SlideShare a Scribd company logo
1 of 23
Download to read offline
EOSC547:
                                             EOSC547:
                                       Tunnelling &
                                    Underground Design
                                         g       D g


                                                    Topic 1:
                                         Geological Hazards
                                            in Tunnelling




    1 of 46         Tunnelling Grad Class (2012)               Dr. Erik Eberhardt




Tunnel Construction: In the Beginning

All major ancient
civilizations developed
tunneling methods. In
Babylonia, tunnels were
     y      ,
used extensively for
irrigation; and a brick-
lined pedestrian passage
some 900 m long was
built around 2180 BC
under the Euphrates
River to connect the
royal p l
      l palace with the
                ith th
temple. Construction was
accomplished by diverting
the river during the dry
season.


    2 of 46          Tunnelling Grad Class (2012)              Dr. Erik Eberhardt




                                                                                    1
Tunnel Construction: In the Beginning
The Greeks and Romans both made extensive use of tunnels to
reclaim land by drainage and for water aqueducts.

6th-century-BC Greek water tunnel on the
isle f S m d i
i l of Samos driven some 1100 m through
                       m           th    h
limestone with a cross section about 2 x 2 m.




                                Perhaps the largest tunnel in ancient
                                times was a 1600 m long, 8 m wide, 10 m
                                high road tunnel (the Pausilippo) between
                                Naples and Pozzuoli, built in 36 BC.


    3 of 46           Tunnelling Grad Class (2012)          Dr. Erik Eberhardt




Tunnel Construction: In the Beginning




                      In the AD 41, Romans used some 30,000 men to push a
                      6 km tunnel over 10 years to drain Lacus Fucinus. They
                      worked from shafts 40 m apart and up to 125 m deep.
                      Far more attention was paid to ventilation and safety
                      measures when workers were freemen.


    4 of 46           Tunnelling Grad Class (2012)          Dr. Erik Eberhardt




                                                                                 2
Tunnel Construction: In the Beginning
                      Ancient construction was carried out using a succession
                      of closely spaced shafts to provide ventilation. String
                      line and plumb bobs were used for surveying.

                           Ventilation methods were primitive, often limited
                           to waving a canvas at the mouth of the shaft, and
                           most tunnels claimed the lives of hundreds or even
                           thousands of the slaves used as workers.




 To save the need for a lining, most ancient tunnels
 were located in strong rock, which was excavated
 by heating the rock with fire and suddenly cooling it
 by dousing with water causing the rock to spall.


     5 of 46             Tunnelling Grad Class (2012)        Dr. Erik Eberhardt




Modern Beginnings: The Thames
Tunnelling in soft, water saturated
ground began with Marc Brunel when
he invented the principle of shield
tunnelling and undertook a contract to
tunnel under the Thames between
1825 and 1841. His shield consisted
of 12 independent cells in which
workers hand excavated the ground
behind a secure wall of ‘poling
boards’. One board would be removed
to provide access for digging, after
which it would be replaced and pushed
forward by hydraulic jacks to re-
engage th face support.
        the f           t
Brunel’s shield was 7 m high and 12 m wide, and
enabled 36 miners to work the tunnel face at
one time. The brickwork built right behind the
‘shield’ served as an abutment for the whole
frame. On average, progress was 3-5 m/week.
                                                                   Harding (1981)

     6 of 46             Tunnelling Grad Class (2012)        Dr. Erik Eberhardt




                                                                                    3
Modern Beginnings: The Thames
Flooding was a
constant problem for
Brunel in tunnelling
under the Thames.
In one such flood 6
men drowned.
Brunel’s complaint to
those offering advice
on tunnelling in such
difficult conditions,
“In every case they
make the ground to
suit the plan and not
the plan to suit the
ground”.
        Completed in 1843, Brunel’s tunnel is still in full use as part
        of London’s Underground railway system, exactly as built!

     7 of 46            Tunnelling Grad Class (2012)       Dr. Erik Eberhardt




Modern Beginnings: The Thames
James Greathead solved the problem of containing groundwater
during the construction of subaqueous tunnels in loose soil, by
combining shield tunnelling with the use of compressed air during his
construction of the London Underground.

                               James Greathead’s 2.5 m diameter circular
                               shield, propelled by screw jacks, employed
                               the first use of cast iron lining segments.




     This led to a considerable increase in the number of shield driven
     tunnels world-wide. At the beginning of the 20th century, the majority
     of the tunnels were built with Greathead shields.

     8 of 46            Tunnelling Grad Class (2012)       Dr. Erik Eberhardt




                                                                                4
Geotechnical Challenges: Gotthard Base Tunnel




                                       The Known Knowns,
                                       Known Unknowns,
                                       & Unknown Unknowns

   9 of 46    Tunnelling Grad Class (2012)         Dr. Erik Eberhardt




                                              AlpTransit

                                  In 1994 the Swiss voted an
                                  alpine protection article into
                                  their constitution, forbidding
                                  the expansion of road
                                  capacity in alpine regions.
                                  This forced the government to
                                  shift heavy goods traffic from
                                  road to rail.


                                  To accommodate this, voters
                                  approved the “Alptransit”
                                  project to build new tunnels
                                  through the Gotthard and
                                  the Lötschberg.


   10 of 46    Tunnelling Grad Class (2012)        Dr. Erik Eberhardt




                                                                        5
Reasons for the Base Tunnels
                                     Increasing Population Demands
                                     & Commercial Traffic
                                     - The Gotthard Road Tunnel, is the
                                      main north-south route through the
                                                                  g
                                      Alps, between Switzerland and Italy.
                                     - 18,000 vehicles/day pass through
                                      the Gotthard Road Tunnel.




                 Safety                      Pollution
                                                            Drivers going
                                                            D
Gotthard Road                                               through the
Tunnel Fire                                                 Gotthard Road
(2001) – 11                                                 Tunnel inhale as
people killed                                               many pollutants
                                                            as if they
                                                            smoked up to
                                                            eight cigarettes.


      11 of 46     Tunnelling Grad Class (2012)          Dr. Erik Eberhardt




AlpTransit Base Tunnels




      12 of 46     Tunnelling Grad Class (2012)          Dr. Erik Eberhardt




                                                                                6
Tunnelling & Geology – The Swiss Base Tunnels
                                           World’s Longest Transportation Tunnels

                                                                                              Length                     Completion
                                                         Tunnel
                                                                                               (km)                        Date

                                          Gotthard Base (CH)
                                                        ( H)                                     57.1
                                                                                                   .                          2012*
                                          Brenner Base (AU)                                      55.4                          2020
                                          Sei-kan (Japan)                                        53.9                          1988
                                          Chunnel (ENG-FR)                                       50.5                          1994
                                          Loetschberg (CH)                                       34.6                          2007


                                                  #30 Mount MacDonald (CAN) @ 14.6 km
                                                  #43 New Cascade (USA) @ 12.5 km

                                                  Gotthard Road Tunnel (CH) = 16.9 km

                                                  Canada = 5 rail tunnels > 2 km
                                                  USA = 4 rail tunnels > 2 km
                                                  Switzerland = 42 rail tunnels > 2 km


      13 of 46          Tunnelling Grad Class (2012)                                                             Dr. Erik Eberhardt




Tunnelling & Geology – The Swiss Base Tunnels
                                           World’s Longest Transportation Tunnels

      COST:                                                                                   Length                     Completion
                                                         Tunnel
                                                                                               (km)                        Date
  1998: $7.2 Billion
  2011: $9 7 Billion *
        $9.7                              Gotthard Base (CH)
                                                        ( H)                                     57.1
                                                                                                   .                          2012*
                                          Brenner Base (AU)                                      55.4                          2020
                                          Sei-kan (Japan)                                        53.9                          1988
      1998: $3.2 Billion                  Chunnel (ENG-FR)                                       50.5                          1994
      2007: $4.3 Billion                  Loetschberg (CH)                                       34.6                          2007

                                 Modernisierung der Bahn
                                 Bauprogramm                                                                                                 Gotthard
                                                                                                                                             San Gottardo




         Financing:                2000             2005                  2010                     2015                 2020            2025

                                   2000    Lötschberg      2007



10%    Oil Tax                     2000             Gotthard

                                                            2006     Zimmerberg
                                                                                 2012

                                                                                       2013
                                                                                                                               2018
15%    Loans
                                                                                                                                      Neat
                                                            2006                Ceneri               2016



55%    Heavy Vehicle Tax
                                                                                      Ausbauten
                                                                  2007      2011      St. Gallen – Arth-Goldau
                                                                                                            Verbindung
                                                                                     2011            2016


20%    1% increase in VAT
                                                                                                            Zürichsee – Gotthard


                                   2000 1. Etappe 2005                                                                                Bahn
                                                                                                                                                       7.5.2_ Modern.Bahnen.Bauprogramm_98_0161_S




                                                                                     2011                2.Etappe              2022   2000

                                   Rollmaterial
                                                                     Infrastruktur                                             Lärmschutz

                                                                                                                       Anschluss an
                                           2002                                        2012
                                                                                                     europäisches Hochleistungsnetz




      14 of 46          Tunnelling Grad Class (2012)                                                             Dr. Erik Eberhardt




                                                                                                                                                                                                    7
Lötschberg Base Tunnel
                Length = 34.6 km
                Total tunnel system = 88.1 km                     80% Drill & Blast
                Excavated material = 16 million tonnes
                                                                   20% TBM




     15 of 46           Tunnelling Grad Class (2012)            Dr. Erik Eberhardt




Geological Challenges: Lötschberg Base Tunnel
Buried Valleys: burial is the consequence of glacial down cutting and alluvial
deposition. Buried valleys are a major concern in tunnelling as they are
often deep (!!), with unknown thicknesses, and filled with water saturated
sediments under high water pressures.

                                   The
                                   Th path of the Lötschberg passed under the
                                           th f th Löt hb            d d th
                                   Gästern Valley, 200 m below the valley floor.
                                   It was estimated that the alluvial sediments
                                   extended 100 m below surface leaving 100 m of
                                   strong limestone to form the roof of the
                                   tunnel.

                                      In actuality, the buried valley reached
                                      depths of more than 185 m. By July 24,
                                      1908, th t
                                      1908 the tunnel had advanced such that
                                                       l h d d        d    h th t
                                      only a thin wall of rock divided the working-
                                      face from the buried valley. Within seconds
                                      of that morning’s blast, 40,000m3 of water
                                      saturated sediments swept into the tunnel
                                      killing 25 men and filling the tunnel for a
                                      distance 1.25 km.

     16 of 46           Tunnelling Grad Class (2012)            Dr. Erik Eberhardt




                                                                                      8
Lötschberg Base Tunnel: Geological Prognosis




                                                                   Loew et al. (2000)
    17 of 46          Tunnelling Grad Class (2012)   Dr. Erik Eberhardt




Geological Challenges: Lötschberg Base Tunnel
Karst:
Given the porous nature of karst,
large volumes of water and a high
risk of water ingress was
                                      1.5m
                                      1 5m
expected over a section about 3
        d                  b
km long. It was constantly
necessary to carry out preliminary
boring in order to discover
whether any large, water-filled
karst sink-holes might endanger
the tunnel driving operations.




    18 of 46          Tunnelling Grad Class (2012)   Dr. Erik Eberhardt




                                                                                        9
Gotthard Base Tunnel
                                        Length = 57 km
                                        Sedrun shaft = 800 m
                                        Pillar = 40 m width
                                        Excavated material = 24 M tonnes




   19 of 46     Tunnelling Grad Class (2012)           Dr. Erik Eberhardt




   Gotthard
  Base Tunnel




   20 of 46      Tunnelling Grad Class (2012)          Dr. Erik Eberhardt




                                                                            10
Gotthard Base Tunnel: Geological Prognosis




                                                                                                           Loew et al. (2000)
      21 of 46               Tunnelling Grad Class (2012)                   Dr. Erik Eberhardt




Geological Challenges: Gotthard Base Tunnel
                                  Potential              Tectonic           Max.
           Geologic Unit
                                 Key Hazard                Unit            Length

       Cataclastic Faults    High pressure water   Crystalline Massifs,   100 @ 5m
                             inflow.               Penninic Gneisses

       Weak Rocks (Phillites Strongly squeezing
                   (Phillites,                     Crystalline Massifs     1.3
                                                                           1 3 km
       Schists, Cataclasites) ground.
                                                                                      Loew et al. (2000)




       Granites              Rockburst.            Crystalline Massifs     >14 km


       Sugar Grained         Water saturated       (Par)autochthonous      200 m
       Dolomites             debris inflow,        Triassic Sediments
                             cohesionless rock.

The first Gotthard rail tunnel was constructed between
1872-1882, and cut the travel time from Zurich to Milan
from 27 to 5.5 hours. However, 310 men died and 877
were incapacitated during construction of the 14.9 km
tunnel. Numerable challenges and harsh conditions were
encountered, many of which were augmented by the equally
harsh contract signed by the tunnel designer Louis Favre .


      22 of 46               Tunnelling Grad Class (2012)                   Dr. Erik Eberhardt




                                                                                                                                11
Geotechnical Challenges: Known Knowns

                                                      Brittle Fault Zones




                                                                 Zangerl et al. (2006)




     23 of 46                Tunnelling Grad Class (2012)        Dr. Erik Eberhardt




Brittle Fault Zones - Water Inflows




                                                                  Loew et al. (2000)



Fault zones may form highly
permeable conduits for
groundwater,
groundwater leading to tunnel
inflows. Encountering large
quantities of water may lead to
flooding of the excavation,
especially if there is no outlet for
the water to drain to.



     24 of 46              Tunnelling Grad Class (2012)          Dr. Erik Eberhardt




                                                                                         12
Brittle Fault Zones – Weak Ground




                                                     Laws et al. (2003)
              Granitic Fault Rocks
                  Aar Massif
                   (3=5MPa)




   25 of 46          Tunnelling Grad Class (2012)   Dr. Erik Eberhardt




Brittle Fault Zones – Ground Support




   26 of 46          Tunnelling Grad Class (2012)   Dr. Erik Eberhardt




                                                                          13
Amsteg (June 2005) – West TBM
                                          ... West TBM crosses
                                          hydrothermally altered rock
                                          adjacent to fault zone, enounters
                                          flows of 2-3 l/s that flushes loose
                                          material into the cutter head.
                                                  l      h         h d



                                                                    Ehrbar (2008)




               ... 5 month delay,
                $10 million cost.

    27 of 46               Tunnelling Grad Class (2012)       Dr. Erik Eberhardt




Geotechnical Challenges: Known Knowns




Squeezing Ground – Tavetsch Massif

Squeezing ground refers to weak,
plastic rock material which displaces
into the tunnel excavation under the
i     h       l         i    d     h
action of gravity and induced stresses.
This squeezing action may result in
damage/failure to the ground support
system, or require the costly re-
excavation of the tunnel section.


    28 of 46             Tunnelling Grad Class (2012)         Dr. Erik Eberhardt




                                                                                    14
Geotechnical Challenges: Squeezing Ground




                                              Ehrbar & Pfenninger (1999)




   29 of 46    Tunnelling Grad Class (2012)      Dr. Erik Eberhardt




Squeezing Ground Support




                   Fabbri (2004)




   30 of 46    Tunnelling Grad Class (2012)      Dr. Erik Eberhardt




                                                                           15
Geotechnical Challenges: Known Unknowns
                                             Where ground possesses the ability
                                             to flow freely (i.e. “running
                                             ground”), for example with water
                                             saturated cohesionless materials,
                                             then special support and control
                                                    p        pp
                                             difficulties can arise.




              Sugar-grained dolomites
              (granular & cohesionless).


   31 of 46           Tunnelling Grad Class (2012)            Dr. Erik Eberhardt




Geotechnical Challenges: Running Ground
                                           Sugar-grained dolomites
                                           (granular & cohesionless).




   32 of 46           Tunnelling Grad Class (2012)            Dr. Erik Eberhardt




                                                                                   16
Geotechnical Challenges: Running Ground
The tunnel will cross the Triassic Piora Zone, a highly weathered and
fractured aquifer under high hydraulic pressure. Based on exploratory
drilling, it was found that the tunnel will pass ~250 meters below the
base of the aquifer through unweathered and unfractured dolomite/
anhydrite-sequences.




Considered the
greatest geological
risk to the
f
feasibility and
          y
success of the
tunnel project, in
Nov. 2008 the
TBM passed safely
through the Piora.


     33 of 46          Tunnelling Grad Class (2012)        Dr. Erik Eberhardt




Geotechnical Challenges: Known Unknowns




 Rockbursts involve sudden releases of stored
 strain energy through the failure of strong
 rock.
 rock They manifest themselves through the
 sudden ejection of rock into the excavation.
 Rockbursting potential is of special concern in
 cases of deep tunnelling where high stress
 concentrations form due to overburden loads or
 tectonic activity.


     34 of 46          Tunnelling Grad Class (2012)        Dr. Erik Eberhardt




                                                                                17
Stress-
Stress-Controlled Failure & Stress Path


                           1
                                                                 Stress
                                                              Concentration
                                   Unstable

                                                         Stable


          Wedge

                                                   In-Situ Stress

                                              Stress Path
      Relaxation
                                                                    3
   Kaiser et al. (2000)



   35 of 46               Tunnelling Grad Class (2012)                Dr. Erik Eberhardt




High Overburden – Spalling & Rock Bursting
                                                                          Baeret al. (2007)




                                                                  2.4 ML – Mar. 25, 2006




                                                     1.6 ML – Nov. 6, 2006




   36 of 46                Tunnelling Grad Class (2012)               Dr. Erik Eberhardt




                                                                                              18
Geotechnical Challenges – Unknown Unknowns




                                              Subhorizontal
                                                 Faults




  37 of 46     Tunnelling Grad Class (2012)      Dr. Erik Eberhardt




Faido-Bodio:
Faido-Bodio: “Unexpected” Faults
                                                              Bonzanigo (2007)




  38 of 46     Tunnelling Grad Class (2012)      Dr. Erik Eberhardt




                                                                                 19
Faido-Bodio:
Faido-Bodio: “Unexpected” Faults

     14’500      Tm EST-Ost                14’000                               13’500
                                          Amphibolite




   14 500
   14’500       Tm EST-West
                   EST West              14 000
                                         14’000                            13 500
                                                                           13’500

              Faido
                                                  Squeezing ground
                                                                        Bodio

                                                    blocks TBM



                                                        The total delay for
                                                                       y
                                                        passing through these
                                                        faults along this section:
                                                        ... one year.




  39 of 46                    Tunnelling Grad Class (2012)           Dr. Erik Eberhardt




Fault Zones & the Faido Cross-Over
                        Cross-



                                                                           Ehrbar (2008)




                               Similar ground conditions (i.e. unexpected faults)
                               at the Faido multipurpose cross-over station
                               were responsible for a further 2-year delay and
                               was over budget by more than 200%.

  40 of 46                    Tunnelling Grad Class (2012)           Dr. Erik Eberhardt




                                                                                           20
Faido-Bodio:
Faido-Bodio: “Unexpected” Faults




    41 of 46    Tunnelling Grad Class (2012)   Dr. Erik Eberhardt




GBT: Other Geological Challenges

Bodio




    42 of 46   Tunnelling Grad Class (2012)    Dr. Erik Eberhardt




                                                                    21
GBT: Other Geological Challenges

                                                               n´= n -  p f

                                                              normal deformation
                                                                   (i.e. closure)

                                                                   “Poison ratio” effect




                                                                                        Zangerl et al. (2008)
     43 of 46             Tunnelling Grad Class (2012)               Dr. Erik Eberhardt




GBT: Other Geological Challenges
                           Given that tunnel overburden will exceed 2000m,
                           temperatures as high as 45°C are projected. In addition,
                           silicosis, an incurable disease of the lungs, caused by the
                           unprotected respiration of quartz dust presents a
                           p
                           potential hazard to workers. Ventilation designs must
                                                                          g
                           account for both factors to ensure worker safety.




More than 13 million m3 of waste rock
will be generated, leading to
environmental issues as to where to
put it. At the same time, the
     it              time
extraction of gravel resources for
concrete in the Swiss midlands is
becoming more difficult. The solution,
therefore, was to specially break, sort
& wash the waste rock so that it could
be used for concrete aggregate.


     44 of 46             Tunnelling Grad Class (2012)               Dr. Erik Eberhardt




                                                                                                                22
Lecture References
Baer, M, Deichmann, N, Braunmiller, J, Clinton, J, Husen, S, Fäh, D, Giardini, D, Kästli, F,
Kradolfer, U & Wiemer, S (2007). Earthquakes in Switzerland and surrounding regions during
2006. Swiss Journal of Geosci.ences, 100: 517–528.
Bonzanigo, L (2007). Brittle tectonics in metamorphic rocks: Implications in the excavation of the
Bodio Section of the Gotthard Base Tunnel. In: Proceedings of the 1st Canada-US Rock Mechanics
Symposium, V
S      i   Vancouver. T l & F
                      Taylor Francis: L d
                                     i London, vol. 2 pp. 1141 1148
                                                 l 2,     1141-1148.
Ehrbar, H (2008). Gotthard Base Tunnel, Switzerland: Experiences with different tunnelling
methods. In: 2º Congresso Brasileiro de Túneis e Estruturas Subterrâneas Seminário Internacional
“South American Tunnelling”.
Ehrbar, H & Pfenninger, I (1999). Umsetzung der Geologie in technische Massnahmen im
Tavetscher, Zwischenmassiv Nord. In: Tagungsband Zum Sympoisums Geologie AlpTransit
(GEAT99), Zurich. A.A. Balkema, Rotterdam, pp. 381-394.
Fabbri, D (2004). The Gotthard-Base Tunnel: Project overview. In: 6th Annual Tunnelling
Conference, Sydney.
Hoek, E (2001). Big tunnels in bad rock: 2000 Terzaghi Lecture. ASCE Journal of Geotechnical and
Geoenvironmental Engineering, 127(9): 726-740.
Kaiser, PK, Diederichs, MS, Martin, D, Sharpe, J & Steiner, W (2000). Underground works in
hard rock tunnelling and mining. In Proceedings, GeoEng2000, Melbourne. Technomic Publishing:
Lancaster, pp. 841-926.




     45 of 46                 Tunnelling Grad Class (2012)                      Dr. Erik Eberhardt




Lecture References
Laws, S, Eberhardt, E, Loew, S & Descoeudres, F (2003). Geomechanical properties of shear
zones in the Eastern Aar Massif, Switzerland and their implication on tunnelling. Rock Mechanics
and Rock Engineering, 36(4): 271-303.
Loew, S, Ziegler, H-J & Keller, F (2000). AlpTransit: Engineering geology of the world’s longest
tunnel system. In: Proceedings, GeoEng 2000, Melbourne. Technomic Publishing, Lancaster, 927–937.
Zangerl, C, Eberhardt, E, Evans,
Zangerl C Eberhardt E Evans KF & Loew S (2008) Consolidation settlements above deep
                                           Loew,    (2008).
tunnels in fractured crystalline rock: Part 2 – Numerical analysis of the Gotthard highway tunnel
case study. International Journal of Rock Mechanics and Mining Sciences, 45(8): 1211-1225.
Zangerl, C, Loew, S & Eberhardt, E (2006). Structure, geometry and formation of brittle
discontinuities in anisotropic crystalline rocks of the Central Gotthard Massif, Switzerland. Eclogae
Geologicae Helvetiae, 99(2): 271-290.




     46 of 46                 Tunnelling Grad Class (2012)                      Dr. Erik Eberhardt




                                                                                                        23

More Related Content

Similar to Topic1 geol hazards

Tunnelling & underground design (Topic4-soft ground tunnelling methods)
Tunnelling & underground design (Topic4-soft ground tunnelling methods)Tunnelling & underground design (Topic4-soft ground tunnelling methods)
Tunnelling & underground design (Topic4-soft ground tunnelling methods)Hamed Zarei
 
Tunnelling & underground design (Topic2-geological uncertainty)
Tunnelling & underground design (Topic2-geological uncertainty)Tunnelling & underground design (Topic2-geological uncertainty)
Tunnelling & underground design (Topic2-geological uncertainty)Hamed Zarei
 
Study of tunnel engineering
Study of tunnel engineeringStudy of tunnel engineering
Study of tunnel engineeringAdil Shaikh
 
Immersed tunnels
Immersed tunnelsImmersed tunnels
Immersed tunnelsarravindsai
 
Seminar Underground Construction PPT.pptx
Seminar Underground Construction PPT.pptxSeminar Underground Construction PPT.pptx
Seminar Underground Construction PPT.pptxMansimishra351962
 
Artikel_Hallandsås Tunnel – Sweden Underground_PREDIMAX Injektionsschlauch_GB...
Artikel_Hallandsås Tunnel – Sweden Underground_PREDIMAX Injektionsschlauch_GB...Artikel_Hallandsås Tunnel – Sweden Underground_PREDIMAX Injektionsschlauch_GB...
Artikel_Hallandsås Tunnel – Sweden Underground_PREDIMAX Injektionsschlauch_GB...BPA-GmbH, Waterproofing is our Passion!
 
Curriculum Vitae Jens Classen 2015_01_e
Curriculum Vitae Jens Classen 2015_01_eCurriculum Vitae Jens Classen 2015_01_e
Curriculum Vitae Jens Classen 2015_01_eJens Classen
 
Chaneltunnel
ChaneltunnelChaneltunnel
Chaneltunneljmtisner
 
A Review Study on Methods of Tunneling in Hard Rocks
A Review Study on Methods of Tunneling in Hard RocksA Review Study on Methods of Tunneling in Hard Rocks
A Review Study on Methods of Tunneling in Hard Rocksijsrd.com
 
Short introduction into norwegian tunnelling history
Short introduction into norwegian tunnelling historyShort introduction into norwegian tunnelling history
Short introduction into norwegian tunnelling historyTim Leung
 
Comacchio Drilling Equipment
Comacchio Drilling EquipmentComacchio Drilling Equipment
Comacchio Drilling EquipmentMECandPMV
 
Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine mohammadsalikali
 
Alp transit euro-t&l-oct13-bro-s
Alp transit euro-t&l-oct13-bro-sAlp transit euro-t&l-oct13-bro-s
Alp transit euro-t&l-oct13-bro-sAbi Abagun
 
Alp transit euro-t&l-oct13-bro-s
Alp transit euro-t&l-oct13-bro-sAlp transit euro-t&l-oct13-bro-s
Alp transit euro-t&l-oct13-bro-sAbi Abagun
 
Alp transit euro-t&l-oct13-bro-s
Alp transit euro-t&l-oct13-bro-sAlp transit euro-t&l-oct13-bro-s
Alp transit euro-t&l-oct13-bro-sAbi Abagun
 
Underwater Tunnels
Underwater TunnelsUnderwater Tunnels
Underwater TunnelsIshan Parekh
 

Similar to Topic1 geol hazards (20)

Tunnelling & underground design (Topic4-soft ground tunnelling methods)
Tunnelling & underground design (Topic4-soft ground tunnelling methods)Tunnelling & underground design (Topic4-soft ground tunnelling methods)
Tunnelling & underground design (Topic4-soft ground tunnelling methods)
 
Tunnelling & underground design (Topic2-geological uncertainty)
Tunnelling & underground design (Topic2-geological uncertainty)Tunnelling & underground design (Topic2-geological uncertainty)
Tunnelling & underground design (Topic2-geological uncertainty)
 
Study of tunnel engineering
Study of tunnel engineeringStudy of tunnel engineering
Study of tunnel engineering
 
Immersed tunnels
Immersed tunnelsImmersed tunnels
Immersed tunnels
 
On the road
On the roadOn the road
On the road
 
Seminar Underground Construction PPT.pptx
Seminar Underground Construction PPT.pptxSeminar Underground Construction PPT.pptx
Seminar Underground Construction PPT.pptx
 
Artikel_Hallandsås Tunnel – Sweden Underground_PREDIMAX Injektionsschlauch_GB...
Artikel_Hallandsås Tunnel – Sweden Underground_PREDIMAX Injektionsschlauch_GB...Artikel_Hallandsås Tunnel – Sweden Underground_PREDIMAX Injektionsschlauch_GB...
Artikel_Hallandsås Tunnel – Sweden Underground_PREDIMAX Injektionsschlauch_GB...
 
The øresund bridge
The øresund bridge  The øresund bridge
The øresund bridge
 
Curriculum Vitae Jens Classen 2015_01_e
Curriculum Vitae Jens Classen 2015_01_eCurriculum Vitae Jens Classen 2015_01_e
Curriculum Vitae Jens Classen 2015_01_e
 
Chaneltunnel
ChaneltunnelChaneltunnel
Chaneltunnel
 
A Review Study on Methods of Tunneling in Hard Rocks
A Review Study on Methods of Tunneling in Hard RocksA Review Study on Methods of Tunneling in Hard Rocks
A Review Study on Methods of Tunneling in Hard Rocks
 
Tunneling
TunnelingTunneling
Tunneling
 
Short introduction into norwegian tunnelling history
Short introduction into norwegian tunnelling historyShort introduction into norwegian tunnelling history
Short introduction into norwegian tunnelling history
 
Comacchio Drilling Equipment
Comacchio Drilling EquipmentComacchio Drilling Equipment
Comacchio Drilling Equipment
 
Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine
 
Alp transit euro-t&l-oct13-bro-s
Alp transit euro-t&l-oct13-bro-sAlp transit euro-t&l-oct13-bro-s
Alp transit euro-t&l-oct13-bro-s
 
Alp transit euro-t&l-oct13-bro-s
Alp transit euro-t&l-oct13-bro-sAlp transit euro-t&l-oct13-bro-s
Alp transit euro-t&l-oct13-bro-s
 
Alp transit euro-t&l-oct13-bro-s
Alp transit euro-t&l-oct13-bro-sAlp transit euro-t&l-oct13-bro-s
Alp transit euro-t&l-oct13-bro-s
 
Underwater Tunnels
Underwater TunnelsUnderwater Tunnels
Underwater Tunnels
 
Under ground railway
Under ground railwayUnder ground railway
Under ground railway
 

Topic1 geol hazards

  • 1. EOSC547: EOSC547: Tunnelling & Underground Design g D g Topic 1: Geological Hazards in Tunnelling 1 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt Tunnel Construction: In the Beginning All major ancient civilizations developed tunneling methods. In Babylonia, tunnels were y , used extensively for irrigation; and a brick- lined pedestrian passage some 900 m long was built around 2180 BC under the Euphrates River to connect the royal p l l palace with the ith th temple. Construction was accomplished by diverting the river during the dry season. 2 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt 1
  • 2. Tunnel Construction: In the Beginning The Greeks and Romans both made extensive use of tunnels to reclaim land by drainage and for water aqueducts. 6th-century-BC Greek water tunnel on the isle f S m d i i l of Samos driven some 1100 m through m th h limestone with a cross section about 2 x 2 m. Perhaps the largest tunnel in ancient times was a 1600 m long, 8 m wide, 10 m high road tunnel (the Pausilippo) between Naples and Pozzuoli, built in 36 BC. 3 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt Tunnel Construction: In the Beginning In the AD 41, Romans used some 30,000 men to push a 6 km tunnel over 10 years to drain Lacus Fucinus. They worked from shafts 40 m apart and up to 125 m deep. Far more attention was paid to ventilation and safety measures when workers were freemen. 4 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt 2
  • 3. Tunnel Construction: In the Beginning Ancient construction was carried out using a succession of closely spaced shafts to provide ventilation. String line and plumb bobs were used for surveying. Ventilation methods were primitive, often limited to waving a canvas at the mouth of the shaft, and most tunnels claimed the lives of hundreds or even thousands of the slaves used as workers. To save the need for a lining, most ancient tunnels were located in strong rock, which was excavated by heating the rock with fire and suddenly cooling it by dousing with water causing the rock to spall. 5 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt Modern Beginnings: The Thames Tunnelling in soft, water saturated ground began with Marc Brunel when he invented the principle of shield tunnelling and undertook a contract to tunnel under the Thames between 1825 and 1841. His shield consisted of 12 independent cells in which workers hand excavated the ground behind a secure wall of ‘poling boards’. One board would be removed to provide access for digging, after which it would be replaced and pushed forward by hydraulic jacks to re- engage th face support. the f t Brunel’s shield was 7 m high and 12 m wide, and enabled 36 miners to work the tunnel face at one time. The brickwork built right behind the ‘shield’ served as an abutment for the whole frame. On average, progress was 3-5 m/week. Harding (1981) 6 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt 3
  • 4. Modern Beginnings: The Thames Flooding was a constant problem for Brunel in tunnelling under the Thames. In one such flood 6 men drowned. Brunel’s complaint to those offering advice on tunnelling in such difficult conditions, “In every case they make the ground to suit the plan and not the plan to suit the ground”. Completed in 1843, Brunel’s tunnel is still in full use as part of London’s Underground railway system, exactly as built! 7 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt Modern Beginnings: The Thames James Greathead solved the problem of containing groundwater during the construction of subaqueous tunnels in loose soil, by combining shield tunnelling with the use of compressed air during his construction of the London Underground. James Greathead’s 2.5 m diameter circular shield, propelled by screw jacks, employed the first use of cast iron lining segments. This led to a considerable increase in the number of shield driven tunnels world-wide. At the beginning of the 20th century, the majority of the tunnels were built with Greathead shields. 8 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt 4
  • 5. Geotechnical Challenges: Gotthard Base Tunnel The Known Knowns, Known Unknowns, & Unknown Unknowns 9 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt AlpTransit In 1994 the Swiss voted an alpine protection article into their constitution, forbidding the expansion of road capacity in alpine regions. This forced the government to shift heavy goods traffic from road to rail. To accommodate this, voters approved the “Alptransit” project to build new tunnels through the Gotthard and the Lötschberg. 10 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt 5
  • 6. Reasons for the Base Tunnels Increasing Population Demands & Commercial Traffic - The Gotthard Road Tunnel, is the main north-south route through the g Alps, between Switzerland and Italy. - 18,000 vehicles/day pass through the Gotthard Road Tunnel. Safety Pollution Drivers going D Gotthard Road through the Tunnel Fire Gotthard Road (2001) – 11 Tunnel inhale as people killed many pollutants as if they smoked up to eight cigarettes. 11 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt AlpTransit Base Tunnels 12 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt 6
  • 7. Tunnelling & Geology – The Swiss Base Tunnels World’s Longest Transportation Tunnels Length Completion Tunnel (km) Date Gotthard Base (CH) ( H) 57.1 . 2012* Brenner Base (AU) 55.4 2020 Sei-kan (Japan) 53.9 1988 Chunnel (ENG-FR) 50.5 1994 Loetschberg (CH) 34.6 2007 #30 Mount MacDonald (CAN) @ 14.6 km #43 New Cascade (USA) @ 12.5 km Gotthard Road Tunnel (CH) = 16.9 km Canada = 5 rail tunnels > 2 km USA = 4 rail tunnels > 2 km Switzerland = 42 rail tunnels > 2 km 13 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt Tunnelling & Geology – The Swiss Base Tunnels World’s Longest Transportation Tunnels COST: Length Completion Tunnel (km) Date 1998: $7.2 Billion 2011: $9 7 Billion * $9.7 Gotthard Base (CH) ( H) 57.1 . 2012* Brenner Base (AU) 55.4 2020 Sei-kan (Japan) 53.9 1988 1998: $3.2 Billion Chunnel (ENG-FR) 50.5 1994 2007: $4.3 Billion Loetschberg (CH) 34.6 2007 Modernisierung der Bahn Bauprogramm Gotthard San Gottardo Financing: 2000 2005 2010 2015 2020 2025 2000 Lötschberg 2007 10% Oil Tax 2000 Gotthard 2006 Zimmerberg 2012 2013 2018 15% Loans Neat 2006 Ceneri 2016 55% Heavy Vehicle Tax Ausbauten 2007 2011 St. Gallen – Arth-Goldau Verbindung 2011 2016 20% 1% increase in VAT Zürichsee – Gotthard 2000 1. Etappe 2005 Bahn 7.5.2_ Modern.Bahnen.Bauprogramm_98_0161_S 2011 2.Etappe 2022 2000 Rollmaterial Infrastruktur Lärmschutz Anschluss an 2002 2012 europäisches Hochleistungsnetz 14 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt 7
  • 8. Lötschberg Base Tunnel Length = 34.6 km Total tunnel system = 88.1 km 80% Drill & Blast Excavated material = 16 million tonnes 20% TBM 15 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt Geological Challenges: Lötschberg Base Tunnel Buried Valleys: burial is the consequence of glacial down cutting and alluvial deposition. Buried valleys are a major concern in tunnelling as they are often deep (!!), with unknown thicknesses, and filled with water saturated sediments under high water pressures. The Th path of the Lötschberg passed under the th f th Löt hb d d th Gästern Valley, 200 m below the valley floor. It was estimated that the alluvial sediments extended 100 m below surface leaving 100 m of strong limestone to form the roof of the tunnel. In actuality, the buried valley reached depths of more than 185 m. By July 24, 1908, th t 1908 the tunnel had advanced such that l h d d d h th t only a thin wall of rock divided the working- face from the buried valley. Within seconds of that morning’s blast, 40,000m3 of water saturated sediments swept into the tunnel killing 25 men and filling the tunnel for a distance 1.25 km. 16 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt 8
  • 9. Lötschberg Base Tunnel: Geological Prognosis Loew et al. (2000) 17 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt Geological Challenges: Lötschberg Base Tunnel Karst: Given the porous nature of karst, large volumes of water and a high risk of water ingress was 1.5m 1 5m expected over a section about 3 d b km long. It was constantly necessary to carry out preliminary boring in order to discover whether any large, water-filled karst sink-holes might endanger the tunnel driving operations. 18 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt 9
  • 10. Gotthard Base Tunnel Length = 57 km Sedrun shaft = 800 m Pillar = 40 m width Excavated material = 24 M tonnes 19 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt Gotthard Base Tunnel 20 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt 10
  • 11. Gotthard Base Tunnel: Geological Prognosis Loew et al. (2000) 21 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt Geological Challenges: Gotthard Base Tunnel Potential Tectonic Max. Geologic Unit Key Hazard Unit Length Cataclastic Faults High pressure water Crystalline Massifs, 100 @ 5m inflow. Penninic Gneisses Weak Rocks (Phillites Strongly squeezing (Phillites, Crystalline Massifs 1.3 1 3 km Schists, Cataclasites) ground. Loew et al. (2000) Granites Rockburst. Crystalline Massifs >14 km Sugar Grained Water saturated (Par)autochthonous 200 m Dolomites debris inflow, Triassic Sediments cohesionless rock. The first Gotthard rail tunnel was constructed between 1872-1882, and cut the travel time from Zurich to Milan from 27 to 5.5 hours. However, 310 men died and 877 were incapacitated during construction of the 14.9 km tunnel. Numerable challenges and harsh conditions were encountered, many of which were augmented by the equally harsh contract signed by the tunnel designer Louis Favre . 22 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt 11
  • 12. Geotechnical Challenges: Known Knowns Brittle Fault Zones Zangerl et al. (2006) 23 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt Brittle Fault Zones - Water Inflows Loew et al. (2000) Fault zones may form highly permeable conduits for groundwater, groundwater leading to tunnel inflows. Encountering large quantities of water may lead to flooding of the excavation, especially if there is no outlet for the water to drain to. 24 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt 12
  • 13. Brittle Fault Zones – Weak Ground Laws et al. (2003) Granitic Fault Rocks Aar Massif (3=5MPa) 25 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt Brittle Fault Zones – Ground Support 26 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt 13
  • 14. Amsteg (June 2005) – West TBM ... West TBM crosses hydrothermally altered rock adjacent to fault zone, enounters flows of 2-3 l/s that flushes loose material into the cutter head. l h h d Ehrbar (2008) ... 5 month delay, $10 million cost. 27 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt Geotechnical Challenges: Known Knowns Squeezing Ground – Tavetsch Massif Squeezing ground refers to weak, plastic rock material which displaces into the tunnel excavation under the i h l i d h action of gravity and induced stresses. This squeezing action may result in damage/failure to the ground support system, or require the costly re- excavation of the tunnel section. 28 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt 14
  • 15. Geotechnical Challenges: Squeezing Ground Ehrbar & Pfenninger (1999) 29 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt Squeezing Ground Support Fabbri (2004) 30 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt 15
  • 16. Geotechnical Challenges: Known Unknowns Where ground possesses the ability to flow freely (i.e. “running ground”), for example with water saturated cohesionless materials, then special support and control p pp difficulties can arise. Sugar-grained dolomites (granular & cohesionless). 31 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt Geotechnical Challenges: Running Ground Sugar-grained dolomites (granular & cohesionless). 32 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt 16
  • 17. Geotechnical Challenges: Running Ground The tunnel will cross the Triassic Piora Zone, a highly weathered and fractured aquifer under high hydraulic pressure. Based on exploratory drilling, it was found that the tunnel will pass ~250 meters below the base of the aquifer through unweathered and unfractured dolomite/ anhydrite-sequences. Considered the greatest geological risk to the f feasibility and y success of the tunnel project, in Nov. 2008 the TBM passed safely through the Piora. 33 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt Geotechnical Challenges: Known Unknowns Rockbursts involve sudden releases of stored strain energy through the failure of strong rock. rock They manifest themselves through the sudden ejection of rock into the excavation. Rockbursting potential is of special concern in cases of deep tunnelling where high stress concentrations form due to overburden loads or tectonic activity. 34 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt 17
  • 18. Stress- Stress-Controlled Failure & Stress Path 1 Stress Concentration Unstable Stable Wedge In-Situ Stress Stress Path Relaxation 3 Kaiser et al. (2000) 35 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt High Overburden – Spalling & Rock Bursting Baeret al. (2007) 2.4 ML – Mar. 25, 2006 1.6 ML – Nov. 6, 2006 36 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt 18
  • 19. Geotechnical Challenges – Unknown Unknowns Subhorizontal Faults 37 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt Faido-Bodio: Faido-Bodio: “Unexpected” Faults Bonzanigo (2007) 38 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt 19
  • 20. Faido-Bodio: Faido-Bodio: “Unexpected” Faults 14’500 Tm EST-Ost 14’000 13’500 Amphibolite 14 500 14’500 Tm EST-West EST West 14 000 14’000 13 500 13’500 Faido Squeezing ground Bodio blocks TBM The total delay for y passing through these faults along this section: ... one year. 39 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt Fault Zones & the Faido Cross-Over Cross- Ehrbar (2008) Similar ground conditions (i.e. unexpected faults) at the Faido multipurpose cross-over station were responsible for a further 2-year delay and was over budget by more than 200%. 40 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt 20
  • 21. Faido-Bodio: Faido-Bodio: “Unexpected” Faults 41 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt GBT: Other Geological Challenges Bodio 42 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt 21
  • 22. GBT: Other Geological Challenges  n´= n -  p f  normal deformation (i.e. closure)  “Poison ratio” effect Zangerl et al. (2008) 43 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt GBT: Other Geological Challenges Given that tunnel overburden will exceed 2000m, temperatures as high as 45°C are projected. In addition, silicosis, an incurable disease of the lungs, caused by the unprotected respiration of quartz dust presents a p potential hazard to workers. Ventilation designs must g account for both factors to ensure worker safety. More than 13 million m3 of waste rock will be generated, leading to environmental issues as to where to put it. At the same time, the it time extraction of gravel resources for concrete in the Swiss midlands is becoming more difficult. The solution, therefore, was to specially break, sort & wash the waste rock so that it could be used for concrete aggregate. 44 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt 22
  • 23. Lecture References Baer, M, Deichmann, N, Braunmiller, J, Clinton, J, Husen, S, Fäh, D, Giardini, D, Kästli, F, Kradolfer, U & Wiemer, S (2007). Earthquakes in Switzerland and surrounding regions during 2006. Swiss Journal of Geosci.ences, 100: 517–528. Bonzanigo, L (2007). Brittle tectonics in metamorphic rocks: Implications in the excavation of the Bodio Section of the Gotthard Base Tunnel. In: Proceedings of the 1st Canada-US Rock Mechanics Symposium, V S i Vancouver. T l & F Taylor Francis: L d i London, vol. 2 pp. 1141 1148 l 2, 1141-1148. Ehrbar, H (2008). Gotthard Base Tunnel, Switzerland: Experiences with different tunnelling methods. In: 2º Congresso Brasileiro de Túneis e Estruturas Subterrâneas Seminário Internacional “South American Tunnelling”. Ehrbar, H & Pfenninger, I (1999). Umsetzung der Geologie in technische Massnahmen im Tavetscher, Zwischenmassiv Nord. In: Tagungsband Zum Sympoisums Geologie AlpTransit (GEAT99), Zurich. A.A. Balkema, Rotterdam, pp. 381-394. Fabbri, D (2004). The Gotthard-Base Tunnel: Project overview. In: 6th Annual Tunnelling Conference, Sydney. Hoek, E (2001). Big tunnels in bad rock: 2000 Terzaghi Lecture. ASCE Journal of Geotechnical and Geoenvironmental Engineering, 127(9): 726-740. Kaiser, PK, Diederichs, MS, Martin, D, Sharpe, J & Steiner, W (2000). Underground works in hard rock tunnelling and mining. In Proceedings, GeoEng2000, Melbourne. Technomic Publishing: Lancaster, pp. 841-926. 45 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt Lecture References Laws, S, Eberhardt, E, Loew, S & Descoeudres, F (2003). Geomechanical properties of shear zones in the Eastern Aar Massif, Switzerland and their implication on tunnelling. Rock Mechanics and Rock Engineering, 36(4): 271-303. Loew, S, Ziegler, H-J & Keller, F (2000). AlpTransit: Engineering geology of the world’s longest tunnel system. In: Proceedings, GeoEng 2000, Melbourne. Technomic Publishing, Lancaster, 927–937. Zangerl, C, Eberhardt, E, Evans, Zangerl C Eberhardt E Evans KF & Loew S (2008) Consolidation settlements above deep Loew, (2008). tunnels in fractured crystalline rock: Part 2 – Numerical analysis of the Gotthard highway tunnel case study. International Journal of Rock Mechanics and Mining Sciences, 45(8): 1211-1225. Zangerl, C, Loew, S & Eberhardt, E (2006). Structure, geometry and formation of brittle discontinuities in anisotropic crystalline rocks of the Central Gotthard Massif, Switzerland. Eclogae Geologicae Helvetiae, 99(2): 271-290. 46 of 46 Tunnelling Grad Class (2012) Dr. Erik Eberhardt 23