SlideShare a Scribd company logo
COLLEGE OF ENGINEERING
           Construction Management

                       Group 3
By
1- Saleh Aladdadh
2- Naif Alharbi
3- Salman Almansor



                    Submitted to .Dr.

                  Tomas Ucol Ganiron, Jr
PROJECT CONTROL PROCESS



- What is Controlling Process
   - PM responsibility




                                2
Advanced Control: An
     Overview

  I attribute my success to
  this: I never gave or took
           an excuse.
     Florence Nightingale



                               3
PROJECT CONTROL PROCESS

Purpose : to ensure that project objectives are met by monitoring and
measuring progress and taking corrective actions when necessary




                                                                   4
Progress Measurement


    If we don’t change our
direction, we are likely to end
   up where we’re headed.
          Anonymous



                                  5
Traditional Approaches to Progress
          Measurement


• Budget vs. actual
• Percent complete
• “Trust me”



                              6
Modern Approaches

• Smaller projects or projects with unstable
  scope:
    – Weekly or biweekly deliverables
    – Done or not done
• Larger projects:
    – Earned value



                                               7
Earned Value Concepts




                        8
Earned Value Mechanics

• Build (and plot) your baseline
• Record (and plot) the actuals
• Measure (and plot) progress




                                   9
Build Your Baseline

• Information developed by planning:
    – WBS with 108 technical activities and 18
      management activities.
    – Estimates show that all 126 activities will
      require 1 person for 1 week.
    – You are constrained to have three full-time
      staffers plus one half-time project manager.
    – Staff and PM both cost $1,000 per week.

                                                     10
Build Your Baseline

Month      Staff     PM       Total
  1       $12,000    $2,000   $14,000
  2       $12,000    $2,000   $14,000
 …          …         …         …

  9       $12,000    $2,000   $14,000
          $108,00             $126,00
Total               $18,000
                0                   0

                                        11
Plot Your Baseline

                          Scheduled Cost
                            ($126,000)
Cumulative
  Values




                                    Time
                                           12
Record Your Actuals

Month # Staff   Staff $    PM      Total
                $12,00             $14,00
  1      3.5              $2,000
                     0                  0
                $12,00             $14,00
  2      3.5              $2,000
                     0                  0
                $16,00             $19,00
  3      4.7              $3,000
                     0                  0
                $16,00             $18,00
  4      4.5              $2,000
                     0                  0
         n/a    $56,00             $65,00
Total                     $9,000
                     0                  0
                                            13
Plot Your Actuals

                          Scheduled Cost
                            ($126,000)
Cumulative
  Values




                Actual
                 Cost
              ($65,000)




                                    Time
                                           14
Measure Your Progress
 Earned value = budget for completed item
Mo. Done      Not    Staff   PM      Total
                                     $12,00
 1     10+2   2     $10,000 $2,000
                                          0
                                     $11,00
 2     9+2    5      $9,000 $2,000
                                          0
                                     $15,00
 3     13+2   4     $13,000 $2,000
                                          0
                                     $18,00
 4     16+2   0     $16,000 $2,000
                                          0
                                     $56,00
Tot.   56     n/a   $48,000 $8,000            15
                                          0
Plot Your Progress

                                  Scheduled Cost
                                    ($126,000)
Cumulative
  Values




                Actual
                 Cost
              ($65,000)



                          Earned Value ($56,000)

                                             Time
                                                    16
Use Ratios to
         Estimate Completion
• Cost Performance Index (CPI) =
   Earned Value / Actual Cost
• Cost Estimate At Completion (Cost EAC) =
   Total Scheduled Cost / CPI
• Schedule Performance Index (SPI) =
   Earned Value / Scheduled Cost
• Schedule EAC = Planned Duration / SPI
                                             17
Sample Earned Value Calculations

• Cost Performance Index (CPI) =
      56,000 / 65,000 = 0.86

• Cost Estimate At Completion (Cost EAC) =
      126,000 / CPI = 126,000 / 0.86 =
       146,500

• Schedule Performance Index (SPI) =
      56,000 / 56,000 = 1.00

• Schedule EAC = 9 months / 1.0 = 9 months
                                             18
Other Earned Value Acronyms

• SC = BCWS = PV
   – Budgeted Cost of Work Scheduled
   – Planned Value
• AC = ACWP
   – Actual Cost of Work Performed
• EV = BCWP
   – Budgeted Cost of Work Performed

                                       19
More Earned Value
        Acronyms

                         Estimate
Budgeted At Completion
                             d
        (BAC)
                         Overrun
                   Estimate To
 Actual Cost
                  Complete (ETC)

  Estimate At Completion (EAC)

                                    20
Sample Values


                          Total Scheduled Cost = 3,500
Cumulative
  Values




             Actual Cost = 1,800            Duration =
                                            12 months

                                   Budgeted Cost = 900

                           Earned Value = 600

                                          Time
                                                         21
Sample Earned Value Calculations

• Cost Performance Index (CPI) =
      600 / 1,800 = 0.33

• Cost Estimate At Completion (Cost EAC) =
      3,500 / CPI = 3,500 / 0.33 = 10,500

• Schedule Performance Index (SPI) =
      600 / 900 = 0.67

• Schedule EAC = 12 months / 0.67 = 18 months

                                             22
… continued


  Budget =
                Estimated Overrun = 7,000
   3,500

Actual
         Cost Estimate To Complete (ETC) =
  =
                       8,700
1,800

Cost Estimate At Completion (EAC) = 10,500


                                             23
Interpreting Results

• Negative is bad:
    – If CV < 0, you are over budget.
    – If SV < 0, you are behind schedule.
• Less than 1.0 is bad:
    – If CPI < 1.0, you are over budget.
    – If SPI < 1.0, you are behind schedule.


                                               24
Time Variance


• Earned Schedule (ES) — the number of
  periods planned for the current Earned Value.
• Actual Time (AT) — the number of periods
  that have elapsed since the project started.
• TPI (Time Performance Index) = ES / AT


                                              25
… continued …


                                 Scheduled Cost
Cumulative
  Values




                       AT = 22
                                       PD = 52
             ES = 18



                           Earned Value


                                       Time
                                                  26
… continued

• Time to Complete (TC) =
      Planned Duration / TPI =
      52 / 0.8 = 65 = 13 weeks late
• SPI will give similar results early in the project,
  but becomes less reliable later.



                                                   27
Summary of
                Key Points
• Earned value is the most reliable approach to
  progress measurement when scope is
  reasonably stable.
• Keep work-items small and short to avoid
  measurement errors.




                                              28

More Related Content

What's hot

07. Project Integration Management
07. Project Integration Management07. Project Integration Management
07. Project Integration Management
BhuWan Khadka
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
Kateri Manglicmot
 
A simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementA simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value Management
ProPM Academy
 
Earned value management
Earned value managementEarned value management
Earned value management
Ashif AR
 
Earned value management for Beginners
Earned value management for Beginners Earned value management for Beginners
Earned value management for Beginners Shenin Hassan
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
Saqib Raza
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
mohamed elashri
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost Management
BhuWan Khadka
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
Russell Taylor BEng CEng FAPM FIET
 
A brief on project time management
A brief on project time managementA brief on project time management
A brief on project time management
Imran Jamil
 
Project cost management PMBOK 5th Edition
Project cost management PMBOK 5th EditionProject cost management PMBOK 5th Edition
Project cost management PMBOK 5th Edition
pankajsh10
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)Glen Alleman
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Schedulingsslovepk
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
waleed hamdy
 
Project Duration Estimation
Project Duration EstimationProject Duration Estimation
Project Duration Estimation
Harsh Behl
 
Project termination, reporting and project closure
Project termination, reporting and project closureProject termination, reporting and project closure
Project termination, reporting and project closure
Aswin prakash i , Xantus Technologies
 
Common causes of cost overruns in construction projects
Common causes of cost overruns in construction projectsCommon causes of cost overruns in construction projects
Common causes of cost overruns in construction projects
SANJEEV Wazir
 
Project Management Tools and Techniques
Project Management Tools and TechniquesProject Management Tools and Techniques
Project Management Tools and Techniques
MaRS Discovery District
 

What's hot (20)

07. Project Integration Management
07. Project Integration Management07. Project Integration Management
07. Project Integration Management
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
A simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementA simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value Management
 
Earned value management
Earned value managementEarned value management
Earned value management
 
Earned value management for Beginners
Earned value management for Beginners Earned value management for Beginners
Earned value management for Beginners
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost Management
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
A brief on project time management
A brief on project time managementA brief on project time management
A brief on project time management
 
Project cost management PMBOK 5th Edition
Project cost management PMBOK 5th EditionProject cost management PMBOK 5th Edition
Project cost management PMBOK 5th Edition
 
07 project cost management
07 project cost management07 project cost management
07 project cost management
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Scheduling
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
 
Project Duration Estimation
Project Duration EstimationProject Duration Estimation
Project Duration Estimation
 
Project termination, reporting and project closure
Project termination, reporting and project closureProject termination, reporting and project closure
Project termination, reporting and project closure
 
Common causes of cost overruns in construction projects
Common causes of cost overruns in construction projectsCommon causes of cost overruns in construction projects
Common causes of cost overruns in construction projects
 
Pert
PertPert
Pert
 
Project Management Tools and Techniques
Project Management Tools and TechniquesProject Management Tools and Techniques
Project Management Tools and Techniques
 

Viewers also liked

PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS
Akash Prasanna
 
ODD + Project Control 0.9
ODD + Project Control 0.9ODD + Project Control 0.9
ODD + Project Control 0.9
Jonathan Herring
 
Project control
Project controlProject control
Project control
Alexander Prins
 
How to Create S Curve by MS Project 2013
How to Create S Curve by MS Project 2013How to Create S Curve by MS Project 2013
How to Create S Curve by MS Project 2013
Ong-Art Sanpinit
 
Project Monitoring And Controlling
Project Monitoring And ControllingProject Monitoring And Controlling
Project Monitoring And Controlling
Tom Milner
 
Project Controlling and Project Monitoring
Project Controlling and Project MonitoringProject Controlling and Project Monitoring
Project Controlling and Project Monitoringharoldtaylor1113
 
Project Monitoring and Control
Project Monitoring and ControlProject Monitoring and Control
Project Monitoring and Control
guy_davis
 
Project control. Management
Project control. ManagementProject control. Management
Project control. Management
Marius Miron
 

Viewers also liked (10)

PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS
 
Chap013 4er1
Chap013 4er1Chap013 4er1
Chap013 4er1
 
ODD + Project Control 0.9
ODD + Project Control 0.9ODD + Project Control 0.9
ODD + Project Control 0.9
 
Project control
Project controlProject control
Project control
 
How to Create S Curve by MS Project 2013
How to Create S Curve by MS Project 2013How to Create S Curve by MS Project 2013
How to Create S Curve by MS Project 2013
 
Project Monitoring and Control
Project Monitoring and ControlProject Monitoring and Control
Project Monitoring and Control
 
Project Monitoring And Controlling
Project Monitoring And ControllingProject Monitoring And Controlling
Project Monitoring And Controlling
 
Project Controlling and Project Monitoring
Project Controlling and Project MonitoringProject Controlling and Project Monitoring
Project Controlling and Project Monitoring
 
Project Monitoring and Control
Project Monitoring and ControlProject Monitoring and Control
Project Monitoring and Control
 
Project control. Management
Project control. ManagementProject control. Management
Project control. Management
 

Similar to Project Control Process

Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
Mansoor Shoaib
 
Figuring out where you are and does your contractor agree?
Figuring out where you are and does your contractor agree?Figuring out where you are and does your contractor agree?
Figuring out where you are and does your contractor agree?
Public Technology Institute
 
Sample cba contact center upgrade project
Sample cba   contact center upgrade projectSample cba   contact center upgrade project
Sample cba contact center upgrade project
Ken Hicks
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)Glen Alleman
 
fm10e ch 10.pptx
fm10e ch 10.pptxfm10e ch 10.pptx
fm10e ch 10.pptx
jhonbauckland
 
Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the Numbers
Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the NumbersSymposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers
Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the Numbers
PMI-Montréal
 
case study in corporate finance npv irr arr
case study in corporate finance npv irr arrcase study in corporate finance npv irr arr
case study in corporate finance npv irr arr
manjhujayakumar
 
Business Finance Chapter 8
Business Finance Chapter 8Business Finance Chapter 8
Business Finance Chapter 8
Tinku Kumar
 
Capital budgeting the basics-2
Capital budgeting the basics-2Capital budgeting the basics-2
Capital budgeting the basics-2Junaid Alam
 
Module 06 Adv PM Budget Mgmt.ppt
Module 06 Adv PM Budget Mgmt.pptModule 06 Adv PM Budget Mgmt.ppt
Module 06 Adv PM Budget Mgmt.ppt
SandeepChauhan334237
 
Module 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.pptModule 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.ppt
AsBali1
 
Financial concepts
Financial conceptsFinancial concepts
Financial concepts
cebrandt
 
Capital budgeting techniques
Capital budgeting techniquesCapital budgeting techniques
Capital budgeting techniquesusman_sabir
 
Evm class 02 1to15 by upad
Evm   class 02  1to15 by upadEvm   class 02  1to15 by upad
Evm class 02 1to15 by upad
hvostik
 
Chapter 8.Capital Budgeting Techniques
Chapter 8.Capital Budgeting TechniquesChapter 8.Capital Budgeting Techniques
Chapter 8.Capital Budgeting Techniques
ZahraMirzayeva
 

Similar to Project Control Process (20)

Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Figuring out where you are and does your contractor agree?
Figuring out where you are and does your contractor agree?Figuring out where you are and does your contractor agree?
Figuring out where you are and does your contractor agree?
 
Sample cba contact center upgrade project
Sample cba   contact center upgrade projectSample cba   contact center upgrade project
Sample cba contact center upgrade project
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)
 
fm10e ch 10.pptx
fm10e ch 10.pptxfm10e ch 10.pptx
fm10e ch 10.pptx
 
Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the Numbers
Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the NumbersSymposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers
Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the Numbers
 
case study in corporate finance npv irr arr
case study in corporate finance npv irr arrcase study in corporate finance npv irr arr
case study in corporate finance npv irr arr
 
Business Finance Chapter 8
Business Finance Chapter 8Business Finance Chapter 8
Business Finance Chapter 8
 
Ch.11
Ch.11Ch.11
Ch.11
 
Capital budgeting the basics-2
Capital budgeting the basics-2Capital budgeting the basics-2
Capital budgeting the basics-2
 
NEDSI-2015_Final
NEDSI-2015_FinalNEDSI-2015_Final
NEDSI-2015_Final
 
Module 06 Adv PM Budget Mgmt.ppt
Module 06 Adv PM Budget Mgmt.pptModule 06 Adv PM Budget Mgmt.ppt
Module 06 Adv PM Budget Mgmt.ppt
 
Module 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.pptModule 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.ppt
 
Cai annual conference 2002final
Cai annual conference 2002finalCai annual conference 2002final
Cai annual conference 2002final
 
Financial concepts
Financial conceptsFinancial concepts
Financial concepts
 
EVMS Made Simple
EVMS Made SimpleEVMS Made Simple
EVMS Made Simple
 
Capital budgeting techniques
Capital budgeting techniquesCapital budgeting techniques
Capital budgeting techniques
 
Evm class 02 1to15 by upad
Evm   class 02  1to15 by upadEvm   class 02  1to15 by upad
Evm class 02 1to15 by upad
 
Chapter 8.Capital Budgeting Techniques
Chapter 8.Capital Budgeting TechniquesChapter 8.Capital Budgeting Techniques
Chapter 8.Capital Budgeting Techniques
 
Chapter 9 q&p
Chapter 9 q&pChapter 9 q&p
Chapter 9 q&p
 

More from haroldtaylor1113

Design Coordinates Incorporated
Design Coordinates IncorporatedDesign Coordinates Incorporated
Design Coordinates Incorporated
haroldtaylor1113
 
Case Study No. 9-Philippines’ Integrated Stormwater Management
Case Study No. 9-Philippines’ Integrated Stormwater ManagementCase Study No. 9-Philippines’ Integrated Stormwater Management
Case Study No. 9-Philippines’ Integrated Stormwater Management
haroldtaylor1113
 
Case Study No. 2-Lumot lake in Laguna
Case Study No. 2-Lumot lake in LagunaCase Study No. 2-Lumot lake in Laguna
Case Study No. 2-Lumot lake in Laguna
haroldtaylor1113
 
Case Study No. 1-Groundwater Supply of Cavite Province
Case Study No. 1-Groundwater Supply of Cavite ProvinceCase Study No. 1-Groundwater Supply of Cavite Province
Case Study No. 1-Groundwater Supply of Cavite Province
haroldtaylor1113
 
Case Study No. 8-Managing Floods in Metro Manila
Case  Study No. 8-Managing Floods in Metro ManilaCase  Study No. 8-Managing Floods in Metro Manila
Case Study No. 8-Managing Floods in Metro Manila
haroldtaylor1113
 
Case Study No. 12-Presidential Decree No. 1067
Case Study No. 12-Presidential Decree No. 1067Case Study No. 12-Presidential Decree No. 1067
Case Study No. 12-Presidential Decree No. 1067
haroldtaylor1113
 
Case Study No. 11- Hydroelectric Power Plant in the Philippines
Case Study No. 11- Hydroelectric Power Plant in the PhilippinesCase Study No. 11- Hydroelectric Power Plant in the Philippines
Case Study No. 11- Hydroelectric Power Plant in the Philippines
haroldtaylor1113
 
Case Study No. 10-Construction of Box Culverts in the Philippines
Case Study No. 10-Construction of Box Culverts in the PhilippinesCase Study No. 10-Construction of Box Culverts in the Philippines
Case Study No. 10-Construction of Box Culverts in the Philippines
haroldtaylor1113
 
Case Study No. 6-Road and Drainage Improvement Project in Caloocan City
Case Study No. 6-Road and Drainage Improvement Project in Caloocan CityCase Study No. 6-Road and Drainage Improvement Project in Caloocan City
Case Study No. 6-Road and Drainage Improvement Project in Caloocan City
haroldtaylor1113
 
Case Study No. 5-Pasig River Open Channel in Aquaculture
Case Study No. 5-Pasig River Open Channel in AquacultureCase Study No. 5-Pasig River Open Channel in Aquaculture
Case Study No. 5-Pasig River Open Channel in Aquaculture
haroldtaylor1113
 
Case Study No. 4-Design of Water Distribution System using Naugong spring as ...
Case Study No. 4-Design of Water Distribution System using Naugong spring as ...Case Study No. 4-Design of Water Distribution System using Naugong spring as ...
Case Study No. 4-Design of Water Distribution System using Naugong spring as ...
haroldtaylor1113
 
Case Study No. 3-Molino Dam in Bacoor, Cavite
Case Study No. 3-Molino Dam in Bacoor, CaviteCase Study No. 3-Molino Dam in Bacoor, Cavite
Case Study No. 3-Molino Dam in Bacoor, Cavite
haroldtaylor1113
 
Case Study 13-A Color for All Seasons & A New Variety of Success
Case Study 13-A Color for All Seasons & A New Variety of SuccessCase Study 13-A Color for All Seasons & A New Variety of Success
Case Study 13-A Color for All Seasons & A New Variety of Success
haroldtaylor1113
 
Case Study 12B-The Gugo Queen
Case Study 12B-The Gugo Queen  Case Study 12B-The Gugo Queen
Case Study 12B-The Gugo Queen
haroldtaylor1113
 
Case Study 12A-From Herbal Folklore to Modern Medicine
Case Study 12A-From Herbal Folklore to Modern Medicine Case Study 12A-From Herbal Folklore to Modern Medicine
Case Study 12A-From Herbal Folklore to Modern Medicine
haroldtaylor1113
 
Case Study 11-Rising Above the Competition & Thriving on IP Protection
Case Study 11-Rising Above the Competition & Thriving on IP Protection Case Study 11-Rising Above the Competition & Thriving on IP Protection
Case Study 11-Rising Above the Competition & Thriving on IP Protection
haroldtaylor1113
 
Case Study 10-Shaping a Regional IP Tool & Folk Art and the Opportunities of ...
Case Study 10-Shaping a Regional IP Tool & Folk Art and the Opportunities of ...Case Study 10-Shaping a Regional IP Tool & Folk Art and the Opportunities of ...
Case Study 10-Shaping a Regional IP Tool & Folk Art and the Opportunities of ...
haroldtaylor1113
 
Case Study 8-Electrifying Economic Development & From Heavy to Light_Accelera...
Case Study 8-Electrifying Economic Development & From Heavy to Light_Accelera...Case Study 8-Electrifying Economic Development & From Heavy to Light_Accelera...
Case Study 8-Electrifying Economic Development & From Heavy to Light_Accelera...
haroldtaylor1113
 
Case Study 9-Strategic Partnership Linked to IP in the Development & Planting...
Case Study 9-Strategic Partnership Linked to IP in the Development & Planting...Case Study 9-Strategic Partnership Linked to IP in the Development & Planting...
Case Study 9-Strategic Partnership Linked to IP in the Development & Planting...
haroldtaylor1113
 
Case Study 7- A Bold Step into the Modern Economy & A Remote Solution for a G...
Case Study 7- A Bold Step into the Modern Economy & A Remote Solution for a G...Case Study 7- A Bold Step into the Modern Economy & A Remote Solution for a G...
Case Study 7- A Bold Step into the Modern Economy & A Remote Solution for a G...
haroldtaylor1113
 

More from haroldtaylor1113 (20)

Design Coordinates Incorporated
Design Coordinates IncorporatedDesign Coordinates Incorporated
Design Coordinates Incorporated
 
Case Study No. 9-Philippines’ Integrated Stormwater Management
Case Study No. 9-Philippines’ Integrated Stormwater ManagementCase Study No. 9-Philippines’ Integrated Stormwater Management
Case Study No. 9-Philippines’ Integrated Stormwater Management
 
Case Study No. 2-Lumot lake in Laguna
Case Study No. 2-Lumot lake in LagunaCase Study No. 2-Lumot lake in Laguna
Case Study No. 2-Lumot lake in Laguna
 
Case Study No. 1-Groundwater Supply of Cavite Province
Case Study No. 1-Groundwater Supply of Cavite ProvinceCase Study No. 1-Groundwater Supply of Cavite Province
Case Study No. 1-Groundwater Supply of Cavite Province
 
Case Study No. 8-Managing Floods in Metro Manila
Case  Study No. 8-Managing Floods in Metro ManilaCase  Study No. 8-Managing Floods in Metro Manila
Case Study No. 8-Managing Floods in Metro Manila
 
Case Study No. 12-Presidential Decree No. 1067
Case Study No. 12-Presidential Decree No. 1067Case Study No. 12-Presidential Decree No. 1067
Case Study No. 12-Presidential Decree No. 1067
 
Case Study No. 11- Hydroelectric Power Plant in the Philippines
Case Study No. 11- Hydroelectric Power Plant in the PhilippinesCase Study No. 11- Hydroelectric Power Plant in the Philippines
Case Study No. 11- Hydroelectric Power Plant in the Philippines
 
Case Study No. 10-Construction of Box Culverts in the Philippines
Case Study No. 10-Construction of Box Culverts in the PhilippinesCase Study No. 10-Construction of Box Culverts in the Philippines
Case Study No. 10-Construction of Box Culverts in the Philippines
 
Case Study No. 6-Road and Drainage Improvement Project in Caloocan City
Case Study No. 6-Road and Drainage Improvement Project in Caloocan CityCase Study No. 6-Road and Drainage Improvement Project in Caloocan City
Case Study No. 6-Road and Drainage Improvement Project in Caloocan City
 
Case Study No. 5-Pasig River Open Channel in Aquaculture
Case Study No. 5-Pasig River Open Channel in AquacultureCase Study No. 5-Pasig River Open Channel in Aquaculture
Case Study No. 5-Pasig River Open Channel in Aquaculture
 
Case Study No. 4-Design of Water Distribution System using Naugong spring as ...
Case Study No. 4-Design of Water Distribution System using Naugong spring as ...Case Study No. 4-Design of Water Distribution System using Naugong spring as ...
Case Study No. 4-Design of Water Distribution System using Naugong spring as ...
 
Case Study No. 3-Molino Dam in Bacoor, Cavite
Case Study No. 3-Molino Dam in Bacoor, CaviteCase Study No. 3-Molino Dam in Bacoor, Cavite
Case Study No. 3-Molino Dam in Bacoor, Cavite
 
Case Study 13-A Color for All Seasons & A New Variety of Success
Case Study 13-A Color for All Seasons & A New Variety of SuccessCase Study 13-A Color for All Seasons & A New Variety of Success
Case Study 13-A Color for All Seasons & A New Variety of Success
 
Case Study 12B-The Gugo Queen
Case Study 12B-The Gugo Queen  Case Study 12B-The Gugo Queen
Case Study 12B-The Gugo Queen
 
Case Study 12A-From Herbal Folklore to Modern Medicine
Case Study 12A-From Herbal Folklore to Modern Medicine Case Study 12A-From Herbal Folklore to Modern Medicine
Case Study 12A-From Herbal Folklore to Modern Medicine
 
Case Study 11-Rising Above the Competition & Thriving on IP Protection
Case Study 11-Rising Above the Competition & Thriving on IP Protection Case Study 11-Rising Above the Competition & Thriving on IP Protection
Case Study 11-Rising Above the Competition & Thriving on IP Protection
 
Case Study 10-Shaping a Regional IP Tool & Folk Art and the Opportunities of ...
Case Study 10-Shaping a Regional IP Tool & Folk Art and the Opportunities of ...Case Study 10-Shaping a Regional IP Tool & Folk Art and the Opportunities of ...
Case Study 10-Shaping a Regional IP Tool & Folk Art and the Opportunities of ...
 
Case Study 8-Electrifying Economic Development & From Heavy to Light_Accelera...
Case Study 8-Electrifying Economic Development & From Heavy to Light_Accelera...Case Study 8-Electrifying Economic Development & From Heavy to Light_Accelera...
Case Study 8-Electrifying Economic Development & From Heavy to Light_Accelera...
 
Case Study 9-Strategic Partnership Linked to IP in the Development & Planting...
Case Study 9-Strategic Partnership Linked to IP in the Development & Planting...Case Study 9-Strategic Partnership Linked to IP in the Development & Planting...
Case Study 9-Strategic Partnership Linked to IP in the Development & Planting...
 
Case Study 7- A Bold Step into the Modern Economy & A Remote Solution for a G...
Case Study 7- A Bold Step into the Modern Economy & A Remote Solution for a G...Case Study 7- A Bold Step into the Modern Economy & A Remote Solution for a G...
Case Study 7- A Bold Step into the Modern Economy & A Remote Solution for a G...
 

Recently uploaded

Set off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptxSet off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptx
HARSHITHV26
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
anasabutalha2013
 
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdfMeas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
dylandmeas
 
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
taqyed
 
Unveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdfUnveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdf
Sam H
 
Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...
dylandmeas
 
Project File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdfProject File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdf
RajPriye
 
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptxCADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
fakeloginn69
 
Brand Analysis for an artist named Struan
Brand Analysis for an artist named StruanBrand Analysis for an artist named Struan
Brand Analysis for an artist named Struan
sarahvanessa51503
 
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deckPitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
HajeJanKamps
 
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
Kumar Satyam
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
ofm712785
 
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
BBPMedia1
 
Filing Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed GuideFiling Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed Guide
YourLegal Accounting
 
Role of Remote Sensing and Monitoring in Mining
Role of Remote Sensing and Monitoring in MiningRole of Remote Sensing and Monitoring in Mining
Role of Remote Sensing and Monitoring in Mining
Naaraayani Minerals Pvt.Ltd
 
What are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdfWhat are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdf
HumanResourceDimensi1
 
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdfDigital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
Jos Voskuil
 
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-indiafalcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
Falcon Invoice Discounting
 
20240425_ TJ Communications Credentials_compressed.pdf
20240425_ TJ Communications Credentials_compressed.pdf20240425_ TJ Communications Credentials_compressed.pdf
20240425_ TJ Communications Credentials_compressed.pdf
tjcomstrang
 
The-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic managementThe-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic management
Bojamma2
 

Recently uploaded (20)

Set off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptxSet off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptx
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
 
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdfMeas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
 
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
 
Unveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdfUnveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdf
 
Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...
 
Project File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdfProject File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdf
 
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptxCADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
 
Brand Analysis for an artist named Struan
Brand Analysis for an artist named StruanBrand Analysis for an artist named Struan
Brand Analysis for an artist named Struan
 
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deckPitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
 
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
 
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
 
Filing Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed GuideFiling Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed Guide
 
Role of Remote Sensing and Monitoring in Mining
Role of Remote Sensing and Monitoring in MiningRole of Remote Sensing and Monitoring in Mining
Role of Remote Sensing and Monitoring in Mining
 
What are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdfWhat are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdf
 
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdfDigital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
 
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-indiafalcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
 
20240425_ TJ Communications Credentials_compressed.pdf
20240425_ TJ Communications Credentials_compressed.pdf20240425_ TJ Communications Credentials_compressed.pdf
20240425_ TJ Communications Credentials_compressed.pdf
 
The-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic managementThe-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic management
 

Project Control Process

  • 1. COLLEGE OF ENGINEERING Construction Management Group 3 By 1- Saleh Aladdadh 2- Naif Alharbi 3- Salman Almansor Submitted to .Dr. Tomas Ucol Ganiron, Jr
  • 2. PROJECT CONTROL PROCESS - What is Controlling Process - PM responsibility 2
  • 3. Advanced Control: An Overview I attribute my success to this: I never gave or took an excuse. Florence Nightingale 3
  • 4. PROJECT CONTROL PROCESS Purpose : to ensure that project objectives are met by monitoring and measuring progress and taking corrective actions when necessary 4
  • 5. Progress Measurement If we don’t change our direction, we are likely to end up where we’re headed. Anonymous 5
  • 6. Traditional Approaches to Progress Measurement • Budget vs. actual • Percent complete • “Trust me” 6
  • 7. Modern Approaches • Smaller projects or projects with unstable scope: – Weekly or biweekly deliverables – Done or not done • Larger projects: – Earned value 7
  • 9. Earned Value Mechanics • Build (and plot) your baseline • Record (and plot) the actuals • Measure (and plot) progress 9
  • 10. Build Your Baseline • Information developed by planning: – WBS with 108 technical activities and 18 management activities. – Estimates show that all 126 activities will require 1 person for 1 week. – You are constrained to have three full-time staffers plus one half-time project manager. – Staff and PM both cost $1,000 per week. 10
  • 11. Build Your Baseline Month Staff PM Total 1 $12,000 $2,000 $14,000 2 $12,000 $2,000 $14,000 … … … … 9 $12,000 $2,000 $14,000 $108,00 $126,00 Total $18,000 0 0 11
  • 12. Plot Your Baseline Scheduled Cost ($126,000) Cumulative Values Time 12
  • 13. Record Your Actuals Month # Staff Staff $ PM Total $12,00 $14,00 1 3.5 $2,000 0 0 $12,00 $14,00 2 3.5 $2,000 0 0 $16,00 $19,00 3 4.7 $3,000 0 0 $16,00 $18,00 4 4.5 $2,000 0 0 n/a $56,00 $65,00 Total $9,000 0 0 13
  • 14. Plot Your Actuals Scheduled Cost ($126,000) Cumulative Values Actual Cost ($65,000) Time 14
  • 15. Measure Your Progress Earned value = budget for completed item Mo. Done Not Staff PM Total $12,00 1 10+2 2 $10,000 $2,000 0 $11,00 2 9+2 5 $9,000 $2,000 0 $15,00 3 13+2 4 $13,000 $2,000 0 $18,00 4 16+2 0 $16,000 $2,000 0 $56,00 Tot. 56 n/a $48,000 $8,000 15 0
  • 16. Plot Your Progress Scheduled Cost ($126,000) Cumulative Values Actual Cost ($65,000) Earned Value ($56,000) Time 16
  • 17. Use Ratios to Estimate Completion • Cost Performance Index (CPI) = Earned Value / Actual Cost • Cost Estimate At Completion (Cost EAC) = Total Scheduled Cost / CPI • Schedule Performance Index (SPI) = Earned Value / Scheduled Cost • Schedule EAC = Planned Duration / SPI 17
  • 18. Sample Earned Value Calculations • Cost Performance Index (CPI) = 56,000 / 65,000 = 0.86 • Cost Estimate At Completion (Cost EAC) = 126,000 / CPI = 126,000 / 0.86 = 146,500 • Schedule Performance Index (SPI) = 56,000 / 56,000 = 1.00 • Schedule EAC = 9 months / 1.0 = 9 months 18
  • 19. Other Earned Value Acronyms • SC = BCWS = PV – Budgeted Cost of Work Scheduled – Planned Value • AC = ACWP – Actual Cost of Work Performed • EV = BCWP – Budgeted Cost of Work Performed 19
  • 20. More Earned Value Acronyms Estimate Budgeted At Completion d (BAC) Overrun Estimate To Actual Cost Complete (ETC) Estimate At Completion (EAC) 20
  • 21. Sample Values Total Scheduled Cost = 3,500 Cumulative Values Actual Cost = 1,800 Duration = 12 months Budgeted Cost = 900 Earned Value = 600 Time 21
  • 22. Sample Earned Value Calculations • Cost Performance Index (CPI) = 600 / 1,800 = 0.33 • Cost Estimate At Completion (Cost EAC) = 3,500 / CPI = 3,500 / 0.33 = 10,500 • Schedule Performance Index (SPI) = 600 / 900 = 0.67 • Schedule EAC = 12 months / 0.67 = 18 months 22
  • 23. … continued Budget = Estimated Overrun = 7,000 3,500 Actual Cost Estimate To Complete (ETC) = = 8,700 1,800 Cost Estimate At Completion (EAC) = 10,500 23
  • 24. Interpreting Results • Negative is bad: – If CV < 0, you are over budget. – If SV < 0, you are behind schedule. • Less than 1.0 is bad: – If CPI < 1.0, you are over budget. – If SPI < 1.0, you are behind schedule. 24
  • 25. Time Variance • Earned Schedule (ES) — the number of periods planned for the current Earned Value. • Actual Time (AT) — the number of periods that have elapsed since the project started. • TPI (Time Performance Index) = ES / AT 25
  • 26. … continued … Scheduled Cost Cumulative Values AT = 22 PD = 52 ES = 18 Earned Value Time 26
  • 27. … continued • Time to Complete (TC) = Planned Duration / TPI = 52 / 0.8 = 65 = 13 weeks late • SPI will give similar results early in the project, but becomes less reliable later. 27
  • 28. Summary of Key Points • Earned value is the most reliable approach to progress measurement when scope is reasonably stable. • Keep work-items small and short to avoid measurement errors. 28