SlideShare a Scribd company logo
The WHY-The WHAT and The HOW?


Author: Jihad Daniel
WHY Do Cost Management?
THE WHY?      The Developer aims at developing a
              Project for the purpose of Financial
                              Gain


                    Before proceeding with the
                  development the Developer will
                   prepare a FEASIBILITY STUDY



        If Expenditure                       If Income exceeds
       exceeds Income                            Expenditure



       Project is NOT
                                              Project is viable
           viable



                                            Developer employs
                                          Architects/Engineers to
                                          design his project and a
                                           Contractor to built it
THE WHY?
 When preparing the Financial Feasibility Study, the Developer
 will consider the following prime cost centers:
      Land Cost-market prices (Purchase of the site)
      Construction Costs (Cost of the Project)
      Financial Charges (Institutional Funding)
      Professional Fees and other costs and charges
      Disposal Costs (Advertising and selling costs).


 The Developer only makes his money after completion of the
 development, i.e. Profit is obtained only after completion of
 the project and this can take years.
THE WHY?
 It is essential to identify the Cost of Construction at the
 Feasibility Stage and to ensure that the cost of
 construction does not substantially vary during the
 Design Stage-Tender-and on completion of the
 Construction Stage (Final Account).
Example Feasibility Study
Example Feasibility Study
 Proposed Development:
       8 story Apartment Building with Penthouse located in Beirut
       4 No. Apartments per floor each offering 150m2 of accommodation
       Common circulation area of 20% net apartment area
       1 No. Penthouse on the roof.
 Factors to Consider:
       Cost of Land = 475,000 US$
       Construction Cost = 4,284,900 US$
       Disposal Cost = 238,000 US$
       Revenue on Sale = 4,760,000 US$
Example Feasibility Study
 Feasibility of Project:
        Gross Development Income = 4,760,000 US$

        Gross Development Expenditure = 4,998,100 US$
        Land Cost = 475,000 US$
        Construction Cost = 4,284,900 US$ (@500 US$/m2)
        Disposal Cost = 238,000 US$

                             LOSS = 238,100 US$
                       The Development is NOT FEASIBLE


 The Professional Role of the Design Team in Making the
 Project Viable.
WHAT Do We Do to Satisfy the
         WHY?
THE WHAT?
 Cost Variations and their effect on Profit.

 The Procedures adopted for cost monitoring during
 different project stages are divided into:
     Pre-Contract (Design Stage)
     Post Contract (Construction Stage)
THE WHAT?
 For Pre-Contract (Design Stage):
   Initial Cost-Feasibility Design Stage (the design is less than
   20% complete)
   a)   Feasibility           Cost Prediction is based on a Cost
        Model
   Design Development
        Conceptual Design Stage (design stage +/- 20%)
   b)   Conceptual             Cost Prediction is based on functional
        costs/m2 and verifies (a)
        Preliminary Design Stage (design stage +/- 50%)
   c)   Preliminary            Cost Prediction is based on a Cost Plan
        Elemental Analysis and verifies (a)
THE WHAT?
 For Pre-Contract (Design Stage): cont’
   Design Development (cont’)
        Fundamental Design Stage (design stage +/- 75%)
   d)   Fundamental                Cost Prediction is based on the
        Review of the Cost Plan and verifies (a)
   Tender Stage
        Final Design Stage (design stage 100%)
   e)   Final Design               Cost Prediction is based on a Priced
        BOQ and verifies (a)
THE WHAT?
 For Post-Contract (Construction Stage):
 Contract Forms provide administrative procedures to
 monitor and limit cost variations/claims arising between
 the Tender Cost and Final Accounts Costs.
HOW We Do WHAT We Do?
THE HOW?
 During the Feasibility Design Stage (Design less than 20%
 complete) a COST MODEL is used.
        A Cost Model is data extracted from a similar previous completed
        project
        Differences from the Cost Model and Proposed Project are isolated
        Historical cost data is updated to present day costs BASE DATE
        accounting for the differences
        The Cost Model’s modified costs are equated to cost/m2 and then
        applied to the built-up floor area of the Proposed Project.

      The Above Procedures provide an Indicative Cost based on cost/m2.
THE HOW?
 During the Conceptual Design Stage (Design +/- 20%
 complete).
          Assumptions made at the Feasibility Stage Estimate are verified
          Elements should be quantified, if possible
          The estimated total cost should be similar to that already
          reported. But if there are differences, these should be discussed
          with the Designer/Developer.

        The Above Procedures provide an Indicative Cost based on cost/m2
          but with more certainty.
THE HOW?
 During the Preliminary Design Stage (Design +/- 50%
 complete).
       Design advances to approximate quantification priced at composite
       unit rates
       A Cost Plan is prepared
       The estimated total cost should be similar to that already reported.
       But if there are differences, these should be discussed with the
       Designer/Developer.
THE HOW?
 During the Fundamental Design Stage (Design +/- 75%
 complete).
       An updated Cost Plan incorporating additional details is prepared
       The estimated total cost should be similar to that already reported.
       But if there are differences, these should be discussed with the
       Designer/Developer.
 During the Final Design Stage (Design 100% complete).
       A BOQ is priced using market prices in an attempt to predict tender
       results (Fair Priced Estimate)
       The estimated total cost should be similar to that already reported.
       But if there are differences, these should be discussed with the
       Designer/Developer.
THE HOW?
 Tender Results-Contractor’s Prices
       In the event the Tender results differ from the Tender Predications
       (Priced BOQ), differences should be discussed with the Designer and
       the Developer.
 Keeping a Cost Data Base
       A Data Base of Building Costs is maintained for the purposes of
       preparing those estimates required by the various design stages.
       In addition to the Data Base, continuous attention must be made to
       the various economic conditions arising during extended
       development and construction programmes and the effect of these
       conditions on prices.
COMMENTS & QUESTIONS!?

More Related Content

What's hot

Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential Building
SHAZEBALIKHAN1
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Management
srinivas2036
 
ACH 216 Lecture 08 (Scheduling)
ACH 216 Lecture 08 (Scheduling)ACH 216 Lecture 08 (Scheduling)
ACH 216 Lecture 08 (Scheduling)
Anne Arundel Community College
 
Construction phases
Construction phasesConstruction phases
Construction phases
Meesum Zaidi
 
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
HossamNegidaPMPRMPPS
 
Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...
ijtsrd
 
Project management-planning and scheduling
Project management-planning and schedulingProject management-planning and scheduling
Project management-planning and scheduling
Aditi Garg
 
S curves
S curvesS curves
S curves
Sagar Rana
 
ACH 216 Lecture 09 (Issues During Project)
ACH 216 Lecture 09 (Issues During Project)ACH 216 Lecture 09 (Issues During Project)
ACH 216 Lecture 09 (Issues During Project)
Anne Arundel Community College
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
Ahmed Al-Senosy Ph.D(cand),MSc,PMP,RMP
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
Farhan Moosa
 
Process of pre construction phase drawbacks
Process of pre construction phase drawbacksProcess of pre construction phase drawbacks
Process of pre construction phase drawbacks
glibson rojer
 
Construction project scheduling and quality control
Construction project scheduling and quality controlConstruction project scheduling and quality control
Construction project scheduling and quality control
monishkumark
 
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Antonio Coladarce
 
Construction Planning
Construction PlanningConstruction Planning
Construction Planning
Susitra Anandan
 
Understanding p6 dates
Understanding p6 datesUnderstanding p6 dates
Understanding p6 dates
krunalplanning
 
J.S. Daniel paper of fast tracking design in megaproject construction
J.S. Daniel paper of fast tracking design in megaproject constructionJ.S. Daniel paper of fast tracking design in megaproject construction
J.S. Daniel paper of fast tracking design in megaproject construction
J.S. Daniel
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
Procept Associates
 
Project controls function
Project controls functionProject controls function
Project controls function
Hatem Hegazi
 
Construction Project Process Flow
Construction Project Process FlowConstruction Project Process Flow
Construction Project Process Flow
Rajasekar M
 

What's hot (20)

Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential Building
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Management
 
ACH 216 Lecture 08 (Scheduling)
ACH 216 Lecture 08 (Scheduling)ACH 216 Lecture 08 (Scheduling)
ACH 216 Lecture 08 (Scheduling)
 
Construction phases
Construction phasesConstruction phases
Construction phases
 
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 
Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...
 
Project management-planning and scheduling
Project management-planning and schedulingProject management-planning and scheduling
Project management-planning and scheduling
 
S curves
S curvesS curves
S curves
 
ACH 216 Lecture 09 (Issues During Project)
ACH 216 Lecture 09 (Issues During Project)ACH 216 Lecture 09 (Issues During Project)
ACH 216 Lecture 09 (Issues During Project)
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
 
Process of pre construction phase drawbacks
Process of pre construction phase drawbacksProcess of pre construction phase drawbacks
Process of pre construction phase drawbacks
 
Construction project scheduling and quality control
Construction project scheduling and quality controlConstruction project scheduling and quality control
Construction project scheduling and quality control
 
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
 
Construction Planning
Construction PlanningConstruction Planning
Construction Planning
 
Understanding p6 dates
Understanding p6 datesUnderstanding p6 dates
Understanding p6 dates
 
J.S. Daniel paper of fast tracking design in megaproject construction
J.S. Daniel paper of fast tracking design in megaproject constructionJ.S. Daniel paper of fast tracking design in megaproject construction
J.S. Daniel paper of fast tracking design in megaproject construction
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 
Project controls function
Project controls functionProject controls function
Project controls function
 
Construction Project Process Flow
Construction Project Process FlowConstruction Project Process Flow
Construction Project Process Flow
 

Similar to J.S. Daniel paper for presentation cost management

Learnit buildit-manageit-141124083859-conversion-gate01
Learnit buildit-manageit-141124083859-conversion-gate01Learnit buildit-manageit-141124083859-conversion-gate01
Learnit buildit-manageit-141124083859-conversion-gate01
David Eagle
 
Phases of a Project
Phases of a ProjectPhases of a Project
Phases of a Project
DaltonCompany
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
reddvise
 
Project Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge AreaProject Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge Area
Joshua Render
 
Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...
IRJET Journal
 
Ch. 4 Cost Plan.pptx
Ch. 4 Cost Plan.pptxCh. 4 Cost Plan.pptx
Ch. 4 Cost Plan.pptx
MUHAMMADSAEED509568
 
L06 cost management
L06 cost managementL06 cost management
L06 cost management
Asa Chan
 
Rev207 matrixexcelfile
Rev207 matrixexcelfileRev207 matrixexcelfile
Rev207 matrixexcelfile
jbonvier
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost management
ejlp12
 
Construction process
Construction processConstruction process
Construction process
Mazen Al-Qadi
 
Procurement Strategies: A Seminar
Procurement Strategies: A SeminarProcurement Strategies: A Seminar
Procurement Strategies: A Seminar
Pang Khai Shuen
 
COST MANAGEMENT REPORT
COST MANAGEMENT REPORT COST MANAGEMENT REPORT
COST MANAGEMENT REPORT
Jo Balucanag - Bitonio
 
Design-Build: The Owner’s Role in Successful Outcomes
Design-Build: The Owner’s Role in Successful OutcomesDesign-Build: The Owner’s Role in Successful Outcomes
Design-Build: The Owner’s Role in Successful Outcomes
McCarthy Holdings, Inc.
 
Introduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsIntroduction to cost management & control in construction projects
Introduction to cost management & control in construction projects
Essam Lotffy, PMP®, CCP®
 
Lecture 06 project_cost_management
Lecture 06 project_cost_managementLecture 06 project_cost_management
Lecture 06 project_cost_management
Sayed Ahmed
 
Abdul Ghafoor (SQS) ( )
Abdul Ghafoor (SQS) ( )Abdul Ghafoor (SQS) ( )
Abdul Ghafoor (SQS) ( )
Ghafoor Butt
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
Ahmed Elshaboury,PMP,LEED GA
 
04d_Process_Map_Templates-V2.0_(PowerPiont).ppt
04d_Process_Map_Templates-V2.0_(PowerPiont).ppt04d_Process_Map_Templates-V2.0_(PowerPiont).ppt
04d_Process_Map_Templates-V2.0_(PowerPiont).ppt
gmundacat
 
Template-Process-Maps-V2-0-MS-Powerpoint-Format.ppt
Template-Process-Maps-V2-0-MS-Powerpoint-Format.pptTemplate-Process-Maps-V2-0-MS-Powerpoint-Format.ppt
Template-Process-Maps-V2-0-MS-Powerpoint-Format.ppt
ssuser3f4412
 
Template-Process-Maps-V2-0-MS-Powerpoint-Format.ppt
Template-Process-Maps-V2-0-MS-Powerpoint-Format.pptTemplate-Process-Maps-V2-0-MS-Powerpoint-Format.ppt
Template-Process-Maps-V2-0-MS-Powerpoint-Format.ppt
JessDazaOsorio
 

Similar to J.S. Daniel paper for presentation cost management (20)

Learnit buildit-manageit-141124083859-conversion-gate01
Learnit buildit-manageit-141124083859-conversion-gate01Learnit buildit-manageit-141124083859-conversion-gate01
Learnit buildit-manageit-141124083859-conversion-gate01
 
Phases of a Project
Phases of a ProjectPhases of a Project
Phases of a Project
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
 
Project Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge AreaProject Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge Area
 
Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...
 
Ch. 4 Cost Plan.pptx
Ch. 4 Cost Plan.pptxCh. 4 Cost Plan.pptx
Ch. 4 Cost Plan.pptx
 
L06 cost management
L06 cost managementL06 cost management
L06 cost management
 
Rev207 matrixexcelfile
Rev207 matrixexcelfileRev207 matrixexcelfile
Rev207 matrixexcelfile
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost management
 
Construction process
Construction processConstruction process
Construction process
 
Procurement Strategies: A Seminar
Procurement Strategies: A SeminarProcurement Strategies: A Seminar
Procurement Strategies: A Seminar
 
COST MANAGEMENT REPORT
COST MANAGEMENT REPORT COST MANAGEMENT REPORT
COST MANAGEMENT REPORT
 
Design-Build: The Owner’s Role in Successful Outcomes
Design-Build: The Owner’s Role in Successful OutcomesDesign-Build: The Owner’s Role in Successful Outcomes
Design-Build: The Owner’s Role in Successful Outcomes
 
Introduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsIntroduction to cost management & control in construction projects
Introduction to cost management & control in construction projects
 
Lecture 06 project_cost_management
Lecture 06 project_cost_managementLecture 06 project_cost_management
Lecture 06 project_cost_management
 
Abdul Ghafoor (SQS) ( )
Abdul Ghafoor (SQS) ( )Abdul Ghafoor (SQS) ( )
Abdul Ghafoor (SQS) ( )
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
04d_Process_Map_Templates-V2.0_(PowerPiont).ppt
04d_Process_Map_Templates-V2.0_(PowerPiont).ppt04d_Process_Map_Templates-V2.0_(PowerPiont).ppt
04d_Process_Map_Templates-V2.0_(PowerPiont).ppt
 
Template-Process-Maps-V2-0-MS-Powerpoint-Format.ppt
Template-Process-Maps-V2-0-MS-Powerpoint-Format.pptTemplate-Process-Maps-V2-0-MS-Powerpoint-Format.ppt
Template-Process-Maps-V2-0-MS-Powerpoint-Format.ppt
 
Template-Process-Maps-V2-0-MS-Powerpoint-Format.ppt
Template-Process-Maps-V2-0-MS-Powerpoint-Format.pptTemplate-Process-Maps-V2-0-MS-Powerpoint-Format.ppt
Template-Process-Maps-V2-0-MS-Powerpoint-Format.ppt
 

Recently uploaded

❼❷⓿❺❻❷❽❷❼❽ Dpboss Matka Result Satta Matka Guessing Satta Fix jodi Kalyan Fin...
❼❷⓿❺❻❷❽❷❼❽ Dpboss Matka Result Satta Matka Guessing Satta Fix jodi Kalyan Fin...❼❷⓿❺❻❷❽❷❼❽ Dpboss Matka Result Satta Matka Guessing Satta Fix jodi Kalyan Fin...
❼❷⓿❺❻❷❽❷❼❽ Dpboss Matka Result Satta Matka Guessing Satta Fix jodi Kalyan Fin...
❼❷⓿❺❻❷❽❷❼❽ Dpboss Kalyan Satta Matka Guessing Matka Result Main Bazar chart
 
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
my Pandit
 
Industrial Tech SW: Category Renewal and Creation
Industrial Tech SW:  Category Renewal and CreationIndustrial Tech SW:  Category Renewal and Creation
Industrial Tech SW: Category Renewal and Creation
Christian Dahlen
 
Mastering B2B Payments Webinar from BlueSnap
Mastering B2B Payments Webinar from BlueSnapMastering B2B Payments Webinar from BlueSnap
Mastering B2B Payments Webinar from BlueSnap
Norma Mushkat Gaffin
 
Understanding User Needs and Satisfying Them
Understanding User Needs and Satisfying ThemUnderstanding User Needs and Satisfying Them
Understanding User Needs and Satisfying Them
Aggregage
 
3 Simple Steps To Buy Verified Payoneer Account In 2024
3 Simple Steps To Buy Verified Payoneer Account In 20243 Simple Steps To Buy Verified Payoneer Account In 2024
3 Simple Steps To Buy Verified Payoneer Account In 2024
SEOSMMEARTH
 
-- June 2024 is National Volunteer Month --
-- June 2024 is National Volunteer Month ---- June 2024 is National Volunteer Month --
-- June 2024 is National Volunteer Month --
NZSG
 
How to Implement a Strategy: Transform Your Strategy with BSC Designer's Comp...
How to Implement a Strategy: Transform Your Strategy with BSC Designer's Comp...How to Implement a Strategy: Transform Your Strategy with BSC Designer's Comp...
How to Implement a Strategy: Transform Your Strategy with BSC Designer's Comp...
Aleksey Savkin
 
Top mailing list providers in the USA.pptx
Top mailing list providers in the USA.pptxTop mailing list providers in the USA.pptx
Top mailing list providers in the USA.pptx
JeremyPeirce1
 
Income Tax exemption for Start up : Section 80 IAC
Income Tax  exemption for Start up : Section 80 IACIncome Tax  exemption for Start up : Section 80 IAC
Income Tax exemption for Start up : Section 80 IAC
CA Dr. Prithvi Ranjan Parhi
 
Creative Web Design Company in Singapore
Creative Web Design Company in SingaporeCreative Web Design Company in Singapore
Creative Web Design Company in Singapore
techboxsqauremedia
 
BeMetals Investor Presentation_June 1, 2024.pdf
BeMetals Investor Presentation_June 1, 2024.pdfBeMetals Investor Presentation_June 1, 2024.pdf
BeMetals Investor Presentation_June 1, 2024.pdf
DerekIwanaka1
 
Part 2 Deep Dive: Navigating the 2024 Slowdown
Part 2 Deep Dive: Navigating the 2024 SlowdownPart 2 Deep Dive: Navigating the 2024 Slowdown
Part 2 Deep Dive: Navigating the 2024 Slowdown
jeffkluth1
 
Hamster Kombat' Telegram Game Surpasses 100 Million Players—Token Release Sch...
Hamster Kombat' Telegram Game Surpasses 100 Million Players—Token Release Sch...Hamster Kombat' Telegram Game Surpasses 100 Million Players—Token Release Sch...
Hamster Kombat' Telegram Game Surpasses 100 Million Players—Token Release Sch...
SOFTTECHHUB
 
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
Neil Horowitz
 
Creative Web Design Company in Singapore
Creative Web Design Company in SingaporeCreative Web Design Company in Singapore
Creative Web Design Company in Singapore
techboxsqauremedia
 
Lundin Gold Corporate Presentation - June 2024
Lundin Gold Corporate Presentation - June 2024Lundin Gold Corporate Presentation - June 2024
Lundin Gold Corporate Presentation - June 2024
Adnet Communications
 
Digital Marketing with a Focus on Sustainability
Digital Marketing with a Focus on SustainabilityDigital Marketing with a Focus on Sustainability
Digital Marketing with a Focus on Sustainability
sssourabhsharma
 
Organizational Change Leadership Agile Tour Geneve 2024
Organizational Change Leadership Agile Tour Geneve 2024Organizational Change Leadership Agile Tour Geneve 2024
Organizational Change Leadership Agile Tour Geneve 2024
Kirill Klimov
 
一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理
一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理
一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理
taqyea
 

Recently uploaded (20)

❼❷⓿❺❻❷❽❷❼❽ Dpboss Matka Result Satta Matka Guessing Satta Fix jodi Kalyan Fin...
❼❷⓿❺❻❷❽❷❼❽ Dpboss Matka Result Satta Matka Guessing Satta Fix jodi Kalyan Fin...❼❷⓿❺❻❷❽❷❼❽ Dpboss Matka Result Satta Matka Guessing Satta Fix jodi Kalyan Fin...
❼❷⓿❺❻❷❽❷❼❽ Dpboss Matka Result Satta Matka Guessing Satta Fix jodi Kalyan Fin...
 
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
 
Industrial Tech SW: Category Renewal and Creation
Industrial Tech SW:  Category Renewal and CreationIndustrial Tech SW:  Category Renewal and Creation
Industrial Tech SW: Category Renewal and Creation
 
Mastering B2B Payments Webinar from BlueSnap
Mastering B2B Payments Webinar from BlueSnapMastering B2B Payments Webinar from BlueSnap
Mastering B2B Payments Webinar from BlueSnap
 
Understanding User Needs and Satisfying Them
Understanding User Needs and Satisfying ThemUnderstanding User Needs and Satisfying Them
Understanding User Needs and Satisfying Them
 
3 Simple Steps To Buy Verified Payoneer Account In 2024
3 Simple Steps To Buy Verified Payoneer Account In 20243 Simple Steps To Buy Verified Payoneer Account In 2024
3 Simple Steps To Buy Verified Payoneer Account In 2024
 
-- June 2024 is National Volunteer Month --
-- June 2024 is National Volunteer Month ---- June 2024 is National Volunteer Month --
-- June 2024 is National Volunteer Month --
 
How to Implement a Strategy: Transform Your Strategy with BSC Designer's Comp...
How to Implement a Strategy: Transform Your Strategy with BSC Designer's Comp...How to Implement a Strategy: Transform Your Strategy with BSC Designer's Comp...
How to Implement a Strategy: Transform Your Strategy with BSC Designer's Comp...
 
Top mailing list providers in the USA.pptx
Top mailing list providers in the USA.pptxTop mailing list providers in the USA.pptx
Top mailing list providers in the USA.pptx
 
Income Tax exemption for Start up : Section 80 IAC
Income Tax  exemption for Start up : Section 80 IACIncome Tax  exemption for Start up : Section 80 IAC
Income Tax exemption for Start up : Section 80 IAC
 
Creative Web Design Company in Singapore
Creative Web Design Company in SingaporeCreative Web Design Company in Singapore
Creative Web Design Company in Singapore
 
BeMetals Investor Presentation_June 1, 2024.pdf
BeMetals Investor Presentation_June 1, 2024.pdfBeMetals Investor Presentation_June 1, 2024.pdf
BeMetals Investor Presentation_June 1, 2024.pdf
 
Part 2 Deep Dive: Navigating the 2024 Slowdown
Part 2 Deep Dive: Navigating the 2024 SlowdownPart 2 Deep Dive: Navigating the 2024 Slowdown
Part 2 Deep Dive: Navigating the 2024 Slowdown
 
Hamster Kombat' Telegram Game Surpasses 100 Million Players—Token Release Sch...
Hamster Kombat' Telegram Game Surpasses 100 Million Players—Token Release Sch...Hamster Kombat' Telegram Game Surpasses 100 Million Players—Token Release Sch...
Hamster Kombat' Telegram Game Surpasses 100 Million Players—Token Release Sch...
 
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
 
Creative Web Design Company in Singapore
Creative Web Design Company in SingaporeCreative Web Design Company in Singapore
Creative Web Design Company in Singapore
 
Lundin Gold Corporate Presentation - June 2024
Lundin Gold Corporate Presentation - June 2024Lundin Gold Corporate Presentation - June 2024
Lundin Gold Corporate Presentation - June 2024
 
Digital Marketing with a Focus on Sustainability
Digital Marketing with a Focus on SustainabilityDigital Marketing with a Focus on Sustainability
Digital Marketing with a Focus on Sustainability
 
Organizational Change Leadership Agile Tour Geneve 2024
Organizational Change Leadership Agile Tour Geneve 2024Organizational Change Leadership Agile Tour Geneve 2024
Organizational Change Leadership Agile Tour Geneve 2024
 
一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理
一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理
一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理
 

J.S. Daniel paper for presentation cost management

  • 1. The WHY-The WHAT and The HOW? Author: Jihad Daniel
  • 2. WHY Do Cost Management?
  • 3. THE WHY? The Developer aims at developing a Project for the purpose of Financial Gain Before proceeding with the development the Developer will prepare a FEASIBILITY STUDY If Expenditure If Income exceeds exceeds Income Expenditure Project is NOT Project is viable viable Developer employs Architects/Engineers to design his project and a Contractor to built it
  • 4. THE WHY? When preparing the Financial Feasibility Study, the Developer will consider the following prime cost centers: Land Cost-market prices (Purchase of the site) Construction Costs (Cost of the Project) Financial Charges (Institutional Funding) Professional Fees and other costs and charges Disposal Costs (Advertising and selling costs). The Developer only makes his money after completion of the development, i.e. Profit is obtained only after completion of the project and this can take years.
  • 5. THE WHY? It is essential to identify the Cost of Construction at the Feasibility Stage and to ensure that the cost of construction does not substantially vary during the Design Stage-Tender-and on completion of the Construction Stage (Final Account).
  • 7. Example Feasibility Study Proposed Development: 8 story Apartment Building with Penthouse located in Beirut 4 No. Apartments per floor each offering 150m2 of accommodation Common circulation area of 20% net apartment area 1 No. Penthouse on the roof. Factors to Consider: Cost of Land = 475,000 US$ Construction Cost = 4,284,900 US$ Disposal Cost = 238,000 US$ Revenue on Sale = 4,760,000 US$
  • 8. Example Feasibility Study Feasibility of Project: Gross Development Income = 4,760,000 US$ Gross Development Expenditure = 4,998,100 US$ Land Cost = 475,000 US$ Construction Cost = 4,284,900 US$ (@500 US$/m2) Disposal Cost = 238,000 US$ LOSS = 238,100 US$ The Development is NOT FEASIBLE The Professional Role of the Design Team in Making the Project Viable.
  • 9. WHAT Do We Do to Satisfy the WHY?
  • 10. THE WHAT? Cost Variations and their effect on Profit. The Procedures adopted for cost monitoring during different project stages are divided into: Pre-Contract (Design Stage) Post Contract (Construction Stage)
  • 11. THE WHAT? For Pre-Contract (Design Stage): Initial Cost-Feasibility Design Stage (the design is less than 20% complete) a) Feasibility Cost Prediction is based on a Cost Model Design Development Conceptual Design Stage (design stage +/- 20%) b) Conceptual Cost Prediction is based on functional costs/m2 and verifies (a) Preliminary Design Stage (design stage +/- 50%) c) Preliminary Cost Prediction is based on a Cost Plan Elemental Analysis and verifies (a)
  • 12. THE WHAT? For Pre-Contract (Design Stage): cont’ Design Development (cont’) Fundamental Design Stage (design stage +/- 75%) d) Fundamental Cost Prediction is based on the Review of the Cost Plan and verifies (a) Tender Stage Final Design Stage (design stage 100%) e) Final Design Cost Prediction is based on a Priced BOQ and verifies (a)
  • 13. THE WHAT? For Post-Contract (Construction Stage): Contract Forms provide administrative procedures to monitor and limit cost variations/claims arising between the Tender Cost and Final Accounts Costs.
  • 14. HOW We Do WHAT We Do?
  • 15. THE HOW? During the Feasibility Design Stage (Design less than 20% complete) a COST MODEL is used. A Cost Model is data extracted from a similar previous completed project Differences from the Cost Model and Proposed Project are isolated Historical cost data is updated to present day costs BASE DATE accounting for the differences The Cost Model’s modified costs are equated to cost/m2 and then applied to the built-up floor area of the Proposed Project. The Above Procedures provide an Indicative Cost based on cost/m2.
  • 16. THE HOW? During the Conceptual Design Stage (Design +/- 20% complete). Assumptions made at the Feasibility Stage Estimate are verified Elements should be quantified, if possible The estimated total cost should be similar to that already reported. But if there are differences, these should be discussed with the Designer/Developer. The Above Procedures provide an Indicative Cost based on cost/m2 but with more certainty.
  • 17. THE HOW? During the Preliminary Design Stage (Design +/- 50% complete). Design advances to approximate quantification priced at composite unit rates A Cost Plan is prepared The estimated total cost should be similar to that already reported. But if there are differences, these should be discussed with the Designer/Developer.
  • 18. THE HOW? During the Fundamental Design Stage (Design +/- 75% complete). An updated Cost Plan incorporating additional details is prepared The estimated total cost should be similar to that already reported. But if there are differences, these should be discussed with the Designer/Developer. During the Final Design Stage (Design 100% complete). A BOQ is priced using market prices in an attempt to predict tender results (Fair Priced Estimate) The estimated total cost should be similar to that already reported. But if there are differences, these should be discussed with the Designer/Developer.
  • 19. THE HOW? Tender Results-Contractor’s Prices In the event the Tender results differ from the Tender Predications (Priced BOQ), differences should be discussed with the Designer and the Developer. Keeping a Cost Data Base A Data Base of Building Costs is maintained for the purposes of preparing those estimates required by the various design stages. In addition to the Data Base, continuous attention must be made to the various economic conditions arising during extended development and construction programmes and the effect of these conditions on prices.