SlideShare a Scribd company logo
DoD Metrics Favorable is > 1.0, Unfavorable is < 1.0
Cost Efficiency CPI = Burn Up Status / Actual Cost (BCWP / ACWP)
Schedule Efficiency SPI = Burn Up Status / Release Plan (BCWP / BCWS)
Program Agile Team Estimate @ Completion
ETC = Velocity x Remaining Backlog
EAC = Actual Cost + (Velocity x Remaining Backlog)
Independent Estimate @ Completion #
= ACTUALS TO DATE + [(REMAINING WORK) / (PERFORMANCE FACTOR)]
EACCPI = ACWPCUM + [Remaining Backlog / CPICUM ]
= ACWPCUM + [(BAC – BCWPCUM) / CPICUM ]
EACComposite = ACWPCUM + [Remaining Backlog / (CPICUM * SPICUM)]
= ACWPCUM + [(BAC – BCWPCUM) / (CPICUM * SPICUM)]
To Complete Performance Index (TCPI) = Work Remaining / Cost Remaining
TCPIEAC = Remaining Backlog / (Velocity * Remaining Backlog)
= (BAC – BCWPCUM) / (EAC – ACWPCUM)
PLATINUM CARD
EVM FOR AGILE DEVELOPMENT
MR (for rate impacts, R&O liens)
Cost
Variance
Schedule Variance
(Actual Cost
ACWP Cum)
BURN UP CHART STATUS
(BCWP Cum)
RELEASE PLAN
(BCWS Cum)
$
EAC
Time
Now
Completion
Date
PMB
Total Allocated Budget
BAC
Time
Variances Positive is Favorable, Negative is Unfavorable
Cost Variance CV = Burn Up Status – Actual Cost (BCWP – ACWP)
CV % = (CV / BCWP) * 100
Schedule Variance SV = Burn Up Status – Release Plan (BCWP – BCWS)
SV % = (SV / BCWS) * 100
Variance at Completion VAC = BAC – EAC
VAC % = (VAC / BAC) * 100
ProjectedSlip
REMAINING
BACKLOG
(BCWR Cum)
VELOCITY X
REMAINING BACKLOG
(ETC Cum)
©2015 Lockheed Martin Corporation. All Rights Reserved.
AGILE DEVELOPMENT
EVM HIERARCHY
Agile Terminology
Backlog Collection of user stories the agile team will work on at some point in the future
Burn Up Chart Representation of the amount of user stories completed
Feature Coherent business function or attribute of the product or system. A single feature typically is
implemented through many stories. Features provide the basis for organizing stories
Iteration (Sprint) Time period of fixed length during which the agile development team produces an increment of
completed product
Release Plan Schedule for releasing products into productive use, made up of features and user stories
Stories (User) Small system function with well defined success criteria that can be developed by one team
within one iteration. User stories define the work that must be done to create and deliver a
feature
Story Points Characteristics of a user story; relative size measurement used by agile teams for work product
estimation
Velocity Measures amount of work a team can complete in an iteration, typically in Story Points; used to
measure how long it will take a particular team to deliver future outcomes by extrapolating on the
basis of prior performance
Acronyms
ACWP Actual Cost of Work Performed Cost actually incurred in accomplishing work performed
APC Actual Percent Complete (BCWP) BCWP claiming criteria (completed/planned Story Points )
BAC Budget At Completion Total budget for contract through any given level
BCWP Budgeted Cost for Work Performed Value of completed work in terms of the assigned budget
BCWS Budgeted Cost for Work Scheduled Time-phased Budget Plan for work currently scheduled
CA Control Account Management point for planning/controlling scope/schedule/budget
EAC Estimate At Completion Estimate of total cost for contract through any given level
ETC Estimate To Complete Estimate of total cost for remaining work
MR Management Reserve Budget withheld by PM for unknowns/risk management
PMB Performance Measurement Baseline Contract time-phased budget plan, cost/schedule/technical objectives
PP Planning Package Far-term CA activities not yet defined into Work Packages
SPs Story Points Characteristics of a user story
TAB Total Allocated Budget Sum of all budgets for work on contract
TCPI To Complete Performance Index Efficiency needed from ‘time now’ to achieve the EAC
WP Work Package Near-term, detail-planned activities within a CA
©2015 Lockheed Martin Corporation. All Rights Reserved.

More Related Content

What's hot

Project planning and scheduling
Project planning and schedulingProject planning and scheduling
Project planning and scheduling
adeel hamid
 
Practical Project Cost Control for Large Complex Projects
Practical Project Cost Control for Large Complex ProjectsPractical Project Cost Control for Large Complex Projects
Practical Project Cost Control for Large Complex Projects
Jeremie Averous
 
VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule Analyses
The Vertex Companies, LLC
 
50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Construction KPIs & Dashboards
Construction KPIs & DashboardsConstruction KPIs & Dashboards
Construction KPIs & Dashboards
Mohamed ElSaadany, PMP, CCP, PMI-RMP, SCE-PE
 
A simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementA simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value Management
ProPM Academy
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
Mansoor Shoaib
 
Pmp study-notes
Pmp study-notesPmp study-notes
Pmp study-notes
Krishna Murthy RVN
 
Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEI
Chris Carson
 
Project Controls Framework
Project Controls FrameworkProject Controls Framework
Project Controls FrameworkReuben Gonzales
 
Earned Value Analysis - Basic Concepts
Earned Value Analysis  - Basic ConceptsEarned Value Analysis  - Basic Concepts
Earned Value Analysis - Basic Concepts
Ricardo Viana Vargas
 
Update Delay Analysis
Update Delay AnalysisUpdate Delay Analysis
Update Delay Analysis
Chris Carson
 
Eot claims hr__may2012
Eot claims hr__may2012Eot claims hr__may2012
Eot claims hr__may2012
McLachlan Lister Pty Limited
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
Saqib Raza
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement
ignitetribes
 
Project integration management
Project integration managementProject integration management
Project integration management
Prabudh Dhingra
 
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m magedDelay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
Michael Pink
 
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo
 

What's hot (20)

Project planning and scheduling
Project planning and schedulingProject planning and scheduling
Project planning and scheduling
 
Practical Project Cost Control for Large Complex Projects
Practical Project Cost Control for Large Complex ProjectsPractical Project Cost Control for Large Complex Projects
Practical Project Cost Control for Large Complex Projects
 
VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule Analyses
 
50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only
 
Project Control Process
Project Control ProcessProject Control Process
Project Control Process
 
Construction KPIs & Dashboards
Construction KPIs & DashboardsConstruction KPIs & Dashboards
Construction KPIs & Dashboards
 
A simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementA simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value Management
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Pmp study-notes
Pmp study-notesPmp study-notes
Pmp study-notes
 
Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEI
 
Project Controls Framework
Project Controls FrameworkProject Controls Framework
Project Controls Framework
 
Earned Value Analysis - Basic Concepts
Earned Value Analysis  - Basic ConceptsEarned Value Analysis  - Basic Concepts
Earned Value Analysis - Basic Concepts
 
Update Delay Analysis
Update Delay AnalysisUpdate Delay Analysis
Update Delay Analysis
 
Eot claims hr__may2012
Eot claims hr__may2012Eot claims hr__may2012
Eot claims hr__may2012
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement
 
Project integration management
Project integration managementProject integration management
Project integration management
 
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m magedDelay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
 
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
 

Viewers also liked

Economicx
EconomicxEconomicx
Economicx
victor okoth
 
El entorno
El entornoEl entorno
The micronutrient paradigm
The micronutrient paradigmThe micronutrient paradigm
The micronutrient paradigm
Osouan
 
Lessons from major rail infrastructure programmes
Lessons from major rail infrastructure programmesLessons from major rail infrastructure programmes
Lessons from major rail infrastructure programmes
Association for Project Management
 
Znameniti lyudi nashogo_krayu
Znameniti lyudi nashogo_krayuZnameniti lyudi nashogo_krayu
Znameniti lyudi nashogo_krayu
kysia1995
 
presentasion de informatica
presentasion de informaticapresentasion de informatica
presentasion de informatica
jazbekziitha5915
 
So you think you need a PMO presentation SWWE 11th February 2016
So you think you need a PMO presentation SWWE 11th February 2016So you think you need a PMO presentation SWWE 11th February 2016
So you think you need a PMO presentation SWWE 11th February 2016
Association for Project Management
 
Bim presentation Belfast 13th September 2016
Bim   presentation Belfast 13th September 2016Bim   presentation Belfast 13th September 2016
Bim presentation Belfast 13th September 2016
Association for Project Management
 
9th.bces.conference.program.2011.07.06.1
9th.bces.conference.program.2011.07.06.19th.bces.conference.program.2011.07.06.1
9th.bces.conference.program.2011.07.06.1Wikus Geyer
 
Knowledge Management Case Study
Knowledge Management Case StudyKnowledge Management Case Study
Knowledge Management Case StudyRobert Leach
 
Un problema de crítica textual
Un problema de crítica textualUn problema de crítica textual
Un problema de crítica textual
Maria de la Paz Carbonari
 
A midsummer night's dream
A midsummer night's dreamA midsummer night's dream
A midsummer night's dream
Richard Perelonia
 
Word2Vec Neologdで作るアニメ人工知能
Word2Vec Neologdで作るアニメ人工知能Word2Vec Neologdで作るアニメ人工知能
Word2Vec Neologdで作るアニメ人工知能
Junichi Noda
 
8th Grade Registration Night PowerPoint
8th Grade Registration Night PowerPoint8th Grade Registration Night PowerPoint
8th Grade Registration Night PowerPoint
Andy Lombardo
 
Current recommendations for internal parasite control in small ruminants
Current recommendations for internal parasite control in small ruminantsCurrent recommendations for internal parasite control in small ruminants
Current recommendations for internal parasite control in small ruminants
University of Maryland Extension Small Ruminant Program
 
Facilities for Small-Scale Goat Farms
Facilities for Small-Scale Goat FarmsFacilities for Small-Scale Goat Farms
Facilities for Small-Scale Goat Farms
University of Maryland Extension Small Ruminant Program
 
Building business relationships Benefits through Collaboration
Building business relationships Benefits through CollaborationBuilding business relationships Benefits through Collaboration
Building business relationships Benefits through Collaboration
Association for Project Management
 
モチコン
モチコンモチコン
モチコン
omoshirokayac
 

Viewers also liked (18)

Economicx
EconomicxEconomicx
Economicx
 
El entorno
El entornoEl entorno
El entorno
 
The micronutrient paradigm
The micronutrient paradigmThe micronutrient paradigm
The micronutrient paradigm
 
Lessons from major rail infrastructure programmes
Lessons from major rail infrastructure programmesLessons from major rail infrastructure programmes
Lessons from major rail infrastructure programmes
 
Znameniti lyudi nashogo_krayu
Znameniti lyudi nashogo_krayuZnameniti lyudi nashogo_krayu
Znameniti lyudi nashogo_krayu
 
presentasion de informatica
presentasion de informaticapresentasion de informatica
presentasion de informatica
 
So you think you need a PMO presentation SWWE 11th February 2016
So you think you need a PMO presentation SWWE 11th February 2016So you think you need a PMO presentation SWWE 11th February 2016
So you think you need a PMO presentation SWWE 11th February 2016
 
Bim presentation Belfast 13th September 2016
Bim   presentation Belfast 13th September 2016Bim   presentation Belfast 13th September 2016
Bim presentation Belfast 13th September 2016
 
9th.bces.conference.program.2011.07.06.1
9th.bces.conference.program.2011.07.06.19th.bces.conference.program.2011.07.06.1
9th.bces.conference.program.2011.07.06.1
 
Knowledge Management Case Study
Knowledge Management Case StudyKnowledge Management Case Study
Knowledge Management Case Study
 
Un problema de crítica textual
Un problema de crítica textualUn problema de crítica textual
Un problema de crítica textual
 
A midsummer night's dream
A midsummer night's dreamA midsummer night's dream
A midsummer night's dream
 
Word2Vec Neologdで作るアニメ人工知能
Word2Vec Neologdで作るアニメ人工知能Word2Vec Neologdで作るアニメ人工知能
Word2Vec Neologdで作るアニメ人工知能
 
8th Grade Registration Night PowerPoint
8th Grade Registration Night PowerPoint8th Grade Registration Night PowerPoint
8th Grade Registration Night PowerPoint
 
Current recommendations for internal parasite control in small ruminants
Current recommendations for internal parasite control in small ruminantsCurrent recommendations for internal parasite control in small ruminants
Current recommendations for internal parasite control in small ruminants
 
Facilities for Small-Scale Goat Farms
Facilities for Small-Scale Goat FarmsFacilities for Small-Scale Goat Farms
Facilities for Small-Scale Goat Farms
 
Building business relationships Benefits through Collaboration
Building business relationships Benefits through CollaborationBuilding business relationships Benefits through Collaboration
Building business relationships Benefits through Collaboration
 
モチコン
モチコンモチコン
モチコン
 

Similar to Platinum card for agile ev mr4

Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
Russell Taylor BEng CEng FAPM FIET
 
Evm Basics
Evm BasicsEvm Basics
Evm Basicsgfbreaux
 
PM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfPM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdf
Najm Naqvi
 
Cost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdfCost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdf
Nabeel Ahmad
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value Management
Baroness PM
 
Top Metrics for Agile @Agile NCR2011
Top Metrics for Agile @Agile NCR2011Top Metrics for Agile @Agile NCR2011
Top Metrics for Agile @Agile NCR2011Priyank Pathak
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost managementejlp12
 
Nasa+evm+reference+card nov+2015
Nasa+evm+reference+card nov+2015Nasa+evm+reference+card nov+2015
Nasa+evm+reference+card nov+2015
Dr Ezzat Mansour
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
sagarlesley
 
EVMS Gold Card
EVMS Gold CardEVMS Gold Card
EVMS Gold Card
Rusmin Nuryadin
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.ppt
RedhaElhuni
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updatedShraddha PMP
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
Dhamo daran
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
Ahmed Rami Elsherif, PMP, ITBMC
 
dfgd
dfgddfgd
dfgd
pisal3
 
EVA - Metrics.ppt
EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.ppt
NivethaSampath3
 
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Tipsographic . com
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-control
eidalin95
 

Similar to Platinum card for agile ev mr4 (20)

Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Evm Basics
Evm BasicsEvm Basics
Evm Basics
 
PM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfPM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdf
 
Cost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdfCost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdf
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value Management
 
Top Metrics for Agile @Agile NCR2011
Top Metrics for Agile @Agile NCR2011Top Metrics for Agile @Agile NCR2011
Top Metrics for Agile @Agile NCR2011
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost management
 
Schulte
SchulteSchulte
Schulte
 
Nasa+evm+reference+card nov+2015
Nasa+evm+reference+card nov+2015Nasa+evm+reference+card nov+2015
Nasa+evm+reference+card nov+2015
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
 
EVMS Gold Card
EVMS Gold CardEVMS Gold Card
EVMS Gold Card
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.ppt
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updated
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
dfgd
dfgddfgd
dfgd
 
EVA - Metrics.ppt
EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.ppt
 
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-control
 

More from Association for Project Management

Including Mental Health Support in Project Delivery, 14 May.pdf
Including Mental Health Support in Project Delivery, 14 May.pdfIncluding Mental Health Support in Project Delivery, 14 May.pdf
Including Mental Health Support in Project Delivery, 14 May.pdf
Association for Project Management
 
Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...
Association for Project Management
 
Spatium Project Simulation student brief
Spatium Project Simulation student briefSpatium Project Simulation student brief
Spatium Project Simulation student brief
Association for Project Management
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
Association for Project Management
 
Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...
Association for Project Management
 
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
Association for Project Management
 
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Association for Project Management
 
The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...
Association for Project Management
 
Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...
Association for Project Management
 
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Association for Project Management
 
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Association for Project Management
 
Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024
Association for Project Management
 
APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...
Association for Project Management
 
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
Association for Project Management
 
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Association for Project Management
 
Staurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptxStaurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptx
Association for Project Management
 
If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?
Association for Project Management
 
AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...
Association for Project Management
 
Katharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainabilityKatharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainability
Association for Project Management
 
The silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutionsThe silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutions
Association for Project Management
 

More from Association for Project Management (20)

Including Mental Health Support in Project Delivery, 14 May.pdf
Including Mental Health Support in Project Delivery, 14 May.pdfIncluding Mental Health Support in Project Delivery, 14 May.pdf
Including Mental Health Support in Project Delivery, 14 May.pdf
 
Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...
 
Spatium Project Simulation student brief
Spatium Project Simulation student briefSpatium Project Simulation student brief
Spatium Project Simulation student brief
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...
 
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
 
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
 
The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...
 
Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...
 
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
 
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
 
Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024
 
APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...
 
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
 
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
 
Staurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptxStaurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptx
 
If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?
 
AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...
 
Katharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainabilityKatharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainability
 
The silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutionsThe silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutions
 

Recently uploaded

Exploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social DreamingExploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social Dreaming
Nicola Wreford-Howard
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
Cynthia Clay
 
chapter 10 - excise tax of transfer and business taxation
chapter 10 - excise tax of transfer and business taxationchapter 10 - excise tax of transfer and business taxation
chapter 10 - excise tax of transfer and business taxation
AUDIJEAngelo
 
Lookback Analysis
Lookback AnalysisLookback Analysis
Lookback Analysis
Safe PaaS
 
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deckPitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
HajeJanKamps
 
Skye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto AirportSkye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto Airport
marketingjdass
 
Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111
zoyaansari11365
 
April 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products NewsletterApril 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products Newsletter
NathanBaughman3
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
Workforce Group
 
Project File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdfProject File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdf
RajPriye
 
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-indiafalcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
Falcon Invoice Discounting
 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
Operational Excellence Consulting
 
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Navpack & Print
 
What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
seoforlegalpillers
 
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
BBPMedia1
 
Role of Remote Sensing and Monitoring in Mining
Role of Remote Sensing and Monitoring in MiningRole of Remote Sensing and Monitoring in Mining
Role of Remote Sensing and Monitoring in Mining
Naaraayani Minerals Pvt.Ltd
 
Filing Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed GuideFiling Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed Guide
YourLegal Accounting
 
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
PaulBryant58
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
ofm712785
 
The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...
awaisafdar
 

Recently uploaded (20)

Exploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social DreamingExploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social Dreaming
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
chapter 10 - excise tax of transfer and business taxation
chapter 10 - excise tax of transfer and business taxationchapter 10 - excise tax of transfer and business taxation
chapter 10 - excise tax of transfer and business taxation
 
Lookback Analysis
Lookback AnalysisLookback Analysis
Lookback Analysis
 
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deckPitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
 
Skye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto AirportSkye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto Airport
 
Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111
 
April 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products NewsletterApril 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products Newsletter
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
 
Project File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdfProject File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdf
 
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-indiafalcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
 
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
 
What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
 
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
 
Role of Remote Sensing and Monitoring in Mining
Role of Remote Sensing and Monitoring in MiningRole of Remote Sensing and Monitoring in Mining
Role of Remote Sensing and Monitoring in Mining
 
Filing Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed GuideFiling Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed Guide
 
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
 
The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...
 

Platinum card for agile ev mr4

  • 1. DoD Metrics Favorable is > 1.0, Unfavorable is < 1.0 Cost Efficiency CPI = Burn Up Status / Actual Cost (BCWP / ACWP) Schedule Efficiency SPI = Burn Up Status / Release Plan (BCWP / BCWS) Program Agile Team Estimate @ Completion ETC = Velocity x Remaining Backlog EAC = Actual Cost + (Velocity x Remaining Backlog) Independent Estimate @ Completion # = ACTUALS TO DATE + [(REMAINING WORK) / (PERFORMANCE FACTOR)] EACCPI = ACWPCUM + [Remaining Backlog / CPICUM ] = ACWPCUM + [(BAC – BCWPCUM) / CPICUM ] EACComposite = ACWPCUM + [Remaining Backlog / (CPICUM * SPICUM)] = ACWPCUM + [(BAC – BCWPCUM) / (CPICUM * SPICUM)] To Complete Performance Index (TCPI) = Work Remaining / Cost Remaining TCPIEAC = Remaining Backlog / (Velocity * Remaining Backlog) = (BAC – BCWPCUM) / (EAC – ACWPCUM) PLATINUM CARD EVM FOR AGILE DEVELOPMENT MR (for rate impacts, R&O liens) Cost Variance Schedule Variance (Actual Cost ACWP Cum) BURN UP CHART STATUS (BCWP Cum) RELEASE PLAN (BCWS Cum) $ EAC Time Now Completion Date PMB Total Allocated Budget BAC Time Variances Positive is Favorable, Negative is Unfavorable Cost Variance CV = Burn Up Status – Actual Cost (BCWP – ACWP) CV % = (CV / BCWP) * 100 Schedule Variance SV = Burn Up Status – Release Plan (BCWP – BCWS) SV % = (SV / BCWS) * 100 Variance at Completion VAC = BAC – EAC VAC % = (VAC / BAC) * 100 ProjectedSlip REMAINING BACKLOG (BCWR Cum) VELOCITY X REMAINING BACKLOG (ETC Cum) ©2015 Lockheed Martin Corporation. All Rights Reserved. AGILE DEVELOPMENT EVM HIERARCHY Agile Terminology Backlog Collection of user stories the agile team will work on at some point in the future Burn Up Chart Representation of the amount of user stories completed Feature Coherent business function or attribute of the product or system. A single feature typically is implemented through many stories. Features provide the basis for organizing stories Iteration (Sprint) Time period of fixed length during which the agile development team produces an increment of completed product Release Plan Schedule for releasing products into productive use, made up of features and user stories Stories (User) Small system function with well defined success criteria that can be developed by one team within one iteration. User stories define the work that must be done to create and deliver a feature Story Points Characteristics of a user story; relative size measurement used by agile teams for work product estimation Velocity Measures amount of work a team can complete in an iteration, typically in Story Points; used to measure how long it will take a particular team to deliver future outcomes by extrapolating on the basis of prior performance Acronyms ACWP Actual Cost of Work Performed Cost actually incurred in accomplishing work performed APC Actual Percent Complete (BCWP) BCWP claiming criteria (completed/planned Story Points ) BAC Budget At Completion Total budget for contract through any given level BCWP Budgeted Cost for Work Performed Value of completed work in terms of the assigned budget BCWS Budgeted Cost for Work Scheduled Time-phased Budget Plan for work currently scheduled CA Control Account Management point for planning/controlling scope/schedule/budget EAC Estimate At Completion Estimate of total cost for contract through any given level ETC Estimate To Complete Estimate of total cost for remaining work MR Management Reserve Budget withheld by PM for unknowns/risk management PMB Performance Measurement Baseline Contract time-phased budget plan, cost/schedule/technical objectives PP Planning Package Far-term CA activities not yet defined into Work Packages SPs Story Points Characteristics of a user story TAB Total Allocated Budget Sum of all budgets for work on contract TCPI To Complete Performance Index Efficiency needed from ‘time now’ to achieve the EAC WP Work Package Near-term, detail-planned activities within a CA ©2015 Lockheed Martin Corporation. All Rights Reserved.