SlideShare a Scribd company logo
Bachelor of Quantity Surveyor
ESTIMATING
QSB 60504
Seminars - Question 1
Group Members: Lee Shze Hwa (0320053)
Hing Pui Kei (0325961)
Ko Bou Sim (0325271)
Esther Chuah (0321422)
Lecturer: Ms. Azrina Md Yaakob
Tutorial Group : Section 2
Question 1 (a) :
Explain to your client the importance of estimating at
different stages of procurement.
[9 marks]
Question 1 (a)
Construction Procurement Process
Question 1 (a)
● It provides a comparison with budget and cashflow estimate.
● It provides a basis to compare and assess the tender from contractors.
● It provides a prediction of the construction period.
● It provides the expected project cost.
● It uses to allocate the budget and the feasibility of the construction
project.
● It forms the basis of the future budget and cost control.
Importance of estimating in pre-contract :
● It provides budget to the Management and enable them to
control costs during construction execution.
● It is used for many assessments that made during the
construction stage.
● It is used for judgements that made during the construction
stage.
Question 1 (a)
Importance of estimating in post-contract :
Question 1 (b) :
Explain to your client the differences of measurement,
tendering and estimating.
[9 marks]
Question 1 (b)
Differences Measurement Tendering Estimating
Measurement is a process of
calculating the quantity for
different materials to produce
an accurate quantities and
descriptions by apply a rule or
set of rules.
Tendering is a process of bidding
and obtaining the construction
project by contractors.
Estimating is the process of
calculating the net cost required
to carry out the construction
work.
Involve in different
construction
procurement process
Involved in both pre-contract
and post-contract work.
Involved in pre-contract work
only.
Involved in both pre-contract and
post-contract work.
Purpose It provides the quantity of
materials required for the
construction project.
It provides the price of estimated
cost and profit for contractors to
tender the project.
It provides the estimating cost of
preliminaries, plant, labour and
material cost, daywork, provisional
sums, prime cost sums and
contingencies.
Profit Without profit. With profit. Without profit.
Application Application on SMM. Application on Bill of Quantity. Application on the building up
rate.
Item + Quantity
Measurement + Rates
Estimating + Profit
Question 1 (c) :
Explain to your client what preliminaries items are and
provide five (5) examples.
[7 marks]
● Include:
- Financials of the construction project.
- Outlying necessary details.
- Getting approvals for things like building permits or equipment leases.
● Preliminaries also used to give important details about testing measures
and the goals for completion.
Definition of Preliminary items :
Question 1 (c)
Question 1 (c)
Examples of preliminaries items :
● Site administration and security ● Requirement for the operating
and maintenance manual
Question 1 (c)
Examples of preliminaries items :
● Site waste management plan ● Insurances
- Example: risks insurance
(covers physical damage to the works and
site materials.)
Question 1 (c)
Examples of preliminaries items :
● Relevant report, like soil report. ● Electrical supply.
Question 1 (c)
Examples of preliminaries items :
● Allowance for small plant, tools and
machinery.
1. "Pre-Tender Estimate For Contracts - Designing Buildings Wiki". Designingbuildings.co.uk. N.p.,
2017. Web. 12 Apr. 2017.
2. "Measurement - Designing Buildings Wiki". Designingbuildings.co.uk. N.p., 2017. Web. 12 Apr.
2017.
3. "Pearson Qualifications | Edexcel, BTEC, LCCI And EDI | Pearson Qualifications".
Qualifications.pearson.com. N.p., 2017. Web. 12 Apr. 2017.
4. Mishra, Gopal. "COST ESTIMATION OF CONSTRUCTION PROJECTS". The Constructor.
N.p., 2017. Web. 12 Apr. 2017.
5. Associates, JAK. "Preliminary And General Costs | J.A. Kruger & Associates". Blog.jak-
associates.com. N.p., 2017. Web. 12 Apr. 2017.
6. "Tender Pricing Document - Designing Buildings Wiki". Designingbuildings.co.uk. N.p., 2017.
Web. 12 Apr. 2017.
7. Burger, Rachel. "The Ultimate Guide To Construction Cost Estimating - Capterra Blog".
Blog.capterra.com. N.p., 2017. Web. 12 Apr. 2017.
References
THE END
THANK YOU

More Related Content

What's hot

Quantity-Surveyor (ICI+ITD)-pdf.pdf
Quantity-Surveyor (ICI+ITD)-pdf.pdfQuantity-Surveyor (ICI+ITD)-pdf.pdf
Quantity-Surveyor (ICI+ITD)-pdf.pdfChong Yi Hui
 
Quantity Surveyor presentation
Quantity Surveyor presentationQuantity Surveyor presentation
Quantity Surveyor presentation
cynfang Fong
 
Civil Quantity Survey and Estimation
Civil Quantity Survey and EstimationCivil Quantity Survey and Estimation
Civil Quantity Survey and Estimation
Gide India
 
Qs(ici&itd)
Qs(ici&itd)Qs(ici&itd)
Qs(ici&itd)
Jy Chong
 
ICI ITD QS PROJECT 1 (1).pptx
ICI ITD QS PROJECT 1 (1).pptxICI ITD QS PROJECT 1 (1).pptx
ICI ITD QS PROJECT 1 (1).pptxmkyong1996
 
ITD Presentation
ITD PresentationITD Presentation
ITD Presentation
masonsth
 
Estimating group 1
Estimating group 1Estimating group 1
Estimating group 1
Lai Vlyn
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYING
lizwi nyandu
 
Ici qs
Ici qsIci qs
Ici qs
Gynie
 
Costestimating 110323025231-phpapp02
Costestimating 110323025231-phpapp02Costestimating 110323025231-phpapp02
Costestimating 110323025231-phpapp02
hlksd
 
Itd project one (a) 4 m
Itd project one (a) 4 mItd project one (a) 4 m
Itd project one (a) 4 m
euxuanong
 
Rate analysis brief
Rate analysis briefRate analysis brief
Rate analysis brief
sonali parashar
 
Pp1 seminar
Pp1 seminarPp1 seminar
Pp1 seminar
Timun Loh
 
Quantity Surveying
Quantity SurveyingQuantity Surveying
Quantity Surveyinggeddolan
 
rate analysis
rate analysisrate analysis
rate analysis
Ganesh Tatikonda
 
Qs(ici&itd) (1)
Qs(ici&itd) (1)Qs(ici&itd) (1)
Qs(ici&itd) (1)
Js Cheok
 
1# introduction to Quantity Surveying
1# introduction to Quantity Surveying1# introduction to Quantity Surveying
1# introduction to Quantity Surveying
LIJI A
 
Quantity surveying course
Quantity surveying courseQuantity surveying course
Quantity surveying course
Javid Hussain
 
Bills of quantities
Bills of quantitiesBills of quantities
Bills of quantities
Ar.Vijay Kumar
 

What's hot (19)

Quantity-Surveyor (ICI+ITD)-pdf.pdf
Quantity-Surveyor (ICI+ITD)-pdf.pdfQuantity-Surveyor (ICI+ITD)-pdf.pdf
Quantity-Surveyor (ICI+ITD)-pdf.pdf
 
Quantity Surveyor presentation
Quantity Surveyor presentationQuantity Surveyor presentation
Quantity Surveyor presentation
 
Civil Quantity Survey and Estimation
Civil Quantity Survey and EstimationCivil Quantity Survey and Estimation
Civil Quantity Survey and Estimation
 
Qs(ici&itd)
Qs(ici&itd)Qs(ici&itd)
Qs(ici&itd)
 
ICI ITD QS PROJECT 1 (1).pptx
ICI ITD QS PROJECT 1 (1).pptxICI ITD QS PROJECT 1 (1).pptx
ICI ITD QS PROJECT 1 (1).pptx
 
ITD Presentation
ITD PresentationITD Presentation
ITD Presentation
 
Estimating group 1
Estimating group 1Estimating group 1
Estimating group 1
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYING
 
Ici qs
Ici qsIci qs
Ici qs
 
Costestimating 110323025231-phpapp02
Costestimating 110323025231-phpapp02Costestimating 110323025231-phpapp02
Costestimating 110323025231-phpapp02
 
Itd project one (a) 4 m
Itd project one (a) 4 mItd project one (a) 4 m
Itd project one (a) 4 m
 
Rate analysis brief
Rate analysis briefRate analysis brief
Rate analysis brief
 
Pp1 seminar
Pp1 seminarPp1 seminar
Pp1 seminar
 
Quantity Surveying
Quantity SurveyingQuantity Surveying
Quantity Surveying
 
rate analysis
rate analysisrate analysis
rate analysis
 
Qs(ici&itd) (1)
Qs(ici&itd) (1)Qs(ici&itd) (1)
Qs(ici&itd) (1)
 
1# introduction to Quantity Surveying
1# introduction to Quantity Surveying1# introduction to Quantity Surveying
1# introduction to Quantity Surveying
 
Quantity surveying course
Quantity surveying courseQuantity surveying course
Quantity surveying course
 
Bills of quantities
Bills of quantitiesBills of quantities
Bills of quantities
 

Viewers also liked

Estimating presentation (QS)
Estimating presentation (QS)Estimating presentation (QS)
Estimating presentation (QS)
Hasif Alias
 
Estimating presentation
Estimating presentationEstimating presentation
Estimating presentation
Kailyn Lee
 
Estimating presentation (1)
Estimating presentation (1)Estimating presentation (1)
Estimating presentation (1)
tfkc1212
 
BBHB Estimating Presentation GOHBA Renovators Council July 21,2010 Copyright
BBHB Estimating Presentation GOHBA Renovators Council July 21,2010 CopyrightBBHB Estimating Presentation GOHBA Renovators Council July 21,2010 Copyright
BBHB Estimating Presentation GOHBA Renovators Council July 21,2010 Copyright
rickottenhof
 
Estimating presentation
Estimating presentationEstimating presentation
Estimating presentation
tfkc1212
 
Estimating presentation
Estimating presentationEstimating presentation
Estimating presentation
Hasif Alias
 
Estimating presentation
Estimating presentationEstimating presentation
Estimating presentation
kohwenqi
 
Estimating Presentation Slides - To Client
Estimating Presentation Slides - To ClientEstimating Presentation Slides - To Client
Estimating Presentation Slides - To Client
Pang Khai Shuen
 
Tender Presentation ( Estimating )
Tender Presentation ( Estimating )Tender Presentation ( Estimating )
Tender Presentation ( Estimating )
Lee Pei Gie
 
Estimating presentation
Estimating presentationEstimating presentation
Estimating presentation
Shze Hwa Lee
 
Assignment - Single Storey Show House (Presentation)
Assignment - Single Storey Show House (Presentation)Assignment - Single Storey Show House (Presentation)
Assignment - Single Storey Show House (Presentation)
Kai Yun Pang
 

Viewers also liked (11)

Estimating presentation (QS)
Estimating presentation (QS)Estimating presentation (QS)
Estimating presentation (QS)
 
Estimating presentation
Estimating presentationEstimating presentation
Estimating presentation
 
Estimating presentation (1)
Estimating presentation (1)Estimating presentation (1)
Estimating presentation (1)
 
BBHB Estimating Presentation GOHBA Renovators Council July 21,2010 Copyright
BBHB Estimating Presentation GOHBA Renovators Council July 21,2010 CopyrightBBHB Estimating Presentation GOHBA Renovators Council July 21,2010 Copyright
BBHB Estimating Presentation GOHBA Renovators Council July 21,2010 Copyright
 
Estimating presentation
Estimating presentationEstimating presentation
Estimating presentation
 
Estimating presentation
Estimating presentationEstimating presentation
Estimating presentation
 
Estimating presentation
Estimating presentationEstimating presentation
Estimating presentation
 
Estimating Presentation Slides - To Client
Estimating Presentation Slides - To ClientEstimating Presentation Slides - To Client
Estimating Presentation Slides - To Client
 
Tender Presentation ( Estimating )
Tender Presentation ( Estimating )Tender Presentation ( Estimating )
Tender Presentation ( Estimating )
 
Estimating presentation
Estimating presentationEstimating presentation
Estimating presentation
 
Assignment - Single Storey Show House (Presentation)
Assignment - Single Storey Show House (Presentation)Assignment - Single Storey Show House (Presentation)
Assignment - Single Storey Show House (Presentation)
 

Similar to Estimating presentation (question 1)

Study on Procurement Method Selection Procedure in Construction Industry
Study on Procurement Method Selection Procedure in Construction IndustryStudy on Procurement Method Selection Procedure in Construction Industry
Study on Procurement Method Selection Procedure in Construction Industry
IRJET Journal
 
Qs(ici&itd)
Qs(ici&itd)Qs(ici&itd)
Qs(ici&itd)
Sysy Jnthn
 
NCIT civil Syllabus 2013-2014
NCIT civil Syllabus 2013-2014NCIT civil Syllabus 2013-2014
NCIT civil Syllabus 2013-2014
LAKSHITHA RAJAPAKSHA
 
QSS
QSSQSS
Lec.1 Introduction to Estimation
Lec.1   Introduction to EstimationLec.1   Introduction to Estimation
Lec.1 Introduction to Estimation
Muthanna Abbu
 
EstimatesPresentation.pptx
EstimatesPresentation.pptxEstimatesPresentation.pptx
EstimatesPresentation.pptx
CharmelDiazCainglet
 
IRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction ProjectIRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET Journal
 
Resource Optimization in Mivan Construction Project
Resource Optimization in Mivan Construction ProjectResource Optimization in Mivan Construction Project
Resource Optimization in Mivan Construction Project
IRJET Journal
 
Construction project scheduling and quality control
Construction project scheduling and quality controlConstruction project scheduling and quality control
Construction project scheduling and quality control
monishkumark
 
Lec.2 binifits of estamations...Types of Estimation
Lec.2  binifits of estamations...Types of EstimationLec.2  binifits of estamations...Types of Estimation
Lec.2 binifits of estamations...Types of Estimation
Muthanna Abbu
 
Performance evaluation of design build projects with and without agency const...
Performance evaluation of design build projects with and without agency const...Performance evaluation of design build projects with and without agency const...
Performance evaluation of design build projects with and without agency const...IAEME Publication
 
Performance evaluation of design build (d-b) projects
Performance evaluation of design build (d-b) projectsPerformance evaluation of design build (d-b) projects
Performance evaluation of design build (d-b) projectsiaemedu
 
Measuring tendering and estimating for CBE
Measuring tendering and estimating for CBEMeasuring tendering and estimating for CBE
Measuring tendering and estimating for CBE
Sahl Buhary
 
Ecm442 lecture 1 latest
Ecm442 lecture 1 latestEcm442 lecture 1 latest
Ecm442 lecture 1 latest
MUHAMMADSYAHMIFADZIL
 
IIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction Project
IRJET Journal
 
IRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in ConstructionIRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in Construction
IRJET Journal
 
Study of Factors Affecting the Implementation of BIM: An Evaluation of Risk V...
Study of Factors Affecting the Implementation of BIM: An Evaluation of Risk V...Study of Factors Affecting the Implementation of BIM: An Evaluation of Risk V...
Study of Factors Affecting the Implementation of BIM: An Evaluation of Risk V...
IRJET Journal
 
COVERTITLE PAGE Table of ContentsI. Integrated Projec
COVERTITLE PAGE Table of ContentsI. Integrated ProjecCOVERTITLE PAGE Table of ContentsI. Integrated Projec
COVERTITLE PAGE Table of ContentsI. Integrated Projec
CruzIbarra161
 

Similar to Estimating presentation (question 1) (20)

Study on Procurement Method Selection Procedure in Construction Industry
Study on Procurement Method Selection Procedure in Construction IndustryStudy on Procurement Method Selection Procedure in Construction Industry
Study on Procurement Method Selection Procedure in Construction Industry
 
Qsx
QsxQsx
Qsx
 
Qs(ici&itd)
Qs(ici&itd)Qs(ici&itd)
Qs(ici&itd)
 
NCIT civil Syllabus 2013-2014
NCIT civil Syllabus 2013-2014NCIT civil Syllabus 2013-2014
NCIT civil Syllabus 2013-2014
 
QSS
QSSQSS
QSS
 
Lec.1 Introduction to Estimation
Lec.1   Introduction to EstimationLec.1   Introduction to Estimation
Lec.1 Introduction to Estimation
 
EstimatesPresentation.pptx
EstimatesPresentation.pptxEstimatesPresentation.pptx
EstimatesPresentation.pptx
 
Cost studies model_answers_2014_jan
Cost studies model_answers_2014_janCost studies model_answers_2014_jan
Cost studies model_answers_2014_jan
 
IRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction ProjectIRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction Project
 
Resource Optimization in Mivan Construction Project
Resource Optimization in Mivan Construction ProjectResource Optimization in Mivan Construction Project
Resource Optimization in Mivan Construction Project
 
Construction project scheduling and quality control
Construction project scheduling and quality controlConstruction project scheduling and quality control
Construction project scheduling and quality control
 
Lec.2 binifits of estamations...Types of Estimation
Lec.2  binifits of estamations...Types of EstimationLec.2  binifits of estamations...Types of Estimation
Lec.2 binifits of estamations...Types of Estimation
 
Performance evaluation of design build projects with and without agency const...
Performance evaluation of design build projects with and without agency const...Performance evaluation of design build projects with and without agency const...
Performance evaluation of design build projects with and without agency const...
 
Performance evaluation of design build (d-b) projects
Performance evaluation of design build (d-b) projectsPerformance evaluation of design build (d-b) projects
Performance evaluation of design build (d-b) projects
 
Measuring tendering and estimating for CBE
Measuring tendering and estimating for CBEMeasuring tendering and estimating for CBE
Measuring tendering and estimating for CBE
 
Ecm442 lecture 1 latest
Ecm442 lecture 1 latestEcm442 lecture 1 latest
Ecm442 lecture 1 latest
 
IIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction Project
 
IRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in ConstructionIRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in Construction
 
Study of Factors Affecting the Implementation of BIM: An Evaluation of Risk V...
Study of Factors Affecting the Implementation of BIM: An Evaluation of Risk V...Study of Factors Affecting the Implementation of BIM: An Evaluation of Risk V...
Study of Factors Affecting the Implementation of BIM: An Evaluation of Risk V...
 
COVERTITLE PAGE Table of ContentsI. Integrated Projec
COVERTITLE PAGE Table of ContentsI. Integrated ProjecCOVERTITLE PAGE Table of ContentsI. Integrated Projec
COVERTITLE PAGE Table of ContentsI. Integrated Projec
 

More from Shze Hwa Lee

Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
Shze Hwa Lee
 
Pp2 p5
Pp2   p5Pp2   p5
Pp2 p5
Shze Hwa Lee
 
Cp 24062018 2241
Cp 24062018 2241Cp 24062018 2241
Cp 24062018 2241
Shze Hwa Lee
 
Be finalise a3
Be finalise a3Be finalise a3
Be finalise a3
Shze Hwa Lee
 
Be presentation slides
Be presentation slidesBe presentation slides
Be presentation slides
Shze Hwa Lee
 
Be Report Finalize
Be Report FinalizeBe Report Finalize
Be Report Finalize
Shze Hwa Lee
 
Fm report template
Fm report templateFm report template
Fm report template
Shze Hwa Lee
 
Csi presentation
Csi   presentationCsi   presentation
Csi presentation
Shze Hwa Lee
 
Finased csi report
Finased csi reportFinased csi report
Finased csi report
Shze Hwa Lee
 
Software Presentation Slides
Software Presentation SlidesSoftware Presentation Slides
Software Presentation Slides
Shze Hwa Lee
 
Software Application Report
Software Application ReportSoftware Application Report
Software Application Report
Shze Hwa Lee
 
Seminar 1 Questions
Seminar 1 QuestionsSeminar 1 Questions
Seminar 1 Questions
Shze Hwa Lee
 
PP1 presentation
PP1 presentationPP1 presentation
PP1 presentation
Shze Hwa Lee
 
PP1 report group 7 (finalized)
PP1 report group 7 (finalized)PP1 report group 7 (finalized)
PP1 report group 7 (finalized)
Shze Hwa Lee
 
Measurement 4 presentation
Measurement 4 presentation Measurement 4 presentation
Measurement 4 presentation
Shze Hwa Lee
 
ECA presentation
ECA presentationECA presentation
ECA presentation
Shze Hwa Lee
 
Bs 2 group assignment
Bs 2 group assignmentBs 2 group assignment
Bs 2 group assignment
Shze Hwa Lee
 
People dynamic (assingment 1)
People dynamic (assingment 1) People dynamic (assingment 1)
People dynamic (assingment 1)
Shze Hwa Lee
 
Safety and Health individual assignment
Safety and Health individual assignment Safety and Health individual assignment
Safety and Health individual assignment
Shze Hwa Lee
 
Traffic management safety six key issues (presentaion 1)
Traffic management safety   six key issues (presentaion 1)Traffic management safety   six key issues (presentaion 1)
Traffic management safety six key issues (presentaion 1)
Shze Hwa Lee
 

More from Shze Hwa Lee (20)

Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
Pp2 p5
Pp2   p5Pp2   p5
Pp2 p5
 
Cp 24062018 2241
Cp 24062018 2241Cp 24062018 2241
Cp 24062018 2241
 
Be finalise a3
Be finalise a3Be finalise a3
Be finalise a3
 
Be presentation slides
Be presentation slidesBe presentation slides
Be presentation slides
 
Be Report Finalize
Be Report FinalizeBe Report Finalize
Be Report Finalize
 
Fm report template
Fm report templateFm report template
Fm report template
 
Csi presentation
Csi   presentationCsi   presentation
Csi presentation
 
Finased csi report
Finased csi reportFinased csi report
Finased csi report
 
Software Presentation Slides
Software Presentation SlidesSoftware Presentation Slides
Software Presentation Slides
 
Software Application Report
Software Application ReportSoftware Application Report
Software Application Report
 
Seminar 1 Questions
Seminar 1 QuestionsSeminar 1 Questions
Seminar 1 Questions
 
PP1 presentation
PP1 presentationPP1 presentation
PP1 presentation
 
PP1 report group 7 (finalized)
PP1 report group 7 (finalized)PP1 report group 7 (finalized)
PP1 report group 7 (finalized)
 
Measurement 4 presentation
Measurement 4 presentation Measurement 4 presentation
Measurement 4 presentation
 
ECA presentation
ECA presentationECA presentation
ECA presentation
 
Bs 2 group assignment
Bs 2 group assignmentBs 2 group assignment
Bs 2 group assignment
 
People dynamic (assingment 1)
People dynamic (assingment 1) People dynamic (assingment 1)
People dynamic (assingment 1)
 
Safety and Health individual assignment
Safety and Health individual assignment Safety and Health individual assignment
Safety and Health individual assignment
 
Traffic management safety six key issues (presentaion 1)
Traffic management safety   six key issues (presentaion 1)Traffic management safety   six key issues (presentaion 1)
Traffic management safety six key issues (presentaion 1)
 

Recently uploaded

PART A. Introduction to Costumer Service
PART A. Introduction to Costumer ServicePART A. Introduction to Costumer Service
PART A. Introduction to Costumer Service
PedroFerreira53928
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
EugeneSaldivar
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
TechSoup
 
Fish and Chips - have they had their chips
Fish and Chips - have they had their chipsFish and Chips - have they had their chips
Fish and Chips - have they had their chips
GeoBlogs
 
Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)
rosedainty
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
GeoBlogs
 
Digital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and ResearchDigital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and Research
Vikramjit Singh
 
Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345
beazzy04
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
Special education needs
 
How to Break the cycle of negative Thoughts
How to Break the cycle of negative ThoughtsHow to Break the cycle of negative Thoughts
How to Break the cycle of negative Thoughts
Col Mukteshwar Prasad
 
Operation Blue Star - Saka Neela Tara
Operation Blue Star   -  Saka Neela TaraOperation Blue Star   -  Saka Neela Tara
Operation Blue Star - Saka Neela Tara
Balvir Singh
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
joachimlavalley1
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
Pavel ( NSTU)
 
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXPhrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
MIRIAMSALINAS13
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
siemaillard
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
Atul Kumar Singh
 
The Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfThe Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdf
kaushalkr1407
 
How to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERPHow to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERP
Celine George
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
Sandy Millin
 
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptxMARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
bennyroshan06
 

Recently uploaded (20)

PART A. Introduction to Costumer Service
PART A. Introduction to Costumer ServicePART A. Introduction to Costumer Service
PART A. Introduction to Costumer Service
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
 
Fish and Chips - have they had their chips
Fish and Chips - have they had their chipsFish and Chips - have they had their chips
Fish and Chips - have they had their chips
 
Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
 
Digital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and ResearchDigital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and Research
 
Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
 
How to Break the cycle of negative Thoughts
How to Break the cycle of negative ThoughtsHow to Break the cycle of negative Thoughts
How to Break the cycle of negative Thoughts
 
Operation Blue Star - Saka Neela Tara
Operation Blue Star   -  Saka Neela TaraOperation Blue Star   -  Saka Neela Tara
Operation Blue Star - Saka Neela Tara
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
 
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXPhrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
 
The Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfThe Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdf
 
How to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERPHow to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERP
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
 
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptxMARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
 

Estimating presentation (question 1)

  • 1. Bachelor of Quantity Surveyor ESTIMATING QSB 60504 Seminars - Question 1 Group Members: Lee Shze Hwa (0320053) Hing Pui Kei (0325961) Ko Bou Sim (0325271) Esther Chuah (0321422) Lecturer: Ms. Azrina Md Yaakob Tutorial Group : Section 2
  • 2. Question 1 (a) : Explain to your client the importance of estimating at different stages of procurement. [9 marks]
  • 3. Question 1 (a) Construction Procurement Process
  • 4. Question 1 (a) ● It provides a comparison with budget and cashflow estimate. ● It provides a basis to compare and assess the tender from contractors. ● It provides a prediction of the construction period. ● It provides the expected project cost. ● It uses to allocate the budget and the feasibility of the construction project. ● It forms the basis of the future budget and cost control. Importance of estimating in pre-contract :
  • 5. ● It provides budget to the Management and enable them to control costs during construction execution. ● It is used for many assessments that made during the construction stage. ● It is used for judgements that made during the construction stage. Question 1 (a) Importance of estimating in post-contract :
  • 6. Question 1 (b) : Explain to your client the differences of measurement, tendering and estimating. [9 marks]
  • 7. Question 1 (b) Differences Measurement Tendering Estimating Measurement is a process of calculating the quantity for different materials to produce an accurate quantities and descriptions by apply a rule or set of rules. Tendering is a process of bidding and obtaining the construction project by contractors. Estimating is the process of calculating the net cost required to carry out the construction work. Involve in different construction procurement process Involved in both pre-contract and post-contract work. Involved in pre-contract work only. Involved in both pre-contract and post-contract work. Purpose It provides the quantity of materials required for the construction project. It provides the price of estimated cost and profit for contractors to tender the project. It provides the estimating cost of preliminaries, plant, labour and material cost, daywork, provisional sums, prime cost sums and contingencies. Profit Without profit. With profit. Without profit. Application Application on SMM. Application on Bill of Quantity. Application on the building up rate. Item + Quantity Measurement + Rates Estimating + Profit
  • 8. Question 1 (c) : Explain to your client what preliminaries items are and provide five (5) examples. [7 marks]
  • 9. ● Include: - Financials of the construction project. - Outlying necessary details. - Getting approvals for things like building permits or equipment leases. ● Preliminaries also used to give important details about testing measures and the goals for completion. Definition of Preliminary items : Question 1 (c)
  • 10. Question 1 (c) Examples of preliminaries items : ● Site administration and security ● Requirement for the operating and maintenance manual
  • 11. Question 1 (c) Examples of preliminaries items : ● Site waste management plan ● Insurances - Example: risks insurance (covers physical damage to the works and site materials.)
  • 12. Question 1 (c) Examples of preliminaries items : ● Relevant report, like soil report. ● Electrical supply.
  • 13. Question 1 (c) Examples of preliminaries items : ● Allowance for small plant, tools and machinery.
  • 14. 1. "Pre-Tender Estimate For Contracts - Designing Buildings Wiki". Designingbuildings.co.uk. N.p., 2017. Web. 12 Apr. 2017. 2. "Measurement - Designing Buildings Wiki". Designingbuildings.co.uk. N.p., 2017. Web. 12 Apr. 2017. 3. "Pearson Qualifications | Edexcel, BTEC, LCCI And EDI | Pearson Qualifications". Qualifications.pearson.com. N.p., 2017. Web. 12 Apr. 2017. 4. Mishra, Gopal. "COST ESTIMATION OF CONSTRUCTION PROJECTS". The Constructor. N.p., 2017. Web. 12 Apr. 2017. 5. Associates, JAK. "Preliminary And General Costs | J.A. Kruger & Associates". Blog.jak- associates.com. N.p., 2017. Web. 12 Apr. 2017. 6. "Tender Pricing Document - Designing Buildings Wiki". Designingbuildings.co.uk. N.p., 2017. Web. 12 Apr. 2017. 7. Burger, Rachel. "The Ultimate Guide To Construction Cost Estimating - Capterra Blog". Blog.capterra.com. N.p., 2017. Web. 12 Apr. 2017. References