This curriculum vitae outlines the professional experience of Azwyn Binti Abd. Aziz, a Malaysian civil and structural engineer with over 11 years of experience working on various projects in Malaysia. She has held roles such as project manager, contract holder, and senior engineer on projects in the oil and gas industry and has a Bachelor's Degree in Civil Engineering from the University of Technology Malaysia. The CV lists her qualifications, skills, experience on specific projects, responsibilities, and membership in professional organizations.
Curriculum vitae updated as of 01 April,2017Renilo Ubusan
I am a Civil Engineer by profession. I had worked for twenty two (22) years in the Project Management level, about 11 and a half years in the Philippines, six (6) years in Vietnam, two and a half (2 1/2) years in Mongolia and nearly three (3) years in Macau. Started as a Project Engineer and rose to the rank of a Construction Project Manager through hard work. I believe that even small details of the work has to be taken cared of, putting perfection in all the work that I do.
Curriculum vitae updated as of 01 April,2017Renilo Ubusan
I am a Civil Engineer by profession. I had worked for twenty two (22) years in the Project Management level, about 11 and a half years in the Philippines, six (6) years in Vietnam, two and a half (2 1/2) years in Mongolia and nearly three (3) years in Macau. Started as a Project Engineer and rose to the rank of a Construction Project Manager through hard work. I believe that even small details of the work has to be taken cared of, putting perfection in all the work that I do.
1. Page 1 of 7
Curriculum Vitae
Azwyn Binti Abd. Aziz
C&S Engineer
Date of Birth:
22/02/1982
Nationality:
Malaysian
Education:
University of Technology
Malaysia
- Bachelor of Civil
Engineering – (2005)
Qualifications:
- Bachelor Degree (honor)
2nd
Class Upper
Language Skills:
- English
- Bahasa Malaysia
Contact No.:
- +6012-2827841
Email :
- azwynaziz@gmail.com
Professional Summary
A well-educated engineer with over 11 years of all rounded
experience in the Civil & Structural for various industries.
Graduated with honors from the University of Technology
Malaysia, with a Bachelor Degree in Civil Engineering. Recent
experiences in Oil and Gas industry with Shell MDS and
previously with other companies with projects with local and
international exposure ranging from EPCC engineering design
consultancy (BED, FEED and Detail design), plant
maintenance work, project management including site
supervision experience.
Operated with diversified domain projects in Civil Engineering
ranging from small to medium scale industries which resulted
in depth understanding of how to handle various subject
matter and areas in Civil Engineering efficiently. Handled
multiple critical and challenging projects from design stage to
implementation and ensured that the projects were
implemented as specified in stipulated time with quality and
within allocated budgets with zero LTI.
Well prepared and subject matter experts in different latest
engineering tools and techniques, cost evaluation techniques
and tools which has been applied throughout professional
career to produce cost-effective solutions for each projects
involved.
Excellent ability to handle high pressure environments with
ease and open mind and an awesome team player. Efficient
communication skill to present points precisely to clients and
upper managements.
PROFESSIONAL MEMBERSHIP:
• Board of Engineer, Malaysia. (2006)
• The Institution of Engineers, Malaysia. (2007)
Experience in SHELL MDS (Malaysia) Sdn. Bhd. (Oct 14 – present)
Position: Project Manager CUI Project and Contract Holder
Project Brief : CUI Project is put in place to ensure the plant will still be in operation for
another 20 years reliably and meet SMDS long-term production strategy. Project phase cover
2. Page 2 of 7
the inspection and mitigation work to the related piping and equipment as outline in the
inspection strategy.
Duties and Responsibility;
• Successfully work with civil team to develop the project cost estimation including
the schedule requirement. As a Contract Holder closely work with procurement and
contracting department to develop the contracting strategy with the total contract
value at RM12.4 million. Define the qualification level for the civil including TSA
work with effective bid evaluation and selection. Align with project control team to
ensure budget is sufficient and if an increase to ACV is needed. Manage the PO and
changes, analysis if additional scope/cost occurs.
• Successfully started the online Thermal Sprayed Application (TSA) as part of the
mitigation for CUI Project. Managed stakeholder’s expectation, influent and
affected by the critical progress of the project. Map stakeholder interests against
decision ability and develop action to fit the map. Share an honest point of view and
stayed open minded to other perspectives. Continuously engaged the stakeholder
to ensure project was executed smoothly.
• Clocked 165,100 MH at current project progress of 50% with zero LTI recorded.
Continuously engaging contractor management and site team by conducting
regular HSE Engagement, Stand Down, walk down and rewarded for appreciation.
Guided and trained with zero compromise on safety, ethics and compliance. Lead
by example.
• Reviewed all invoices and claims to confirm that expenses are still within budgetary
guidelines. No Variation Order expected by end of project.
• Achieved and maintained excellent relationship between team members by
effectively managing project team’s responsibility, accountability and
expectations. All of which were laid out at the very beginning. This is important so
the team members are able to deliver what was outline to them at the end of the
project. Support and continuously coach manpower by having regular
engagement, review task and target. Set clear sense of purpose. Swift action and
mitigate any foreseen delay or issues by maintaining resilience under pressure.
• Full involvement in project phase and contributed tosome major decision.
Responsible for work pack approval prior commencement of work including JMS
and JHA. Lead the team on day to day activity including PTW, safety tool box and
walkdown.
Position and Responsibility: Project Manager and Contract Holder for Jetty
Rejuvenation.
Brief : The main objective of the jetty rejuvenation project is to maintain the jetty’s asset
which was to align with the company’s long term business strategy. The scopes were to replace
as in “like for like” replacement for the fixed fender, splash zone beams, retrieve ladder and oil
pit including the underwater inspection which looked for any abnormalities such as cracking,
the extent of the marine growth, corrosion, dented piles, location of the anode (CP) & etc.
Duties and Responsibility
• Primary responsibility was to ensure proper planning from the beginning of the
contract stage valued at RM6.5 mill until the execution of work including contract &
procurement, cost control and schedule management. Adhered to HSSE standards,
3. Page 3 of 7
and delivered projects within budget, schedule and quality requirements.
Responsible for HSSE leadership to drive Goal Zero policy.
• Successfully developed the scope of work based on the Civil Fixed Asset Internal
Review (FAIR) in order to develop contract document for Contract and Procurement
purposes.
• Continuously engaged the stakeholders to ensure all steps were executed smoothly
specifically on the business strategy for shipment schedule which have the direct
impact to the construction schedule activity.
Additional knowledge;
Prior to the above project, attended a basic course on the Marine Facilities Engineering at
Rijswijk, Netherland. The course covers the port layout, navigation, dredging, jetties, mooring
and transfer system. Familiar with the marine facilities component and gain a very useful
knowledge to comply during the project stage.
Position : Lead and Contract Holder, OOS tank inspection & Blasting/painting work in
PTA.
Project Brief : Out of service inspection for tanks and painting work is required in order to
maintain the asset integrity and to prolong the service life of the related equipments. Work
need to be executed during the shutdown as most of the equipment cannot be released online.
Duties and Responsibility
• Primary responsibility was to plan for proper planning from the beginning of the
contract stage all the way to the execution of work including contract &
procurement, cost control and schedule management. Adhered to Shell HSSE
standards, and delivered projects within budget, schedule and quality requirements.
Responsible for HSSE leadership to drive Goal Zero policy.
• Successfully delivered total of RM1.7 million project within the target date including
the additional discovery work which was completed within the stipulated time.
• Project completion with zero LTI recorded. Continuously engage with contractor
management, Stand Down if necessary, walk down and appreciate by reward. Guide
and trained with uncompromising on safety, Ethics and compliance. Lead by
example
Position and Responsibility: Lead for Civil Maintenance CAPEX item
• The primary responsibility was to raise documentation for budgeting purposes for civil
capex and non routine maintenance and to develop work schedule related to the CAPEX
item i.e Jetty rejuvenation, Structures & tank roof replacement, painting/blasting work
and etc.
• Successfully completed the T-8231 structure replacement, painting/blasting for
Chemical shelters, Reactor R-1041/1051/1061 and security house including the T-7061
roof replacement with zero LTI recorded with full involvement in project phase and
responsibled for work pack approval prior commencement of work including JMS and
JHA. Lead the team on day to day activity including PTW and safety tool box.
Other Position and Responsibility: Goal Zero (GZ) Ambassador Lead
• Successfully became the role model for Safety leadership behaviors and act as the
4. Page 4 of 7
change agents by continuously and actively engaging with the GZ members.
• Successfully develop the schedule and identify the tool-box session for the
ambassador together with GZ owner and follow-up by email to ensure the
ambassadors followed the given schedule.
• Working together with HSSE Focal Person to ensure all the GZ findings are
documented and to follow-up to “closed” on the related finding item. Having a good
team of ambassador to further review and analyze the GZ findings and action need to
be taken.
Experience in Toyo Engineering & Construction Sdn. Bhd. (Mar 08 – Sept 14)
EPCC Flare Gas Recovery Unit (FGRU) at Gas Processing Plant Complex A & B, Kerteh,
Terengganu.
Owner – Petronas Gas Berhad
Position & Responsibility : Senior Civil & Structure Engineer
Project Brief : The flare gas recovery unit (FGRU) was designed to capture routine blanketing
gases that goes directly to the flare system. The recovered flare gas to be sent back to gas
processing plant as fuel gas or sales gas. The FGRU reduces the continuous flare operation,
which subsequently reduces the associated smoke, thermal radiation, noise and pollutant
emissions associated with flaring.
• The primary responsibility as Civil lead, leading civil design started from front end
development (Assess, Select & Define phases) to detail design and construction
(Execute phase) including procurement, bill of quantities and schedule management.
Adhered to Petronas HSSE standards, and deliver projects within budget, schedule and
quality requirements. Responsible for HSSE leadership to drive Goal Zero policy.
• Successfully delivered design stage (FEED, Detail Design) meeting project schedule.
100% completion without carry over work to construction by coordination work with
the design firms, ensure deliverables meet the schedule and compliance with the
requirements (Owner, Local Authority and Design Standard);
• Full involvement in the construction phase to solve major/minor issues by raising the
“Field Revision Instruction / Engineering Revision Instruction” related to the design
including updating drawings as per site condition.
• Final acceptance and approval of civil deliverables from the design firm e.g.
specification, plot plan, soil report, structural drawings and etc.
OTHER PROJECT INVOLVED:
• Details Engineering for 24” Benfield Solution System at NH3 Plant.
Owner – Petronas Chemical Fertilizer Kedah Sdn. Bhd.
• Front End Engineering Design (FEED) for Grade Range Extension and Scippy
Expansion (GREASE) Project, Jurong Island, Singapore.
Owner – SHELL Seraya, Singapore.
• EPCC of Bio-Ethanol Production Project, Nusajaya, Johor.
Owner – Malaysian Bio-Xcell Sdn. Bhd
Piling Design for LampsUp-MY Project, Kuantan, Pahang.
Owner LYNAS Malaysian Sdn. Bhd.
5. Page 5 of 7
• Basic Engineering Design (BED) of LampsUp-My Project, Kuantan Pahang.
Owner : Lynas Malaysia Sdn. Bhd.
• EPCC of TITAN TPC2 Heat Exchanger Energy Improvement Project, Pasir
Gudang, Johor
Owner – TITAN Petchem (M) Sdn. Bhd.
EPCC of TITAN TPC2 Liquid Dryer Upgrade Project, Pasir Gudang Johor.
Owner – TITAN Petchem (M) Sdn. Bhd.
EPCC of New Reactor Expansion Project, Klang, Selangor.
Owner – Cosmo Scientex (M) Sdn. Bhd.
EPCC of Post Hydrogenation Project, Kuantan, Pahang
Owner – FPG Oleochemical (M) Sdn. Bhd.
PROPOSAL INVOLVED:
• Engineering, Procurement, Installation and Commissioning (EPIC) For
Hydrogen Recovery unit.
Owner – Petronas Chemicals Ammonia Sdn Bhd.
• Installation of Butadine Column Condenser In BD Plant
Owner – Lotte Chemical Titan (M) Sdn. Bhd.
• Bio-Ethanol Production Proposal, Nusajaya, Johor.
Owner – Malaysian Bio-Xcell Sdn. Bhd.
• TITAN TPC2 Heat Exchanger Energy Improvement Proposal, Pasir Gudang,
Johor
Owner – TITAN Petchem (M) Sdn. Bhd.
TITAN TPC2 Liquid Dryer Upgrade Proposal, Pasir Gudang Johor.
Owner – TITAN Petchem (M) Sdn. Bhd.
Post Hydrogenation Proposal, Kuantan, Pahang.
Owner – FPG Oleochemical (M) Sdn. Bhd.
Work Descriptions
EPCC Project ;
Coordinated with all the other disciplines in order to get civil information for the civil
and structure design of the project;
Coordinated between design firms, monitor the schedule and make sure the design
calculation/drawings are in compliance with the requirements (Owner, Local Authority
and Design Standard);
Assistance to constructions; issued engineering instruction and site supervision;
Prepared the Bill of Quantities (BQ) for civil and structural works;
Maintained and monitored records for incoming and outgoing project documents;
Amended drawings using AUTOCAD software to meet changes and updates when the
need arised during project implementations.
FEED/BED Project ;
6. Page 6 of 7
Studied the proposal/enquiry document received from client to understand the scope of
work.
Carried out Site Survey to confirm FEED design.
Justified and verified the existing structure can cater for the new equipment/loading by
using the existing data and engineering software
Produce the FEED calculations, drawings and specifications in compliance with the
requirements (Owner, Local Authority and Design Standard);
Justified and verified the existing structure can cater for the new equipment/loading by
using the existing data and engineering software
Estimate the Bill of Quantities corresponding to the scope of civil and structural work by
carrying out FEED based on available data.
Proposal Project ;
• Studied the proposal/enquiry document received from client to understand the scope of
work.
• Carried out Site Survey to confirm preliminary design.
• Estimated the Bill of Quantities corresponding to the scope of civil and structures work
by carrying out basic design based on available data and analysing R.C and steel
structures by using STAAD.Pro 2006 software.
• Justified and verified the existing structure can cater for the new equipment/loading by
using the existing data and engineering software (if any)
• Prepared General design specifications (based on BS 8110-1:1997 for RC structure, BS
5950-1:2000 for steel structures or using requirement codes/references from client)
and proposal/standard drawings to be included in the offer to client to explain the basis
of BOQ estimation in a proposal.
• Prepared brief description of various facilities with finishing schedule.
Experience in Sime Enginering Sdn. Bhd. (Sept 06 – Feb 08)
Position : Junior Civil Engineer
Work Description ;
Performed detailed engineering design and preparation of design basis, specification
and material taking-off (MTO) for R.C. and Steel Structures;
Prepared the Bill of Quantities (BQ) for structures and infra. works;
Performed STAAD.Pro 2006 software aided computations to analyse R.C and Steel
Structure;
Produced Design Calculations for R.C. and Steel Structures; familiar with the standard
codes/references applied in the R.C. Structures (BS 8110-1:1997) and Steel Structures
(BS 5950-1:2000);
Maintained and monitored records for incoming and outgoing project documents;
Amended drawings using AUTOCAD software to meet the changes when the need
arises during project implementations.
Involved in basic engineering design for bidding purposes.
Experience in Reinforced Earth Management Services Sdn. Bhd. (Aug 05 – Aug 06)
7. Page 7 of 7
Position : Civil Engineer
Carried out construction design and shop drawings;
Prepared and presented proposals within specified time frame;
Prepared design calculations and drawings for structure-related
sizing/selection;
Undertake Material Take Off (MTO) and Preparation of Bill
Quantities (BQ) for bidding purposes; and
Conducted site visits for ascertaining site conditions