diameter.
Currently, the TBM has been stuck since
December 2013, after only 10% of the way
through. Investigators believe that Bertha
was overheating—that grime and gunk had
gotten past bearing seals, entered the
machine, and muddied the operation.
Engineers still aren't sure why this
happened, but they have decided they need
to replace not only the seals but also the $5
million main bearing.
2. 2
3 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
Tunnelling Challenges: Bertha
The contractor is now
asking for an additional
$188 million to cover the
unexpected expenses. As
a Design-Build contract,
the state is refusing to
pay, which will likely
result in a claims law
suit—or, if costs rise too
much, the contractor
could possibly abandon
the project.
4 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
Tunnelling Challenges: Seymour-Capilano
Litigation is underway over the $200M Seymour-Capilano Twin
Tunnels, where a dispute had arose regarding the safety of the
design because of unexpected rock mass conditions. The contractor
stopped work half way through, and Metro Vancouver cancelled the
contract and sued for breach of contract. A new contractor was
brought in to complete the tunnels – using the same design; the
estimated cost overrun is 100%.
3. 3
5 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
Tunnelling Challenges
The Boston "Big Dig"
rerouted a major highway
that passed through the
city centre underground.
This freed up an
unprecedented 30 acres in
downtown Boston, giving
planners a historic
opportunity to shape the
future of the city.
At US$14.6 billion, this was the most costly highway project in
the U.S., but it was plagued by escalating costs, scheduling
overruns, leaks, design flaws, charges of poor execution and use
of substandard materials, criminal arrests, and one death. The
project was completed 9 years late and about 190% over budget.
6 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
Tunnelling Successes – Canada Line
The $2 billion Canada Line was completed 15 weeks
ahead of schedule and on budget. Although Cambie
Street merchants protested over lost business
incurred during construction, property values along
the line have increased and ridership has steadily
grown and exceeded projections. In terms of
environmental benefits, Canada Line’s
transportation capacity represents a reduction of
14,000 tons of CO2 emission over its first 5 years.
4. 4
7 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
Course Overview
The topics we’ll examine will step through the
tunnel design process, from the writing and
review of geotechnical baseline reports, to
tunnelling methods for different ground
conditions, to support design.
In this course, we’ll examine the
different principles, approaches, and
tools used in tunnel excavation and
underground design. The examples and
case histories reviewed will focus on
tunnel excavations in both soft soil and
hard rock.
8 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
Content
Tunnelling in Weak Rock
– Terzaghi’s rock load; sequential excavation; observational approach.
Tunnelling in Burst-Prone Rock
– stress as a boundary condition; in situ stress determination.
Soft Ground Tunnelling Methods
– cut and cover; compressed air; earth pressure balance machines.
Support of Tunnels
– ground response & support interaction curves.
Rock Support & Excavation
– NATM.
Introduction
– state of tunnelling, tunnelling in Canada.
Geotechnical Baseline Reports
– contract types; baseline reports; site investigation; risk.
Geological Uncertainty
– “The Known Knowns, Known Unknowns, & Unknown Unknowns”.
Hard Rock Tunnelling Methods
– drill and blast; open tunnel boring machines, ground support types.
5. 5
9 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
General Information
Lectures: Monday, 11:00 to 13:00 (ESB 5108)
Grades: tunnel design assignment
Part 1 – Baseline Report 15%
Part 2 – Squeezing Ground 25%
Part 3 – Spalling & Bursting 25%
student prepared lecture 25%
peer review participation 10%
Contact Info – 251 EOS South
Phone: (604) 827-5573
E-mail: erik@eos.ubc.ca
10 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
All major ancient
civilizations developed
tunneling methods. In
Babylonia, tunnels were
used extensively for
irrigation; and a brick-
lined pedestrian passage
some 900 m long was
built around 2180 BC
under the Euphrates
River to connect the
royal palace with the
temple. Construction was
accomplished by diverting
the river during the dry
season.
Tunnel Construction: In the Beginning
6. 6
11 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
Tunnel Construction: In the Beginning
Perhaps the largest tunnel in ancient
times was a 1600 m long, 8 m wide, 10 m
high road tunnel (the Pausilippo) between
Naples and Pozzuoli, built in 36 BC.
The Greeks and Romans both made extensive use of tunnels to
reclaim land by drainage and for water aqueducts.
6th-century-BC Greek water tunnel on the
isle of Samos driven some 1100 m through
limestone with a cross section about 2 x 2 m.
12 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
Tunnel Construction: In the Beginning
In the AD 41, Romans used some 30,000 men to push
a 6 km tunnel over 10 years to drain Lacus Fucinus.
They worked from shafts 40 m apart and up to 125 m
deep. Far more attention was paid to ventilation and
safety measures when workers were freemen,
compared to those who were slaves.
7. 7
13 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
Tunnel Construction: In the Beginning
Ancient construction was carried out using a succession
of closely spaced shafts to provide ventilation. String
line and plumb bobs were used for surveying.
Ventilation methods were primitive, often limited
to waving a canvas at the mouth of the shaft, and
most tunnels claimed the lives of hundreds or even
thousands of the slaves used as workers.
To save the need for a lining, most ancient tunnels
were located in strong rock, which was excavated
by heating the rock with fire and suddenly cooling it
by dousing with water causing the rock to spall.
14 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
Modern Beginnings: The Thames
Tunnelling in soft, water saturated
ground began with Marc Brunel when
he invented the principle of shield
tunnelling and undertook a contract to
tunnel under the Thames between
1825 and 1841. His shield consisted
of 12 independent cells in which
workers hand excavated the ground
behind a secure wall of ‘poling
boards’. One board would be removed
to provide access for digging, after
which it would be replaced and pushed
forward by hydraulic jacks to re-
engage the face support.
Brunel’s shield was 7 m high and 12 m wide, and
enabled 36 miners to work the tunnel face at
one time. The brickwork built right behind the
‘shield’ served as an abutment for the whole
frame. On average, progress was 3-5 m/week.
Harding (1981)
8. 8
15 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
Modern Beginnings: The Thames
Flooding was a
constant problem for
Brunel in tunnelling
under the Thames.
In one such flood 6
men drowned.
Brunel’s complaint to
those offering advice
on tunnelling in such
difficult conditions,
“In every case they
make the ground to
suit the plan and not
the plan to suit the
ground”.
Completed in 1843, Brunel’s tunnel is still in full use as part
of London’s Underground railway system, exactly as built!
16 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
Modern Beginnings: The Thames
James Greathead solved the problem of containing groundwater
during the construction of subaqueous tunnels in loose soil, by
combining shield tunnelling with the use of compressed air during his
construction of the London Underground.
This led to a considerable increase in the number of shield driven
tunnels world-wide. At the beginning of the 20th century, the majority
of the tunnels were built with Greathead shields.
James Greathead’s 2.5 m diameter circular
shield, propelled by screw jacks, employed
the first use of cast iron lining segments.
9. 9
17 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
State of Tunnelling in Canada
18 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
Canada, Mining & Tunnelling
10. 10
19 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
Canada, Mining & Tunnelling
20 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
Canada, Mining & Tunnelling
11. 11
21 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
Canada’s First Tunnel
22 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
1890 St. Clair Tunnel
First full-size
subaqueous tunnel built
in North America.
12. 12
23 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
1909 Spiral Tunnel
24 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
1930 Windsor-Detroit Tunnel
13. 13
25 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
Tunnel
Length
(km)
Completion
Date
Gotthard Base (CH) 57.1 2018
Brenner Base (Au-It) 55 2025
Sei-kan (Japan) 53.9 1988
Mont d’Ambin (Fr-It) 52 2023
Chunnel (ENG-FR) 50.5 1994
Loetschberg (CH) 34.6 2007
World’s Longest Rail Tunnels
#30 Mount MacDonald (CAN) @ 14.6 km
#43 New Cascade (USA) @ 12.5 km
Canada = 5 rail tunnels > 2 km
USA = 4 rail tunnels > 2 km
Switzerland = 42 rail tunnels > 2 km
Perspectives – Value of Tunnels
26 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
Tunnel
Length
(km)
Completion
Date
Gotthard Base (CH) 57.1 2018
Brenner Base (Au-It) 55 2025
Sei-kan (Japan) 53.9 1988
Mont d’Ambin (Fr-It) 52 2023
Chunnel (ENG-FR) 50.5 1994
Loetschberg (CH) 34.6 2007
World’s Longest Rail Tunnels
#30 Mount MacDonald (CAN) @ 14.6 km
#43 New Cascade (USA) @ 12.5 km
Canada = 5 rail tunnels > 2 km
USA = 4 rail tunnels > 2 km
Switzerland = 42 rail tunnels > 2 km
Perspectives – Value of Tunnels
Estimated Costs:
$12 Billion CDN
$4.3 Billion CDN
14. 14
27 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
Eglinton-Scarborough Crosstown Light Rail Transit
• $8.2 billion public transit
investment, one of the
largest in Canadian history.
• 10 km of tunnels along
Eglinton Avenue corridor in
midtown Toronto.
• Tunnelling is being carried
out by two TBMs – Dennis
& Lea.
• Project completion
scheduled for 2020.
Top Canadian Infrastructure Projects
28 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
La Romaine Hydroelectric Complex
• $6.5 billion, 1550 MW
hydroelectric complex , to be
completed in 2020.
• Four rockfill dams , with multiple
bypass and pressure tunnels.
Top Canadian Infrastructure Projects
15. 15
29 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
240 m Level
A Canadian Export – High Stress Expertise
30 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
3
1
420 m Level
Martin(1997)
A Canadian Export – High Stress Expertise
16. 16
31 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
Loetschberg Tunnel
A Canadian Export – High Stress Expertise
32 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
max = 0.4 UCS
Martin et al. (1999)
ci = 0.4 UCS
Eberhardt et al. (1999)
A Canadian Export – High Stress Expertise
17. 17
33 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
A Canadian Export – High Stress Expertise
Using Martin et al.
(1999)’s empirical
relationship
1.5a
34 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
• 7.1 km long, 3.8 m
diameter twin tunnels
(joint venture of
Aecon, JF Shea &
Frontier Kemper).
• Both tunnels were
completed by
November 2010.
• Final shotcrete lining
and steel liner
installation is 100%
complete as of August
2014.
Seymour-Capilano Twin Tunnels
B.C. Tunnelling Projects – Water Conveyance
18. 18
35 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
Port Mann Water Supply Tunnel • Approximately 1km
long, 3.5 m diameter,
40 m under the Fraser
River.
• Excavation is being
carried out using a
CAT EPB TBM;
construction is being
undertaken by the
McNally-Aecon Joint
Venture.
• Expected completion in
late 2014.
B.C. Tunnelling Projects – Water Conveyance
36 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
Evergreen Line
B.C. Tunnelling Projects - Transportation
• 11 km extension to
GVRD’s rapid transit
system, which includes
a 2 km long 10 m
diameter bored
tunnel.
• Design-build-finance
contract with
tunnelling work being
conducted by SNC-
SELI JV.
• The tunnel is being
excavated with a CAT
EPB TBM and is
expected to finish in
early 2015.
19. 19
37 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
B.C. Tunnelling Projects
B.C. is also currently experiencing an
increase in activity in hydroelectric
project development.
● AltaGas has completed their 195 MW
Forrest Kerr Hydro Project in northern
B.C. The project included over 5000 m of
access, tailrace and power tunnels.
Tunnel construction was carried out by
Procon. The project is now in service.
● AltaGas is also constructing the 66 MW
McLymont Creek Hydro Project
downstream of Forrest Kerr. This project
includes an intake, surface powerhouse
and a 2.7 km long power tunnel. Tunnel
excavation commenced in Q2 2013, with
tunnel excavation being carried out by
Procon Mining and Tunnelling. The project
is scheduled for completion in mid 2015.
38 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
B.C. Tunnelling Projects - Hydroelectric
● BC Hydro’s $1B John Hart Generating Station Replacement Project,
located near Campbell River on Vancouver Island, includes a 2.1 km long
tunnel, underground powerhouse, and associated shafts and access
tunnels. Underground construction is scheduled to start in Fall 2014.
● Innergex Renewable Energy is constructing the Upper Lillooet
Hydroelectric Project 70 km northwest of Pemberton. The project
includes two facilities, the Upper Lillooet and Boulder Creek, with 2500
m and 2900 m long drill and blast power tunnels, to be completed in mid
2016.
● The province has approved the
$8.8 billion Site C hydroelectric
dam, the third generating
station on the Peace River. Site
C will provide enough energy to
power the equivalent of about
450,000 homes per year.
20. 20
39 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
B.C. Tunnelling Projects – Mining & Energy
Seabridge Gold’s KSM
40 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
Tunnelling Association of Canada – B.C. Chapter
The Tunnelling Association of Canada and its B.C.
Chapter are highly active, organizing monthly talks at
the Steamworks Pub in downtown Vancouver. These
have been highly successful in allowing graduate
students and junior engineers to network with locally-
based tunnelling professionals.
Student Membership $15 !!
http://www.tunnelcanada.ca/
21. 21
41 of 46 Tunnelling Grad Class (2015) Erik Eberhardt
Future Perspectives
• The level of tunnelling expertise within Canada is
extensive, honed through the large number of tunnels
that have been completed in a variety of challenging
geological settings, in major cities and remote locations.
• Our collective experiences with EPB in glacial deposits
and hard rock tunnelling in high stresses are only two
examples where Canada has positioned itself as an
international leader.
• The tunnelling industry is active in B.C., with a number
of transportation, water and sewer, hydroelectric, mining
and pipeline projects planned, ongoing and completed in
Greater Vancouver and other regions of the province.