SlideShare a Scribd company logo
By
VISHAL KUMAR SINGH
1CR12CV057
Guided by:
Vibha N. Dalawai
CONTENTS
 Introduction
 Objective
 Major construction of TBM
 Tunnel lining
 Surveying
 Geotechnical consideration
 Different types of TBM
 Annulus grouts & Mortars
 References
INTRODUCTION
 First tunneling shield by Sir Marc Isambard
Brunel to excavate under the Thames in 1825.
 Actual boring machine built-in 1845 by Henri-
Joseph Maus
OBJECTIVES
 To give an understanding of what is a
TBM.
 To build up an awareness of the wide
variety of perils TBMs are exposed to.
 Role of civil engineers in this machine
tunneling work.
 How we utilizes our geotechnical and
survey knowledge.
MAJOR COMPONENTS OF
TBM
TUNNEL LINING
 5 segments and 1 key segment, each 1.2 and
1.5 m long and 275 mm thick.
 The segments were precast with M50 grade
concrete at the casting yard
SURVEYING
 After doing general survey i.e. identifying
geographical extent of the construction work,
reconnaissance survey, establishing new
survey stations from known control stations.
 Computation of global coordinates of control
stations are performed
 Secondary control station established for TBM
launching shaft at surface & then transfer that
to tunnel control station at underground level
GEOTECHNICAL
CONSIDERATION
Rock-quality designation (RQD) is a rough
measure of the degree of jointing or fracture
in a rock mass, measured as a percentage of
the drill core in lengths of 10 cm or more.
High-quality rock has an RQD of more than
75%, low quality of less than 50%.
DIFFERENT TYPES OF TBM
 1. SLURRY SHIELD TBM
slurry test programmed will generally include the above parameters[ 2]
 2. Earth pressure balance TBM
indicates typical particle size distributions for the use of EPBM[ 3 ]
ANNULUS GROUTS &
MORTARS
 To prevent flotation and heave
 To prevent surface subsidence
 To prevent misalignment of the segment rings
 To bond the soil and segments into a single
component
REFERENCES
 1).To my training, which I did in tunneling, on the metro site of Delhi, which was under
construction under Shanghai Urban Construction Group (SUCG), joint venture with L&T.
 2). Andrew Hung Shing Lee, “ENGINEERING SURVEY SYSTEM FOR TBM (Tunnel
Boring Machine TUNNEL CONSTRUCTION)”, Hong Kong ISBN 978-56-56-65-55
 3). Kolymbass, 2005 “TUNNELING & TUNNEL MECHANICS”, 2005, ISBN 456-23-
59-20-12
 4). “A GENERAL OVERVIEW ON TUNNEL BORING MACHINES” By Prof. jian
ZHAQ, rock mechanics and tunnelling. UK ISBN 111-419-23-45-71-83
 M. Cigla, S. Yagiz & l.Ozdemir,"APPLICATION OF TUNNEL BORING MACHINES IN
THANK YOU

More Related Content

What's hot

Tunnel boring machine
Tunnel boring machineTunnel boring machine
Tunneling
TunnelingTunneling
Tunneling
Safdar Ali
 
report for tunnelling by tunnel boring machine
report for tunnelling by tunnel boring machinereport for tunnelling by tunnel boring machine
report for tunnelling by tunnel boring machine
VISHAL KUMAR SINGH
 
Tunnel boring machines123
Tunnel boring machines123Tunnel boring machines123
Tunnel boring machines123
Arpit Srivastava
 
NEW AUSTRIAN TUNNELING METHOD
NEW AUSTRIAN TUNNELING METHODNEW AUSTRIAN TUNNELING METHOD
NEW AUSTRIAN TUNNELING METHOD
ADIL BIN AYOUB
 
Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine mohammadsalikali
 
Tunneling Construction - NATM
Tunneling Construction - NATMTunneling Construction - NATM
Tunneling Construction - NATM
luisaam
 
Tunnels ppt
Tunnels pptTunnels ppt
Tunnels ppt
1971995
 
Excavators: Power Shovel, Backhoe an Front Shovel (by Faisal VA and Karthik V)
Excavators: Power Shovel, Backhoe an Front Shovel (by Faisal VA and Karthik V)Excavators: Power Shovel, Backhoe an Front Shovel (by Faisal VA and Karthik V)
Excavators: Power Shovel, Backhoe an Front Shovel (by Faisal VA and Karthik V)
Construction Tech. and Mgmt., VNIT Nagpur
 
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
Hitesh Khanna
 
Study of tunnel engineering
Study of tunnel engineeringStudy of tunnel engineering
Study of tunnel engineering
Adil Shaikh
 
NATM Tunneling ppt
NATM Tunneling pptNATM Tunneling ppt
NATM Tunneling ppt
Suman Paul
 
Different types of pile
Different types of pile Different types of pile
Different types of pile
Gaurang Kakadiya
 
Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
jagadish chintu
 
Bridge foundation
Bridge foundationBridge foundation
Bridge foundation
SHUBHAM DABHADE
 
Tunnel Boring Machines
Tunnel Boring Machines  Tunnel Boring Machines
Segmental Lining Design Presentation
Segmental Lining Design PresentationSegmental Lining Design Presentation
Segmental Lining Design PresentationKeith Kong
 
Shaft sinking 1
Shaft sinking 1Shaft sinking 1
Shaft sinking 1
Er.Sunil Wasade
 

What's hot (20)

Tunnel boring machine
Tunnel boring machineTunnel boring machine
Tunnel boring machine
 
Tbm
TbmTbm
Tbm
 
Tunneling
TunnelingTunneling
Tunneling
 
report for tunnelling by tunnel boring machine
report for tunnelling by tunnel boring machinereport for tunnelling by tunnel boring machine
report for tunnelling by tunnel boring machine
 
Tunnel boring machines123
Tunnel boring machines123Tunnel boring machines123
Tunnel boring machines123
 
NEW AUSTRIAN TUNNELING METHOD
NEW AUSTRIAN TUNNELING METHODNEW AUSTRIAN TUNNELING METHOD
NEW AUSTRIAN TUNNELING METHOD
 
Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine
 
Tunneling Construction - NATM
Tunneling Construction - NATMTunneling Construction - NATM
Tunneling Construction - NATM
 
Tunnels ppt
Tunnels pptTunnels ppt
Tunnels ppt
 
Excavators: Power Shovel, Backhoe an Front Shovel (by Faisal VA and Karthik V)
Excavators: Power Shovel, Backhoe an Front Shovel (by Faisal VA and Karthik V)Excavators: Power Shovel, Backhoe an Front Shovel (by Faisal VA and Karthik V)
Excavators: Power Shovel, Backhoe an Front Shovel (by Faisal VA and Karthik V)
 
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
 
Study of tunnel engineering
Study of tunnel engineeringStudy of tunnel engineering
Study of tunnel engineering
 
NATM Tunneling ppt
NATM Tunneling pptNATM Tunneling ppt
NATM Tunneling ppt
 
Different types of pile
Different types of pile Different types of pile
Different types of pile
 
Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
 
Tunnel construction
Tunnel constructionTunnel construction
Tunnel construction
 
Bridge foundation
Bridge foundationBridge foundation
Bridge foundation
 
Tunnel Boring Machines
Tunnel Boring Machines  Tunnel Boring Machines
Tunnel Boring Machines
 
Segmental Lining Design Presentation
Segmental Lining Design PresentationSegmental Lining Design Presentation
Segmental Lining Design Presentation
 
Shaft sinking 1
Shaft sinking 1Shaft sinking 1
Shaft sinking 1
 

Viewers also liked

Continuous miner
Continuous minerContinuous miner
Continuous miner
Chandan Chaman
 
(TBM) ماشین حفاری تونل
(TBM) ماشین حفاری تونل(TBM) ماشین حفاری تونل
(TBM) ماشین حفاری تونلHamed Zarei
 
Latest technological developments in underground mining
Latest technological developments in underground miningLatest technological developments in underground mining
Latest technological developments in underground miningPartha Sarathi Panda
 
CONTINUOUS MINERS
CONTINUOUS MINERSCONTINUOUS MINERS
CONTINUOUS MINERS
Tauhid Mohammad
 
Guidelines
GuidelinesGuidelines
Guidelines
Šumadin Šumić
 
Bridge
BridgeBridge
Strukturas General Presentation (200ppi)
Strukturas General Presentation (200ppi)Strukturas General Presentation (200ppi)
Strukturas General Presentation (200ppi)
Strukturas
 
Innovative Precast Bridge System
Innovative Precast Bridge SystemInnovative Precast Bridge System
Innovative Precast Bridge System
AltosMarketing
 
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
Mohit Shukla
 
Ecg533 rock-tunnel-engineering
Ecg533 rock-tunnel-engineeringEcg533 rock-tunnel-engineering
Ecg533 rock-tunnel-engineeringJunaida Wally
 
Tunnel engg.2
Tunnel engg.2Tunnel engg.2
Tunnel engg.2
SHUBHAM DABHADE
 
Structural design of tunnel lining
Structural design of tunnel liningStructural design of tunnel lining
Structural design of tunnel lining
Mahesh Raj Bhatt
 
tunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessitytunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessity
Shashank Gaurav
 
Bridges precast
Bridges precastBridges precast
Bridges precast
Dr Fereidoun Dejahang
 
My publication Tunnels and Tunnelling magazine
My publication Tunnels and Tunnelling magazineMy publication Tunnels and Tunnelling magazine
My publication Tunnels and Tunnelling magazineFilipe Mello
 
Corrugated Steel Bridge and Tunnel Solutions
Corrugated Steel Bridge and Tunnel SolutionsCorrugated Steel Bridge and Tunnel Solutions
Corrugated Steel Bridge and Tunnel Solutions
Communications Branding
 
Diaphragm Wall Presentation By Gagan
Diaphragm Wall Presentation By GaganDiaphragm Wall Presentation By Gagan
Diaphragm Wall Presentation By Gagan
HERITAGE INFRASPACE INDIA PRIVATE LIMITED
 
Precast segmental concrete bridges a
Precast segmental concrete bridges aPrecast segmental concrete bridges a
Precast segmental concrete bridges a
Palmer Consulting Services, LLC
 

Viewers also liked (20)

Continuous miner
Continuous minerContinuous miner
Continuous miner
 
(TBM) ماشین حفاری تونل
(TBM) ماشین حفاری تونل(TBM) ماشین حفاری تونل
(TBM) ماشین حفاری تونل
 
Latest technological developments in underground mining
Latest technological developments in underground miningLatest technological developments in underground mining
Latest technological developments in underground mining
 
Continuous miners
Continuous minersContinuous miners
Continuous miners
 
CONTINUOUS MINERS
CONTINUOUS MINERSCONTINUOUS MINERS
CONTINUOUS MINERS
 
Guidelines
GuidelinesGuidelines
Guidelines
 
Bridge
BridgeBridge
Bridge
 
Strukturas General Presentation (200ppi)
Strukturas General Presentation (200ppi)Strukturas General Presentation (200ppi)
Strukturas General Presentation (200ppi)
 
Innovative Precast Bridge System
Innovative Precast Bridge SystemInnovative Precast Bridge System
Innovative Precast Bridge System
 
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
 
Ecg533 rock-tunnel-engineering
Ecg533 rock-tunnel-engineeringEcg533 rock-tunnel-engineering
Ecg533 rock-tunnel-engineering
 
Tunnel engg.2
Tunnel engg.2Tunnel engg.2
Tunnel engg.2
 
Structural design of tunnel lining
Structural design of tunnel liningStructural design of tunnel lining
Structural design of tunnel lining
 
tunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessitytunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessity
 
Bridges precast
Bridges precastBridges precast
Bridges precast
 
My publication Tunnels and Tunnelling magazine
My publication Tunnels and Tunnelling magazineMy publication Tunnels and Tunnelling magazine
My publication Tunnels and Tunnelling magazine
 
Tunneling
Tunneling  Tunneling
Tunneling
 
Corrugated Steel Bridge and Tunnel Solutions
Corrugated Steel Bridge and Tunnel SolutionsCorrugated Steel Bridge and Tunnel Solutions
Corrugated Steel Bridge and Tunnel Solutions
 
Diaphragm Wall Presentation By Gagan
Diaphragm Wall Presentation By GaganDiaphragm Wall Presentation By Gagan
Diaphragm Wall Presentation By Gagan
 
Precast segmental concrete bridges a
Precast segmental concrete bridges aPrecast segmental concrete bridges a
Precast segmental concrete bridges a
 

Similar to Tunneling by tunnel boring machine

Rates of Soft Ground Tunneling in Vicinity of Existing Structures
Rates of Soft Ground Tunneling in Vicinity of Existing StructuresRates of Soft Ground Tunneling in Vicinity of Existing Structures
Rates of Soft Ground Tunneling in Vicinity of Existing Structures
IJAEMSJORNAL
 
Dmrctrainingpresentation 161115165907
Dmrctrainingpresentation 161115165907Dmrctrainingpresentation 161115165907
Dmrctrainingpresentation 161115165907
yogesh pal
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...
Rajesh Prasad
 
TRENCHLESS TECHNOLOGY
TRENCHLESS TECHNOLOGYTRENCHLESS TECHNOLOGY
TRENCHLESS TECHNOLOGY
Yatiraj Battul
 
STRESSES BELOW EXISTING STRUCTURES DURING TUNNEL EXCAVATION USING TUNNEL BORI...
STRESSES BELOW EXISTING STRUCTURES DURING TUNNEL EXCAVATION USING TUNNEL BORI...STRESSES BELOW EXISTING STRUCTURES DURING TUNNEL EXCAVATION USING TUNNEL BORI...
STRESSES BELOW EXISTING STRUCTURES DURING TUNNEL EXCAVATION USING TUNNEL BORI...
ijiert bestjournal
 
Study of Dynamic Analysis for Immersed Tube Tunnel
Study of Dynamic Analysis for Immersed Tube TunnelStudy of Dynamic Analysis for Immersed Tube Tunnel
Study of Dynamic Analysis for Immersed Tube Tunnel
ijceronline
 
Metro Underground civil structures and track structures AR.pdf
Metro Underground civil structures and track structures AR.pdfMetro Underground civil structures and track structures AR.pdf
Metro Underground civil structures and track structures AR.pdf
AshutoshRankawat
 
Metro Underground civil structures and track structures AR.pdf
Metro Underground civil structures and track structures AR.pdfMetro Underground civil structures and track structures AR.pdf
Metro Underground civil structures and track structures AR.pdf
AshutoshRankawat
 
Underground Coal Mining Study
Underground Coal Mining StudyUnderground Coal Mining Study
Underground Coal Mining Study
Onur Tuncay
 
Presentation on Piling Machine & TMB
Presentation on Piling Machine & TMBPresentation on Piling Machine & TMB
Presentation on Piling Machine & TMB
indranjanGhosh
 
Eurasia tunnel1
Eurasia tunnel1Eurasia tunnel1
Eurasia tunnel1
Ujwal Ujwal
 
Full paper 2014 trb 93rd arsta bridge, oh-sl-mss, sweden 07 (draft)
Full paper 2014 trb 93rd arsta bridge, oh-sl-mss, sweden 07 (draft)Full paper 2014 trb 93rd arsta bridge, oh-sl-mss, sweden 07 (draft)
Full paper 2014 trb 93rd arsta bridge, oh-sl-mss, sweden 07 (draft)Ton Watanapong
 
Building Construction I Report
Building Construction I ReportBuilding Construction I Report
Building Construction I Report
kelvinyong95
 
Bcon revised
Bcon revisedBcon revised
Bcon revised
Ken Wong
 
B construction I
B construction IB construction I
B construction I
Kelvin Yong
 
Building Construction Report
Building Construction ReportBuilding Construction Report
Building Construction Report
Joshua Lee
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
AlexASquare1
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
AlexASquare1
 
Effect of underground tunnelling by (TBM) on foundations of existing structures
Effect of underground tunnelling by (TBM) on foundations of existing structuresEffect of underground tunnelling by (TBM) on foundations of existing structures
Effect of underground tunnelling by (TBM) on foundations of existing structures
Kishor Ade
 
Hybrid epb tunnelling in rio de janeiro 2015
Hybrid epb tunnelling in rio de janeiro 2015Hybrid epb tunnelling in rio de janeiro 2015
Hybrid epb tunnelling in rio de janeiro 2015Abner Silva
 

Similar to Tunneling by tunnel boring machine (20)

Rates of Soft Ground Tunneling in Vicinity of Existing Structures
Rates of Soft Ground Tunneling in Vicinity of Existing StructuresRates of Soft Ground Tunneling in Vicinity of Existing Structures
Rates of Soft Ground Tunneling in Vicinity of Existing Structures
 
Dmrctrainingpresentation 161115165907
Dmrctrainingpresentation 161115165907Dmrctrainingpresentation 161115165907
Dmrctrainingpresentation 161115165907
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...
 
TRENCHLESS TECHNOLOGY
TRENCHLESS TECHNOLOGYTRENCHLESS TECHNOLOGY
TRENCHLESS TECHNOLOGY
 
STRESSES BELOW EXISTING STRUCTURES DURING TUNNEL EXCAVATION USING TUNNEL BORI...
STRESSES BELOW EXISTING STRUCTURES DURING TUNNEL EXCAVATION USING TUNNEL BORI...STRESSES BELOW EXISTING STRUCTURES DURING TUNNEL EXCAVATION USING TUNNEL BORI...
STRESSES BELOW EXISTING STRUCTURES DURING TUNNEL EXCAVATION USING TUNNEL BORI...
 
Study of Dynamic Analysis for Immersed Tube Tunnel
Study of Dynamic Analysis for Immersed Tube TunnelStudy of Dynamic Analysis for Immersed Tube Tunnel
Study of Dynamic Analysis for Immersed Tube Tunnel
 
Metro Underground civil structures and track structures AR.pdf
Metro Underground civil structures and track structures AR.pdfMetro Underground civil structures and track structures AR.pdf
Metro Underground civil structures and track structures AR.pdf
 
Metro Underground civil structures and track structures AR.pdf
Metro Underground civil structures and track structures AR.pdfMetro Underground civil structures and track structures AR.pdf
Metro Underground civil structures and track structures AR.pdf
 
Underground Coal Mining Study
Underground Coal Mining StudyUnderground Coal Mining Study
Underground Coal Mining Study
 
Presentation on Piling Machine & TMB
Presentation on Piling Machine & TMBPresentation on Piling Machine & TMB
Presentation on Piling Machine & TMB
 
Eurasia tunnel1
Eurasia tunnel1Eurasia tunnel1
Eurasia tunnel1
 
Full paper 2014 trb 93rd arsta bridge, oh-sl-mss, sweden 07 (draft)
Full paper 2014 trb 93rd arsta bridge, oh-sl-mss, sweden 07 (draft)Full paper 2014 trb 93rd arsta bridge, oh-sl-mss, sweden 07 (draft)
Full paper 2014 trb 93rd arsta bridge, oh-sl-mss, sweden 07 (draft)
 
Building Construction I Report
Building Construction I ReportBuilding Construction I Report
Building Construction I Report
 
Bcon revised
Bcon revisedBcon revised
Bcon revised
 
B construction I
B construction IB construction I
B construction I
 
Building Construction Report
Building Construction ReportBuilding Construction Report
Building Construction Report
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
 
Effect of underground tunnelling by (TBM) on foundations of existing structures
Effect of underground tunnelling by (TBM) on foundations of existing structuresEffect of underground tunnelling by (TBM) on foundations of existing structures
Effect of underground tunnelling by (TBM) on foundations of existing structures
 
Hybrid epb tunnelling in rio de janeiro 2015
Hybrid epb tunnelling in rio de janeiro 2015Hybrid epb tunnelling in rio de janeiro 2015
Hybrid epb tunnelling in rio de janeiro 2015
 

Recently uploaded

ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 

Recently uploaded (20)

ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 

Tunneling by tunnel boring machine

  • 2. CONTENTS  Introduction  Objective  Major construction of TBM  Tunnel lining  Surveying  Geotechnical consideration  Different types of TBM  Annulus grouts & Mortars  References
  • 3. INTRODUCTION  First tunneling shield by Sir Marc Isambard Brunel to excavate under the Thames in 1825.  Actual boring machine built-in 1845 by Henri- Joseph Maus
  • 4. OBJECTIVES  To give an understanding of what is a TBM.  To build up an awareness of the wide variety of perils TBMs are exposed to.  Role of civil engineers in this machine tunneling work.  How we utilizes our geotechnical and survey knowledge.
  • 6. TUNNEL LINING  5 segments and 1 key segment, each 1.2 and 1.5 m long and 275 mm thick.  The segments were precast with M50 grade concrete at the casting yard
  • 7. SURVEYING  After doing general survey i.e. identifying geographical extent of the construction work, reconnaissance survey, establishing new survey stations from known control stations.  Computation of global coordinates of control stations are performed  Secondary control station established for TBM launching shaft at surface & then transfer that to tunnel control station at underground level
  • 8.
  • 9.
  • 10.
  • 11. GEOTECHNICAL CONSIDERATION Rock-quality designation (RQD) is a rough measure of the degree of jointing or fracture in a rock mass, measured as a percentage of the drill core in lengths of 10 cm or more. High-quality rock has an RQD of more than 75%, low quality of less than 50%.
  • 12. DIFFERENT TYPES OF TBM  1. SLURRY SHIELD TBM
  • 13. slurry test programmed will generally include the above parameters[ 2]
  • 14.  2. Earth pressure balance TBM
  • 15. indicates typical particle size distributions for the use of EPBM[ 3 ]
  • 16. ANNULUS GROUTS & MORTARS  To prevent flotation and heave  To prevent surface subsidence  To prevent misalignment of the segment rings  To bond the soil and segments into a single component
  • 17.
  • 18. REFERENCES  1).To my training, which I did in tunneling, on the metro site of Delhi, which was under construction under Shanghai Urban Construction Group (SUCG), joint venture with L&T.  2). Andrew Hung Shing Lee, “ENGINEERING SURVEY SYSTEM FOR TBM (Tunnel Boring Machine TUNNEL CONSTRUCTION)”, Hong Kong ISBN 978-56-56-65-55  3). Kolymbass, 2005 “TUNNELING & TUNNEL MECHANICS”, 2005, ISBN 456-23- 59-20-12  4). “A GENERAL OVERVIEW ON TUNNEL BORING MACHINES” By Prof. jian ZHAQ, rock mechanics and tunnelling. UK ISBN 111-419-23-45-71-83  M. Cigla, S. Yagiz & l.Ozdemir,"APPLICATION OF TUNNEL BORING MACHINES IN