SlideShare a Scribd company logo
1 of 51
Download to read offline
Scheduling, PERT, Critical Path Analysis
1
Network Techniques
Chapter 8
Scheduling, PERT, Critical Path Analysis 2
INTRODUCTION
■ Schedule converts action plan into operating
time table
■ Basis for monitoring and controlling project
■ Scheduling more important in projects than
in production, because unique nature
■ Sometimes customer specified/approved
requirement-e.g: JKR projects
■ Based on Work Breakdown Structure (WBS)
Chapter 8
Scheduling, PERT, Critical Path Analysis 3
NETWORK TECHNIQUES
PERT CPM
-Program Evaluation and
Review Technique
- developed by the US
Navy with Booz
Hamilton Lockheed
- on the Polaris
Missile/Submarine
program 1958
Critical Path Method
Developed by El Dupont
for Chemical Plant
Shutdown Project- about
same time as PERT
✓ Both use same calculations, almost similar
✓ Main difference is probabilistic and deterministic in time estimation
✓ Gantt Chart also used in scheduling
Chapter 8
Scheduling, PERT, Critical Path Analysis 4
■ Graphical portrayal of activities and event
■ Shows dependency relationships between tasks/
activities in a project
■ Clearly shows tasks that must precede
(precedence) or follow (succeeding) other tasks
in a logical manner
■ Clear representation of plan – a powerful tool for
planning and controlling project
NETWORK
Chapter 8
Scheduling, PERT, Critical Path Analysis 5
Example of Simple Network –
Survey
Chapter 8
Scheduling, PERT, Critical Path Analysis 6
Example of Network –
More Complex
Chapter 8
Scheduling, PERT, Critical Path Analysis 7
DEFINITION OF TERMS IN A NETWORK
■ Activity : any portions of project (tasks) which required
by project, uses up resource and consumes
time – may involve labor, paper work,
contractual negotiations, machinery operations Activity
on Arrow (AOA) showed as arrow, AON – Activity on
Node
■ Event : beginning or ending points of one or more
activities, instantaneous point in time, also
called ‘nodes’
■ Network : Combination of all project activities and the events
ACTIVITY
PRECEEDING SUCCESSOR
EVENT
Chapter 8
Scheduling, PERT, Critical Path Analysis 8
Emphasis on Logic in Network Construction
■ Construction of network should be based on logical or
technical dependencies among activities
■ Example - before activity ‘Approve Drawing’ can be
started the activity ‘Prepare Drawing’ must be completed
■ Common error – build network on the basis of time logic
(a feeling for proper sequence ) see example below
WRONG !!!
CORRECT ✓
Chapter 8
Scheduling, PERT, Critical Path Analysis 9
Example 1- A simple network
Consider the list of four activities for making a simple product:
Activity Description Immediate
predecessors
A Buy Plastic Body -
B Design Component -
C Make Component B
D Assemble product A,C
Immediate predecessors for a particular activity are the activities
that, when completed, enable the start of the activity in question.
Chapter 8
Scheduling, PERT, Critical Path Analysis 10
Sequence of activities
■ Can start work on activities A and B anytime, since
neither of these activities depends upon the
completion of prior activities.
■ Activity C cannot be started until activity B has been
completed
■ Activity D cannot be started until both activities A and
C have been completed.
■ The graphical representation (next slide) is referred to
as the PERT/CPM network
Chapter 8
Scheduling, PERT, Critical Path Analysis 11
Network of Four Activities
1 3 4
2
A
B C
D
Arcs indicate project activities
Nodes correspond to the beginning
and ending of activities
Chapter 8
Scheduling, PERT, Critical Path Analysis 12
Example 2
Develop the network for a project with following activities and
immediate predecessors:
Activity Immediate
predecessors
A -
B -
C B
D A, C
E C
F C
G D,E,F
Try to do for the first five (A,B,C,D,E) activities
Chapter 8
Scheduling, PERT, Critical Path Analysis 13
Network of first five activities
1 3 4
2
A
B
C
D
5
E
We need to introduce
a dummy activity
Chapter 8
Scheduling, PERT, Critical Path Analysis 14
•Note how the network correctly identifies D, E, and F as the
immediate predecessors for activity G.
•Dummy activities is used to identify precedence relationships
correctly and to eliminate possible confusion of two or more activities
having the same starting and ending nodes
•Dummy activities have no resources (time, labor, machinery, etc) –
purpose is to PRESERVE LOGIC of the network
Network of Seven Activities
1 3 4
2
A
B
C
D
5
E
7
6
F
G
dummy
Chapter 8
Scheduling, PERT, Critical Path Analysis 15
EXAMPLES OF THE USE OF DUMMYACTIVITY
Dummy
RIGHT ✓
1
1
2
Activity c not required
for e
a
b
c
d
e
a
b
c
d
e
WRONG!
!!
RIGHT
✓
Network concurrent activities
1 2 1
2
3
a
WRONG!!!
a
b
b
WRONG !
RIGHT ✓
Chapter 8
Scheduling, PERT, Critical Path Analysis 16
1 1
2 2
3 3
4
a d
b e
c f
a d
b
e
f
c
WRONG!!! RIGHT!!!
a precedes d.
a and b precede e,
b and c precede f (a does not precede f)
Chapter 8
Scheduling, PERT, Critical Path Analysis 17
Scheduling with activity time
Activity Immediate Completion
predecessors Time (week)
A - 5
B - 6
C A 4
D A 3
E A 1
F E 4
G D,F 14
H B,C 12
I G,H 2
Total …… 51
This information indicates that the total time required to complete activities
is 51 weeks. However, we can see from the network that several of the
activities can be conducted simultaneously (A and B, for example).
Chapter 8
Scheduling, PERT, Critical Path Analysis 18
Earliest start & earliest finish time
■ We are interested in the longest path through the
network, i.e., the critical path.
■ Starting at the network’s origin (node 1) and using a
starting time of 0, we compute an earliest start (ES) and
earliest finish (EF) time for each activity in the network.
■ The expression EF = ES + t can be used to find the earliest
finish time for a given activity.
For example, for activity A, ES = 0 and t = 5; thus the
earliest finish time for activity A is
EF = 0 + 5 = 5
Chapter 8
Scheduling, PERT, Critical Path Analysis 19
Arc with ES & EF time
1
2
A [0,5]
5
Activity
ES = earliest start time
EF = earliest finish time
t = expected activity
time
Chapter 8
Scheduling, PERT, Critical Path Analysis 20
Network with ES & EF time
1
3
4
2
5
7
6
A
[
0
,
5
]
5
B[0,6]
6
C
[
5
,
9
]
4
D[5,8]
3
E[5,6]
1 F[6,10]
4
G
[
1
0
,
2
4
]
1
4
H[9,21]
12
I[24,26]
2
Earliest start time rule:
The earliest start time for an activity leaving a particular node is equal to
the largest of the earliest finish times for all activities entering the node.
Chapter 8
Scheduling, PERT, Critical Path Analysis 21
Activity, duration, ES, EF, LS, LF
2
3
C [5,9]
4 [8,12]
Activity
ES = earliest start time
EF = earliest finish time
LF = latest finish time
LS = latest start time
Chapter 8
Scheduling, PERT, Critical Path Analysis 22
■ To find the critical path we need a backward pass calculation.
■ Starting at the completion point (node 7) and using a latest
finish time (LF) of 26 for activity I, we trace back through the
network computing a latest start (LS) and latest finish time
for each activity
■ The expression LS = LF – t can be used to calculate latest start
time for each activity. For example, for activity I, LF = 26 and t
= 2, thus the latest start time for activity I is
LS = 26 – 2 = 24
Latest start & latest finish time
Chapter 8
Scheduling, PERT, Critical Path Analysis 23
Network with LS & LF time
1
3
4
2
5
7
6
A
[
0
,
5
]
5
[
0
,
5
]
B[0,6]
6[6,12]
C
[
5
,
9
]
4
[
8
,
1
2
]
D[5,8]
3[7,10]
E[5,6]
1[5,6]
F[6,10]
4[6,10]
G
[
1
0
,
2
4
]
1
4
[
1
0
,
2
4
]
H[9,21]
12[12,24]
I[24,26]
2[24,26]
Latest finish time rule:
The latest finish time for an activity entering a particular node is equal to
the smallest of the latest start times for all activities leaving the node.
Chapter 8
Scheduling, PERT, Critical Path Analysis 24
Slack or Free Time or Float
Slack is the length of time an activity can be delayed without affecting the
completion date for the entire project.
For example, slack for C = 3 weeks, i.e Activity C can be delayed up to 3
weeks
(start anywhere between weeks 5 and 8).
ES
5
LS
8
EF
9
LF-EF = 12 –9 =3
LS-ES = 8 – 5 = 3
LF-ES-t = 12-5-4 = 3
EF
12
2
3
C [5,9]
4 [8,12]
Chapter 8
Scheduling, PERT, Critical Path Analysis 25
Activity schedule for our example
Activity Earliest
start (ES)
Latest
start (LS)
Earliest
finish (EF)
Latest
finish (LF)
Slack
(LS-ES)
Critical
path
A 0 0 5 5 0 Yes
B 0 6 6 12 6
C 5 8 9 12 3
D 5 7 8 10 2
E 5 5 6 6 0 Yes
F 6 6 10 10 0 Yes
G 10 10 24 24 0 Yes
H 9 12 21 24 3
I 24 24 26 26 0 Yes
Chapter 8
Scheduling, PERT, Critical Path Analysis 26
IMPORTANT QUESTIONS
■ What is the total time to complete the project?
■ 26 weeks if the individual activities are completed on schedule.
■ What are the scheduled start and completion times for each activity?
■ ES, EF, LS, LF are given for each activity.
■ What activities are critical and must be completed as scheduled in order to
keep the project on time?
■ Critical path activities: A, E, F, G, and I.
■ How long can non-critical activities be delayed before they cause a delay
in the project’s completion time
■ Slack time available for all activities are given.
Chapter 8
Scheduling, PERT, Critical Path Analysis 27
Importance of Float (Slack) and Critical Path
1. Slack or Float shows how much allowance each activity has, i.e how
long it can be delayed without affecting completion date of project
2. Critical path is a sequence of activities from start to finish with zero
slack. Critical activities are activities on the critical path.
3. Critical path identifies the minimum time to complete project
4. If any activity on the critical path is shortened or extended, project
time will be shortened or extended accordingly
Chapter 8
Scheduling, PERT, Critical Path Analysis 28
5. So, a lot of effort should be put in trying to control activities along this path,
so that project can meet due date. If any activity is lengthened, be aware that
project will not meet deadline and some action needs to be taken.
6. If can spend resources to speed up some activity, do so only for critical
activities.
7. Don’t waste resources on non-critical activity, it will not shorten the project
time.
8. If resources can be saved by lengthening some activities, do so for non-
critical activities, up to limit of float.
9. Total Float belongs to the path
Importance of Float (Slack) and Critical Path (cont)
Chapter 8
Scheduling, PERT, Critical Path Analysis 29
PERT For Dealing With Uncertainty
■ So far, times can be estimated with relative certainty, confidence
■ For many situations this is not possible, e.g Research, development,
new products and projects etc.
■ Use 3 time estimates
m= most likely time estimate, mode.
a = optimistic time estimate,
b = pessimistic time estimate, and
Expected Value (TE) = (a + 4m + b) /6
Variance (V) = ( ( b – a) / 6 ) 2
Std Deviation (δ) = SQRT (V)
Chapter 8
Scheduling, PERT, Critical Path Analysis 30
Precedences And Project Activity Times
Immediate Optimistic Most Likely Pessimistic EXP Var S.Dev
Activity Predecessor Time Time Time TE V σ
a - 10 22 22 20 4 2
b - 20 20 20 20 0 0
c - 4 10 16 10 4 2
d a 2 14 32 15 25 5
e b,c 8 8 20 10 4 2
f b,c 8 14 20 14 4 2
g b,c 4 4 4 4 0 0
h c 2 12 16 11 5.4 2.32
I g,h 6 16 38 18 28.4 5.33
j d,e 2 8 14 8 4 2
Chapter 8
Scheduling, PERT, Critical Path Analysis 31
The complete network
2 6
1 3 7
4 5
a
(20,4)
d
(15,25)
e
(10,4)
f
(14,4)
j
(8,4)
i
(18,28.4)
g
(4,0)
h
(11,5.4)
c
(10,4)
b
(20,0)
Chapter 8
Scheduling, PERT, Critical Path Analysis 32
Figure 8-13 The complete Network
2 6
1 3 7
4 5
b
(20,0)
d
(15,25)
e
(10,4)
f
(14,4)
j
(8,4)
i
(18,28.4)
g
(4,0)
h
(11,5.4)
c
(10,4)
CRIT. TIME = 43
EF=20 35
43
24
10
20
a
(20,4)
Chapter 8
Scheduling, PERT, Critical Path Analysis 33
Critical Path Analysis (PERT)
Activity LS ES Slacks Critical ?
a 0 0 0 Yes
b 1 0 1
c 4 0 4
d 20 20 0 Yes
e 25 20 5
f 29 20 9
g 21 20 1
h 14 10 4
i 25 24 1
j 35 35 0 Yes
Chapter 8
Scheduling, PERT, Critical Path Analysis 34
Assume, PM promised to complete the project in the fifty days.
What are the chances of meeting that deadline?
Calculate Z, where
Z = (D-S) / √V
Example,
D = 50; S(Scheduled date) = 20+15+8 =43; V = (4+25+4) =33
Z = (50 – 43) / 5.745
= 1.22 standard deviations.
The probability value of Z = 1.22, is 0.888
1.22
Chapter 8
Scheduling, PERT, Critical Path Analysis 35
What deadline are you 95% sure of meeting
Z value associated with 0.95 is 1.645
D = S + 5.745 (1.645)
= 43 + 9.45
= 52.45 days
Thus, there is a 95 percent chance of finishing the project by 52.45
days.
Chapter 8
Scheduling, PERT, Critical Path Analysis 36
Comparison Between CPM and PERT
CPM PERT
1 Uses network, calculate float or slack,
identify critical path and activities,
guides to monitor and controlling
project
Same as CPM
2 Uses one value of activity time Requires 3 estimates of activity time
Calculates mean and variance of time
3 Used where times can be estimated
with confidence, familiar activities
Used where times cannot be estimated
with confidence.
Unfamiliar or new activities
4 Minimizing cost is more important Meeting time target or estimating
percent completion is more important
5 Example: construction projects,
building one off machines, ships, etc
Example: Involving new activities or
products, research and development
etc
Chapter 8
Scheduling, PERT, Critical Path Analysis 37
BENEFITS OFCPM / PERT NETWORK
Consistent framework for planning, scheduling, monitoring,
and controlling project.
• Shows interdependence of all tasks, work packages, and
work units.
• Helps proper communications between departments and
functions.
• Determines expected project completion date.
• Identifies so-called critical activities, which can delay the
project completion time.
Chapter 8
Scheduling, PERT, Critical Path Analysis 38
• Identified activities with slacks that can be delayed for
specified periods without penalty, or from which resources
may be temporarily borrowed
• Determines the dates on which tasks may be started or must
be started if the project is to stay in schedule.
• Shows which tasks must be coordinated to avoid resource or
timing conflicts.
• Shows which tasks may run in parallel to meet project
completion date
BENEFITS OFCPM / PERT NETWORK (cont.)
Chapter 8
Scheduling, PERT, Critical Path Analysis 39
Gantt Charts
■ Since 1917; Useful for showing work vs time in form of bar charts
e.g.
• Can draw directly or from CPM/PERT network
Chapter 8
Scheduling, PERT, Critical Path Analysis 40
Modified PERT/CPM diagram from network
1
1
1
4
3
3
2
5
7
4
3
6
e
f
a d
b
c dummy
h
0 5 10 15 20 25 30 35 40 45
Legend
[ Scheduled Start
] Scheduled Finish
− Actual Progress
⊗ Unavailable
Λ Current Date
◊ Milestone
Scheduled
♦ Milestone
Achieved
Days
Chapter 8
Scheduling, PERT, Critical Path Analysis 41
GANTT CHART
Chapter 8
Scheduling, PERT, Critical Path Analysis 42
Chapter 8
Scheduling, PERT, Critical Path Analysis 43
Chapter 8
Scheduling, PERT, Critical Path Analysis 44
Gantt Charts and CPM/PERT Networks
Gantt Charts:
■ Even though a lot of info, easy to read and , understand to
monitor and follow progress.
■ Not very good for logical constraints
■ Should be used to COMPLEMENT networks, not replace
Chapter 8
Scheduling, PERT, Critical Path Analysis 45
RESOURCE ANALYSIS AND SCHEDULING
▪ Ability to carry out projects depend on the availability
of resources
▪Analyze resource implication
-How requirements can be met and changes needed
▪Use resources efficiently
▪Use network to give information about time, resources
and cost
Chapter 8
Scheduling, PERT, Critical Path Analysis 46
Activities D, E, F, G and H require fitters.
Construct a bar chart with activities at their EST indicating
person required and total float.
0 5 10 15 20
H
G
F
E
D
4 4 4 4 4 4 4 4 4 4 4 4
2 2 2 2
2 2
2 2 2 2 2 2
2 2 2 2 2 2 2 2
Time
Activity
Add up across all activities to get the total number of men
required.
Chapter 8
Scheduling, PERT, Critical Path Analysis 47
Convert the bar chart to a histogram
Shows: i) Variation from week to week (fitters)
ii) Maximum number of person required (12) during
week 5-6
Examine resource implication.
0 5 10 15 20
1
2
3
4
5
6
7
8
9
10
11
12
13
14
Total
number
of
man
required
Time
Resource analysis before scheduling
Chapter 8
Scheduling, PERT, Critical Path Analysis 48
Example
If only 8 fitters are available at any period during the projects:
New bar chart:
0 5 10 15 20
H
G
F
E
D
4 4 4 4 4 4 4 4 4 4 4 4
2 2 2 2
2 2
2 2 2 2 2 2
2 2 2 2 2 2 2 2
Time
Activity
Chapter 8
Scheduling, PERT, Critical Path Analysis 49
Additional Restriction – no fitters available until the end of
week 5.
Revised Schedule:
0 5 10 15 20
H
G
F
E
D
4 4 4 4 4 4 4 4 4 4 4 4
2 2 2 2
2 2
2 2 2 2 2 2
2 2 2 2 2 2 2 2
Time
Activity
Chapter 8
Scheduling, PERT, Critical Path Analysis 50
Resource constraints relates to:
1. Variations in resource requirements
2. Resource availability
Smaller variations:
1. Easier control of the job
2. Better utilization of resources
Big variations:
1. Frequent moving of manpower
2. Require close control
3. Affect efficiency
Chapter 8
Scheduling, PERT, Critical Path Analysis 51
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Total
number
of
man
required
Time
Histogram showing large resource variations
Chapter 8

More Related Content

Similar to Example of Simple Network –.pdf

Programme Evaluation and Review Technique
Programme Evaluation and Review TechniqueProgramme Evaluation and Review Technique
Programme Evaluation and Review TechniqueDrAsifMohammad
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)Debanjan15
 
PERT-CPM.pdf
PERT-CPM.pdfPERT-CPM.pdf
PERT-CPM.pdflimchoy
 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering EconomicsDeepak Paithankar
 
Lec - 3 Construction_Management_Time_Estimation_2014_summer23.pptx
Lec - 3 Construction_Management_Time_Estimation_2014_summer23.pptxLec - 3 Construction_Management_Time_Estimation_2014_summer23.pptx
Lec - 3 Construction_Management_Time_Estimation_2014_summer23.pptxNegeseTeklearegay
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project managementRahul Dubey
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxTecnicoItca
 
PMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersPMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersIIMSE Edu
 
Project Networking Techniques
Project Networking TechniquesProject Networking Techniques
Project Networking TechniquesAaliButt1
 
Lec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesLec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesSAJID ALI RUK
 

Similar to Example of Simple Network –.pdf (16)

Programme Evaluation and Review Technique
Programme Evaluation and Review TechniqueProgramme Evaluation and Review Technique
Programme Evaluation and Review Technique
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
 
PERT-CPM.pdf
PERT-CPM.pdfPERT-CPM.pdf
PERT-CPM.pdf
 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering Economics
 
Lec - 3 Construction_Management_Time_Estimation_2014_summer23.pptx
Lec - 3 Construction_Management_Time_Estimation_2014_summer23.pptxLec - 3 Construction_Management_Time_Estimation_2014_summer23.pptx
Lec - 3 Construction_Management_Time_Estimation_2014_summer23.pptx
 
Pert cpm
Pert cpm Pert cpm
Pert cpm
 
PM-Problems.pptx
PM-Problems.pptxPM-Problems.pptx
PM-Problems.pptx
 
Project management
Project managementProject management
Project management
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptx
 
PMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersPMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For Beginners
 
Project Networking Techniques
Project Networking TechniquesProject Networking Techniques
Project Networking Techniques
 
Lec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesLec 09 network scheduling_techniques
Lec 09 network scheduling_techniques
 
PERT-Overview1.pdf
PERT-Overview1.pdfPERT-Overview1.pdf
PERT-Overview1.pdf
 
cpmpertmy (1)
cpmpertmy (1)cpmpertmy (1)
cpmpertmy (1)
 

More from ssuserc9c6261

Network of first five activities.pdf
Network of first five activities.pdfNetwork of first five activities.pdf
Network of first five activities.pdfssuserc9c6261
 
commercial banks.pdf
commercial banks.pdfcommercial banks.pdf
commercial banks.pdfssuserc9c6261
 
Modified PERT CPM diagram from network.pdf
Modified PERT CPM diagram from network.pdfModified PERT CPM diagram from network.pdf
Modified PERT CPM diagram from network.pdfssuserc9c6261
 
Gantt Charts and CPM PERT Networks–.pdf
Gantt Charts and CPM PERT Networks–.pdfGantt Charts and CPM PERT Networks–.pdf
Gantt Charts and CPM PERT Networks–.pdfssuserc9c6261
 
Slack or Free Time or Float.pdf
Slack or Free Time or Float.pdfSlack or Free Time or Float.pdf
Slack or Free Time or Float.pdfssuserc9c6261
 
Network with ES & EF time.pdf
Network with ES & EF time.pdfNetwork with ES & EF time.pdf
Network with ES & EF time.pdfssuserc9c6261
 
Scheduling with activity time.pdf
Scheduling with activity time.pdfScheduling with activity time.pdf
Scheduling with activity time.pdfssuserc9c6261
 
Network of Seven Activities.pdf
Network of Seven Activities.pdfNetwork of Seven Activities.pdf
Network of Seven Activities.pdfssuserc9c6261
 
EXAMPLES OF THE USE OF DUMMYACTIVITY.pdf
EXAMPLES OF THE USE OF DUMMYACTIVITY.pdfEXAMPLES OF THE USE OF DUMMYACTIVITY.pdf
EXAMPLES OF THE USE OF DUMMYACTIVITY.pdfssuserc9c6261
 
Activity, duration, ES, EF, LS, LF–.pdf
Activity, duration, ES, EF, LS, LF–.pdfActivity, duration, ES, EF, LS, LF–.pdf
Activity, duration, ES, EF, LS, LF–.pdfssuserc9c6261
 
Arc with ES & EF time –.pdf
Arc with ES & EF time –.pdfArc with ES & EF time –.pdf
Arc with ES & EF time –.pdfssuserc9c6261
 
Network of Four Activities.pdf
Network of Four Activities.pdfNetwork of Four Activities.pdf
Network of Four Activities.pdfssuserc9c6261
 
DEFINITION OF TERMS IN A NETWORK.pdf
DEFINITION OF TERMS IN A NETWORK.pdfDEFINITION OF TERMS IN A NETWORK.pdf
DEFINITION OF TERMS IN A NETWORK.pdfssuserc9c6261
 
chapter 8 examples of networks.pdf
chapter 8 examples of networks.pdfchapter 8 examples of networks.pdf
chapter 8 examples of networks.pdfssuserc9c6261
 
Scheduling, PERT, Critical Path Analysis.pdf
Scheduling, PERT, Critical Path Analysis.pdfScheduling, PERT, Critical Path Analysis.pdf
Scheduling, PERT, Critical Path Analysis.pdfssuserc9c6261
 
Strategic Business Plan.pdf
Strategic Business Plan.pdfStrategic Business Plan.pdf
Strategic Business Plan.pdfssuserc9c6261
 
network techniquies.pdf
network techniquies.pdfnetwork techniquies.pdf
network techniquies.pdfssuserc9c6261
 
Marketing-Channel 1-2.ppt
Marketing-Channel 1-2.pptMarketing-Channel 1-2.ppt
Marketing-Channel 1-2.pptssuserc9c6261
 

More from ssuserc9c6261 (20)

Network of first five activities.pdf
Network of first five activities.pdfNetwork of first five activities.pdf
Network of first five activities.pdf
 
commercial banks.pdf
commercial banks.pdfcommercial banks.pdf
commercial banks.pdf
 
Modified PERT CPM diagram from network.pdf
Modified PERT CPM diagram from network.pdfModified PERT CPM diagram from network.pdf
Modified PERT CPM diagram from network.pdf
 
Gantt Charts and CPM PERT Networks–.pdf
Gantt Charts and CPM PERT Networks–.pdfGantt Charts and CPM PERT Networks–.pdf
Gantt Charts and CPM PERT Networks–.pdf
 
Slack or Free Time or Float.pdf
Slack or Free Time or Float.pdfSlack or Free Time or Float.pdf
Slack or Free Time or Float.pdf
 
Network with ES & EF time.pdf
Network with ES & EF time.pdfNetwork with ES & EF time.pdf
Network with ES & EF time.pdf
 
Scheduling with activity time.pdf
Scheduling with activity time.pdfScheduling with activity time.pdf
Scheduling with activity time.pdf
 
Network of Seven Activities.pdf
Network of Seven Activities.pdfNetwork of Seven Activities.pdf
Network of Seven Activities.pdf
 
EXAMPLES OF THE USE OF DUMMYACTIVITY.pdf
EXAMPLES OF THE USE OF DUMMYACTIVITY.pdfEXAMPLES OF THE USE OF DUMMYACTIVITY.pdf
EXAMPLES OF THE USE OF DUMMYACTIVITY.pdf
 
Activity, duration, ES, EF, LS, LF–.pdf
Activity, duration, ES, EF, LS, LF–.pdfActivity, duration, ES, EF, LS, LF–.pdf
Activity, duration, ES, EF, LS, LF–.pdf
 
Arc with ES & EF time –.pdf
Arc with ES & EF time –.pdfArc with ES & EF time –.pdf
Arc with ES & EF time –.pdf
 
Network of Four Activities.pdf
Network of Four Activities.pdfNetwork of Four Activities.pdf
Network of Four Activities.pdf
 
DEFINITION OF TERMS IN A NETWORK.pdf
DEFINITION OF TERMS IN A NETWORK.pdfDEFINITION OF TERMS IN A NETWORK.pdf
DEFINITION OF TERMS IN A NETWORK.pdf
 
chapter 8 examples of networks.pdf
chapter 8 examples of networks.pdfchapter 8 examples of networks.pdf
chapter 8 examples of networks.pdf
 
Scheduling, PERT, Critical Path Analysis.pdf
Scheduling, PERT, Critical Path Analysis.pdfScheduling, PERT, Critical Path Analysis.pdf
Scheduling, PERT, Critical Path Analysis.pdf
 
Strategic Business Plan.pdf
Strategic Business Plan.pdfStrategic Business Plan.pdf
Strategic Business Plan.pdf
 
network techniquies.pdf
network techniquies.pdfnetwork techniquies.pdf
network techniquies.pdf
 
report type .pdf
report type .pdfreport type .pdf
report type .pdf
 
report writing.pdf
report writing.pdfreport writing.pdf
report writing.pdf
 
Marketing-Channel 1-2.ppt
Marketing-Channel 1-2.pptMarketing-Channel 1-2.ppt
Marketing-Channel 1-2.ppt
 

Recently uploaded

毕业文凭制作#回国入职#diploma#degree澳洲弗林德斯大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
毕业文凭制作#回国入职#diploma#degree澳洲弗林德斯大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree 毕业文凭制作#回国入职#diploma#degree澳洲弗林德斯大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
毕业文凭制作#回国入职#diploma#degree澳洲弗林德斯大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree ttt fff
 
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一Fi L
 
2024新版美国旧金山州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
2024新版美国旧金山州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree2024新版美国旧金山州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
2024新版美国旧金山州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degreeyuu sss
 
How to Be Famous in your Field just visit our Site
How to Be Famous in your Field just visit our SiteHow to Be Famous in your Field just visit our Site
How to Be Famous in your Field just visit our Sitegalleryaagency
 
Abu Dhabi Call Girls O58993O4O2 Call Girls in Abu Dhabi`
Abu Dhabi Call Girls O58993O4O2 Call Girls in Abu Dhabi`Abu Dhabi Call Girls O58993O4O2 Call Girls in Abu Dhabi`
Abu Dhabi Call Girls O58993O4O2 Call Girls in Abu Dhabi`dajasot375
 
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
办理学位证(NUS证书)新加坡国立大学毕业证成绩单原版一比一
办理学位证(NUS证书)新加坡国立大学毕业证成绩单原版一比一办理学位证(NUS证书)新加坡国立大学毕业证成绩单原版一比一
办理学位证(NUS证书)新加坡国立大学毕业证成绩单原版一比一Fi L
 
Call In girls Bhikaji Cama Place 🔝 ⇛8377877756 FULL Enjoy Delhi NCR
Call In girls Bhikaji Cama Place 🔝 ⇛8377877756 FULL Enjoy Delhi NCRCall In girls Bhikaji Cama Place 🔝 ⇛8377877756 FULL Enjoy Delhi NCR
Call In girls Bhikaji Cama Place 🔝 ⇛8377877756 FULL Enjoy Delhi NCRdollysharma2066
 
306MTAMount UCLA University Bachelor's Diploma in Social Media
306MTAMount UCLA University Bachelor's Diploma in Social Media306MTAMount UCLA University Bachelor's Diploma in Social Media
306MTAMount UCLA University Bachelor's Diploma in Social MediaD SSS
 
Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Rndexperts
 
Call Girls Aslali 7397865700 Ridhima Hire Me Full Night
Call Girls Aslali 7397865700 Ridhima Hire Me Full NightCall Girls Aslali 7397865700 Ridhima Hire Me Full Night
Call Girls Aslali 7397865700 Ridhima Hire Me Full Nightssuser7cb4ff
 
Call Girls Meghani Nagar 7397865700 Independent Call Girls
Call Girls Meghani Nagar 7397865700  Independent Call GirlsCall Girls Meghani Nagar 7397865700  Independent Call Girls
Call Girls Meghani Nagar 7397865700 Independent Call Girlsssuser7cb4ff
 
PORTAFOLIO 2024_ ANASTASIYA KUDINOVA
PORTAFOLIO   2024_  ANASTASIYA  KUDINOVAPORTAFOLIO   2024_  ANASTASIYA  KUDINOVA
PORTAFOLIO 2024_ ANASTASIYA KUDINOVAAnastasiya Kudinova
 
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCRdollysharma2066
 
办理(USYD毕业证书)澳洲悉尼大学毕业证成绩单原版一比一
办理(USYD毕业证书)澳洲悉尼大学毕业证成绩单原版一比一办理(USYD毕业证书)澳洲悉尼大学毕业证成绩单原版一比一
办理(USYD毕业证书)澳洲悉尼大学毕业证成绩单原版一比一diploma 1
 
定制(RMIT毕业证书)澳洲墨尔本皇家理工大学毕业证成绩单原版一比一
定制(RMIT毕业证书)澳洲墨尔本皇家理工大学毕业证成绩单原版一比一定制(RMIT毕业证书)澳洲墨尔本皇家理工大学毕业证成绩单原版一比一
定制(RMIT毕业证书)澳洲墨尔本皇家理工大学毕业证成绩单原版一比一lvtagr7
 
NATA 2024 SYLLABUS, full syllabus explained in detail
NATA 2024 SYLLABUS, full syllabus explained in detailNATA 2024 SYLLABUS, full syllabus explained in detail
NATA 2024 SYLLABUS, full syllabus explained in detailDesigntroIntroducing
 
Kindergarten Assessment Questions Via LessonUp
Kindergarten Assessment Questions Via LessonUpKindergarten Assessment Questions Via LessonUp
Kindergarten Assessment Questions Via LessonUpmainac1
 
VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130
VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130
VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130Suhani Kapoor
 

Recently uploaded (20)

毕业文凭制作#回国入职#diploma#degree澳洲弗林德斯大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
毕业文凭制作#回国入职#diploma#degree澳洲弗林德斯大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree 毕业文凭制作#回国入职#diploma#degree澳洲弗林德斯大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
毕业文凭制作#回国入职#diploma#degree澳洲弗林德斯大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
 
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一
 
2024新版美国旧金山州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
2024新版美国旧金山州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree2024新版美国旧金山州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
2024新版美国旧金山州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
 
How to Be Famous in your Field just visit our Site
How to Be Famous in your Field just visit our SiteHow to Be Famous in your Field just visit our Site
How to Be Famous in your Field just visit our Site
 
Abu Dhabi Call Girls O58993O4O2 Call Girls in Abu Dhabi`
Abu Dhabi Call Girls O58993O4O2 Call Girls in Abu Dhabi`Abu Dhabi Call Girls O58993O4O2 Call Girls in Abu Dhabi`
Abu Dhabi Call Girls O58993O4O2 Call Girls in Abu Dhabi`
 
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
办理学位证(NUS证书)新加坡国立大学毕业证成绩单原版一比一
办理学位证(NUS证书)新加坡国立大学毕业证成绩单原版一比一办理学位证(NUS证书)新加坡国立大学毕业证成绩单原版一比一
办理学位证(NUS证书)新加坡国立大学毕业证成绩单原版一比一
 
Call In girls Bhikaji Cama Place 🔝 ⇛8377877756 FULL Enjoy Delhi NCR
Call In girls Bhikaji Cama Place 🔝 ⇛8377877756 FULL Enjoy Delhi NCRCall In girls Bhikaji Cama Place 🔝 ⇛8377877756 FULL Enjoy Delhi NCR
Call In girls Bhikaji Cama Place 🔝 ⇛8377877756 FULL Enjoy Delhi NCR
 
306MTAMount UCLA University Bachelor's Diploma in Social Media
306MTAMount UCLA University Bachelor's Diploma in Social Media306MTAMount UCLA University Bachelor's Diploma in Social Media
306MTAMount UCLA University Bachelor's Diploma in Social Media
 
Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025
 
Call Girls Aslali 7397865700 Ridhima Hire Me Full Night
Call Girls Aslali 7397865700 Ridhima Hire Me Full NightCall Girls Aslali 7397865700 Ridhima Hire Me Full Night
Call Girls Aslali 7397865700 Ridhima Hire Me Full Night
 
Call Girls Meghani Nagar 7397865700 Independent Call Girls
Call Girls Meghani Nagar 7397865700  Independent Call GirlsCall Girls Meghani Nagar 7397865700  Independent Call Girls
Call Girls Meghani Nagar 7397865700 Independent Call Girls
 
PORTAFOLIO 2024_ ANASTASIYA KUDINOVA
PORTAFOLIO   2024_  ANASTASIYA  KUDINOVAPORTAFOLIO   2024_  ANASTASIYA  KUDINOVA
PORTAFOLIO 2024_ ANASTASIYA KUDINOVA
 
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR
 
办理(USYD毕业证书)澳洲悉尼大学毕业证成绩单原版一比一
办理(USYD毕业证书)澳洲悉尼大学毕业证成绩单原版一比一办理(USYD毕业证书)澳洲悉尼大学毕业证成绩单原版一比一
办理(USYD毕业证书)澳洲悉尼大学毕业证成绩单原版一比一
 
定制(RMIT毕业证书)澳洲墨尔本皇家理工大学毕业证成绩单原版一比一
定制(RMIT毕业证书)澳洲墨尔本皇家理工大学毕业证成绩单原版一比一定制(RMIT毕业证书)澳洲墨尔本皇家理工大学毕业证成绩单原版一比一
定制(RMIT毕业证书)澳洲墨尔本皇家理工大学毕业证成绩单原版一比一
 
NATA 2024 SYLLABUS, full syllabus explained in detail
NATA 2024 SYLLABUS, full syllabus explained in detailNATA 2024 SYLLABUS, full syllabus explained in detail
NATA 2024 SYLLABUS, full syllabus explained in detail
 
Call Girls in Pratap Nagar, 9953056974 Escort Service
Call Girls in Pratap Nagar,  9953056974 Escort ServiceCall Girls in Pratap Nagar,  9953056974 Escort Service
Call Girls in Pratap Nagar, 9953056974 Escort Service
 
Kindergarten Assessment Questions Via LessonUp
Kindergarten Assessment Questions Via LessonUpKindergarten Assessment Questions Via LessonUp
Kindergarten Assessment Questions Via LessonUp
 
VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130
VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130
VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130
 

Example of Simple Network –.pdf

  • 1. Scheduling, PERT, Critical Path Analysis 1 Network Techniques Chapter 8
  • 2. Scheduling, PERT, Critical Path Analysis 2 INTRODUCTION ■ Schedule converts action plan into operating time table ■ Basis for monitoring and controlling project ■ Scheduling more important in projects than in production, because unique nature ■ Sometimes customer specified/approved requirement-e.g: JKR projects ■ Based on Work Breakdown Structure (WBS) Chapter 8
  • 3. Scheduling, PERT, Critical Path Analysis 3 NETWORK TECHNIQUES PERT CPM -Program Evaluation and Review Technique - developed by the US Navy with Booz Hamilton Lockheed - on the Polaris Missile/Submarine program 1958 Critical Path Method Developed by El Dupont for Chemical Plant Shutdown Project- about same time as PERT ✓ Both use same calculations, almost similar ✓ Main difference is probabilistic and deterministic in time estimation ✓ Gantt Chart also used in scheduling Chapter 8
  • 4. Scheduling, PERT, Critical Path Analysis 4 ■ Graphical portrayal of activities and event ■ Shows dependency relationships between tasks/ activities in a project ■ Clearly shows tasks that must precede (precedence) or follow (succeeding) other tasks in a logical manner ■ Clear representation of plan – a powerful tool for planning and controlling project NETWORK Chapter 8
  • 5. Scheduling, PERT, Critical Path Analysis 5 Example of Simple Network – Survey Chapter 8
  • 6. Scheduling, PERT, Critical Path Analysis 6 Example of Network – More Complex Chapter 8
  • 7. Scheduling, PERT, Critical Path Analysis 7 DEFINITION OF TERMS IN A NETWORK ■ Activity : any portions of project (tasks) which required by project, uses up resource and consumes time – may involve labor, paper work, contractual negotiations, machinery operations Activity on Arrow (AOA) showed as arrow, AON – Activity on Node ■ Event : beginning or ending points of one or more activities, instantaneous point in time, also called ‘nodes’ ■ Network : Combination of all project activities and the events ACTIVITY PRECEEDING SUCCESSOR EVENT Chapter 8
  • 8. Scheduling, PERT, Critical Path Analysis 8 Emphasis on Logic in Network Construction ■ Construction of network should be based on logical or technical dependencies among activities ■ Example - before activity ‘Approve Drawing’ can be started the activity ‘Prepare Drawing’ must be completed ■ Common error – build network on the basis of time logic (a feeling for proper sequence ) see example below WRONG !!! CORRECT ✓ Chapter 8
  • 9. Scheduling, PERT, Critical Path Analysis 9 Example 1- A simple network Consider the list of four activities for making a simple product: Activity Description Immediate predecessors A Buy Plastic Body - B Design Component - C Make Component B D Assemble product A,C Immediate predecessors for a particular activity are the activities that, when completed, enable the start of the activity in question. Chapter 8
  • 10. Scheduling, PERT, Critical Path Analysis 10 Sequence of activities ■ Can start work on activities A and B anytime, since neither of these activities depends upon the completion of prior activities. ■ Activity C cannot be started until activity B has been completed ■ Activity D cannot be started until both activities A and C have been completed. ■ The graphical representation (next slide) is referred to as the PERT/CPM network Chapter 8
  • 11. Scheduling, PERT, Critical Path Analysis 11 Network of Four Activities 1 3 4 2 A B C D Arcs indicate project activities Nodes correspond to the beginning and ending of activities Chapter 8
  • 12. Scheduling, PERT, Critical Path Analysis 12 Example 2 Develop the network for a project with following activities and immediate predecessors: Activity Immediate predecessors A - B - C B D A, C E C F C G D,E,F Try to do for the first five (A,B,C,D,E) activities Chapter 8
  • 13. Scheduling, PERT, Critical Path Analysis 13 Network of first five activities 1 3 4 2 A B C D 5 E We need to introduce a dummy activity Chapter 8
  • 14. Scheduling, PERT, Critical Path Analysis 14 •Note how the network correctly identifies D, E, and F as the immediate predecessors for activity G. •Dummy activities is used to identify precedence relationships correctly and to eliminate possible confusion of two or more activities having the same starting and ending nodes •Dummy activities have no resources (time, labor, machinery, etc) – purpose is to PRESERVE LOGIC of the network Network of Seven Activities 1 3 4 2 A B C D 5 E 7 6 F G dummy Chapter 8
  • 15. Scheduling, PERT, Critical Path Analysis 15 EXAMPLES OF THE USE OF DUMMYACTIVITY Dummy RIGHT ✓ 1 1 2 Activity c not required for e a b c d e a b c d e WRONG! !! RIGHT ✓ Network concurrent activities 1 2 1 2 3 a WRONG!!! a b b WRONG ! RIGHT ✓ Chapter 8
  • 16. Scheduling, PERT, Critical Path Analysis 16 1 1 2 2 3 3 4 a d b e c f a d b e f c WRONG!!! RIGHT!!! a precedes d. a and b precede e, b and c precede f (a does not precede f) Chapter 8
  • 17. Scheduling, PERT, Critical Path Analysis 17 Scheduling with activity time Activity Immediate Completion predecessors Time (week) A - 5 B - 6 C A 4 D A 3 E A 1 F E 4 G D,F 14 H B,C 12 I G,H 2 Total …… 51 This information indicates that the total time required to complete activities is 51 weeks. However, we can see from the network that several of the activities can be conducted simultaneously (A and B, for example). Chapter 8
  • 18. Scheduling, PERT, Critical Path Analysis 18 Earliest start & earliest finish time ■ We are interested in the longest path through the network, i.e., the critical path. ■ Starting at the network’s origin (node 1) and using a starting time of 0, we compute an earliest start (ES) and earliest finish (EF) time for each activity in the network. ■ The expression EF = ES + t can be used to find the earliest finish time for a given activity. For example, for activity A, ES = 0 and t = 5; thus the earliest finish time for activity A is EF = 0 + 5 = 5 Chapter 8
  • 19. Scheduling, PERT, Critical Path Analysis 19 Arc with ES & EF time 1 2 A [0,5] 5 Activity ES = earliest start time EF = earliest finish time t = expected activity time Chapter 8
  • 20. Scheduling, PERT, Critical Path Analysis 20 Network with ES & EF time 1 3 4 2 5 7 6 A [ 0 , 5 ] 5 B[0,6] 6 C [ 5 , 9 ] 4 D[5,8] 3 E[5,6] 1 F[6,10] 4 G [ 1 0 , 2 4 ] 1 4 H[9,21] 12 I[24,26] 2 Earliest start time rule: The earliest start time for an activity leaving a particular node is equal to the largest of the earliest finish times for all activities entering the node. Chapter 8
  • 21. Scheduling, PERT, Critical Path Analysis 21 Activity, duration, ES, EF, LS, LF 2 3 C [5,9] 4 [8,12] Activity ES = earliest start time EF = earliest finish time LF = latest finish time LS = latest start time Chapter 8
  • 22. Scheduling, PERT, Critical Path Analysis 22 ■ To find the critical path we need a backward pass calculation. ■ Starting at the completion point (node 7) and using a latest finish time (LF) of 26 for activity I, we trace back through the network computing a latest start (LS) and latest finish time for each activity ■ The expression LS = LF – t can be used to calculate latest start time for each activity. For example, for activity I, LF = 26 and t = 2, thus the latest start time for activity I is LS = 26 – 2 = 24 Latest start & latest finish time Chapter 8
  • 23. Scheduling, PERT, Critical Path Analysis 23 Network with LS & LF time 1 3 4 2 5 7 6 A [ 0 , 5 ] 5 [ 0 , 5 ] B[0,6] 6[6,12] C [ 5 , 9 ] 4 [ 8 , 1 2 ] D[5,8] 3[7,10] E[5,6] 1[5,6] F[6,10] 4[6,10] G [ 1 0 , 2 4 ] 1 4 [ 1 0 , 2 4 ] H[9,21] 12[12,24] I[24,26] 2[24,26] Latest finish time rule: The latest finish time for an activity entering a particular node is equal to the smallest of the latest start times for all activities leaving the node. Chapter 8
  • 24. Scheduling, PERT, Critical Path Analysis 24 Slack or Free Time or Float Slack is the length of time an activity can be delayed without affecting the completion date for the entire project. For example, slack for C = 3 weeks, i.e Activity C can be delayed up to 3 weeks (start anywhere between weeks 5 and 8). ES 5 LS 8 EF 9 LF-EF = 12 –9 =3 LS-ES = 8 – 5 = 3 LF-ES-t = 12-5-4 = 3 EF 12 2 3 C [5,9] 4 [8,12] Chapter 8
  • 25. Scheduling, PERT, Critical Path Analysis 25 Activity schedule for our example Activity Earliest start (ES) Latest start (LS) Earliest finish (EF) Latest finish (LF) Slack (LS-ES) Critical path A 0 0 5 5 0 Yes B 0 6 6 12 6 C 5 8 9 12 3 D 5 7 8 10 2 E 5 5 6 6 0 Yes F 6 6 10 10 0 Yes G 10 10 24 24 0 Yes H 9 12 21 24 3 I 24 24 26 26 0 Yes Chapter 8
  • 26. Scheduling, PERT, Critical Path Analysis 26 IMPORTANT QUESTIONS ■ What is the total time to complete the project? ■ 26 weeks if the individual activities are completed on schedule. ■ What are the scheduled start and completion times for each activity? ■ ES, EF, LS, LF are given for each activity. ■ What activities are critical and must be completed as scheduled in order to keep the project on time? ■ Critical path activities: A, E, F, G, and I. ■ How long can non-critical activities be delayed before they cause a delay in the project’s completion time ■ Slack time available for all activities are given. Chapter 8
  • 27. Scheduling, PERT, Critical Path Analysis 27 Importance of Float (Slack) and Critical Path 1. Slack or Float shows how much allowance each activity has, i.e how long it can be delayed without affecting completion date of project 2. Critical path is a sequence of activities from start to finish with zero slack. Critical activities are activities on the critical path. 3. Critical path identifies the minimum time to complete project 4. If any activity on the critical path is shortened or extended, project time will be shortened or extended accordingly Chapter 8
  • 28. Scheduling, PERT, Critical Path Analysis 28 5. So, a lot of effort should be put in trying to control activities along this path, so that project can meet due date. If any activity is lengthened, be aware that project will not meet deadline and some action needs to be taken. 6. If can spend resources to speed up some activity, do so only for critical activities. 7. Don’t waste resources on non-critical activity, it will not shorten the project time. 8. If resources can be saved by lengthening some activities, do so for non- critical activities, up to limit of float. 9. Total Float belongs to the path Importance of Float (Slack) and Critical Path (cont) Chapter 8
  • 29. Scheduling, PERT, Critical Path Analysis 29 PERT For Dealing With Uncertainty ■ So far, times can be estimated with relative certainty, confidence ■ For many situations this is not possible, e.g Research, development, new products and projects etc. ■ Use 3 time estimates m= most likely time estimate, mode. a = optimistic time estimate, b = pessimistic time estimate, and Expected Value (TE) = (a + 4m + b) /6 Variance (V) = ( ( b – a) / 6 ) 2 Std Deviation (δ) = SQRT (V) Chapter 8
  • 30. Scheduling, PERT, Critical Path Analysis 30 Precedences And Project Activity Times Immediate Optimistic Most Likely Pessimistic EXP Var S.Dev Activity Predecessor Time Time Time TE V σ a - 10 22 22 20 4 2 b - 20 20 20 20 0 0 c - 4 10 16 10 4 2 d a 2 14 32 15 25 5 e b,c 8 8 20 10 4 2 f b,c 8 14 20 14 4 2 g b,c 4 4 4 4 0 0 h c 2 12 16 11 5.4 2.32 I g,h 6 16 38 18 28.4 5.33 j d,e 2 8 14 8 4 2 Chapter 8
  • 31. Scheduling, PERT, Critical Path Analysis 31 The complete network 2 6 1 3 7 4 5 a (20,4) d (15,25) e (10,4) f (14,4) j (8,4) i (18,28.4) g (4,0) h (11,5.4) c (10,4) b (20,0) Chapter 8
  • 32. Scheduling, PERT, Critical Path Analysis 32 Figure 8-13 The complete Network 2 6 1 3 7 4 5 b (20,0) d (15,25) e (10,4) f (14,4) j (8,4) i (18,28.4) g (4,0) h (11,5.4) c (10,4) CRIT. TIME = 43 EF=20 35 43 24 10 20 a (20,4) Chapter 8
  • 33. Scheduling, PERT, Critical Path Analysis 33 Critical Path Analysis (PERT) Activity LS ES Slacks Critical ? a 0 0 0 Yes b 1 0 1 c 4 0 4 d 20 20 0 Yes e 25 20 5 f 29 20 9 g 21 20 1 h 14 10 4 i 25 24 1 j 35 35 0 Yes Chapter 8
  • 34. Scheduling, PERT, Critical Path Analysis 34 Assume, PM promised to complete the project in the fifty days. What are the chances of meeting that deadline? Calculate Z, where Z = (D-S) / √V Example, D = 50; S(Scheduled date) = 20+15+8 =43; V = (4+25+4) =33 Z = (50 – 43) / 5.745 = 1.22 standard deviations. The probability value of Z = 1.22, is 0.888 1.22 Chapter 8
  • 35. Scheduling, PERT, Critical Path Analysis 35 What deadline are you 95% sure of meeting Z value associated with 0.95 is 1.645 D = S + 5.745 (1.645) = 43 + 9.45 = 52.45 days Thus, there is a 95 percent chance of finishing the project by 52.45 days. Chapter 8
  • 36. Scheduling, PERT, Critical Path Analysis 36 Comparison Between CPM and PERT CPM PERT 1 Uses network, calculate float or slack, identify critical path and activities, guides to monitor and controlling project Same as CPM 2 Uses one value of activity time Requires 3 estimates of activity time Calculates mean and variance of time 3 Used where times can be estimated with confidence, familiar activities Used where times cannot be estimated with confidence. Unfamiliar or new activities 4 Minimizing cost is more important Meeting time target or estimating percent completion is more important 5 Example: construction projects, building one off machines, ships, etc Example: Involving new activities or products, research and development etc Chapter 8
  • 37. Scheduling, PERT, Critical Path Analysis 37 BENEFITS OFCPM / PERT NETWORK Consistent framework for planning, scheduling, monitoring, and controlling project. • Shows interdependence of all tasks, work packages, and work units. • Helps proper communications between departments and functions. • Determines expected project completion date. • Identifies so-called critical activities, which can delay the project completion time. Chapter 8
  • 38. Scheduling, PERT, Critical Path Analysis 38 • Identified activities with slacks that can be delayed for specified periods without penalty, or from which resources may be temporarily borrowed • Determines the dates on which tasks may be started or must be started if the project is to stay in schedule. • Shows which tasks must be coordinated to avoid resource or timing conflicts. • Shows which tasks may run in parallel to meet project completion date BENEFITS OFCPM / PERT NETWORK (cont.) Chapter 8
  • 39. Scheduling, PERT, Critical Path Analysis 39 Gantt Charts ■ Since 1917; Useful for showing work vs time in form of bar charts e.g. • Can draw directly or from CPM/PERT network Chapter 8
  • 40. Scheduling, PERT, Critical Path Analysis 40 Modified PERT/CPM diagram from network 1 1 1 4 3 3 2 5 7 4 3 6 e f a d b c dummy h 0 5 10 15 20 25 30 35 40 45 Legend [ Scheduled Start ] Scheduled Finish − Actual Progress ⊗ Unavailable Λ Current Date ◊ Milestone Scheduled ♦ Milestone Achieved Days Chapter 8
  • 41. Scheduling, PERT, Critical Path Analysis 41 GANTT CHART Chapter 8
  • 42. Scheduling, PERT, Critical Path Analysis 42 Chapter 8
  • 43. Scheduling, PERT, Critical Path Analysis 43 Chapter 8
  • 44. Scheduling, PERT, Critical Path Analysis 44 Gantt Charts and CPM/PERT Networks Gantt Charts: ■ Even though a lot of info, easy to read and , understand to monitor and follow progress. ■ Not very good for logical constraints ■ Should be used to COMPLEMENT networks, not replace Chapter 8
  • 45. Scheduling, PERT, Critical Path Analysis 45 RESOURCE ANALYSIS AND SCHEDULING ▪ Ability to carry out projects depend on the availability of resources ▪Analyze resource implication -How requirements can be met and changes needed ▪Use resources efficiently ▪Use network to give information about time, resources and cost Chapter 8
  • 46. Scheduling, PERT, Critical Path Analysis 46 Activities D, E, F, G and H require fitters. Construct a bar chart with activities at their EST indicating person required and total float. 0 5 10 15 20 H G F E D 4 4 4 4 4 4 4 4 4 4 4 4 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 Time Activity Add up across all activities to get the total number of men required. Chapter 8
  • 47. Scheduling, PERT, Critical Path Analysis 47 Convert the bar chart to a histogram Shows: i) Variation from week to week (fitters) ii) Maximum number of person required (12) during week 5-6 Examine resource implication. 0 5 10 15 20 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Total number of man required Time Resource analysis before scheduling Chapter 8
  • 48. Scheduling, PERT, Critical Path Analysis 48 Example If only 8 fitters are available at any period during the projects: New bar chart: 0 5 10 15 20 H G F E D 4 4 4 4 4 4 4 4 4 4 4 4 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 Time Activity Chapter 8
  • 49. Scheduling, PERT, Critical Path Analysis 49 Additional Restriction – no fitters available until the end of week 5. Revised Schedule: 0 5 10 15 20 H G F E D 4 4 4 4 4 4 4 4 4 4 4 4 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 Time Activity Chapter 8
  • 50. Scheduling, PERT, Critical Path Analysis 50 Resource constraints relates to: 1. Variations in resource requirements 2. Resource availability Smaller variations: 1. Easier control of the job 2. Better utilization of resources Big variations: 1. Frequent moving of manpower 2. Require close control 3. Affect efficiency Chapter 8
  • 51. Scheduling, PERT, Critical Path Analysis 51 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 Total number of man required Time Histogram showing large resource variations Chapter 8