SlideShare a Scribd company logo
1 of 13
ROLE OF HOPT, HODT & SO
Cawangan Pengurusan Projek Kompleks
Objective of the presentation
 To define & clarify the roles and
responsibilities of HOPT, HODT & SO at
each phases of the project lifecycle
 To provide initial impetus for further
discussion so that R & R of the HOPT,HOPT
& SO can be further refined and agreed
Overview
Of
Assignment of Main
Responsibilities in JKR Project
Lifecycle Phases
LESSONS
LEARNED
TYPICAL APPROACH TO A PROJECT IN JKR
ORGANISATION
PLANNING HAND / OVER
CONSTRUCTION
PROCUREMENT
DESIGN
POOL OF PROJECT
MANAGERS
PROGRAM LEVEL
SBU PORTFOLIO LEVEL
DG / DDG
SBUs
JKR HEADQUARTERS STATE/DISTRICT /PROJ TEAM
ASSIGN
PROJECT
MANAGER (HOPT)
INPUT FROM KEY STAKEHOLDERS TO THE PROJECT
SPECIALIST
BRANCHES
HOPT HODT HODT SO SO
Proj Impt
TECHNICAL
PM’S RESPONSIBILITY FOR PROJ MGT THROUGHOUT THE PROJECT LIFE CYCLE
ASSIGNS PROJECTS
RECEIVED FROM CLIENTS
TO VARIOUS SBUs
Roles & Responsibilities Of HOPT,
HODT & SO
Role & Responsibilities of HOPT
 Prepare project management plan and monitor &
control of the project throughout the project lifecycle
 Proactively influencing outcomes
 Ensuring technical issues are resolved
 Manage, document and report on overall status of
the project at defined points
 Ensuring completing the project on time and to
budget with quality outcomes
 Managing all the key stakeholders of the project
Role & Responsibilities of HOPT
 Focus on overall needs and expectations of
customers and other stakeholders
 Single point of contact for clients
 Set the overall project scope, schedule and
budget that the HODT & SO will deliver
 Full-time project managers, with no supervisory
duties
 Prepare responsibility assignment matrix for
project team members
Role & Responsibilities of HODT
 Responsible for the technical aspect of the project by
focussing on technical scope, schedule, budget and
quality including assisting and support HOPT in
QA/QC throughout the project life cycle
 Plan and design product realisation within defined
scope, time, cost and agreed quality/performance
standards & helps to resolve technical issues on the
project
 Perform technical audit on the project at any point
throughout the project life cycle as QA/QC
requirement
 Supports and assists in contract management
Role & Responsibilities of HODT
 Collaborates with other stakeholders (eg other
HODTs, SO etc) to provide support and services to
the project
 Manages, documents and reports on overall project
technical scope, schedule and budget at regular
interval as required for monitoring & controlling
 Prepare documentations, reports & lessons learned
in accordance with the assigned tasks for future
projects
Role & Responsibilities of the SO
 The SO may not be a party to a contract but he/she is named
in the contract document as the person fully responsible to
administer the contract between the government and the
contractor except for clauses reserved for other officers’
named, during the entire contract period of construction and
handover phase of the project
 Supervise, monitor & control of the project in accordance with
the drawings & specifications to achieve the outcomes of:
 Quality
 Time
 Cost
 As a certifier under the contract the SO has a duty to act fairly
and impartially when doing certification
 Laise with HOPT should there be any ambiguity, discrepancy
or inadequacy of drawings/specs etc
Role & Responsibilities of the SO
 Obtain consent from HOPT for change of scope and cost
to the project
 Manages overall risks, budget, and resources assigned
to the project
 Plan and manage communication plan eg. Meetings,
reports,flow of communication etc
 Managing the stakeholders eg. Public, TNB,
Waterworks, TM etc during contract stage
 Assists in the technical or quality audits carried out
during construction/handover stage
 Prepare close out report incorporating lessons learnt to
be submitted to the HOPT for future projects
Summary & Conclusion
 HOPT: as a project manager fully responsible to lead &
manage the project to the needs and expectations of the
clients
 HODT: as a technical expert fully responsible for the
technical aspects of the project but must conformed to
the scope, time & cost requirements as defined &
planned by the HOPT to meet the clients needs and
expectations
 SO: as the contract administrator has full authority over
the contractor as defined by the power given by the
contract, but no absolute authority over the project. The
SO must not deviate from the scope, time & cost as
planned by the HOPT
Thank you

More Related Content

What's hot

Shakeel Sarwar CV Civil+QS.July-2015
Shakeel Sarwar CV Civil+QS.July-2015Shakeel Sarwar CV Civil+QS.July-2015
Shakeel Sarwar CV Civil+QS.July-2015
Shakeel Sarwar
 
Construction Phase Mgmt Srvcs (2)
Construction Phase Mgmt Srvcs (2)Construction Phase Mgmt Srvcs (2)
Construction Phase Mgmt Srvcs (2)
Lee Maserian R.D.I.
 
Post Implementation Review Template
Post Implementation Review TemplatePost Implementation Review Template
Post Implementation Review Template
Edmond Cheng
 
CV Planning Manager (Sundeep Khare)
CV Planning Manager (Sundeep Khare)CV Planning Manager (Sundeep Khare)
CV Planning Manager (Sundeep Khare)
sundeep khare
 
Schedule management-plan template
Schedule management-plan templateSchedule management-plan template
Schedule management-plan template
Vivek Srivastava
 

What's hot (20)

Template kick off-meeting
Template kick off-meeting Template kick off-meeting
Template kick off-meeting
 
Shakeel Sarwar CV Civil+QS.July-2015
Shakeel Sarwar CV Civil+QS.July-2015Shakeel Sarwar CV Civil+QS.July-2015
Shakeel Sarwar CV Civil+QS.July-2015
 
Construction Phase Mgmt Srvcs (2)
Construction Phase Mgmt Srvcs (2)Construction Phase Mgmt Srvcs (2)
Construction Phase Mgmt Srvcs (2)
 
Project management-Report
Project management-ReportProject management-Report
Project management-Report
 
Construction Project Process Flow
Construction Project Process FlowConstruction Project Process Flow
Construction Project Process Flow
 
Post Implementation Review Template
Post Implementation Review TemplatePost Implementation Review Template
Post Implementation Review Template
 
Google_Retreat_Charter-WTCS
Google_Retreat_Charter-WTCSGoogle_Retreat_Charter-WTCS
Google_Retreat_Charter-WTCS
 
Project closeoutprocess
Project closeoutprocessProject closeoutprocess
Project closeoutprocess
 
CV Swapnil S
CV Swapnil SCV Swapnil S
CV Swapnil S
 
Building services planning manual 2007
Building services planning manual 2007Building services planning manual 2007
Building services planning manual 2007
 
projec kickoff presentation template
 projec kickoff presentation template projec kickoff presentation template
projec kickoff presentation template
 
Final Project Closing
Final Project ClosingFinal Project Closing
Final Project Closing
 
project on construction of house report.
project on construction of house report.project on construction of house report.
project on construction of house report.
 
CV Planning Manager (Sundeep Khare)
CV Planning Manager (Sundeep Khare)CV Planning Manager (Sundeep Khare)
CV Planning Manager (Sundeep Khare)
 
EPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
EPC Group's PMO Methodology to Ensure On Time and On Budget InitiativesEPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
EPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
 
Construction Management Services
Construction Management ServicesConstruction Management Services
Construction Management Services
 
Schedule management-plan template
Schedule management-plan templateSchedule management-plan template
Schedule management-plan template
 
Pm chapter 7
Pm chapter 7Pm chapter 7
Pm chapter 7
 
First Steps in Project Planning for Libraries
First Steps in Project Planning for LibrariesFirst Steps in Project Planning for Libraries
First Steps in Project Planning for Libraries
 
Raman Rezaei Infographic
Raman Rezaei InfographicRaman Rezaei Infographic
Raman Rezaei Infographic
 

Similar to Role hopt hodt_so_1_(1)

Frans Fourie CV Current N 2015
Frans Fourie CV Current N 2015Frans Fourie CV Current N 2015
Frans Fourie CV Current N 2015
loracfou
 
Fundamentals of project management july 7, 2012 revised
Fundamentals of project management july 7, 2012 revisedFundamentals of project management july 7, 2012 revised
Fundamentals of project management july 7, 2012 revised
gorby626
 
Senior Planning Engineer -Mohidee Sheik Asan
Senior Planning Engineer -Mohidee Sheik AsanSenior Planning Engineer -Mohidee Sheik Asan
Senior Planning Engineer -Mohidee Sheik Asan
Mohideen Sheik Asan
 
Project Management Presentation Template.pdf
Project Management Presentation Template.pdfProject Management Presentation Template.pdf
Project Management Presentation Template.pdf
apoorvaguptaspn27
 
Project Management Process Groups
Project Management Process GroupsProject Management Process Groups
Project Management Process Groups
TechNoleGirl
 

Similar to Role hopt hodt_so_1_(1) (20)

Contract management
Contract managementContract management
Contract management
 
CV-Kunwar Aftab Ahmad Khan-29Oct2015
CV-Kunwar Aftab Ahmad Khan-29Oct2015CV-Kunwar Aftab Ahmad Khan-29Oct2015
CV-Kunwar Aftab Ahmad Khan-29Oct2015
 
Frans Fourie CV Current N 2015
Frans Fourie CV Current N 2015Frans Fourie CV Current N 2015
Frans Fourie CV Current N 2015
 
Fundamentals of project management july 7, 2012 revised
Fundamentals of project management july 7, 2012 revisedFundamentals of project management july 7, 2012 revised
Fundamentals of project management july 7, 2012 revised
 
Primavera trainer
Primavera trainerPrimavera trainer
Primavera trainer
 
Henry CV
Henry CVHenry CV
Henry CV
 
Project charter template
Project charter templateProject charter template
Project charter template
 
Communication
CommunicationCommunication
Communication
 
Senior Planning Engineer -Mohidee Sheik Asan
Senior Planning Engineer -Mohidee Sheik AsanSenior Planning Engineer -Mohidee Sheik Asan
Senior Planning Engineer -Mohidee Sheik Asan
 
Project Planning & Management
Project Planning & Management Project Planning & Management
Project Planning & Management
 
Define the Project
Define the ProjectDefine the Project
Define the Project
 
Planning skill.pdf
Planning skill.pdfPlanning skill.pdf
Planning skill.pdf
 
UNIT-1.pptx
UNIT-1.pptxUNIT-1.pptx
UNIT-1.pptx
 
Assignment
AssignmentAssignment
Assignment
 
EPC Group's Project Management Organization’s Methodology
EPC Group's Project Management Organization’s MethodologyEPC Group's Project Management Organization’s Methodology
EPC Group's Project Management Organization’s Methodology
 
Phases of a Project
Phases of a ProjectPhases of a Project
Phases of a Project
 
Project Management Project 1 Report: Defining & Documenting A Project
Project Management Project 1 Report: Defining & Documenting A ProjectProject Management Project 1 Report: Defining & Documenting A Project
Project Management Project 1 Report: Defining & Documenting A Project
 
Project Management Presentation Template.pdf
Project Management Presentation Template.pdfProject Management Presentation Template.pdf
Project Management Presentation Template.pdf
 
CV - Azwyn Abd Aziz
CV - Azwyn Abd AzizCV - Azwyn Abd Aziz
CV - Azwyn Abd Aziz
 
Project Management Process Groups
Project Management Process GroupsProject Management Process Groups
Project Management Process Groups
 

More from Mohd Zulhairi Mohd Noor

273109087-Kursus-Asas-Rekabentuk-Sistem-Pam-Pengairan-Pertanian.pptx
273109087-Kursus-Asas-Rekabentuk-Sistem-Pam-Pengairan-Pertanian.pptx273109087-Kursus-Asas-Rekabentuk-Sistem-Pam-Pengairan-Pertanian.pptx
273109087-Kursus-Asas-Rekabentuk-Sistem-Pam-Pengairan-Pertanian.pptx
Mohd Zulhairi Mohd Noor
 
230033095-Industrialised-building-system (1).ppt
230033095-Industrialised-building-system (1).ppt230033095-Industrialised-building-system (1).ppt
230033095-Industrialised-building-system (1).ppt
Mohd Zulhairi Mohd Noor
 

More from Mohd Zulhairi Mohd Noor (20)

(1)_Terminologi_Kuasa.pdf
(1)_Terminologi_Kuasa.pdf(1)_Terminologi_Kuasa.pdf
(1)_Terminologi_Kuasa.pdf
 
ASAS_KAWALAN.ppt
ASAS_KAWALAN.pptASAS_KAWALAN.ppt
ASAS_KAWALAN.ppt
 
Dental_Chair_2.doc
Dental_Chair_2.docDental_Chair_2.doc
Dental_Chair_2.doc
 
CONVENTIONS_OF_CASE_WRITING.ppt
CONVENTIONS_OF_CASE_WRITING.pptCONVENTIONS_OF_CASE_WRITING.ppt
CONVENTIONS_OF_CASE_WRITING.ppt
 
120595370-CARA-PEMBINAAN-RUMAH.pptx
120595370-CARA-PEMBINAAN-RUMAH.pptx120595370-CARA-PEMBINAAN-RUMAH.pptx
120595370-CARA-PEMBINAAN-RUMAH.pptx
 
273109087-Kursus-Asas-Rekabentuk-Sistem-Pam-Pengairan-Pertanian.pptx
273109087-Kursus-Asas-Rekabentuk-Sistem-Pam-Pengairan-Pertanian.pptx273109087-Kursus-Asas-Rekabentuk-Sistem-Pam-Pengairan-Pertanian.pptx
273109087-Kursus-Asas-Rekabentuk-Sistem-Pam-Pengairan-Pertanian.pptx
 
All-about-Tokyo.pptx
All-about-Tokyo.pptxAll-about-Tokyo.pptx
All-about-Tokyo.pptx
 
FUTURE_CHALLENGES_IN_PROJECT_MANAGEMENT.pptx
FUTURE_CHALLENGES_IN_PROJECT_MANAGEMENT.pptxFUTURE_CHALLENGES_IN_PROJECT_MANAGEMENT.pptx
FUTURE_CHALLENGES_IN_PROJECT_MANAGEMENT.pptx
 
61973559-Unit-5-Kerja-Tanah.ppt
61973559-Unit-5-Kerja-Tanah.ppt61973559-Unit-5-Kerja-Tanah.ppt
61973559-Unit-5-Kerja-Tanah.ppt
 
230033095-Industrialised-building-system (1).ppt
230033095-Industrialised-building-system (1).ppt230033095-Industrialised-building-system (1).ppt
230033095-Industrialised-building-system (1).ppt
 
59794367-JENTERA-PEMBINAAN-JALAN-RAYA.ppt
59794367-JENTERA-PEMBINAAN-JALAN-RAYA.ppt59794367-JENTERA-PEMBINAAN-JALAN-RAYA.ppt
59794367-JENTERA-PEMBINAAN-JALAN-RAYA.ppt
 
22513791-Lantai.ppt
22513791-Lantai.ppt22513791-Lantai.ppt
22513791-Lantai.ppt
 
95123497-CESMM-Malaysia.ppt
95123497-CESMM-Malaysia.ppt95123497-CESMM-Malaysia.ppt
95123497-CESMM-Malaysia.ppt
 
57910334-5-MEP-Fire-Protection-rev.ppt
57910334-5-MEP-Fire-Protection-rev.ppt57910334-5-MEP-Fire-Protection-rev.ppt
57910334-5-MEP-Fire-Protection-rev.ppt
 
20306223-3-Tips-For-Professional-Engineer-Interview-in-Malaysia.ppt
20306223-3-Tips-For-Professional-Engineer-Interview-in-Malaysia.ppt20306223-3-Tips-For-Professional-Engineer-Interview-in-Malaysia.ppt
20306223-3-Tips-For-Professional-Engineer-Interview-in-Malaysia.ppt
 
525412627-2-Project-Management-2018-BAIS-3-4.ppt
525412627-2-Project-Management-2018-BAIS-3-4.ppt525412627-2-Project-Management-2018-BAIS-3-4.ppt
525412627-2-Project-Management-2018-BAIS-3-4.ppt
 
271710575-Lecture-14-Project-Monitoring.ppt
271710575-Lecture-14-Project-Monitoring.ppt271710575-Lecture-14-Project-Monitoring.ppt
271710575-Lecture-14-Project-Monitoring.ppt
 
258681760-Asphaltic-Concrete-Mix-Design.ppt
258681760-Asphaltic-Concrete-Mix-Design.ppt258681760-Asphaltic-Concrete-Mix-Design.ppt
258681760-Asphaltic-Concrete-Mix-Design.ppt
 
372601839 boq-vrf
372601839 boq-vrf372601839 boq-vrf
372601839 boq-vrf
 
29629597 psychrometric-course
29629597 psychrometric-course29629597 psychrometric-course
29629597 psychrometric-course
 

Recently uploaded

Performance enhancement of machine learning algorithm for breast cancer diagn...
Performance enhancement of machine learning algorithm for breast cancer diagn...Performance enhancement of machine learning algorithm for breast cancer diagn...
Performance enhancement of machine learning algorithm for breast cancer diagn...
IJECEIAES
 
Final DBMS Manual (2).pdf final lab manual
Final DBMS Manual (2).pdf final lab manualFinal DBMS Manual (2).pdf final lab manual
Final DBMS Manual (2).pdf final lab manual
BalamuruganV28
 
electrical installation and maintenance.
electrical installation and maintenance.electrical installation and maintenance.
electrical installation and maintenance.
benjamincojr
 
Microkernel in Operating System | Operating System
Microkernel in Operating System | Operating SystemMicrokernel in Operating System | Operating System
Microkernel in Operating System | Operating System
Sampad Kar
 

Recently uploaded (20)

What is Coordinate Measuring Machine? CMM Types, Features, Functions
What is Coordinate Measuring Machine? CMM Types, Features, FunctionsWhat is Coordinate Measuring Machine? CMM Types, Features, Functions
What is Coordinate Measuring Machine? CMM Types, Features, Functions
 
"United Nations Park" Site Visit Report.
"United Nations Park" Site  Visit Report."United Nations Park" Site  Visit Report.
"United Nations Park" Site Visit Report.
 
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024
 
Performance enhancement of machine learning algorithm for breast cancer diagn...
Performance enhancement of machine learning algorithm for breast cancer diagn...Performance enhancement of machine learning algorithm for breast cancer diagn...
Performance enhancement of machine learning algorithm for breast cancer diagn...
 
Final DBMS Manual (2).pdf final lab manual
Final DBMS Manual (2).pdf final lab manualFinal DBMS Manual (2).pdf final lab manual
Final DBMS Manual (2).pdf final lab manual
 
5G and 6G refer to generations of mobile network technology, each representin...
5G and 6G refer to generations of mobile network technology, each representin...5G and 6G refer to generations of mobile network technology, each representin...
5G and 6G refer to generations of mobile network technology, each representin...
 
Basics of Relay for Engineering Students
Basics of Relay for Engineering StudentsBasics of Relay for Engineering Students
Basics of Relay for Engineering Students
 
Autodesk Construction Cloud (Autodesk Build).pptx
Autodesk Construction Cloud (Autodesk Build).pptxAutodesk Construction Cloud (Autodesk Build).pptx
Autodesk Construction Cloud (Autodesk Build).pptx
 
Passive Air Cooling System and Solar Water Heater.ppt
Passive Air Cooling System and Solar Water Heater.pptPassive Air Cooling System and Solar Water Heater.ppt
Passive Air Cooling System and Solar Water Heater.ppt
 
CLOUD COMPUTING SERVICES - Cloud Reference Modal
CLOUD COMPUTING SERVICES - Cloud Reference ModalCLOUD COMPUTING SERVICES - Cloud Reference Modal
CLOUD COMPUTING SERVICES - Cloud Reference Modal
 
Piping and instrumentation diagram p.pdf
Piping and instrumentation diagram p.pdfPiping and instrumentation diagram p.pdf
Piping and instrumentation diagram p.pdf
 
Lab Manual Arduino UNO Microcontrollar.docx
Lab Manual Arduino UNO Microcontrollar.docxLab Manual Arduino UNO Microcontrollar.docx
Lab Manual Arduino UNO Microcontrollar.docx
 
Artificial Intelligence in due diligence
Artificial Intelligence in due diligenceArtificial Intelligence in due diligence
Artificial Intelligence in due diligence
 
electrical installation and maintenance.
electrical installation and maintenance.electrical installation and maintenance.
electrical installation and maintenance.
 
Filters for Electromagnetic Compatibility Applications
Filters for Electromagnetic Compatibility ApplicationsFilters for Electromagnetic Compatibility Applications
Filters for Electromagnetic Compatibility Applications
 
NO1 Best Powerful Vashikaran Specialist Baba Vashikaran Specialist For Love V...
NO1 Best Powerful Vashikaran Specialist Baba Vashikaran Specialist For Love V...NO1 Best Powerful Vashikaran Specialist Baba Vashikaran Specialist For Love V...
NO1 Best Powerful Vashikaran Specialist Baba Vashikaran Specialist For Love V...
 
Seismic Hazard Assessment Software in Python by Prof. Dr. Costas Sachpazis
Seismic Hazard Assessment Software in Python by Prof. Dr. Costas SachpazisSeismic Hazard Assessment Software in Python by Prof. Dr. Costas Sachpazis
Seismic Hazard Assessment Software in Python by Prof. Dr. Costas Sachpazis
 
handbook on reinforce concrete and detailing
handbook on reinforce concrete and detailinghandbook on reinforce concrete and detailing
handbook on reinforce concrete and detailing
 
Microkernel in Operating System | Operating System
Microkernel in Operating System | Operating SystemMicrokernel in Operating System | Operating System
Microkernel in Operating System | Operating System
 
Software Engineering Practical File Front Pages.pdf
Software Engineering Practical File Front Pages.pdfSoftware Engineering Practical File Front Pages.pdf
Software Engineering Practical File Front Pages.pdf
 

Role hopt hodt_so_1_(1)

  • 1. ROLE OF HOPT, HODT & SO Cawangan Pengurusan Projek Kompleks
  • 2. Objective of the presentation  To define & clarify the roles and responsibilities of HOPT, HODT & SO at each phases of the project lifecycle  To provide initial impetus for further discussion so that R & R of the HOPT,HOPT & SO can be further refined and agreed
  • 3. Overview Of Assignment of Main Responsibilities in JKR Project Lifecycle Phases
  • 4. LESSONS LEARNED TYPICAL APPROACH TO A PROJECT IN JKR ORGANISATION PLANNING HAND / OVER CONSTRUCTION PROCUREMENT DESIGN POOL OF PROJECT MANAGERS PROGRAM LEVEL SBU PORTFOLIO LEVEL DG / DDG SBUs JKR HEADQUARTERS STATE/DISTRICT /PROJ TEAM ASSIGN PROJECT MANAGER (HOPT) INPUT FROM KEY STAKEHOLDERS TO THE PROJECT SPECIALIST BRANCHES HOPT HODT HODT SO SO Proj Impt TECHNICAL PM’S RESPONSIBILITY FOR PROJ MGT THROUGHOUT THE PROJECT LIFE CYCLE ASSIGNS PROJECTS RECEIVED FROM CLIENTS TO VARIOUS SBUs
  • 5. Roles & Responsibilities Of HOPT, HODT & SO
  • 6. Role & Responsibilities of HOPT  Prepare project management plan and monitor & control of the project throughout the project lifecycle  Proactively influencing outcomes  Ensuring technical issues are resolved  Manage, document and report on overall status of the project at defined points  Ensuring completing the project on time and to budget with quality outcomes  Managing all the key stakeholders of the project
  • 7. Role & Responsibilities of HOPT  Focus on overall needs and expectations of customers and other stakeholders  Single point of contact for clients  Set the overall project scope, schedule and budget that the HODT & SO will deliver  Full-time project managers, with no supervisory duties  Prepare responsibility assignment matrix for project team members
  • 8. Role & Responsibilities of HODT  Responsible for the technical aspect of the project by focussing on technical scope, schedule, budget and quality including assisting and support HOPT in QA/QC throughout the project life cycle  Plan and design product realisation within defined scope, time, cost and agreed quality/performance standards & helps to resolve technical issues on the project  Perform technical audit on the project at any point throughout the project life cycle as QA/QC requirement  Supports and assists in contract management
  • 9. Role & Responsibilities of HODT  Collaborates with other stakeholders (eg other HODTs, SO etc) to provide support and services to the project  Manages, documents and reports on overall project technical scope, schedule and budget at regular interval as required for monitoring & controlling  Prepare documentations, reports & lessons learned in accordance with the assigned tasks for future projects
  • 10. Role & Responsibilities of the SO  The SO may not be a party to a contract but he/she is named in the contract document as the person fully responsible to administer the contract between the government and the contractor except for clauses reserved for other officers’ named, during the entire contract period of construction and handover phase of the project  Supervise, monitor & control of the project in accordance with the drawings & specifications to achieve the outcomes of:  Quality  Time  Cost  As a certifier under the contract the SO has a duty to act fairly and impartially when doing certification  Laise with HOPT should there be any ambiguity, discrepancy or inadequacy of drawings/specs etc
  • 11. Role & Responsibilities of the SO  Obtain consent from HOPT for change of scope and cost to the project  Manages overall risks, budget, and resources assigned to the project  Plan and manage communication plan eg. Meetings, reports,flow of communication etc  Managing the stakeholders eg. Public, TNB, Waterworks, TM etc during contract stage  Assists in the technical or quality audits carried out during construction/handover stage  Prepare close out report incorporating lessons learnt to be submitted to the HOPT for future projects
  • 12. Summary & Conclusion  HOPT: as a project manager fully responsible to lead & manage the project to the needs and expectations of the clients  HODT: as a technical expert fully responsible for the technical aspects of the project but must conformed to the scope, time & cost requirements as defined & planned by the HOPT to meet the clients needs and expectations  SO: as the contract administrator has full authority over the contractor as defined by the power given by the contract, but no absolute authority over the project. The SO must not deviate from the scope, time & cost as planned by the HOPT