SlideShare a Scribd company logo
DoD TRIPWIRE METRICS   Favorable is > 1.0, Unfavorable is < 1.0 Cost Efficiency  CPI  =  BCWP  /  ACWP Schedule Efficiency  SPI  =  BCWP  /  BCWS VARIANCES   Favorable is Positive, Unfavorable is Negative Cost Variance     CV =  BCWP  –  ACWP CV % = (CV /  BCWP )  * 100  Schedule Variance   SV =  BCWP  –  BCWS SV % = (SV /  BCWS )  *  100 Variance at Completion VAC =  BAC  –  EAC OVERALL STATUS % Schedule  =  ( BCWS CUM   /  BAC)  *  100 % Complete =  ( BCWP CUM   /  BAC)  *  100 % Spent =  ( ACWP CUM   /  BAC)  *  100 CPLI  =  (Critical Path Duration + Float Duration  (to baseline finish) ) / Critical Path Duration CRITICAL PATH LENGTH INDEX (CPLI) (Schedule Metric)   TO COMPLETE PERFORMANCE INDEX (TCPI)  # § TCPI EAC  =  Work Remaining / Cost Remaining = (BAC –  BCWP CUM )   / (EAC –  ACWP CUM ) ESTIMATE AT COMPLETION   # EAC =  Actuals to Date +  [(Remaining Work) / (Efficiency Factor)] EAC CPI =  ACWP CUM   +  [(BAC –  BCWP CUM ) / CPI CUM  ]   =   BAC / CPI CUM   EAC Composite =  ACWP CUM   +  [(BAC –  BCWP CUM ) / (CPI CUM   *  SPI CUM )] #   To Determine a Contract Level TCPI or EAC; You May Replace BAC with TAB §  To Determine the TCPI  BAC or LRE  Replace EAC with either BAC or LRE Earned Value Management ‘ Gold Card’ EVM Home Page =  https://acc.dau.mil/evm   eMail Address:  [email_address] DAU POC: (703) 805-5259 (DSN 655) Revised April 2008 TERMINOLOGY NCC Negotiated Contract Cost Contract price less profit / fee(s) AUW Authorized Unpriced Work Work contractually approved, but not yet negotiated / definitized CBB Contract Budget Base Sum of NCC and AUW OTB Over Target Baseline Sum of CBB and recognized overrun   TAB Total Allocated Budget Sum of all budgets for work on contract = NCC, CBB, or OTB   BAC Budget At Completion Total budget for total contract thru any given level PMB Performance Measurement Baseline Contract time-phased budget plan MR Management Reserve Budget withheld by Ktr PM for unknowns / risk management UB Undistributed Budget Broadly defined activities not yet distributed to CAs  CA Control Account Lowest CWBS element assigned to a single focal   point to plan & control scope / schedule / budget WP Work Package Near-term, detail-planned activities within a CA   PP Planning Package Far-term CA activities not yet defined into WPs BCWS Budgeted Cost for Work Scheduled Value of work planned to be accomplished = PLANNED VALUE BCWP Budgeted Cost for Work Performed Value of work accomplished  = EARNED VALUE ACWP Actual Cost of Work Performed Cost of work accomplished  = ACTUAL COST EAC Estimate At Completion Estimate of total cost for total contract thru any given level; may be generated by Ktr, PMO, DCMA, etc. =  EAC Ktr / PMO / DCMA LRE Latest Revised Estimate Ktr’s EAC or EAC Ktr SLPP Summary Level Planning Package Far-term activities not yet defined into CAs   TCPI To Complete Performance Index Efficiency needed from ‘time now’ to achieve an EAC EVM POLICY: DoDI 5000.2, Table E3.T2 .   EVMS in accordance with ANSI/EIA-748 is required for cost or incentive contracts, subcontracts, intra-government work agreements, & other agreements valued  >   $20M  ( T hen- Yr   $ ). EVMS contracts  >   $50M  ( TY $ ) require that the EVM system be formally validated by the cognizant contracting officer. Additional Guidance in  Defense Acquisition Guidebook and the Earned Value Management Implementation Guide (EVMIG).  EVMS is discouraged on  F irm- F ixed  P rice,  L evel  o f  E ffort, &  T ime  &   M aterial efforts regardless of cost.  EVM CONTRACTING REQUIREMENTS: Non-DoD   FAR Clauses – Solicitation – 52.234-2 (Pre-Award IBR) or 52.234-3 (Post Award IBR)    –   Solicitation & Contract – 52.234-4 DoD(  ≥ $20M) DFAR Clauses - 252.234-7001 for solicitations and 252.234-7002 for solicitations & contracts Contract Performance Report – DI-MGMT-81466A *  5 Formats (WBS, Organization, Baseline, Staffing & Explanation)  Integrated Master Schedule  – DI-MGMT-81650 *  (Mandatory for DoD EVMS contracts) Integrated Baseline Review (IBR)  -  Mandatory for all  EVMS contracts  * See the EVMIG for CPR and IMS tailoring guidance. Management Reserve Work Packages  Planning Packages  OVERRUN  AUW  Control  Accounts  NCC  Undistributed Budget OTB  CBB  TAB Profit / Fees  PMB  Summary Level  Planning Packages  Contract Price   BASELINE EXECUTION INDEX (BEI) (Schedule Metric) BEI  =  # of  Baseline Tasks Actually Completed /  # of Baseline Tasks Scheduled for Completion Management Reserve Cost Variance Schedule Variance ACWP BCWP BCWS $ EAC Time Now Completion  Date PMB TAB BAC time

More Related Content

What's hot

9.2 Estimate Activity Resources
9.2 Estimate Activity Resources9.2 Estimate Activity Resources
9.2 Estimate Activity Resources
DavidMcLachlan1
 
pRIMAVERA - Progress report checklist - Substation
pRIMAVERA - Progress report checklist - SubstationpRIMAVERA - Progress report checklist - Substation
pRIMAVERA - Progress report checklist - SubstationRAMESH PANIGRAHI PMP
 
How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2
Abdelhay Ghanem
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Chapter 07 project cost management
Chapter 07 project cost managementChapter 07 project cost management
Chapter 07 project cost managementghizlanejabri
 
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned Value
Chris Carson
 
ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Pro...
ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Pro...ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Pro...
ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Pro...
Project Controls Expo
 
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessPlanning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Alberto Sanchez
 
Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysis
ADITYA GHUMARE
 
Obe training final
Obe training finalObe training final
Obe training final
ErNITIN3
 
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation SlidesExtension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Asia Master Training آسيا ماسترز للتدريب والتطوير
 
Loading cost in primavera schedule using resources and expenses r01
Loading cost in primavera schedule using resources and expenses r01Loading cost in primavera schedule using resources and expenses r01
Loading cost in primavera schedule using resources and expenses r01
Muhammad Mujahid PMP®, PSP®, SP®, APMC®
 
Introduction to schedule management
Introduction to schedule managementIntroduction to schedule management
Introduction to schedule management
Essam Lotffy, PMP®, CCP®
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
Ahmed Al-Senosy Ph.D(cand),MSc,PMP,RMP
 
Performance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value AnalysisPerformance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value AnalysisDeborah Obasogie
 
PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2
Anand Bobade
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement
ignitetribes
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact Analysis
Chris Carson
 

What's hot (20)

9.2 Estimate Activity Resources
9.2 Estimate Activity Resources9.2 Estimate Activity Resources
9.2 Estimate Activity Resources
 
pRIMAVERA - Progress report checklist - Substation
pRIMAVERA - Progress report checklist - SubstationpRIMAVERA - Progress report checklist - Substation
pRIMAVERA - Progress report checklist - Substation
 
How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
 
Chapter 07 project cost management
Chapter 07 project cost managementChapter 07 project cost management
Chapter 07 project cost management
 
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned Value
 
ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Pro...
ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Pro...ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Pro...
ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Pro...
 
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessPlanning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning Process
 
Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysis
 
Obe training final
Obe training finalObe training final
Obe training final
 
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation SlidesExtension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
 
Loading cost in primavera schedule using resources and expenses r01
Loading cost in primavera schedule using resources and expenses r01Loading cost in primavera schedule using resources and expenses r01
Loading cost in primavera schedule using resources and expenses r01
 
Introduction to schedule management
Introduction to schedule managementIntroduction to schedule management
Introduction to schedule management
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
 
Performance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value AnalysisPerformance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value Analysis
 
Project Control Handbook
Project Control HandbookProject Control Handbook
Project Control Handbook
 
PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact Analysis
 

Viewers also liked

Evms Presentation (July2006)Repro
Evms Presentation (July2006)ReproEvms Presentation (July2006)Repro
Evms Presentation (July2006)Repro
Jim Kendrick
 
Great deals on life insurance for seniors over 65
Great deals on life insurance for seniors over 65Great deals on life insurance for seniors over 65
Great deals on life insurance for seniors over 65
LifeNet Insurance Solutions
 
TDGI New presentation 2016 English Version
TDGI New presentation 2016 English VersionTDGI New presentation 2016 English Version
TDGI New presentation 2016 English Version
TDGI - Tecnologia de Gestão de Imóveis
 
Lapsed policy
Lapsed policyLapsed policy
Lapsed policy
Rohit V Gala
 
Resilency
 Resilency  Resilency
Resilency price56
 
Teradata Demand Chain Management (DCM): Version 4
Teradata Demand Chain Management (DCM): Version 4Teradata Demand Chain Management (DCM): Version 4
Teradata Demand Chain Management (DCM): Version 4
Teradata
 

Viewers also liked (6)

Evms Presentation (July2006)Repro
Evms Presentation (July2006)ReproEvms Presentation (July2006)Repro
Evms Presentation (July2006)Repro
 
Great deals on life insurance for seniors over 65
Great deals on life insurance for seniors over 65Great deals on life insurance for seniors over 65
Great deals on life insurance for seniors over 65
 
TDGI New presentation 2016 English Version
TDGI New presentation 2016 English VersionTDGI New presentation 2016 English Version
TDGI New presentation 2016 English Version
 
Lapsed policy
Lapsed policyLapsed policy
Lapsed policy
 
Resilency
 Resilency  Resilency
Resilency
 
Teradata Demand Chain Management (DCM): Version 4
Teradata Demand Chain Management (DCM): Version 4Teradata Demand Chain Management (DCM): Version 4
Teradata Demand Chain Management (DCM): Version 4
 

Similar to EVMS Gold Card

dfgd
dfgddfgd
dfgd
pisal3
 
Nasa+evm+reference+card nov+2015
Nasa+evm+reference+card nov+2015Nasa+evm+reference+card nov+2015
Nasa+evm+reference+card nov+2015
Dr Ezzat Mansour
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
Russell Taylor BEng CEng FAPM FIET
 
Platinum card for agile ev mr4
Platinum card for agile ev mr4Platinum card for agile ev mr4
Platinum card for agile ev mr4
Association for Project Management
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 
Evm.calculations.Summary sheet
Evm.calculations.Summary sheetEvm.calculations.Summary sheet
Evm.calculations.Summary sheet
Essam Lotffy, PMP®, CCP®
 
Cost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdfCost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdf
Nabeel Ahmad
 
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Tipsographic . com
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.ppt
RedhaElhuni
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value Management
Baroness PM
 
PM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfPM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdf
Najm Naqvi
 
How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)
Glen Alleman
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-control
eidalin95
 
Delivering nothing efficiently
Delivering nothing efficientlyDelivering nothing efficiently
Delivering nothing efficiently
Association for Project Management
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
sagarlesley
 
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
Association for Project Management
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Using Technical Performance Progress
Using Technical Performance ProgressUsing Technical Performance Progress
Using Technical Performance Progress
Glen Alleman
 
CCP_SEC4_Progress and Cost Control
CCP_SEC4_Progress and Cost ControlCCP_SEC4_Progress and Cost Control
CCP_SEC4_Progress and Cost Control
Hisham Haridy MBA, PMP®, RMP®, SP®
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
ProfDrAnbalaganChinn
 

Similar to EVMS Gold Card (20)

dfgd
dfgddfgd
dfgd
 
Nasa+evm+reference+card nov+2015
Nasa+evm+reference+card nov+2015Nasa+evm+reference+card nov+2015
Nasa+evm+reference+card nov+2015
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Platinum card for agile ev mr4
Platinum card for agile ev mr4Platinum card for agile ev mr4
Platinum card for agile ev mr4
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Evm.calculations.Summary sheet
Evm.calculations.Summary sheetEvm.calculations.Summary sheet
Evm.calculations.Summary sheet
 
Cost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdfCost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdf
 
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.ppt
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value Management
 
PM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfPM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdf
 
How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-control
 
Delivering nothing efficiently
Delivering nothing efficientlyDelivering nothing efficiently
Delivering nothing efficiently
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
 
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
 
Using Technical Performance Progress
Using Technical Performance ProgressUsing Technical Performance Progress
Using Technical Performance Progress
 
CCP_SEC4_Progress and Cost Control
CCP_SEC4_Progress and Cost ControlCCP_SEC4_Progress and Cost Control
CCP_SEC4_Progress and Cost Control
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
 

Recently uploaded

Assure Contact Center Experiences for Your Customers With ThousandEyes
Assure Contact Center Experiences for Your Customers With ThousandEyesAssure Contact Center Experiences for Your Customers With ThousandEyes
Assure Contact Center Experiences for Your Customers With ThousandEyes
ThousandEyes
 
A tale of scale & speed: How the US Navy is enabling software delivery from l...
A tale of scale & speed: How the US Navy is enabling software delivery from l...A tale of scale & speed: How the US Navy is enabling software delivery from l...
A tale of scale & speed: How the US Navy is enabling software delivery from l...
sonjaschweigert1
 
Quantum Computing: Current Landscape and the Future Role of APIs
Quantum Computing: Current Landscape and the Future Role of APIsQuantum Computing: Current Landscape and the Future Role of APIs
Quantum Computing: Current Landscape and the Future Role of APIs
Vlad Stirbu
 
Monitoring Java Application Security with JDK Tools and JFR Events
Monitoring Java Application Security with JDK Tools and JFR EventsMonitoring Java Application Security with JDK Tools and JFR Events
Monitoring Java Application Security with JDK Tools and JFR Events
Ana-Maria Mihalceanu
 
Enhancing Performance with Globus and the Science DMZ
Enhancing Performance with Globus and the Science DMZEnhancing Performance with Globus and the Science DMZ
Enhancing Performance with Globus and the Science DMZ
Globus
 
UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4
DianaGray10
 
The Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and SalesThe Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and Sales
Laura Byrne
 
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
Sri Ambati
 
Observability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdf
Observability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdfObservability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdf
Observability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdf
Paige Cruz
 
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
DanBrown980551
 
RESUME BUILDER APPLICATION Project for students
RESUME BUILDER APPLICATION Project for studentsRESUME BUILDER APPLICATION Project for students
RESUME BUILDER APPLICATION Project for students
KAMESHS29
 
Accelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish CachingAccelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish Caching
Thijs Feryn
 
zkStudyClub - Reef: Fast Succinct Non-Interactive Zero-Knowledge Regex Proofs
zkStudyClub - Reef: Fast Succinct Non-Interactive Zero-Knowledge Regex ProofszkStudyClub - Reef: Fast Succinct Non-Interactive Zero-Knowledge Regex Proofs
zkStudyClub - Reef: Fast Succinct Non-Interactive Zero-Knowledge Regex Proofs
Alex Pruden
 
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdfFIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance
 
SAP Sapphire 2024 - ASUG301 building better apps with SAP Fiori.pdf
SAP Sapphire 2024 - ASUG301 building better apps with SAP Fiori.pdfSAP Sapphire 2024 - ASUG301 building better apps with SAP Fiori.pdf
SAP Sapphire 2024 - ASUG301 building better apps with SAP Fiori.pdf
Peter Spielvogel
 
The Metaverse and AI: how can decision-makers harness the Metaverse for their...
The Metaverse and AI: how can decision-makers harness the Metaverse for their...The Metaverse and AI: how can decision-makers harness the Metaverse for their...
The Metaverse and AI: how can decision-makers harness the Metaverse for their...
Jen Stirrup
 
Leading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdfLeading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdf
OnBoard
 
PCI PIN Basics Webinar from the Controlcase Team
PCI PIN Basics Webinar from the Controlcase TeamPCI PIN Basics Webinar from the Controlcase Team
PCI PIN Basics Webinar from the Controlcase Team
ControlCase
 
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance
 
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 previewState of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
Prayukth K V
 

Recently uploaded (20)

Assure Contact Center Experiences for Your Customers With ThousandEyes
Assure Contact Center Experiences for Your Customers With ThousandEyesAssure Contact Center Experiences for Your Customers With ThousandEyes
Assure Contact Center Experiences for Your Customers With ThousandEyes
 
A tale of scale & speed: How the US Navy is enabling software delivery from l...
A tale of scale & speed: How the US Navy is enabling software delivery from l...A tale of scale & speed: How the US Navy is enabling software delivery from l...
A tale of scale & speed: How the US Navy is enabling software delivery from l...
 
Quantum Computing: Current Landscape and the Future Role of APIs
Quantum Computing: Current Landscape and the Future Role of APIsQuantum Computing: Current Landscape and the Future Role of APIs
Quantum Computing: Current Landscape and the Future Role of APIs
 
Monitoring Java Application Security with JDK Tools and JFR Events
Monitoring Java Application Security with JDK Tools and JFR EventsMonitoring Java Application Security with JDK Tools and JFR Events
Monitoring Java Application Security with JDK Tools and JFR Events
 
Enhancing Performance with Globus and the Science DMZ
Enhancing Performance with Globus and the Science DMZEnhancing Performance with Globus and the Science DMZ
Enhancing Performance with Globus and the Science DMZ
 
UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4
 
The Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and SalesThe Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and Sales
 
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
 
Observability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdf
Observability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdfObservability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdf
Observability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdf
 
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
 
RESUME BUILDER APPLICATION Project for students
RESUME BUILDER APPLICATION Project for studentsRESUME BUILDER APPLICATION Project for students
RESUME BUILDER APPLICATION Project for students
 
Accelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish CachingAccelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish Caching
 
zkStudyClub - Reef: Fast Succinct Non-Interactive Zero-Knowledge Regex Proofs
zkStudyClub - Reef: Fast Succinct Non-Interactive Zero-Knowledge Regex ProofszkStudyClub - Reef: Fast Succinct Non-Interactive Zero-Knowledge Regex Proofs
zkStudyClub - Reef: Fast Succinct Non-Interactive Zero-Knowledge Regex Proofs
 
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdfFIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
 
SAP Sapphire 2024 - ASUG301 building better apps with SAP Fiori.pdf
SAP Sapphire 2024 - ASUG301 building better apps with SAP Fiori.pdfSAP Sapphire 2024 - ASUG301 building better apps with SAP Fiori.pdf
SAP Sapphire 2024 - ASUG301 building better apps with SAP Fiori.pdf
 
The Metaverse and AI: how can decision-makers harness the Metaverse for their...
The Metaverse and AI: how can decision-makers harness the Metaverse for their...The Metaverse and AI: how can decision-makers harness the Metaverse for their...
The Metaverse and AI: how can decision-makers harness the Metaverse for their...
 
Leading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdfLeading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdf
 
PCI PIN Basics Webinar from the Controlcase Team
PCI PIN Basics Webinar from the Controlcase TeamPCI PIN Basics Webinar from the Controlcase Team
PCI PIN Basics Webinar from the Controlcase Team
 
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
 
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 previewState of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
 

EVMS Gold Card

  • 1. DoD TRIPWIRE METRICS Favorable is > 1.0, Unfavorable is < 1.0 Cost Efficiency CPI = BCWP / ACWP Schedule Efficiency SPI = BCWP / BCWS VARIANCES Favorable is Positive, Unfavorable is Negative Cost Variance CV = BCWP – ACWP CV % = (CV / BCWP ) * 100 Schedule Variance SV = BCWP – BCWS SV % = (SV / BCWS ) * 100 Variance at Completion VAC = BAC – EAC OVERALL STATUS % Schedule = ( BCWS CUM / BAC) * 100 % Complete = ( BCWP CUM / BAC) * 100 % Spent = ( ACWP CUM / BAC) * 100 CPLI = (Critical Path Duration + Float Duration (to baseline finish) ) / Critical Path Duration CRITICAL PATH LENGTH INDEX (CPLI) (Schedule Metric) TO COMPLETE PERFORMANCE INDEX (TCPI) # § TCPI EAC = Work Remaining / Cost Remaining = (BAC – BCWP CUM ) / (EAC – ACWP CUM ) ESTIMATE AT COMPLETION # EAC = Actuals to Date + [(Remaining Work) / (Efficiency Factor)] EAC CPI = ACWP CUM + [(BAC – BCWP CUM ) / CPI CUM ] = BAC / CPI CUM EAC Composite = ACWP CUM + [(BAC – BCWP CUM ) / (CPI CUM * SPI CUM )] # To Determine a Contract Level TCPI or EAC; You May Replace BAC with TAB § To Determine the TCPI BAC or LRE Replace EAC with either BAC or LRE Earned Value Management ‘ Gold Card’ EVM Home Page = https://acc.dau.mil/evm eMail Address: [email_address] DAU POC: (703) 805-5259 (DSN 655) Revised April 2008 TERMINOLOGY NCC Negotiated Contract Cost Contract price less profit / fee(s) AUW Authorized Unpriced Work Work contractually approved, but not yet negotiated / definitized CBB Contract Budget Base Sum of NCC and AUW OTB Over Target Baseline Sum of CBB and recognized overrun TAB Total Allocated Budget Sum of all budgets for work on contract = NCC, CBB, or OTB BAC Budget At Completion Total budget for total contract thru any given level PMB Performance Measurement Baseline Contract time-phased budget plan MR Management Reserve Budget withheld by Ktr PM for unknowns / risk management UB Undistributed Budget Broadly defined activities not yet distributed to CAs CA Control Account Lowest CWBS element assigned to a single focal point to plan & control scope / schedule / budget WP Work Package Near-term, detail-planned activities within a CA PP Planning Package Far-term CA activities not yet defined into WPs BCWS Budgeted Cost for Work Scheduled Value of work planned to be accomplished = PLANNED VALUE BCWP Budgeted Cost for Work Performed Value of work accomplished = EARNED VALUE ACWP Actual Cost of Work Performed Cost of work accomplished = ACTUAL COST EAC Estimate At Completion Estimate of total cost for total contract thru any given level; may be generated by Ktr, PMO, DCMA, etc. = EAC Ktr / PMO / DCMA LRE Latest Revised Estimate Ktr’s EAC or EAC Ktr SLPP Summary Level Planning Package Far-term activities not yet defined into CAs TCPI To Complete Performance Index Efficiency needed from ‘time now’ to achieve an EAC EVM POLICY: DoDI 5000.2, Table E3.T2 . EVMS in accordance with ANSI/EIA-748 is required for cost or incentive contracts, subcontracts, intra-government work agreements, & other agreements valued > $20M ( T hen- Yr $ ). EVMS contracts > $50M ( TY $ ) require that the EVM system be formally validated by the cognizant contracting officer. Additional Guidance in Defense Acquisition Guidebook and the Earned Value Management Implementation Guide (EVMIG). EVMS is discouraged on F irm- F ixed P rice, L evel o f E ffort, & T ime & M aterial efforts regardless of cost. EVM CONTRACTING REQUIREMENTS: Non-DoD FAR Clauses – Solicitation – 52.234-2 (Pre-Award IBR) or 52.234-3 (Post Award IBR) – Solicitation & Contract – 52.234-4 DoD( ≥ $20M) DFAR Clauses - 252.234-7001 for solicitations and 252.234-7002 for solicitations & contracts Contract Performance Report – DI-MGMT-81466A * 5 Formats (WBS, Organization, Baseline, Staffing & Explanation) Integrated Master Schedule – DI-MGMT-81650 * (Mandatory for DoD EVMS contracts) Integrated Baseline Review (IBR) - Mandatory for all EVMS contracts * See the EVMIG for CPR and IMS tailoring guidance. Management Reserve Work Packages Planning Packages OVERRUN AUW Control Accounts NCC Undistributed Budget OTB CBB TAB Profit / Fees PMB Summary Level Planning Packages Contract Price BASELINE EXECUTION INDEX (BEI) (Schedule Metric) BEI = # of Baseline Tasks Actually Completed / # of Baseline Tasks Scheduled for Completion Management Reserve Cost Variance Schedule Variance ACWP BCWP BCWS $ EAC Time Now Completion Date PMB TAB BAC time