SlideShare a Scribd company logo
1 of 127
Download to read offline
Project Value Delivery 
PRACTICAL 
COST CONTROL 
© Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 
FOR 
LARGE, COMPLEX PROJECTS 
Jeremie Averous 
December 2014 
Version 0
More details about the topics 
of this presentation in our 
Cost Control Handbook 
An Advanced Project 
Management book published 
in Singapore! 
2 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Project Value Delivery 
Project Soft Power 
Unleashing Value 
Intercultural leadership Team effectiveness 
from Your 
Large, Complex 
Projects 
Leadership development 
Project Recovery 
Project Control and Reporting 
Project Startup support Advanced project training 
Project Health Check 
Support systems integration 
Remote sites integration 
Organizational maturity 
Advanced risk management 
Convergence planning 
We Empower Organizations 
T o b e R e l i a b l y S u c c e s s f u l i n 
Project Coaching 
Executing Large, Complex Projects 
Discover more on 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Introduction 
© Project Value Delivery, 2014 
3-w Dec-w 14 w . P r Page o 4 j e c t V a l u e D e l i v e r y . c o m 
4 Introduction 
1: Cost Control in Projects 
Why Cost Control is different from Accounting 
Interfaces with Project Control 
Profile & career of Cost Controllers 
2: PVD Cost Control Golden Rules 
3: Forecasting Principles 
Quantity-based Forecasting 
Productivity-based Forecasting 
4: Reflecting forecasts in Project Reporting 
Sensitivities (Achievable vs Prudent) 
Contingency Management 
5: Time-phasing of cost and Financial 
reporting 
6: Cost Control Forensics 
Conclusion
• What is Cost Control all 
about? 
5 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
What is Project Cost Control? 
• Something (secret) that is done by Finance 
• Registration of invoices from vendors and booking 
timesheets 
• Trying to figure out how to squeeze everything in the 
budget (anybody knows what the budget is?) 
• Approval of invoices to pay vendors 
• A back-office function that is on another floor 
• Etc. 
6 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
To run like clockwork, there is a lot more to Project 
Cost Control than what you might think! 
7 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Introduction 
Project cost control’s purpose is to maintain an 
accurate forecast at a specific phase of the 
project, based on all the information available at the 
time the forecast is made. 
The objective is to allow proper decision-making 
by the Project Manager. 
The remit of Cost Control is thus essentially different 
from the usual remit of Accounting. 
8 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
COST CONTROL BASIC 
DEFINITIONS AND CONCEPTS 
© Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Cost Management basic definitions 
Forecast 
Variance 
Budget 
Cost To 
Complete ETC 
Commit-ment 
Accruals 
Invoiced 
Amount 
Forecast 
Estimate 
To 
Complete 
Actual 
Cost 
10 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
The Project Cost Model 
Project Cost 
Model 
-Breakdown 
Structure 
-time-phased 
-Source currencies 
Monthly Project 
Performance Report 
(EAC, fixed FOREX) 
Financial P&L Reports 
(POC, variable FOREX) 
Commitments 
Progress 
Reforecasts 
Management 
of Change 
Cash flow model 
(by currency & entity) 
11 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Part 1: 
Cost Control in 
Projects 
© Project Value Delivery, 2014 
3-w Dec-w 14 w . P r Page o 1 2 j e c t V a l u e D e l i v e r y . c o m 
12 Introduction 
1: Cost Control in Projects 
Why Cost Control is different from Accounting 
Interfaces with Project Control 
Profile & career of Cost Controllers 
2: PVD Cost Control Golden Rules 
3: Forecasting Principles 
Quantity-based Forecasting 
Productivity-based Forecasting 
4: Reflecting forecasts in Project Reporting 
Sensitivities (Achievable vs Prudent) 
Contingency Management 
5: Time-phasing of cost and Financial 
reporting 
6: Cost Control Forensics 
Conclusion
Starting a Project is like 
leaving on an 
Intercontinental journey 
13 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
The sea make look calm 
but it will still get rough 
14 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
The Three Fundamental Questions 
WHERE ARE WE? 
(ARE WE ON COURSE?) 
WHERE ARE WE GOING? 
WHAT DO WE NEED TO DO TO BE 
BACK ON COURSE? 
15 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
In Manufacturing, 
the future is 
an extrapolation 
of the past 
16 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
In Projects, 
the future 
needs to be 
re-forecast 
17 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Cost Control is not Accounting 
TWO DIFFERENT DISCIPLINES THAT NEED 
TO WORK TOGETHER 
COST CONTROL ACCOUNTING / FINANCE 
- Focus on the future 
- Understands the business 
- Follows commitments 
- Focus on project end 
point 
- Focus on the past 
- Same for any business 
- Follows invoicing and 
payment 
- Variable exchange rates 
- Cash flow management 
- Focus on reporting period 
end point (PoC accounting) 
18 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Usual failure mode observed in the 
field of Cost Control 
• The Urgent takes over the Important! 
Invoice processing 
Payments 
Angry vendors 
Cash management 
Financing 
Financial reporting 
Forecasting 
Trend analysis 
Identification of trends on 
actual commitments 
19 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Common “maturity’ observations 
when no strong Cost Management 
• Costs for internal resources as actual costs instead 
of standard rates 
– Extreme complication of cost tracking 
• Commitments are not tracked – only invoicing 
– Invoicing without commitments 
– Poor control on project bottom line because of 
invoicing delays 
• Poor consistency with project execution strategy 
and forecast schedule 
• No support to PM in scenario planning 
20 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
The Cost Controller profile 
• A good Cost Controller is not necessarily someone 
with an accounting profile 
• Graduate engineers are often very successful 
• An excellent path towards Project Controls and 
Project Management roles. 
21 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
The Cost Controller profile 
• Business skills: 
– understanding of contractual arrangements, 
– understanding of the project activity 
• Process skills: able to design, implement and improve 
information gathering processes, and the adequate 
Breakdown Structure 
• Technical skills: 
– knowledge of database basics, how to write requests 
and reports; 
– knowledge of the dedicated Cost Control tool 
• Leadership skills: ability to influence project parties to 
provide the required information at the right moment 
and to devise accurate cost forecasts 
22 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
We Can Deal with Bad News, 
We Can’t Deal With Surprises 
23 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Get out of your seat to 
get the information 
24 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Where are the COMMITMENTS? 
20M$ oversight over 3 months 
25 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
INVOICES TAKE FOREVER TO ARRIVE. 
DON’t COUNT ON THEM TO KEEP CONTROL 
26 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Make sure you know where 
you’re going! 
27 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Don’t end your journey like 
this… and pennyless!... 
28 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Part 2: 
PVD Cost Control 
Golden Rules 
© Project Value Delivery, 2014 
3-w Dec-w 14 w . P r Page o 2 9 j e c t V a l u e D e l i v e r y . c o m 
29 Introduction 
1: Cost Control in Projects 
Why Cost Control is different from Accounting 
Interfaces with Project Control 
Profile & career of Cost Controllers 
2: PVD Cost Control Golden Rules 
3: Forecasting Principles 
Quantity-based Forecasting 
Productivity-based Forecasting 
4: Reflecting forecasts in Project Reporting 
Sensitivities (Achievable vs Prudent) 
Contingency Management 
5: Time-phasing of cost and Financial 
reporting 
6: Cost Control Forensics 
Conclusion
PVD Project Cost Control 
14 Golden Rules 
• The main objective of Cost Management is to 
enable the Project Manager to take decisions 
based on an accurate description of the project 
financial situation, derived from the organization’s 
current knowledge and understanding of reality. 
14 Golden Rules 
30 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Cost Control Golden Rules 1/5 
• Accountability: Budget Owners are 
accountable for their budget (including 
forecast and time-phasing). PM retains 
ultimate accountability. Cost Control supports 
and challenges 
• Forecasting focus: The primary focus of Cost 
Management is accurate and realistic 
Forecasting along with prompt Reporting 
• Maintenance of the reference ‘Project Cost 
Model’: the basis for all financial 
assessments, modelling and reporting of the 
Company’s Forecasts and results on the 
Project 
31 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Cost Control Golden Rules 2/5 
• Project Scope & Schedule consistency: 
Main Contract (plus any Change Orders), 
and latest project schedule. Includes 
comprehensive understanding of the 
Main Contract term. 
• No surprises: Variances should be 
exclusively caused by triggering events 
and not by internal oversights 
• Candidness principles: cost 
acknowledgment and reporting must be 
candid and reflect actual understanding 
of reality 
32 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Cost Control Golden Rules 3/5 
• Immediacy principle: reflect significant 
new costs as soon as they are anticipated 
even if a detailed assessment is not yet 
available 
• Timeliness of reporting: produce the 
relevant reports on time 
33 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Cost Control Golden Rules 4/5 
• Commitment tracking focus: Project Cost 
Management is responsible for ensuring that 
systems, processes and procedures are in 
place to identify and track Commitments for 
all Cost Allocations and categories. 
• Prudence principle for Estimated at 
Completion Forecast: includes recognizing 
Costs as soon as they are probable and not 
recognizing Revenues until they are certain 
• Realism principle for ‘Achievable’ Forecast: 
Project Cost Management reports what is 
realistically achievable, both with respect to 
final Costs and final Revenues 
34 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Cost Control Golden Rules 5/5 
• Accuracy over precision: cost updates 
should be accurate but not necessarily 
precise 
• Data integrity principle: Project Cost 
Management ensures the integrity and 
consistency of the cost and Accounting 
data in the Project’s Forecast and Cost 
• Cost reconciliation principle: project cost 
model and accounting are compared on 
a monthly basis 
35 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Cost Control Golden Rules 
• Golden Rules will be explained throughout the 
presentation 
36 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Part 3: 
Forecasting Principles 
© Project Value Delivery, 2014 
3-w Dec-w 14 w . P r Page o 3 7 j e c t V a l u e D e l i v e r y . c o m 
37 Introduction 
1: Cost Control in Projects 
Why Cost Control is different from Accounting 
Interfaces with Project Control 
Profile & career of Cost Controllers 
2: PVD Cost Control Golden Rules 
3: Forecasting Principles 
Quantity-based Forecasting 
Productivity-based Forecasting 
4: Reflecting forecasts in Project Reporting 
Sensitivities (Achievable vs Prudent) 
Contingency Management 
5: Time-phasing of cost and Financial 
reporting 
6: Cost Control Forensics 
Conclusion
38 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
The Three Fundamental Questions 
WHERE ARE WE? 
(ARE WE ON COURSE?) 
WHERE ARE WE GOING? 
WHAT DO WE NEED TO DO TO BE BACK ON 
COURSE? 
39 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
FORECASTING FUNDAMENTALS 
© Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Should the forecast be precise or 
accurate? 
Accurate, 
not Precise 
© Project Value Delivery, 2013 
Precise, 
not Accurate 
41 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
• “Dead Reckoning” 
42 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Useful definitions 
External Resources (Supply-Chain) 
Procurement 
Subcontracting 
Purchase Order 
(Purchase Order) Equipment 
Subcontract 
Bulk, Standard 
Equipment 
Complicated 
Services 
43 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
2 main types of Forecasting 
BULK & STANDARD MATERIAL 
SERVICES, SUBCONTRACTS 
Quantity-based 
Remains to 
Commit 
Vs 
Committed 
Productivity 
based 
Estimate to 
Complete 
Vs 
Estimate at 
Completion 
44 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
• What are the conditions 
for good forecast?? 
45 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Conditions for Forecast Quality 
• Committed Budget Owners 
– Each Work Package to have ONE Budget Owner 
– Avoid Padding of budgets by Budget Owners 
• Adequate communication between project parties 
– A good cost engineer/controller seeks 
information and does not remain at his/her desk 
• Appropriate Breakdown Structure 
– Relevant granularity and fit with project 
execution structure 
– No need of high level of detail 
• Don’t follow cost at Engineering CTR level 
46 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Forecast for Revenue 
• Recognition of Revenue in Forecast for Variation 
Orders follows very strict rules 
– No recognition when VO is not signed 
– Some organizations allows exceptions but: 
• require the highest levels of approval 
• Requires scope of work approval by Client 
• Needs to be accepted by auditors 
47 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
BULK/ QUANTITIES 
FORECASTING FUNDAMENTALS 
© Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Bulk allowance management 
Forecasting Bulk Quantities 
FORECAST 
Net MTO 
ERECTED 
(Bill of Material) 
Allowance 
for Accuracies 
[Engineering] 
Allowance 
for MTO exclusions 
[Engineering] 
(maturity of MTO) 
Supply factor 
& cuts, nesting 
[Procurement] 
General 
Risk & Opportunity 
Contingency 
49 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Forecast for Bulk Procurement 
• Everything is based on the right level of allowances 
– Be clear on allowances + contingency 
– Allowance for supply/nesting is supplier 
and fabricator dependent! 
– Make sure receipt is done properly 
– Be clear on treatment of extra material 
(take-back clause, scrap etc) 
50 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
EARNED VALUE FORECASTING 
FUNDAMENTALS 
© Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
12h flight 
52 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
53 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m = COST
We’ve been flying for 6 hours. 
We spent 50% of the fuel. 
Are we OK? 
54 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
© Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
We’ve done half the way. 
We spent 40% of the fuel. 
Are we OK? 
56 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Project Controls is a discipline by 
itself 
• My cost is lower than expected: what 
does it mean? 
• My physical progress is lower than 
expected: what does it mean? 
• One risk was realized: what does it 
mean? 
Earned Value Analysis 
57 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Budget 
Cost Variance (<0) 
Schedule Variance (>0) 
Time 
$ 
Earned Value Analysis: 
Forecasting using EVM 
Forecast considering 
Cost Performance Index 
AC 
today 
Forecast considering 
Future as in initial budget 
EV 
BC 
CPI= 
SPI= 
EV 
AC 
EV 
BC 
58 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
What can we take from Earned 
Value Analysis? 
2 Legs to a 
Sound Forecast 
Quality of 
Commitments 
Tracking 
Quality of 
Schedule Progress 
data 
Actual Physical 
Progress?? 
59 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Forecast Trick 
• Investigate quality of forecast when progress on a 
work package is about 20-30% 
– Earlier: not enough trend 
– Later: too late! 
60 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Advanced Earned Value 
• Take into account that productivity changes with 
progress! 
– Typically productivity diminishes when progress 
reaches > 80% 
• For good quality forecast: 
– pinpoint deliverables that have been completed 
already 
– measure productivity on completed deliverables 
to extrapolate to the rest of the project! 
61 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Typical example of productivity 
decrease in engineering 
Engineering productivity 
~100% 
0% 
• Example of causes: 
Time in project 
– Physical progress measurement standard optimistic 
– Rework on documents “AFC” (further revisions) 
– Review process more onerous than expected 
62 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Cost Management basic concepts 
Different 
configurations 
(right or wrong?) 
63 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Cost Management basic concepts 
Budget 
Commitment 
Invoiced 
EAC 
WRONG! 
Actual 
Cost 
64 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Cost Management basic concepts 
Budget 
Commitment 
Invoiced 
EAC 
WRONG! 
Actual 
Cost 
65 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Cost Management basic concepts 
Budget 
Commitment 
Invoiced 
EAC 
WRONG! 
Actual 
Cost 
66 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Cost Management basic concepts 
Budget 
Commitment 
OK 
BUT 
CAREFUL 
Invoiced 
EAC 
Actual 
Cost 
67 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Cost Management basic concepts 
Budget 
WRONG! 
Commitment 
Invoiced 
EAC 
Actual 
Cost 
68 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
BREAKDOWN STRUCTURE ISSUES 
© Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
70 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m Design the appropriate breakdown !
What are the issues to take into 
account? 
• Reporting 
• Client requirements, 
• Legal entities 
• In-/Out-country 
• specific costs that are early indicators e.g. airfreight 
costs 
• Subcontracting strategy 
• Allowances to be split out 
• One WP should generally refer to one type of cost and 
cost follow-up method. 
71 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Too much detail 
drowns the team 
and removes agility 
Optimal 
Breakdown 
Detail 
Range 
Breakdown Structure detail 
Effectiveness 
Too little detail 
will not allow 
to grasp 
the project drivers 
72 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Project Control traps 
73 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Project Control traps 
Too much detail! 
Not enough time for 
analysis 
74 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
KEEPING TRACK OF ALL 
VARIANCES 
© Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Data Integrity: 
Variances traceability 
• All Forecast Variances must be traceable 
– Cost control to maintain detailed (WP by WP) 
register of all EAC variances to allow 
• Auditability trail, 
• Keeping the history makes it easier to hand over cost 
control of the project to a new person if needed, 
• Allows to track discrepancies or budgets that would 
need more attention by looking in the past at all 
variances introduced in the cost model. 
• Repeated variances on a WP is an indicator of an issue 
to be investigated 
76 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
WATCH FOR CONSEQUENTIAL 
COSTS 
© Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Watch for consequential costs! 
• While we have covered the different phases of a project, 
it is essential to always analyze if a Variance observed 
might not lead to other Variances: 
– Late engineering leading to claims and delays from 
suppliers 
– Late procurement leading to extra transportation 
costs (airfreight) and offshore standby 
– Late fabrication leading to offshore standby 
– Etc 
• Always seek the root cause and examine if no 
Consequential Variances! 
78 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Part 4: Reflecting 
Forecasts in Project 
Reporting 
© Project Value Delivery, 2014 
3-w Dec-w 14 w . P r Page o 7 9 j e c t V a l u e D e l i v e r y . c o m 
79 Introduction 
1: Cost Control in Projects 
Why Cost Control is different from Accounting 
Interfaces with Project Control 
Profile & career of Cost Controllers 
2: PVD Cost Control Golden Rules 
3: Forecasting Principles 
Quantity-based Forecasting 
Productivity-based Forecasting 
4: Reflecting forecasts in Project Reporting 
Sensitivities (Achievable vs Prudent) 
Contingency Management 
5: Time-phasing of cost and Financial 
reporting 
6: Cost Control Forensics 
Conclusion
EAC and ‘Achievable’ 
• EAC - Forecast: PRUDENT P80 
• ‘Achievable’ from Sensitivity Analysis 
FORECAST and ‘ACHIEVABLE’ 
are both equally important 
80 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Reforecasting for Revenue 
Unsigned 
Change 
Order 
Cost 
EAC 
Cost 
Revenue 
Sensitivities 
81 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Forecast and Achievable 
Forecast 
Achievable 
Single Project 
Accounting 
Business 
Results 
Expectations 
82 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Reforecasting for COST 
When you know something is going to 
happen to your cost forecast, don’t wait until 
you have got all your cost elements to 
reforecast! 
Reforecast immediately (as soon as 
practicable) even if you have only an order 
of magnitude! 
83 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Sensitivities: the right order 
BEST 
‘Achievable’ 
EAC - FORECAST 
WORST 
84 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
FORECASTING FOR 
CONTINGENCY 
© Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Contingency evolution during 
project execution 
CONTINGENCY IS 
OWNED BY SENIOR 
MANAGEMENT 
Contingency 
Contingency level as 
released by Senior 
Management 
Time in the project 
The area between the two 
curves is in effect 
Management contingency 
Natural evolution of 
calculated (‘Monte Carlo’) for 
contingency 
[based on ETC] 
86 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Contingency: Caution 
• Releasing contingency to compensate for higher 
costs compared to the budget is not acceptable. 
• The engagement of the contingency ‘reserve’ is one 
of the ultimate responsibilities of the Project 
Manager 
• At any time it is not permissible to release 
contingency below the calculated contingency. 
87 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
A BAD EXAMPLE ON A 36 MO 
PROJECT 
Contingency is used (too early) 
to cover cost overruns 
Forecast Revenue 
Forecast Total Cost (EAC) 
Forecast total Cost w/o contingency 
18 months 
88 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
PROJECT DYNAMICS 
© Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
$ 
Forecast Profit evolution during 
project execution 
Late recognition of Change 
Orders create a second 
sudden margin improvement 
Late release of contingency 
create a sudden margin 
improvement 
Project Forecast cost 
End of 
Integration/ 
Commissioning 
Time in the project 
Project Forecast revenue 
Project Contingency 
90 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
$ 
Achievable profit evolution during 
project execution 
Achievable revenue 
Time in the project 
Achievable cost 
91 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Part 5: Time-phasing 
of Cost and Financial 
Reporing 
© Project Value Delivery, 2014 
3-w Dec-w 14 w . P r Page o 9 2 j e c t V a l u e D e l i v e r y . c o m 
92 Introduction 
1: Cost Control in Projects 
Why Cost Control is different from Accounting 
Interfaces with Project Control 
Profile & career of Cost Controllers 
2: PVD Cost Control Golden Rules 
3: Forecasting Principles 
Quantity-based Forecasting 
Productivity-based Forecasting 
4: Reflecting forecasts in Project Reporting 
Sensitivities (Achievable vs Prudent) 
Contingency Management 
5: Time-phasing of cost and Financial 
reporting 
6: Cost Control Forensics 
Conclusion
Forecasting and Time-Spread 
• Forecasting must not just address the issue of 
Estimate-at-Completion forecast, 
But also the forecast needs to be times-spread for 
each Work Package! 
ACTUALS TODAY FORECAST 
M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 
WP1 0 0 0 456 56 435 657 7658 878 9769 969 969 63 242 
WP2 0 0 0 0 0 5456 646 6574 7547 765 989 1324 536 5477 
WP3 4235 535 536 636 47 474 5687 58 6969 979 70 721 21545 3452 
WP4 44 44 44 44 44 44 55 55 77 0 0 0 0 0 
WP5 75 0 0 5536 74 7657 0 0 43 6326 0 0 0 
93 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Why is Time-Spread important? 
For long projects, proper time-spread 
of cost & revenue is critical to the 
organization’s financial performance, 
and in particular to market anticipation 
(quarterly & yearly) 
>> SHARE PRICE OF COMPANY! 
94 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
What is Percentage of Completion 
(POC) Accounting? 
• PoC is the method chosen to report long 
projects lasting over several reporting 
periods 
• PoC= 
Actual cost spent 
Total forecast cost 
• Recognized Profit = PoC x Total Forecast 
Profit 
95 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Cost POC and physical progress POC 
• Cost POC and Physical progress POC are different 
– Cost POC is generally lower than Physical 
progress POC 
• If there is too much of a difference 
between cost POC and physical progress 
POC, INVESTIGATE!! 
96 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
What is PoC accounting? 
Revenue 
Cost 
Profit 
Time 
97 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
What is PoC accounting? 
Recognized 
Profit 
Time 
Profit 
98 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Why should PM’s be 
concerned? 
99 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
PMs and PoC accounting 
PM’s are supposed to focus on the ultimate 
performance of the project at completion 
However, PM you need to be aware of the effect of : 
The variability of the reported project result 
On 
The Company’s financial result 
during the execution of the Project 
100 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
The main 
PoC accounting effects 
101 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
The amplification effect 
PoC accounting 
amplifies 
the impact of changes 
in project profit forecast 
102 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
The amplification effect 
Recognized 
Profit 
Time 
Profit 
EVENT 
103 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
The amplification effect 
Recognized 
Profit 
Time 
Profit 
104 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
The delay effect 
• Delay (slow progress) will impact significantly 
revenue recognition for a given period 
– significant impact on company’s forecast short term 
financials 
105 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
The delay amplification effect 
Recognized 
Profit 
Time 
Profit 
DELAY 
106 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Part 6: Cost Control 
Forensics 
© Project Value Delivery, 2014 
3-w Dec-w 14 w . P r Page o 1 j 07 e c t V a l u e D e l i v e r y . c o m 
107 Introduction 
1: Cost Control in Projects 
Why Cost Control is different from Accounting 
Interfaces with Project Control 
Profile & career of Cost Controllers 
2: PVD Cost Control Golden Rules 
3: Forecasting Principles 
Quantity-based Forecasting 
Productivity-based Forecasting 
4: Reflecting forecasts in Project Reporting 
Sensitivities (Achievable vs Prudent) 
Contingency Management 
5: Time-phasing of cost and Financial 
reporting 
6: Cost Control Forensics 
Conclusion
The Three Fundamental Questions 
WHERE ARE WE? 
(ARE WE ON COURSE?) 
WHERE ARE WE GOING? 
WHAT DO WE NEED TO DO TO BE 
BACK ON COURSE? 
108 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
What information? 
How do we make sense of it? 
109 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
What is Project Controls? 
Project Controls is about building 
information sensors, and making 
sense of the information. 
110 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Cost Control Forensics: 
3 levels of maturity 
• Level 1: quality of Commitments and Actuals 
– Actuals not Invoiced cost, comprehensive 
commitments, cost breakdown structure 
• Level 2: quality of Forecast 
– Consistency with project execution incl. time-phasing, 
allowances & contingency 
management, sensitivities, trends checking 
• Level 3: support to decision-making 
– Ability to run scenario analysis 
111 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Conclusion 
© Project Value Delivery, 2014 
3-w Dec-w 14 w . P r Page o 1 j 12 e c t V a l u e D e l i v e r y . c o m 
112 Introduction 
1: Cost Control in Projects 
Why Cost Control is different from Accounting 
Interfaces with Project Control 
Profile & career of Cost Controllers 
2: PVD Cost Control Golden Rules 
3: Forecasting Principles 
Quantity-based Forecasting 
Productivity-based Forecasting 
4: Reflecting forecasts in Project Reporting 
Sensitivities (Achievable vs Prudent) 
Contingency Management 
5: Time-phasing of cost and Financial 
reporting 
6: Cost Control Forensics 
Conclusion
HOW 
Are you 
taking 
decisions?!? 
113 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Is that the way you are flying? 
114 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Conclusion 
Cost Control for Large, Complex, long duration projects 
requires 
– Structure 
– Consistency 
– Discipline 
…shared by all the project team. 
Cost Control is in charge of advising the project manager 
and making sure that the processes run reliably 
Communicate with the team! 
Invest yourself as much as possible at the start of the 
project – this will decide 90% of the outcome 
115 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
PVD Project Cost Control 
14 Golden Rules 
• The main objective of Cost Management is to 
enable the Project Manager to take decisions 
based on an accurate description of the project 
financial situation, derived from the organization’s 
current knowledge and understanding of reality. 
14 Golden Rules 
116 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Cost Control Golden Rules 1/5 
• Accountability: Budget Owners are 
accountable for their budget (including 
forecast and time-phasing). PM retains 
ultimate accountability. Cost Control supports 
and challenges 
• Forecasting focus: The primary focus of Cost 
Management is accurate and realistic 
Forecasting along with prompt Reporting 
• Maintenance of the reference ‘Project Cost 
Model’: the basis for all financial 
assessments, modelling and reporting of the 
Company’s Forecasts and results on the 
Project 
117 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Cost Control Golden Rules 2/5 
• Project Scope & Schedule consistency: 
Main Contract (plus any Change Orders), 
and latest project schedule. Includes 
comprehensive understanding of the 
Main Contract term. 
• No surprises: Variances should be 
exclusively caused by triggering events 
and not by internal oversights 
• Candidness principles: cost 
acknowledgment and reporting must be 
candid and reflect actual understanding 
of reality 
118 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Cost Control Golden Rules 3/5 
• Immediacy principle: reflect significant 
new costs as soon as they are anticipated 
even if a detailed assessment is not yet 
available 
• Timeliness of reporting: produce the 
relevant reports on time 
119 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Cost Control Golden Rules 4/5 
• Commitment tracking focus: Project Cost 
Management is responsible for ensuring that 
systems, processes and procedures are in 
place to identify and track Commitments for 
all Cost Allocations and categories. 
• Prudence principle for Estimated at 
Completion Forecast: includes recognizing 
Costs as soon as they are probable and not 
recognizing Revenues until they are certain 
• Realism principle for ‘Achievable’ Forecast: 
Project Cost Management reports what is 
realistically achievable, both with respect to 
final Costs and final Revenues 
120 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Cost Control Golden Rules 5/5 
• Accuracy over precision: cost updates 
should be accurate but not necessarily 
precise 
• Data integrity principle: Project Cost 
Management ensures the integrity and 
consistency of the cost and Accounting 
data in the Project’s Forecast and Cost 
• Cost reconciliation principle: project cost 
model and accounting are compared on 
a monthly basis 
121 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Cost Control Golden Rules 
• Golden Rules have been explained throughout the 
presentation 
122 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Get out of your seat to 
get the information 
123 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Project Value Delivery 
THANK YOU! 
We Empower Organizations 
T o b e R e l i a b l y S u c c e s s f u l i n 
Executing Large, Complex Projects 
Discover more on 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Project Value Delivery 
Project Soft Power 
Unleashing Value 
Intercultural leadership Team effectiveness 
from Your 
Large, Complex 
Projects 
Leadership development 
Project Recovery 
Project Control and Reporting 
Project Startup support Advanced project training 
Project Health Check 
Support systems integration 
Remote sites integration 
Organizational maturity 
Advanced risk management 
Convergence planning 
We Empower Organizations 
T o b e R e l i a b l y S u c c e s s f u l i n 
Project Coaching 
Executing Large, Complex Projects 
Discover more on 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
More details about the topics 
of this presentation in our 
Cost Control 
Handbook 
An other Advanced Project 
Management book by Project 
Value Delivery 
126 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Project Value Delivery books 
Available on all e-bookshops 
127 © Project Value Delivery, 2014 
w w w . P r o j e c t V a l u e D e l i v e r y . c o m

More Related Content

What's hot

PVD Project Control Best Practices for Large Projects
PVD Project Control Best Practices for Large ProjectsPVD Project Control Best Practices for Large Projects
PVD Project Control Best Practices for Large ProjectsJeremie Averous
 
Second edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoSecond edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoignitetribes
 
Projectcontrol
ProjectcontrolProjectcontrol
ProjectcontrolRaj Sampat
 
Project planning and scheduling
Project planning and schedulingProject planning and scheduling
Project planning and schedulingadeel hamid
 
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo
 
Advanced project scheduling: proper practices for integrated project schedules
Advanced project scheduling: proper practices for integrated project schedulesAdvanced project scheduling: proper practices for integrated project schedules
Advanced project scheduling: proper practices for integrated project schedulesJeremie Averous
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Schedulingakashpadole
 
construction project planing
 construction project planing construction project planing
construction project planingSANJEEV Wazir
 
Triple Constraints of Projects: Scope, Cost & Schedule
Triple Constraints of Projects: Scope, Cost & ScheduleTriple Constraints of Projects: Scope, Cost & Schedule
Triple Constraints of Projects: Scope, Cost & Scheduleshofiulalom
 
Step by Step Guide to Project Management
Step by Step Guide to Project ManagementStep by Step Guide to Project Management
Step by Step Guide to Project ManagementBrendon Yip
 
Project scope management
Project scope managementProject scope management
Project scope managementJody R Flower
 

What's hot (20)

PVD Project Control Best Practices for Large Projects
PVD Project Control Best Practices for Large ProjectsPVD Project Control Best Practices for Large Projects
PVD Project Control Best Practices for Large Projects
 
Second edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoSecond edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promo
 
Projectcontrol
ProjectcontrolProjectcontrol
Projectcontrol
 
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
 
Project planning and scheduling
Project planning and schedulingProject planning and scheduling
Project planning and scheduling
 
Concurrent Delay in Construction
Concurrent Delay in ConstructionConcurrent Delay in Construction
Concurrent Delay in Construction
 
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
 
Project Charter Guide
Project Charter GuideProject Charter Guide
Project Charter Guide
 
Advanced project scheduling: proper practices for integrated project schedules
Advanced project scheduling: proper practices for integrated project schedulesAdvanced project scheduling: proper practices for integrated project schedules
Advanced project scheduling: proper practices for integrated project schedules
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling
 
construction project planing
 construction project planing construction project planing
construction project planing
 
Project Management Tools and Techniques
Project Management Tools and TechniquesProject Management Tools and Techniques
Project Management Tools and Techniques
 
Claim Presentation Rev 03 FINAL
Claim Presentation Rev 03 FINALClaim Presentation Rev 03 FINAL
Claim Presentation Rev 03 FINAL
 
Triple Constraints of Projects: Scope, Cost & Schedule
Triple Constraints of Projects: Scope, Cost & ScheduleTriple Constraints of Projects: Scope, Cost & Schedule
Triple Constraints of Projects: Scope, Cost & Schedule
 
Step by Step Guide to Project Management
Step by Step Guide to Project ManagementStep by Step Guide to Project Management
Step by Step Guide to Project Management
 
project management
project managementproject management
project management
 
Project scope management
Project scope managementProject scope management
Project scope management
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Project Management Concepts
Project Management ConceptsProject Management Concepts
Project Management Concepts
 
PMP-Cost Management area
PMP-Cost Management areaPMP-Cost Management area
PMP-Cost Management area
 

Viewers also liked

Specifics of Managing Large, Complex Projects
Specifics of Managing Large, Complex ProjectsSpecifics of Managing Large, Complex Projects
Specifics of Managing Large, Complex ProjectsJeremie Averous
 
Large Complex Projects (PMI-MY presentation Sept 2012)
Large Complex Projects (PMI-MY presentation Sept 2012)Large Complex Projects (PMI-MY presentation Sept 2012)
Large Complex Projects (PMI-MY presentation Sept 2012)Jeremie Averous
 
How Governance Makes or Breaks a Project
How Governance Makes or Breaks a ProjectHow Governance Makes or Breaks a Project
How Governance Makes or Breaks a ProjectJeremie Averous
 
Project Value Delivery methodology and interventions
Project Value Delivery methodology and interventionsProject Value Delivery methodology and interventions
Project Value Delivery methodology and interventionsJeremie Averous
 
Organizational Transformation Best Practices (Project-Driven Businesses)
Organizational Transformation Best Practices (Project-Driven Businesses)Organizational Transformation Best Practices (Project-Driven Businesses)
Organizational Transformation Best Practices (Project-Driven Businesses)Jeremie Averous
 

Viewers also liked (6)

Specifics of Managing Large, Complex Projects
Specifics of Managing Large, Complex ProjectsSpecifics of Managing Large, Complex Projects
Specifics of Managing Large, Complex Projects
 
Large Complex Projects (PMI-MY presentation Sept 2012)
Large Complex Projects (PMI-MY presentation Sept 2012)Large Complex Projects (PMI-MY presentation Sept 2012)
Large Complex Projects (PMI-MY presentation Sept 2012)
 
How Governance Makes or Breaks a Project
How Governance Makes or Breaks a ProjectHow Governance Makes or Breaks a Project
How Governance Makes or Breaks a Project
 
Project Value Delivery methodology and interventions
Project Value Delivery methodology and interventionsProject Value Delivery methodology and interventions
Project Value Delivery methodology and interventions
 
Project Soft Power
Project Soft PowerProject Soft Power
Project Soft Power
 
Organizational Transformation Best Practices (Project-Driven Businesses)
Organizational Transformation Best Practices (Project-Driven Businesses)Organizational Transformation Best Practices (Project-Driven Businesses)
Organizational Transformation Best Practices (Project-Driven Businesses)
 

Similar to Practical Project Cost Control for Large Complex Projects

How to Manage the Transition from Small, Simple to Large Complex Projects
How to Manage the Transition from Small, Simple to Large Complex ProjectsHow to Manage the Transition from Small, Simple to Large Complex Projects
How to Manage the Transition from Small, Simple to Large Complex ProjectsJeremie Averous
 
Project Value Delivery methodology and interventions
Project Value Delivery methodology and interventionsProject Value Delivery methodology and interventions
Project Value Delivery methodology and interventionsJeremie Averous
 
Cost Estimation and Control on Projects: Addressing today's challenges
Cost Estimation and Control on Projects: Addressing today's challengesCost Estimation and Control on Projects: Addressing today's challenges
Cost Estimation and Control on Projects: Addressing today's challengesJeremie Averous
 
The Business of Projects
The Business of ProjectsThe Business of Projects
The Business of ProjectsUnanet
 
PM Session 7
PM Session 7PM Session 7
PM Session 7dmdk12
 
Project Management_1.pdf
Project Management_1.pdfProject Management_1.pdf
Project Management_1.pdfSagarNaik81
 
Melbourne streamlining earned value with hd published
Melbourne streamlining earned value with hd publishedMelbourne streamlining earned value with hd published
Melbourne streamlining earned value with hd publishedInSync Conference
 
Large Complex Industrial Projects:Owner specific role and associated requirem...
Large Complex Industrial Projects:Owner specific role and associated requirem...Large Complex Industrial Projects:Owner specific role and associated requirem...
Large Complex Industrial Projects:Owner specific role and associated requirem...Jeremie Averous
 
Iii. principles of_capital_budgeting
Iii. principles of_capital_budgetingIii. principles of_capital_budgeting
Iii. principles of_capital_budgetingEzgi Kurt
 
Addressing the challenges of delivering Mega Projects
Addressing the challenges of delivering Mega ProjectsAddressing the challenges of delivering Mega Projects
Addressing the challenges of delivering Mega ProjectsIbrahim Al-Hudhaif
 
Deliverables Based Planning
Deliverables Based PlanningDeliverables Based Planning
Deliverables Based PlanningGlen Alleman
 
Capital Budgeting Decision
Capital Budgeting DecisionCapital Budgeting Decision
Capital Budgeting DecisionAshish Khera
 
ned-presentation-project-management.pdf
ned-presentation-project-management.pdfned-presentation-project-management.pdf
ned-presentation-project-management.pdfBENALI Idriss
 
Project Costs, Budgeting and Appraisal
Project Costs, Budgeting and AppraisalProject Costs, Budgeting and Appraisal
Project Costs, Budgeting and AppraisalJude Iheanacho
 
The PMO Value - Emma-Ruth Arnaz-Pemberton | Project Challenge March 2018
The PMO Value - Emma-Ruth Arnaz-Pemberton | Project Challenge March 2018The PMO Value - Emma-Ruth Arnaz-Pemberton | Project Challenge March 2018
The PMO Value - Emma-Ruth Arnaz-Pemberton | Project Challenge March 2018Wellingtone
 
INFORMATION SYTEMS .docx
INFORMATION SYTEMS                                                .docxINFORMATION SYTEMS                                                .docx
INFORMATION SYTEMS .docxpauline234567
 

Similar to Practical Project Cost Control for Large Complex Projects (20)

How to Manage the Transition from Small, Simple to Large Complex Projects
How to Manage the Transition from Small, Simple to Large Complex ProjectsHow to Manage the Transition from Small, Simple to Large Complex Projects
How to Manage the Transition from Small, Simple to Large Complex Projects
 
Project Value Delivery methodology and interventions
Project Value Delivery methodology and interventionsProject Value Delivery methodology and interventions
Project Value Delivery methodology and interventions
 
Cost Estimation and Control on Projects: Addressing today's challenges
Cost Estimation and Control on Projects: Addressing today's challengesCost Estimation and Control on Projects: Addressing today's challenges
Cost Estimation and Control on Projects: Addressing today's challenges
 
The Business of Projects
The Business of ProjectsThe Business of Projects
The Business of Projects
 
P ex cost management-1
P ex cost management-1P ex cost management-1
P ex cost management-1
 
PM Session 7
PM Session 7PM Session 7
PM Session 7
 
Project Management_1.pdf
Project Management_1.pdfProject Management_1.pdf
Project Management_1.pdf
 
Melbourne streamlining earned value with hd published
Melbourne streamlining earned value with hd publishedMelbourne streamlining earned value with hd published
Melbourne streamlining earned value with hd published
 
Large Complex Industrial Projects:Owner specific role and associated requirem...
Large Complex Industrial Projects:Owner specific role and associated requirem...Large Complex Industrial Projects:Owner specific role and associated requirem...
Large Complex Industrial Projects:Owner specific role and associated requirem...
 
Iii. principles of_capital_budgeting
Iii. principles of_capital_budgetingIii. principles of_capital_budgeting
Iii. principles of_capital_budgeting
 
Addressing the challenges of delivering Mega Projects
Addressing the challenges of delivering Mega ProjectsAddressing the challenges of delivering Mega Projects
Addressing the challenges of delivering Mega Projects
 
Deliverables Based Planning
Deliverables Based PlanningDeliverables Based Planning
Deliverables Based Planning
 
Capital Budgeting Decision
Capital Budgeting DecisionCapital Budgeting Decision
Capital Budgeting Decision
 
LN I - PPT.pptx
LN I - PPT.pptxLN I - PPT.pptx
LN I - PPT.pptx
 
P ex cost management-1
P ex cost management-1P ex cost management-1
P ex cost management-1
 
Lessons From The Project Front Line - 4th November 2015
Lessons From The Project Front Line - 4th November 2015Lessons From The Project Front Line - 4th November 2015
Lessons From The Project Front Line - 4th November 2015
 
ned-presentation-project-management.pdf
ned-presentation-project-management.pdfned-presentation-project-management.pdf
ned-presentation-project-management.pdf
 
Project Costs, Budgeting and Appraisal
Project Costs, Budgeting and AppraisalProject Costs, Budgeting and Appraisal
Project Costs, Budgeting and Appraisal
 
The PMO Value - Emma-Ruth Arnaz-Pemberton | Project Challenge March 2018
The PMO Value - Emma-Ruth Arnaz-Pemberton | Project Challenge March 2018The PMO Value - Emma-Ruth Arnaz-Pemberton | Project Challenge March 2018
The PMO Value - Emma-Ruth Arnaz-Pemberton | Project Challenge March 2018
 
INFORMATION SYTEMS .docx
INFORMATION SYTEMS                                                .docxINFORMATION SYTEMS                                                .docx
INFORMATION SYTEMS .docx
 

More from Jeremie Averous

Dealing with Extra Long Duration Megaprojects
Dealing with Extra Long Duration MegaprojectsDealing with Extra Long Duration Megaprojects
Dealing with Extra Long Duration MegaprojectsJeremie Averous
 
Advanced Scheduling for Large, Complex Industrial Projects
Advanced Scheduling for Large, Complex Industrial ProjectsAdvanced Scheduling for Large, Complex Industrial Projects
Advanced Scheduling for Large, Complex Industrial ProjectsJeremie Averous
 
Project Value Delivery methodology and interventions
Project Value Delivery methodology and interventionsProject Value Delivery methodology and interventions
Project Value Delivery methodology and interventionsJeremie Averous
 
Grands projets industriels complexes: Rôle spécifique du Maître d’Ouvrage et ...
Grands projets industriels complexes: Rôle spécifique du Maître d’Ouvrage et ...Grands projets industriels complexes: Rôle spécifique du Maître d’Ouvrage et ...
Grands projets industriels complexes: Rôle spécifique du Maître d’Ouvrage et ...Jeremie Averous
 
Estimation et contrôle des coûts sur les projets: répondre aux défis d'aujour...
Estimation et contrôle des coûts sur les projets: répondre aux défis d'aujour...Estimation et contrôle des coûts sur les projets: répondre aux défis d'aujour...
Estimation et contrôle des coûts sur les projets: répondre aux défis d'aujour...Jeremie Averous
 
Jeremie Averous speaking at Lycee Hoche, May 2014 (Presentation au Lycee Hoch...
Jeremie Averous speaking at Lycee Hoche, May 2014 (Presentation au Lycee Hoch...Jeremie Averous speaking at Lycee Hoche, May 2014 (Presentation au Lycee Hoch...
Jeremie Averous speaking at Lycee Hoche, May 2014 (Presentation au Lycee Hoch...Jeremie Averous
 

More from Jeremie Averous (6)

Dealing with Extra Long Duration Megaprojects
Dealing with Extra Long Duration MegaprojectsDealing with Extra Long Duration Megaprojects
Dealing with Extra Long Duration Megaprojects
 
Advanced Scheduling for Large, Complex Industrial Projects
Advanced Scheduling for Large, Complex Industrial ProjectsAdvanced Scheduling for Large, Complex Industrial Projects
Advanced Scheduling for Large, Complex Industrial Projects
 
Project Value Delivery methodology and interventions
Project Value Delivery methodology and interventionsProject Value Delivery methodology and interventions
Project Value Delivery methodology and interventions
 
Grands projets industriels complexes: Rôle spécifique du Maître d’Ouvrage et ...
Grands projets industriels complexes: Rôle spécifique du Maître d’Ouvrage et ...Grands projets industriels complexes: Rôle spécifique du Maître d’Ouvrage et ...
Grands projets industriels complexes: Rôle spécifique du Maître d’Ouvrage et ...
 
Estimation et contrôle des coûts sur les projets: répondre aux défis d'aujour...
Estimation et contrôle des coûts sur les projets: répondre aux défis d'aujour...Estimation et contrôle des coûts sur les projets: répondre aux défis d'aujour...
Estimation et contrôle des coûts sur les projets: répondre aux défis d'aujour...
 
Jeremie Averous speaking at Lycee Hoche, May 2014 (Presentation au Lycee Hoch...
Jeremie Averous speaking at Lycee Hoche, May 2014 (Presentation au Lycee Hoch...Jeremie Averous speaking at Lycee Hoche, May 2014 (Presentation au Lycee Hoch...
Jeremie Averous speaking at Lycee Hoche, May 2014 (Presentation au Lycee Hoch...
 

Recently uploaded

Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMintel Group
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCRashishs7044
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCRashishs7044
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckHajeJanKamps
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Seta Wicaksana
 
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...lizamodels9
 
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...lizamodels9
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailAriel592675
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyotictsugar
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?Olivia Kresic
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCRashishs7044
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Riya Pathan
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchirictsugar
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...ssuserf63bd7
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607dollysharma2066
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesKeppelCorporation
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...lizamodels9
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCRashishs7044
 

Recently uploaded (20)

Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 Edition
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...
 
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
 
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detail
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyot
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchir
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation Slides
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR
 

Practical Project Cost Control for Large Complex Projects

  • 1. Project Value Delivery PRACTICAL COST CONTROL © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m FOR LARGE, COMPLEX PROJECTS Jeremie Averous December 2014 Version 0
  • 2. More details about the topics of this presentation in our Cost Control Handbook An Advanced Project Management book published in Singapore! 2 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 3. Project Value Delivery Project Soft Power Unleashing Value Intercultural leadership Team effectiveness from Your Large, Complex Projects Leadership development Project Recovery Project Control and Reporting Project Startup support Advanced project training Project Health Check Support systems integration Remote sites integration Organizational maturity Advanced risk management Convergence planning We Empower Organizations T o b e R e l i a b l y S u c c e s s f u l i n Project Coaching Executing Large, Complex Projects Discover more on w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 4. Introduction © Project Value Delivery, 2014 3-w Dec-w 14 w . P r Page o 4 j e c t V a l u e D e l i v e r y . c o m 4 Introduction 1: Cost Control in Projects Why Cost Control is different from Accounting Interfaces with Project Control Profile & career of Cost Controllers 2: PVD Cost Control Golden Rules 3: Forecasting Principles Quantity-based Forecasting Productivity-based Forecasting 4: Reflecting forecasts in Project Reporting Sensitivities (Achievable vs Prudent) Contingency Management 5: Time-phasing of cost and Financial reporting 6: Cost Control Forensics Conclusion
  • 5. • What is Cost Control all about? 5 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 6. What is Project Cost Control? • Something (secret) that is done by Finance • Registration of invoices from vendors and booking timesheets • Trying to figure out how to squeeze everything in the budget (anybody knows what the budget is?) • Approval of invoices to pay vendors • A back-office function that is on another floor • Etc. 6 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 7. To run like clockwork, there is a lot more to Project Cost Control than what you might think! 7 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 8. Introduction Project cost control’s purpose is to maintain an accurate forecast at a specific phase of the project, based on all the information available at the time the forecast is made. The objective is to allow proper decision-making by the Project Manager. The remit of Cost Control is thus essentially different from the usual remit of Accounting. 8 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 9. COST CONTROL BASIC DEFINITIONS AND CONCEPTS © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 10. Cost Management basic definitions Forecast Variance Budget Cost To Complete ETC Commit-ment Accruals Invoiced Amount Forecast Estimate To Complete Actual Cost 10 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 11. The Project Cost Model Project Cost Model -Breakdown Structure -time-phased -Source currencies Monthly Project Performance Report (EAC, fixed FOREX) Financial P&L Reports (POC, variable FOREX) Commitments Progress Reforecasts Management of Change Cash flow model (by currency & entity) 11 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 12. Part 1: Cost Control in Projects © Project Value Delivery, 2014 3-w Dec-w 14 w . P r Page o 1 2 j e c t V a l u e D e l i v e r y . c o m 12 Introduction 1: Cost Control in Projects Why Cost Control is different from Accounting Interfaces with Project Control Profile & career of Cost Controllers 2: PVD Cost Control Golden Rules 3: Forecasting Principles Quantity-based Forecasting Productivity-based Forecasting 4: Reflecting forecasts in Project Reporting Sensitivities (Achievable vs Prudent) Contingency Management 5: Time-phasing of cost and Financial reporting 6: Cost Control Forensics Conclusion
  • 13. Starting a Project is like leaving on an Intercontinental journey 13 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 14. The sea make look calm but it will still get rough 14 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 15. The Three Fundamental Questions WHERE ARE WE? (ARE WE ON COURSE?) WHERE ARE WE GOING? WHAT DO WE NEED TO DO TO BE BACK ON COURSE? 15 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 16. In Manufacturing, the future is an extrapolation of the past 16 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 17. In Projects, the future needs to be re-forecast 17 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 18. Cost Control is not Accounting TWO DIFFERENT DISCIPLINES THAT NEED TO WORK TOGETHER COST CONTROL ACCOUNTING / FINANCE - Focus on the future - Understands the business - Follows commitments - Focus on project end point - Focus on the past - Same for any business - Follows invoicing and payment - Variable exchange rates - Cash flow management - Focus on reporting period end point (PoC accounting) 18 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 19. Usual failure mode observed in the field of Cost Control • The Urgent takes over the Important! Invoice processing Payments Angry vendors Cash management Financing Financial reporting Forecasting Trend analysis Identification of trends on actual commitments 19 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 20. Common “maturity’ observations when no strong Cost Management • Costs for internal resources as actual costs instead of standard rates – Extreme complication of cost tracking • Commitments are not tracked – only invoicing – Invoicing without commitments – Poor control on project bottom line because of invoicing delays • Poor consistency with project execution strategy and forecast schedule • No support to PM in scenario planning 20 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 21. The Cost Controller profile • A good Cost Controller is not necessarily someone with an accounting profile • Graduate engineers are often very successful • An excellent path towards Project Controls and Project Management roles. 21 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 22. The Cost Controller profile • Business skills: – understanding of contractual arrangements, – understanding of the project activity • Process skills: able to design, implement and improve information gathering processes, and the adequate Breakdown Structure • Technical skills: – knowledge of database basics, how to write requests and reports; – knowledge of the dedicated Cost Control tool • Leadership skills: ability to influence project parties to provide the required information at the right moment and to devise accurate cost forecasts 22 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 23. We Can Deal with Bad News, We Can’t Deal With Surprises 23 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 24. Get out of your seat to get the information 24 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 25. Where are the COMMITMENTS? 20M$ oversight over 3 months 25 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 26. INVOICES TAKE FOREVER TO ARRIVE. DON’t COUNT ON THEM TO KEEP CONTROL 26 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 27. Make sure you know where you’re going! 27 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 28. Don’t end your journey like this… and pennyless!... 28 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 29. Part 2: PVD Cost Control Golden Rules © Project Value Delivery, 2014 3-w Dec-w 14 w . P r Page o 2 9 j e c t V a l u e D e l i v e r y . c o m 29 Introduction 1: Cost Control in Projects Why Cost Control is different from Accounting Interfaces with Project Control Profile & career of Cost Controllers 2: PVD Cost Control Golden Rules 3: Forecasting Principles Quantity-based Forecasting Productivity-based Forecasting 4: Reflecting forecasts in Project Reporting Sensitivities (Achievable vs Prudent) Contingency Management 5: Time-phasing of cost and Financial reporting 6: Cost Control Forensics Conclusion
  • 30. PVD Project Cost Control 14 Golden Rules • The main objective of Cost Management is to enable the Project Manager to take decisions based on an accurate description of the project financial situation, derived from the organization’s current knowledge and understanding of reality. 14 Golden Rules 30 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 31. Cost Control Golden Rules 1/5 • Accountability: Budget Owners are accountable for their budget (including forecast and time-phasing). PM retains ultimate accountability. Cost Control supports and challenges • Forecasting focus: The primary focus of Cost Management is accurate and realistic Forecasting along with prompt Reporting • Maintenance of the reference ‘Project Cost Model’: the basis for all financial assessments, modelling and reporting of the Company’s Forecasts and results on the Project 31 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 32. Cost Control Golden Rules 2/5 • Project Scope & Schedule consistency: Main Contract (plus any Change Orders), and latest project schedule. Includes comprehensive understanding of the Main Contract term. • No surprises: Variances should be exclusively caused by triggering events and not by internal oversights • Candidness principles: cost acknowledgment and reporting must be candid and reflect actual understanding of reality 32 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 33. Cost Control Golden Rules 3/5 • Immediacy principle: reflect significant new costs as soon as they are anticipated even if a detailed assessment is not yet available • Timeliness of reporting: produce the relevant reports on time 33 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 34. Cost Control Golden Rules 4/5 • Commitment tracking focus: Project Cost Management is responsible for ensuring that systems, processes and procedures are in place to identify and track Commitments for all Cost Allocations and categories. • Prudence principle for Estimated at Completion Forecast: includes recognizing Costs as soon as they are probable and not recognizing Revenues until they are certain • Realism principle for ‘Achievable’ Forecast: Project Cost Management reports what is realistically achievable, both with respect to final Costs and final Revenues 34 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 35. Cost Control Golden Rules 5/5 • Accuracy over precision: cost updates should be accurate but not necessarily precise • Data integrity principle: Project Cost Management ensures the integrity and consistency of the cost and Accounting data in the Project’s Forecast and Cost • Cost reconciliation principle: project cost model and accounting are compared on a monthly basis 35 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 36. Cost Control Golden Rules • Golden Rules will be explained throughout the presentation 36 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 37. Part 3: Forecasting Principles © Project Value Delivery, 2014 3-w Dec-w 14 w . P r Page o 3 7 j e c t V a l u e D e l i v e r y . c o m 37 Introduction 1: Cost Control in Projects Why Cost Control is different from Accounting Interfaces with Project Control Profile & career of Cost Controllers 2: PVD Cost Control Golden Rules 3: Forecasting Principles Quantity-based Forecasting Productivity-based Forecasting 4: Reflecting forecasts in Project Reporting Sensitivities (Achievable vs Prudent) Contingency Management 5: Time-phasing of cost and Financial reporting 6: Cost Control Forensics Conclusion
  • 38. 38 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 39. The Three Fundamental Questions WHERE ARE WE? (ARE WE ON COURSE?) WHERE ARE WE GOING? WHAT DO WE NEED TO DO TO BE BACK ON COURSE? 39 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 40. FORECASTING FUNDAMENTALS © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 41. Should the forecast be precise or accurate? Accurate, not Precise © Project Value Delivery, 2013 Precise, not Accurate 41 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 42. • “Dead Reckoning” 42 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 43. Useful definitions External Resources (Supply-Chain) Procurement Subcontracting Purchase Order (Purchase Order) Equipment Subcontract Bulk, Standard Equipment Complicated Services 43 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 44. 2 main types of Forecasting BULK & STANDARD MATERIAL SERVICES, SUBCONTRACTS Quantity-based Remains to Commit Vs Committed Productivity based Estimate to Complete Vs Estimate at Completion 44 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 45. • What are the conditions for good forecast?? 45 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 46. Conditions for Forecast Quality • Committed Budget Owners – Each Work Package to have ONE Budget Owner – Avoid Padding of budgets by Budget Owners • Adequate communication between project parties – A good cost engineer/controller seeks information and does not remain at his/her desk • Appropriate Breakdown Structure – Relevant granularity and fit with project execution structure – No need of high level of detail • Don’t follow cost at Engineering CTR level 46 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 47. Forecast for Revenue • Recognition of Revenue in Forecast for Variation Orders follows very strict rules – No recognition when VO is not signed – Some organizations allows exceptions but: • require the highest levels of approval • Requires scope of work approval by Client • Needs to be accepted by auditors 47 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 48. BULK/ QUANTITIES FORECASTING FUNDAMENTALS © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 49. Bulk allowance management Forecasting Bulk Quantities FORECAST Net MTO ERECTED (Bill of Material) Allowance for Accuracies [Engineering] Allowance for MTO exclusions [Engineering] (maturity of MTO) Supply factor & cuts, nesting [Procurement] General Risk & Opportunity Contingency 49 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 50. Forecast for Bulk Procurement • Everything is based on the right level of allowances – Be clear on allowances + contingency – Allowance for supply/nesting is supplier and fabricator dependent! – Make sure receipt is done properly – Be clear on treatment of extra material (take-back clause, scrap etc) 50 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 51. EARNED VALUE FORECASTING FUNDAMENTALS © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 52. 12h flight 52 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 53. 53 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m = COST
  • 54. We’ve been flying for 6 hours. We spent 50% of the fuel. Are we OK? 54 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 55. © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 56. We’ve done half the way. We spent 40% of the fuel. Are we OK? 56 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 57. Project Controls is a discipline by itself • My cost is lower than expected: what does it mean? • My physical progress is lower than expected: what does it mean? • One risk was realized: what does it mean? Earned Value Analysis 57 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 58. Budget Cost Variance (<0) Schedule Variance (>0) Time $ Earned Value Analysis: Forecasting using EVM Forecast considering Cost Performance Index AC today Forecast considering Future as in initial budget EV BC CPI= SPI= EV AC EV BC 58 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 59. What can we take from Earned Value Analysis? 2 Legs to a Sound Forecast Quality of Commitments Tracking Quality of Schedule Progress data Actual Physical Progress?? 59 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 60. Forecast Trick • Investigate quality of forecast when progress on a work package is about 20-30% – Earlier: not enough trend – Later: too late! 60 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 61. Advanced Earned Value • Take into account that productivity changes with progress! – Typically productivity diminishes when progress reaches > 80% • For good quality forecast: – pinpoint deliverables that have been completed already – measure productivity on completed deliverables to extrapolate to the rest of the project! 61 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 62. Typical example of productivity decrease in engineering Engineering productivity ~100% 0% • Example of causes: Time in project – Physical progress measurement standard optimistic – Rework on documents “AFC” (further revisions) – Review process more onerous than expected 62 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 63. Cost Management basic concepts Different configurations (right or wrong?) 63 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 64. Cost Management basic concepts Budget Commitment Invoiced EAC WRONG! Actual Cost 64 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 65. Cost Management basic concepts Budget Commitment Invoiced EAC WRONG! Actual Cost 65 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 66. Cost Management basic concepts Budget Commitment Invoiced EAC WRONG! Actual Cost 66 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 67. Cost Management basic concepts Budget Commitment OK BUT CAREFUL Invoiced EAC Actual Cost 67 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 68. Cost Management basic concepts Budget WRONG! Commitment Invoiced EAC Actual Cost 68 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 69. BREAKDOWN STRUCTURE ISSUES © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 70. 70 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m Design the appropriate breakdown !
  • 71. What are the issues to take into account? • Reporting • Client requirements, • Legal entities • In-/Out-country • specific costs that are early indicators e.g. airfreight costs • Subcontracting strategy • Allowances to be split out • One WP should generally refer to one type of cost and cost follow-up method. 71 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 72. Too much detail drowns the team and removes agility Optimal Breakdown Detail Range Breakdown Structure detail Effectiveness Too little detail will not allow to grasp the project drivers 72 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 73. Project Control traps 73 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 74. Project Control traps Too much detail! Not enough time for analysis 74 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 75. KEEPING TRACK OF ALL VARIANCES © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 76. Data Integrity: Variances traceability • All Forecast Variances must be traceable – Cost control to maintain detailed (WP by WP) register of all EAC variances to allow • Auditability trail, • Keeping the history makes it easier to hand over cost control of the project to a new person if needed, • Allows to track discrepancies or budgets that would need more attention by looking in the past at all variances introduced in the cost model. • Repeated variances on a WP is an indicator of an issue to be investigated 76 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 77. WATCH FOR CONSEQUENTIAL COSTS © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 78. Watch for consequential costs! • While we have covered the different phases of a project, it is essential to always analyze if a Variance observed might not lead to other Variances: – Late engineering leading to claims and delays from suppliers – Late procurement leading to extra transportation costs (airfreight) and offshore standby – Late fabrication leading to offshore standby – Etc • Always seek the root cause and examine if no Consequential Variances! 78 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 79. Part 4: Reflecting Forecasts in Project Reporting © Project Value Delivery, 2014 3-w Dec-w 14 w . P r Page o 7 9 j e c t V a l u e D e l i v e r y . c o m 79 Introduction 1: Cost Control in Projects Why Cost Control is different from Accounting Interfaces with Project Control Profile & career of Cost Controllers 2: PVD Cost Control Golden Rules 3: Forecasting Principles Quantity-based Forecasting Productivity-based Forecasting 4: Reflecting forecasts in Project Reporting Sensitivities (Achievable vs Prudent) Contingency Management 5: Time-phasing of cost and Financial reporting 6: Cost Control Forensics Conclusion
  • 80. EAC and ‘Achievable’ • EAC - Forecast: PRUDENT P80 • ‘Achievable’ from Sensitivity Analysis FORECAST and ‘ACHIEVABLE’ are both equally important 80 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 81. Reforecasting for Revenue Unsigned Change Order Cost EAC Cost Revenue Sensitivities 81 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 82. Forecast and Achievable Forecast Achievable Single Project Accounting Business Results Expectations 82 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 83. Reforecasting for COST When you know something is going to happen to your cost forecast, don’t wait until you have got all your cost elements to reforecast! Reforecast immediately (as soon as practicable) even if you have only an order of magnitude! 83 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 84. Sensitivities: the right order BEST ‘Achievable’ EAC - FORECAST WORST 84 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 85. FORECASTING FOR CONTINGENCY © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 86. Contingency evolution during project execution CONTINGENCY IS OWNED BY SENIOR MANAGEMENT Contingency Contingency level as released by Senior Management Time in the project The area between the two curves is in effect Management contingency Natural evolution of calculated (‘Monte Carlo’) for contingency [based on ETC] 86 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 87. Contingency: Caution • Releasing contingency to compensate for higher costs compared to the budget is not acceptable. • The engagement of the contingency ‘reserve’ is one of the ultimate responsibilities of the Project Manager • At any time it is not permissible to release contingency below the calculated contingency. 87 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 88. A BAD EXAMPLE ON A 36 MO PROJECT Contingency is used (too early) to cover cost overruns Forecast Revenue Forecast Total Cost (EAC) Forecast total Cost w/o contingency 18 months 88 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 89. PROJECT DYNAMICS © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 90. $ Forecast Profit evolution during project execution Late recognition of Change Orders create a second sudden margin improvement Late release of contingency create a sudden margin improvement Project Forecast cost End of Integration/ Commissioning Time in the project Project Forecast revenue Project Contingency 90 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 91. $ Achievable profit evolution during project execution Achievable revenue Time in the project Achievable cost 91 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 92. Part 5: Time-phasing of Cost and Financial Reporing © Project Value Delivery, 2014 3-w Dec-w 14 w . P r Page o 9 2 j e c t V a l u e D e l i v e r y . c o m 92 Introduction 1: Cost Control in Projects Why Cost Control is different from Accounting Interfaces with Project Control Profile & career of Cost Controllers 2: PVD Cost Control Golden Rules 3: Forecasting Principles Quantity-based Forecasting Productivity-based Forecasting 4: Reflecting forecasts in Project Reporting Sensitivities (Achievable vs Prudent) Contingency Management 5: Time-phasing of cost and Financial reporting 6: Cost Control Forensics Conclusion
  • 93. Forecasting and Time-Spread • Forecasting must not just address the issue of Estimate-at-Completion forecast, But also the forecast needs to be times-spread for each Work Package! ACTUALS TODAY FORECAST M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 WP1 0 0 0 456 56 435 657 7658 878 9769 969 969 63 242 WP2 0 0 0 0 0 5456 646 6574 7547 765 989 1324 536 5477 WP3 4235 535 536 636 47 474 5687 58 6969 979 70 721 21545 3452 WP4 44 44 44 44 44 44 55 55 77 0 0 0 0 0 WP5 75 0 0 5536 74 7657 0 0 43 6326 0 0 0 93 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 94. Why is Time-Spread important? For long projects, proper time-spread of cost & revenue is critical to the organization’s financial performance, and in particular to market anticipation (quarterly & yearly) >> SHARE PRICE OF COMPANY! 94 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 95. What is Percentage of Completion (POC) Accounting? • PoC is the method chosen to report long projects lasting over several reporting periods • PoC= Actual cost spent Total forecast cost • Recognized Profit = PoC x Total Forecast Profit 95 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 96. Cost POC and physical progress POC • Cost POC and Physical progress POC are different – Cost POC is generally lower than Physical progress POC • If there is too much of a difference between cost POC and physical progress POC, INVESTIGATE!! 96 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 97. What is PoC accounting? Revenue Cost Profit Time 97 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 98. What is PoC accounting? Recognized Profit Time Profit 98 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 99. Why should PM’s be concerned? 99 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 100. PMs and PoC accounting PM’s are supposed to focus on the ultimate performance of the project at completion However, PM you need to be aware of the effect of : The variability of the reported project result On The Company’s financial result during the execution of the Project 100 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 101. The main PoC accounting effects 101 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 102. The amplification effect PoC accounting amplifies the impact of changes in project profit forecast 102 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 103. The amplification effect Recognized Profit Time Profit EVENT 103 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 104. The amplification effect Recognized Profit Time Profit 104 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 105. The delay effect • Delay (slow progress) will impact significantly revenue recognition for a given period – significant impact on company’s forecast short term financials 105 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 106. The delay amplification effect Recognized Profit Time Profit DELAY 106 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 107. Part 6: Cost Control Forensics © Project Value Delivery, 2014 3-w Dec-w 14 w . P r Page o 1 j 07 e c t V a l u e D e l i v e r y . c o m 107 Introduction 1: Cost Control in Projects Why Cost Control is different from Accounting Interfaces with Project Control Profile & career of Cost Controllers 2: PVD Cost Control Golden Rules 3: Forecasting Principles Quantity-based Forecasting Productivity-based Forecasting 4: Reflecting forecasts in Project Reporting Sensitivities (Achievable vs Prudent) Contingency Management 5: Time-phasing of cost and Financial reporting 6: Cost Control Forensics Conclusion
  • 108. The Three Fundamental Questions WHERE ARE WE? (ARE WE ON COURSE?) WHERE ARE WE GOING? WHAT DO WE NEED TO DO TO BE BACK ON COURSE? 108 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 109. What information? How do we make sense of it? 109 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 110. What is Project Controls? Project Controls is about building information sensors, and making sense of the information. 110 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 111. Cost Control Forensics: 3 levels of maturity • Level 1: quality of Commitments and Actuals – Actuals not Invoiced cost, comprehensive commitments, cost breakdown structure • Level 2: quality of Forecast – Consistency with project execution incl. time-phasing, allowances & contingency management, sensitivities, trends checking • Level 3: support to decision-making – Ability to run scenario analysis 111 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 112. Conclusion © Project Value Delivery, 2014 3-w Dec-w 14 w . P r Page o 1 j 12 e c t V a l u e D e l i v e r y . c o m 112 Introduction 1: Cost Control in Projects Why Cost Control is different from Accounting Interfaces with Project Control Profile & career of Cost Controllers 2: PVD Cost Control Golden Rules 3: Forecasting Principles Quantity-based Forecasting Productivity-based Forecasting 4: Reflecting forecasts in Project Reporting Sensitivities (Achievable vs Prudent) Contingency Management 5: Time-phasing of cost and Financial reporting 6: Cost Control Forensics Conclusion
  • 113. HOW Are you taking decisions?!? 113 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 114. Is that the way you are flying? 114 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 115. Conclusion Cost Control for Large, Complex, long duration projects requires – Structure – Consistency – Discipline …shared by all the project team. Cost Control is in charge of advising the project manager and making sure that the processes run reliably Communicate with the team! Invest yourself as much as possible at the start of the project – this will decide 90% of the outcome 115 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 116. PVD Project Cost Control 14 Golden Rules • The main objective of Cost Management is to enable the Project Manager to take decisions based on an accurate description of the project financial situation, derived from the organization’s current knowledge and understanding of reality. 14 Golden Rules 116 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 117. Cost Control Golden Rules 1/5 • Accountability: Budget Owners are accountable for their budget (including forecast and time-phasing). PM retains ultimate accountability. Cost Control supports and challenges • Forecasting focus: The primary focus of Cost Management is accurate and realistic Forecasting along with prompt Reporting • Maintenance of the reference ‘Project Cost Model’: the basis for all financial assessments, modelling and reporting of the Company’s Forecasts and results on the Project 117 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 118. Cost Control Golden Rules 2/5 • Project Scope & Schedule consistency: Main Contract (plus any Change Orders), and latest project schedule. Includes comprehensive understanding of the Main Contract term. • No surprises: Variances should be exclusively caused by triggering events and not by internal oversights • Candidness principles: cost acknowledgment and reporting must be candid and reflect actual understanding of reality 118 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 119. Cost Control Golden Rules 3/5 • Immediacy principle: reflect significant new costs as soon as they are anticipated even if a detailed assessment is not yet available • Timeliness of reporting: produce the relevant reports on time 119 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 120. Cost Control Golden Rules 4/5 • Commitment tracking focus: Project Cost Management is responsible for ensuring that systems, processes and procedures are in place to identify and track Commitments for all Cost Allocations and categories. • Prudence principle for Estimated at Completion Forecast: includes recognizing Costs as soon as they are probable and not recognizing Revenues until they are certain • Realism principle for ‘Achievable’ Forecast: Project Cost Management reports what is realistically achievable, both with respect to final Costs and final Revenues 120 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 121. Cost Control Golden Rules 5/5 • Accuracy over precision: cost updates should be accurate but not necessarily precise • Data integrity principle: Project Cost Management ensures the integrity and consistency of the cost and Accounting data in the Project’s Forecast and Cost • Cost reconciliation principle: project cost model and accounting are compared on a monthly basis 121 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 122. Cost Control Golden Rules • Golden Rules have been explained throughout the presentation 122 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 123. Get out of your seat to get the information 123 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 124. Project Value Delivery THANK YOU! We Empower Organizations T o b e R e l i a b l y S u c c e s s f u l i n Executing Large, Complex Projects Discover more on w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 125. Project Value Delivery Project Soft Power Unleashing Value Intercultural leadership Team effectiveness from Your Large, Complex Projects Leadership development Project Recovery Project Control and Reporting Project Startup support Advanced project training Project Health Check Support systems integration Remote sites integration Organizational maturity Advanced risk management Convergence planning We Empower Organizations T o b e R e l i a b l y S u c c e s s f u l i n Project Coaching Executing Large, Complex Projects Discover more on w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 126. More details about the topics of this presentation in our Cost Control Handbook An other Advanced Project Management book by Project Value Delivery 126 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 127. Project Value Delivery books Available on all e-bookshops 127 © Project Value Delivery, 2014 w w w . P r o j e c t V a l u e D e l i v e r y . c o m