SlideShare a Scribd company logo
Project Monitoring and Control
1
Project Monitoring and Control
 Monitoring – collecting, recording,
and reporting information
concerning project performance
that project manger and others
wish to know
 Controlling – uses data from monitor
activity to bring actual performance
to planned performance
2
Project Monitoring and Control
 Why do we monitor?
 What do we monitor?
 When to we monitor?
 How do we monitor?
3
Why do we monitor?
 Simply because we know that things don’t always go
according to plan (no matter how much we prepare)
 To detect and react appropriately to deviations and
changes to plans
4
What do we monitor?
 Men (human resources)
 Machines
 Materials
 Money
 Space
 Time
 Tasks
 Quality/Technical
Performance
5
What do we monitor?
Inputs
 Time
 Money
 Resources
 Material Usage
 Tasks
 Quality/Technical
Performance
6
Outputs
Progress
Costs
Job starts
Job completion
Engineering / Design
changes
Variation order (VO)
When do we monitor?
 End of the project
 Continuously
 Regularly
 Logically
 While there is still time to react
 As soon as possible
 At task completion
 At pre-planned decision points (milestones)
7
Where do we monitor?
 At head office?
 At the site office?
 On the spot?
 Depends on situation and the ‘whats’
8
How do we monitor
 Through meetings with clients, parties involved in
project (Contractor, supplier,etc.)
 For schedule – Update CPA, PERT Charts, Update Gantt
Charts
 Using Earned Value Analysis
 Calculate Critical Ratios
 Milestones
 Reports
 Tests and inspections
 Delivery or staggered delivery
 PMIS (Project Management Info Sys) Updating
9
Meetings – Some monitoring issues
 What problems do you have and what is being done
to correct them?
 What problems do you anticipate in the future?
 Do you need any resources you do not yet have?
 Do you need information you do not have yet?
 Do you know anything that will give you schedule
difficulties?
 Any possibility your task will finish early/late?
 Will your task be completed under/over/on budget?
10
Project Control Cycle
11
PLAN
Specifications
Project Schedule
Project budget
Resource plan
Vendor contracts MONITOR
Record status
Report progress
Report cost
COMPARE
Actual status
against plan
-Schedule
-Cost
ACTION
Correct
deviations
from plan
RE-PLAN as
necessary
Project Control
 Control – process and activities
needed to correct deviations from
plan
 Control the triple constraints
 time (schedule)
 cost (budget, expenses, etc)
 performance (specifications, testing
results, etc.)
12
Techniques for monitoring and
control
 Earned Value Analysis
 Critical Ratio
13
Earned Value Analysis
 A way of measuring overall performance
(not individual task) is using an aggregate
performance measure - Earned Value
 Earned value of work performed (value
completed) for those tasks in progress
found by multiplying the estimated
percent physical completion of work for
each task by the planned cost for those
tasks. The result is amount that should be
spent on the task so far. This can be
compared with actual amount spent.
14
Earned Value Analysis
 Methods for estimating percent completion
 The 50-50 estimate. 50% is assumed when task is begun, and
remaining 50% when work completed.
 0-100% rule. This rule allows no credit for work until task is
complete, highly conservative rule, project always seem late
until the very end of project when everything appears to
suddenly catch up
 Critical input rule. This rule assigns progress according to
amount of critical input that has been used. Labor or skilled
dependent, machine critical input – buy machine complete
task – may be misinformation
 Proportional rule. This rule divides planned (or actual) time-
to-date by total scheduled time(or budgeted (or actual ) cost-
to-date by total budgeted cast] to calculate percent complete.
This is commonly used rule.
15
Earned Value Analysis
 Refer to earned value chart – basis for
evaluating cost and performance to date
 If total value of the work accomplished is
in balance with the planned (baseline)
cost, and actual cost then top mgmt has
no particular need for a detailed analysis
of individual tasks
 Earned value concept – combines cost
reporting & aggregate performance
reporting into one comprehensive chart
16
Earned Value Analysis
 Baseline cost to completion – referred to as
budget at completion (BAC)
 Actual cost to date – referred to as estimated
cost at completion (EAC)
 Identify several variances according to two
guidelines
1. A negative variance is ‘bad’
2. Cost and schedule variances are calculated as earned
value minus some other measure
17
Earned Value Chart – basis for
evaluating cost & performance to
date
18
Earned Value Analysis -
Variances
 4 types of variances;
 Cost (spending) variance (CV) – difference between
budgeted cost of work performed (earned value)
(BCWP) and actual cost of that work (ACWP)
 Schedule variance (SV) – difference between
earned value (BCWP) and cost of work we scheduled
to perform to date (BCWS)
 Time variance (TV) –difference between time
scheduled for work performed (STWP) and actual
time to perform it (ATWP)
19
Earned Value Variance - Formula
CV = BCWP – ACWP (negative value - cost overrun)
SV = BCWP – BCWS (negative value - behind schedule)
TV = STWP – ATWP (negative value - delay)
Index (Ratios)
Cost Performance Index (CPI) = BCWP/ACWP
Schedule Performance Index (SPI) = BCWP/BCWS
Time Performance Index (TPI) = STWP/ATWP
20
EXAMPLE
Assume that operations on a Work Package cost RM 1,500 to
complete. They were originally scheduled to finish today. At
this point, we actually spent RM1,350. And we estimate that
we have completed two thirds (2/3) of the work. What are the
cost and schedule variances?
CV = BCWP – ACWP = 1500 (2/3) – 1350 = - 350
SV = BCWP – BCWS = 1500 (2/3) – 1500 = - 500
CPI = BCWP/ACWP = 1500(2/3)/1350 = 0.74
SPI = BCWP/BCWS = 1500(2/3)/1500 = 0.67
Spending higher than budget, and given what we have spent,
we are not as far along as we should be (have not completed
as much work as we should have)
21
 Possible to have one of indicators to be favorable while
the other unfavorable
 Might be ahead of schedule and behind costs
 Six possibilities (see figure next slide)
22
6 Possibilities Earned Value Analysis
23
Critical ratio
 Sometimes, especially large projects, it may
be worthwhile calculating a set of critical
ratios for all project activities
 The critical ratio is
actual progress x budgeted cost
scheduled progress actual cost
 If ratio is 1 everything is probably on target
 The further away form 1 the ratio is, the more we
may need to investigate
24
Summary
 Need proper project monitoring and
control mechanisms
 Tools available to help in monitoring
and controlling activities
 There are human control and
management aspects not covered
here
25

More Related Content

What's hot

Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6
Agus Suhanto
 
06. Project Management Process Groups
06. Project Management Process Groups06. Project Management Process Groups
06. Project Management Process Groups
BhuWan Khadka
 
9.2 Estimate Activity Resources
9.2 Estimate Activity Resources9.2 Estimate Activity Resources
9.2 Estimate Activity Resources
DavidMcLachlan1
 
project monitoring and control
project monitoring and controlproject monitoring and control
project monitoring and control
ChandraShekhar Patel
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
PedadaSaikumar
 
Software effort estimation
Software effort estimationSoftware effort estimation
Software effort estimation
tumetr1
 
Primavera P6 Tips and Tricks
Primavera P6 Tips and TricksPrimavera P6 Tips and Tricks
Primavera P6 Tips and Tricks
p6academy
 
Project Integration Management
Project Integration ManagementProject Integration Management
Project Integration Management
pankajsh10
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost managementejlp12
 
Chap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management OverviewChap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management Overview
Anand Bobade
 
Planning and Resourcing a Project
Planning and Resourcing a ProjectPlanning and Resourcing a Project
Planning and Resourcing a Project
Nishant Munjal
 
PMP Training - 04 project integration management
PMP Training - 04 project integration managementPMP Training - 04 project integration management
PMP Training - 04 project integration managementejlp12
 
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
Anand Bobade
 
2_Project Scope Management
2_Project Scope Management2_Project Scope Management
2_Project Scope Management
Hisham Haridy MBA, PMP®, RMP®, SP®
 
Wbs Building Use This
Wbs Building Use ThisWbs Building Use This
Wbs Building Use This
project management
 
Project Time Management
Project Time ManagementProject Time Management
Project Time ManagementSerdar Temiz
 
Introduction to Software Project Management
Introduction to Software Project ManagementIntroduction to Software Project Management
Introduction to Software Project Management
Saadi Jadoon
 

What's hot (20)

Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6
 
06. Project Management Process Groups
06. Project Management Process Groups06. Project Management Process Groups
06. Project Management Process Groups
 
9.2 Estimate Activity Resources
9.2 Estimate Activity Resources9.2 Estimate Activity Resources
9.2 Estimate Activity Resources
 
project monitoring and control
project monitoring and controlproject monitoring and control
project monitoring and control
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
 
Software effort estimation
Software effort estimationSoftware effort estimation
Software effort estimation
 
Primavera P6 Tips and Tricks
Primavera P6 Tips and TricksPrimavera P6 Tips and Tricks
Primavera P6 Tips and Tricks
 
Project Integration Management
Project Integration ManagementProject Integration Management
Project Integration Management
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost management
 
Chap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management OverviewChap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management Overview
 
07 project cost management
07 project cost management07 project cost management
07 project cost management
 
Planning and Resourcing a Project
Planning and Resourcing a ProjectPlanning and Resourcing a Project
Planning and Resourcing a Project
 
PMP Training - 04 project integration management
PMP Training - 04 project integration managementPMP Training - 04 project integration management
PMP Training - 04 project integration management
 
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
 
2_Project Scope Management
2_Project Scope Management2_Project Scope Management
2_Project Scope Management
 
Wbs Building Use This
Wbs Building Use ThisWbs Building Use This
Wbs Building Use This
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Introduction to Software Project Management
Introduction to Software Project ManagementIntroduction to Software Project Management
Introduction to Software Project Management
 

Viewers also liked

Project Controlling and Project Monitoring
Project Controlling and Project MonitoringProject Controlling and Project Monitoring
Project Controlling and Project Monitoringharoldtaylor1113
 
Project monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoringProject monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoring
Sandeep Kumar
 
SDPM - Lecture 7 - Project monitoring and control
SDPM - Lecture 7 - Project monitoring and controlSDPM - Lecture 7 - Project monitoring and control
SDPM - Lecture 7 - Project monitoring and controlOpenLearningLab
 
Monitoring the control
Monitoring the control Monitoring the control
Monitoring the control
north south university
 
Project Monitoring and Control
Project Monitoring and ControlProject Monitoring and Control
Project Monitoring and Control
guy_davis
 
Fundamentals of Project Planning, Scheduling, Monitoring & Control
Fundamentals of Project Planning, Scheduling, Monitoring & ControlFundamentals of Project Planning, Scheduling, Monitoring & Control
Fundamentals of Project Planning, Scheduling, Monitoring & Control
Association for Project Management
 
Project EVE
Project EVEProject EVE
Crictal path identification
Crictal path identificationCrictal path identification
Crictal path identification
Farhana Rehman
 
Business software packages
Business software packagesBusiness software packages
Business software packages
Joel Briza
 
Quality of software
Quality of softwareQuality of software
Quality of software
Palak Pandoh
 
Capability maturity model cmm lecture 8
Capability maturity model cmm lecture 8Capability maturity model cmm lecture 8
Capability maturity model cmm lecture 8Abdul Basit
 
Spm unit iii-risk-monitoring & control1
Spm unit iii-risk-monitoring & control1Spm unit iii-risk-monitoring & control1
Spm unit iii-risk-monitoring & control1
Kanchana Devi
 
PM Session 6
PM Session 6PM Session 6
PM Session 6
dmdk12
 
Project Planning, Monitoring & Control
Project Planning, Monitoring & ControlProject Planning, Monitoring & Control
Project Planning, Monitoring & Control
Pushkar Raj Chandna
 
Modern Software Productivity Measurement: The Pragmatic Guide
Modern Software Productivity Measurement: The Pragmatic GuideModern Software Productivity Measurement: The Pragmatic Guide
Modern Software Productivity Measurement: The Pragmatic Guide
CAST
 
Configuration Management in Software Engineering - SE29
Configuration Management in Software Engineering - SE29Configuration Management in Software Engineering - SE29
Configuration Management in Software Engineering - SE29koolkampus
 
Understanding and improving software productivity
Understanding and improving software productivityUnderstanding and improving software productivity
Understanding and improving software productivityGeorge Valiyaveetil
 
Software configuration management
Software configuration managementSoftware configuration management
Software configuration managementJulia Carolina
 
Lecture 8 monitoring & controlling (1)
Lecture 8  monitoring & controlling (1)Lecture 8  monitoring & controlling (1)
Lecture 8 monitoring & controlling (1)Nur Azwin
 

Viewers also liked (20)

Project Monitoring and Control
Project Monitoring and ControlProject Monitoring and Control
Project Monitoring and Control
 
Project Controlling and Project Monitoring
Project Controlling and Project MonitoringProject Controlling and Project Monitoring
Project Controlling and Project Monitoring
 
Project monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoringProject monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoring
 
SDPM - Lecture 7 - Project monitoring and control
SDPM - Lecture 7 - Project monitoring and controlSDPM - Lecture 7 - Project monitoring and control
SDPM - Lecture 7 - Project monitoring and control
 
Monitoring the control
Monitoring the control Monitoring the control
Monitoring the control
 
Project Monitoring and Control
Project Monitoring and ControlProject Monitoring and Control
Project Monitoring and Control
 
Fundamentals of Project Planning, Scheduling, Monitoring & Control
Fundamentals of Project Planning, Scheduling, Monitoring & ControlFundamentals of Project Planning, Scheduling, Monitoring & Control
Fundamentals of Project Planning, Scheduling, Monitoring & Control
 
Project EVE
Project EVEProject EVE
Project EVE
 
Crictal path identification
Crictal path identificationCrictal path identification
Crictal path identification
 
Business software packages
Business software packagesBusiness software packages
Business software packages
 
Quality of software
Quality of softwareQuality of software
Quality of software
 
Capability maturity model cmm lecture 8
Capability maturity model cmm lecture 8Capability maturity model cmm lecture 8
Capability maturity model cmm lecture 8
 
Spm unit iii-risk-monitoring & control1
Spm unit iii-risk-monitoring & control1Spm unit iii-risk-monitoring & control1
Spm unit iii-risk-monitoring & control1
 
PM Session 6
PM Session 6PM Session 6
PM Session 6
 
Project Planning, Monitoring & Control
Project Planning, Monitoring & ControlProject Planning, Monitoring & Control
Project Planning, Monitoring & Control
 
Modern Software Productivity Measurement: The Pragmatic Guide
Modern Software Productivity Measurement: The Pragmatic GuideModern Software Productivity Measurement: The Pragmatic Guide
Modern Software Productivity Measurement: The Pragmatic Guide
 
Configuration Management in Software Engineering - SE29
Configuration Management in Software Engineering - SE29Configuration Management in Software Engineering - SE29
Configuration Management in Software Engineering - SE29
 
Understanding and improving software productivity
Understanding and improving software productivityUnderstanding and improving software productivity
Understanding and improving software productivity
 
Software configuration management
Software configuration managementSoftware configuration management
Software configuration management
 
Lecture 8 monitoring & controlling (1)
Lecture 8  monitoring & controlling (1)Lecture 8  monitoring & controlling (1)
Lecture 8 monitoring & controlling (1)
 

Similar to 160155061 project-monitoring-control

Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
BECM, RUET, Bangladesh
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part One
Waleed Hamdy Albana
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
waleed hamdy
 
Project monitoring lecture 1
Project monitoring lecture 1Project monitoring lecture 1
Project monitoring lecture 1
BECM, RUET, Bangladesh
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
Dhamo daran
 
Nasa+evm+reference+card nov+2015
Nasa+evm+reference+card nov+2015Nasa+evm+reference+card nov+2015
Nasa+evm+reference+card nov+2015
Dr Ezzat Mansour
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updatedShraddha PMP
 
The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance Management
Craig Brown
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
ProfDrAnbalaganChinn
 
Group 12 - Progress and Performance Measurement and Evaluation.pdf
Group 12 - Progress and Performance Measurement and Evaluation.pdfGroup 12 - Progress and Performance Measurement and Evaluation.pdf
Group 12 - Progress and Performance Measurement and Evaluation.pdf
alvieramada23
 
EVA - Metrics.ppt
EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.ppt
NivethaSampath3
 
Topic 10 - Project Performance Management.pdf
Topic 10 - Project Performance Management.pdfTopic 10 - Project Performance Management.pdf
Topic 10 - Project Performance Management.pdf
HuyNguyen657394
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)
Ejaz Bhatti
 
Pppl evms training_02
Pppl evms training_02Pppl evms training_02
Pppl evms training_02
apocalypto1
 
Performing against the wall - SPI after completion
Performing against the wall - SPI after completionPerforming against the wall - SPI after completion
Performing against the wall - SPI after completion
M Maged Hegazy, LLM, MBA, CCP, P3O
 
L06 cost management
L06 cost managementL06 cost management
L06 cost managementAsa Chan
 
ch10s.ppt
ch10s.pptch10s.ppt
ch10s.ppt
TecnicoItca
 
An introduction to project accounting
An introduction to project accountingAn introduction to project accounting
An introduction to project accounting
Association for Project Management
 
Lecture 5- Monitoring and Controlling Projects.ppt
Lecture 5- Monitoring and Controlling Projects.pptLecture 5- Monitoring and Controlling Projects.ppt
Lecture 5- Monitoring and Controlling Projects.ppt
vitumbikokhoswe1
 

Similar to 160155061 project-monitoring-control (20)

Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part One
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
 
Project monitoring lecture 1
Project monitoring lecture 1Project monitoring lecture 1
Project monitoring lecture 1
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
 
Nasa+evm+reference+card nov+2015
Nasa+evm+reference+card nov+2015Nasa+evm+reference+card nov+2015
Nasa+evm+reference+card nov+2015
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updated
 
The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance Management
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
 
Group 12 - Progress and Performance Measurement and Evaluation.pdf
Group 12 - Progress and Performance Measurement and Evaluation.pdfGroup 12 - Progress and Performance Measurement and Evaluation.pdf
Group 12 - Progress and Performance Measurement and Evaluation.pdf
 
EVA - Metrics.ppt
EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.ppt
 
Topic 10 - Project Performance Management.pdf
Topic 10 - Project Performance Management.pdfTopic 10 - Project Performance Management.pdf
Topic 10 - Project Performance Management.pdf
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)
 
Pppl evms training_02
Pppl evms training_02Pppl evms training_02
Pppl evms training_02
 
Performing against the wall - SPI after completion
Performing against the wall - SPI after completionPerforming against the wall - SPI after completion
Performing against the wall - SPI after completion
 
L06 cost management
L06 cost managementL06 cost management
L06 cost management
 
ch10s.ppt
ch10s.pptch10s.ppt
ch10s.ppt
 
An introduction to project accounting
An introduction to project accountingAn introduction to project accounting
An introduction to project accounting
 
Lecture 5- Monitoring and Controlling Projects.ppt
Lecture 5- Monitoring and Controlling Projects.pptLecture 5- Monitoring and Controlling Projects.ppt
Lecture 5- Monitoring and Controlling Projects.ppt
 

Recently uploaded

Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
MysoreMuleSoftMeetup
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
Atul Kumar Singh
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
Pavel ( NSTU)
 
"Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe..."Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe...
SACHIN R KONDAGURI
 
A Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptxA Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptx
thanhdowork
 
Chapter -12, Antibiotics (One Page Notes).pdf
Chapter -12, Antibiotics (One Page Notes).pdfChapter -12, Antibiotics (One Page Notes).pdf
Chapter -12, Antibiotics (One Page Notes).pdf
Kartik Tiwari
 
Unit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdfUnit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdf
Thiyagu K
 
Natural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama UniversityNatural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama University
Akanksha trivedi rama nursing college kanpur.
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
Celine George
 
A Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in EducationA Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in Education
Peter Windle
 
Normal Labour/ Stages of Labour/ Mechanism of Labour
Normal Labour/ Stages of Labour/ Mechanism of LabourNormal Labour/ Stages of Labour/ Mechanism of Labour
Normal Labour/ Stages of Labour/ Mechanism of Labour
Wasim Ak
 
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Dr. Vinod Kumar Kanvaria
 
Azure Interview Questions and Answers PDF By ScholarHat
Azure Interview Questions and Answers PDF By ScholarHatAzure Interview Questions and Answers PDF By ScholarHat
Azure Interview Questions and Answers PDF By ScholarHat
Scholarhat
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
Celine George
 
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBCSTRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
kimdan468
 
Pride Month Slides 2024 David Douglas School District
Pride Month Slides 2024 David Douglas School DistrictPride Month Slides 2024 David Douglas School District
Pride Month Slides 2024 David Douglas School District
David Douglas School District
 
Lapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdfLapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdf
Jean Carlos Nunes Paixão
 
Embracing GenAI - A Strategic Imperative
Embracing GenAI - A Strategic ImperativeEmbracing GenAI - A Strategic Imperative
Embracing GenAI - A Strategic Imperative
Peter Windle
 
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
Levi Shapiro
 
Acetabularia Information For Class 9 .docx
Acetabularia Information For Class 9  .docxAcetabularia Information For Class 9  .docx
Acetabularia Information For Class 9 .docx
vaibhavrinwa19
 

Recently uploaded (20)

Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
 
"Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe..."Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe...
 
A Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptxA Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptx
 
Chapter -12, Antibiotics (One Page Notes).pdf
Chapter -12, Antibiotics (One Page Notes).pdfChapter -12, Antibiotics (One Page Notes).pdf
Chapter -12, Antibiotics (One Page Notes).pdf
 
Unit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdfUnit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdf
 
Natural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama UniversityNatural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama University
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
 
A Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in EducationA Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in Education
 
Normal Labour/ Stages of Labour/ Mechanism of Labour
Normal Labour/ Stages of Labour/ Mechanism of LabourNormal Labour/ Stages of Labour/ Mechanism of Labour
Normal Labour/ Stages of Labour/ Mechanism of Labour
 
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
 
Azure Interview Questions and Answers PDF By ScholarHat
Azure Interview Questions and Answers PDF By ScholarHatAzure Interview Questions and Answers PDF By ScholarHat
Azure Interview Questions and Answers PDF By ScholarHat
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
 
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBCSTRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
 
Pride Month Slides 2024 David Douglas School District
Pride Month Slides 2024 David Douglas School DistrictPride Month Slides 2024 David Douglas School District
Pride Month Slides 2024 David Douglas School District
 
Lapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdfLapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdf
 
Embracing GenAI - A Strategic Imperative
Embracing GenAI - A Strategic ImperativeEmbracing GenAI - A Strategic Imperative
Embracing GenAI - A Strategic Imperative
 
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
 
Acetabularia Information For Class 9 .docx
Acetabularia Information For Class 9  .docxAcetabularia Information For Class 9  .docx
Acetabularia Information For Class 9 .docx
 

160155061 project-monitoring-control

  • 2. Project Monitoring and Control  Monitoring – collecting, recording, and reporting information concerning project performance that project manger and others wish to know  Controlling – uses data from monitor activity to bring actual performance to planned performance 2
  • 3. Project Monitoring and Control  Why do we monitor?  What do we monitor?  When to we monitor?  How do we monitor? 3
  • 4. Why do we monitor?  Simply because we know that things don’t always go according to plan (no matter how much we prepare)  To detect and react appropriately to deviations and changes to plans 4
  • 5. What do we monitor?  Men (human resources)  Machines  Materials  Money  Space  Time  Tasks  Quality/Technical Performance 5
  • 6. What do we monitor? Inputs  Time  Money  Resources  Material Usage  Tasks  Quality/Technical Performance 6 Outputs Progress Costs Job starts Job completion Engineering / Design changes Variation order (VO)
  • 7. When do we monitor?  End of the project  Continuously  Regularly  Logically  While there is still time to react  As soon as possible  At task completion  At pre-planned decision points (milestones) 7
  • 8. Where do we monitor?  At head office?  At the site office?  On the spot?  Depends on situation and the ‘whats’ 8
  • 9. How do we monitor  Through meetings with clients, parties involved in project (Contractor, supplier,etc.)  For schedule – Update CPA, PERT Charts, Update Gantt Charts  Using Earned Value Analysis  Calculate Critical Ratios  Milestones  Reports  Tests and inspections  Delivery or staggered delivery  PMIS (Project Management Info Sys) Updating 9
  • 10. Meetings – Some monitoring issues  What problems do you have and what is being done to correct them?  What problems do you anticipate in the future?  Do you need any resources you do not yet have?  Do you need information you do not have yet?  Do you know anything that will give you schedule difficulties?  Any possibility your task will finish early/late?  Will your task be completed under/over/on budget? 10
  • 11. Project Control Cycle 11 PLAN Specifications Project Schedule Project budget Resource plan Vendor contracts MONITOR Record status Report progress Report cost COMPARE Actual status against plan -Schedule -Cost ACTION Correct deviations from plan RE-PLAN as necessary
  • 12. Project Control  Control – process and activities needed to correct deviations from plan  Control the triple constraints  time (schedule)  cost (budget, expenses, etc)  performance (specifications, testing results, etc.) 12
  • 13. Techniques for monitoring and control  Earned Value Analysis  Critical Ratio 13
  • 14. Earned Value Analysis  A way of measuring overall performance (not individual task) is using an aggregate performance measure - Earned Value  Earned value of work performed (value completed) for those tasks in progress found by multiplying the estimated percent physical completion of work for each task by the planned cost for those tasks. The result is amount that should be spent on the task so far. This can be compared with actual amount spent. 14
  • 15. Earned Value Analysis  Methods for estimating percent completion  The 50-50 estimate. 50% is assumed when task is begun, and remaining 50% when work completed.  0-100% rule. This rule allows no credit for work until task is complete, highly conservative rule, project always seem late until the very end of project when everything appears to suddenly catch up  Critical input rule. This rule assigns progress according to amount of critical input that has been used. Labor or skilled dependent, machine critical input – buy machine complete task – may be misinformation  Proportional rule. This rule divides planned (or actual) time- to-date by total scheduled time(or budgeted (or actual ) cost- to-date by total budgeted cast] to calculate percent complete. This is commonly used rule. 15
  • 16. Earned Value Analysis  Refer to earned value chart – basis for evaluating cost and performance to date  If total value of the work accomplished is in balance with the planned (baseline) cost, and actual cost then top mgmt has no particular need for a detailed analysis of individual tasks  Earned value concept – combines cost reporting & aggregate performance reporting into one comprehensive chart 16
  • 17. Earned Value Analysis  Baseline cost to completion – referred to as budget at completion (BAC)  Actual cost to date – referred to as estimated cost at completion (EAC)  Identify several variances according to two guidelines 1. A negative variance is ‘bad’ 2. Cost and schedule variances are calculated as earned value minus some other measure 17
  • 18. Earned Value Chart – basis for evaluating cost & performance to date 18
  • 19. Earned Value Analysis - Variances  4 types of variances;  Cost (spending) variance (CV) – difference between budgeted cost of work performed (earned value) (BCWP) and actual cost of that work (ACWP)  Schedule variance (SV) – difference between earned value (BCWP) and cost of work we scheduled to perform to date (BCWS)  Time variance (TV) –difference between time scheduled for work performed (STWP) and actual time to perform it (ATWP) 19
  • 20. Earned Value Variance - Formula CV = BCWP – ACWP (negative value - cost overrun) SV = BCWP – BCWS (negative value - behind schedule) TV = STWP – ATWP (negative value - delay) Index (Ratios) Cost Performance Index (CPI) = BCWP/ACWP Schedule Performance Index (SPI) = BCWP/BCWS Time Performance Index (TPI) = STWP/ATWP 20
  • 21. EXAMPLE Assume that operations on a Work Package cost RM 1,500 to complete. They were originally scheduled to finish today. At this point, we actually spent RM1,350. And we estimate that we have completed two thirds (2/3) of the work. What are the cost and schedule variances? CV = BCWP – ACWP = 1500 (2/3) – 1350 = - 350 SV = BCWP – BCWS = 1500 (2/3) – 1500 = - 500 CPI = BCWP/ACWP = 1500(2/3)/1350 = 0.74 SPI = BCWP/BCWS = 1500(2/3)/1500 = 0.67 Spending higher than budget, and given what we have spent, we are not as far along as we should be (have not completed as much work as we should have) 21
  • 22.  Possible to have one of indicators to be favorable while the other unfavorable  Might be ahead of schedule and behind costs  Six possibilities (see figure next slide) 22
  • 23. 6 Possibilities Earned Value Analysis 23
  • 24. Critical ratio  Sometimes, especially large projects, it may be worthwhile calculating a set of critical ratios for all project activities  The critical ratio is actual progress x budgeted cost scheduled progress actual cost  If ratio is 1 everything is probably on target  The further away form 1 the ratio is, the more we may need to investigate 24
  • 25. Summary  Need proper project monitoring and control mechanisms  Tools available to help in monitoring and controlling activities  There are human control and management aspects not covered here 25