Integrating Project & Portfolio Management
Project Controls Expo – 17th Nov 2017
Emirates Stadium, London
Copyright @ 2011. All rights reserved
About the Speaker
Name: Lateef Daly
Position: Director of Europe & Middle East Operations
Organization: ARES PRISM
 20+ Year of Project Controls & Earned Value Expertise
 Finance, Estimating, Cost Engineering, Change Mgmt, System Integration
 Industries:
 Pharmaceuticals, Defence, Infrastructure, Rail, Nuclear, O&G
 Major Project Experience:
 Crossrail, TFL, High Speed 2, Horizon Nuclear, Expo 2020, Ronald Reagan
Ballistic Missile Défense Test Site
Copyright @ 2011. All rights reserved
About the Topic
Outline:
• Common Coding
• Cost Schedule Integration
• Enterprise Portfolio Management
• Utilizing Various Progress Methods
• ARES PRISM Background
• Project Lifecyle Management
• Integration Engine – Client Customizable Integrations
• Benefits of a Data Warehouse
• Data Integrity & Validation
• Reporting
Copyright @ 2011. All rights reserved
ARES PRISM Background
ARES is a full-service project
controls solution provider
 ARES formed in 1992
 First PRISM US Client in 1995
 First UK client in 2009 (Sellafield)
 UK Entity opened in 2010 to support Crossrail
 Multiple EMEA clients today with strong Repeat
Business
 Local Support Capability backed by the Central PRISM
Team
 Local Services for Project Controls, Estimating,
Scheduling and Contract Administration
Copyright @ 2011. All rights reserved
Global Clients - Common Best Practices
EPC
Nuclear / EnergyInfrastructure Mining & MetalsOil & Gas Government
Copyright @ 2011. All rights reserved
PRISM Integrated Lifecyle Management
Copyright @ 2011. All rights reserved
Integrator
PRISM Integrator
Provides:
• Connection for IT/
ERP/ Risk/ Financial
Systems
• Workflow Modeling
• Code-Free Data
Mapping
PRISM Integrated Lifecyle Management
Copyright @ 2011. All rights reserved
Estimating
PRISM Estimating
Provides:
• 2D/3D/GIS/BIM
Takeoff
• Centralized Cost
Estimates
• Quantity Survey
• Historical Data
PRISM Integrated Lifecyle Management
Copyright @ 2011. All rights reserved
Cost Management
PRISM G2 Cost
Management Provides:
• Time-Phased Budgeting
• Resource Planning
• Schedule
• Commitments
• Risk
• Performance
Measurement
• Variance Analysis
• Forecasting
• Earned Value
PRISM Integrated Lifecyle Management
Copyright @ 2011. All rights reserved
Change
PRISM G2 Change
Management Provides:
• Defined Approvers
and Reviewers
• Tracks Change
Requests
• Manages Change
Workflows
PRISM Integrated Lifecyle Management
Copyright @ 2011. All rights reserved
Engineering
PRISM G2 Engineering
Provides:
• Deliverable Status
and Tracking
• Time-Phased
Engineering
Packages
• Progress
Measurement
• Engineering
Performance
• Forecasting
PRISM Integrated Lifecyle Management
Copyright @ 2011. All rights reserved
Equipment & Materials
PRISM G2
Equipment &
Materials:
• Develops
Requisitions
• Tracks Equipment
and Attributes
• Tracks Materials
PRISM Integrated Lifecyle Management
Copyright @ 2011. All rights reserved
Contracts
PRISM G2 Contracts
Administration
Provides:
• Contract Bids
• Bid Analysis
• Award Contracts
• Vendor
Evaluations
• Contract
Scheduling
• Punch List
Tracking
• Contract Changes
PRISM Integrated Lifecyle Management
Copyright @ 2011. All rights reserved
Invoice
PRISM G2 Invoice
Management:
• Tracks Invoices
From Suppliers
• Tracks Payments
• Traces Back to
Purchase Orders
and Contracts
PRISM Integrated Lifecyle Management
Copyright @ 2011. All rights reserved
Procurement
PRISM G2
Procurement Provides:
• Requisitions &
Purchase Orders
• Procurement
Scheduling
• Shipment
Expediting,
• Supplier
Evaluations
PRISM Integrated Lifecyle Management
Copyright @ 2011. All rights reserved
Field Progress
PRISM G2 Field
Progress Provides:
• Construction
Progress &
Performance
• Installed Quantities
• Unit Rates Analysis
• Rules of Credit
• Mobile Access
• Construction
Changes
PRISM Integrated Lifecyle Management
Copyright @ 2011. All rights reserved
Docs
PRISM Docs
Provides:
• Document Access
and Control
• Automated
Processes
• Team
Collaboration
PRISM Integrated Lifecyle Management
Copyright @ 2011. All rights reserved
Dashboard, Reporting
and Data Warehouse
PRISM Dashboard,
Reporting & Data
Warehouse Provides:
• Executive Insight
• Visualized Data
• Project
Performance
• Forecasts
• Embedded KPIs
PRISM Integrated Lifecyle Management
Copyright @ 2011. All rights reserved
Enterprise Portfolio Management
PRISM Enterprise
Portfolio Reporting
PRISMProjectSpecific
Configuration
Calendars CurrenciesWBS/OBS/Asset Cost Elements
Lbr
Mtl
Eqp
Central Team Report Formats
PRISMEnterprise
Configuration
• Define and promote a Common
Enterprise Structure that is clearly
defined and shared across all
projects
• Still have flexibility
to define project by
project specific
configurations that
rollup to the
Enterprise Level
• Single point of truth for
portfolio reporting
Project A
Calendars
Currencies
WBS/OBS/Asset
Cost Elements
Lbr
Mtl
Eqp
Project Teams
Report Formats
Can Be Setup Same or Unique
Project B
Calendars
Currencies
WBS/OBS/Asset
Cost Elements
Lbr
Mtl
Eqp
Project Teams
Report Formats
Can Be Setup Same or Unique
Project C
Calendars
Currencies
WBS/OBS/Asset
Cost Elements
Lbr
Mtl
Eqp
Project Teams
Report Formats
Can Be Setup Same or Unique
Copyright @ 2011. All rights reserved
Integrated Coding Structure
Cost & Progress
Schedule
Contracts
Estimate
DEFINE SINGLE
INTEGRATED
STRUCTURE
* Provides integration &
traceability from Original
Baseline Estimate and our
operating Budget /Cost data,
which is then time phased with
the Schedule start & finish dates
Copyright @ 2011. All rights reserved
Creation of Integrated Coding Structure
Estimate
Level 1
Estimate
Level 2
Estimate
Etc…
Estimate
Etc…
Estimate
Etc…
Estimate
Estimate
Level 2
Estimate
Level 2
Activity
Level 1
Plan
Level 2
Plan
Etc…
Plan
Etc…
Plan
Etc…
Schedule
Plan
Level 2
Plan
Level 2
Cost
Level 1
Cost
Level 2
Cost
Etc…
Cost
Etc…
Cost
Etc…
Cost & Reporting
Cost
Level 2
Cost
Level 2
PRISM Control Accounts
PRISM
Level 1
PRISM
Level 2
PRISM
Level 2
PRISM
Level 2
PRISM
Etc…
PRISM
Etc…
PRISM
Etc…
Identify Common
Integration Point
Items
Level 1
Items
Level 2
Items
Etc…
Items
Etc…
Items
Etc…
Contracts
Items
Level 2
Items
Level 2
* Backbone of a Projects
Copyright @ 2011. All rights reserved
Promote Common Coding at Projects & Portfolio Level
F A
B
CD
E
Estimating
Packages
Issue RFP /
Compare Bids
Award Contract
Pay items
.Measure Progress
& Performance
Track Invoices
& Actuals
.
Monitor & Make
Payments
.
Copyright @ 2011. All rights reserved
Eliminate Pain Of Cost Loaded Schedules
• Time consuming to setup
& difficult to maintain
• Dates changes in duration can
skew historical & to date
performance
• Level of granularity between
estimate & plan not always clear
& mappable
• Difficult to manage multiple
budgets
• Difficult to manage cost changes
Copyright @ 2011. All rights reserved
PRISM Cost Schedule Integration
CA
Work Pkg
CBS
Cost & Project Management Module
CA
CA
CA
CA
WBS
Bar Charts
Scheduling Software
Resource
Histograms
Schedule
Reports
Activity Data:
• Durations
• Resources
• Progress
Progress Data
25
Estimating Data:
• Costs
• Hours
• Quantities
Estimate Reports
Original Baseline Estimating
Time Phased
Profiles Cost Progress &
Perf Reports
• Use the right tool for
the right job
• True Integration of
disciplines
• Single point of Truth
• Clear Traceability
between systems
• Eliminates Need to
Cost Load Schedule
PRISM Estimator
CostOS
Copyright @ 2011. All rights reserved
Integrated Performance MeasurementIn$1,000’s
Budget at Completion (BAC)
1 2 3 4 5 6 7 8 9 10
Months
TargetCompletionDate
CurrentCompletionDate
200
400
600
800
1000
1200
11
1300
Planned = $500K : Data Date
20
40
60
80
100
120
140
Probable Schedule Delay = 4 weeks
Probable
Cost
Overrun
= $300K
Estimate at Completion (EAC)
Cost Variance -$100K
Schedule
Variance
(Time)
- 4 wks
Schedule Variance ($)
-$200K
Earned = $300K
Actual = $400K
• Project Time Phased Cost Plan
• To Date Actuals Cost of Work
• To Date Earned Value
• To Date Schedule Variance
• To Date Cost Variance
• Estimate At Complete
• Variance At Complete
All generated from PRISM
Copyright @ 2011. All rights reserved
Utilize Variety of Progressing MethodsCOST
MODULE
Engineering
Deliverables
Procurement &
Contracts
Construction Qtys
Installed
• Progress by Defined Rules
• Track Qty & Hours
• Assess Productivity
• Physical % Complete
• (EPPR)
CONTROL ACCOUNTS
SAMPLESOF
PROGRESSINGMETHODS
• Progress by Delivered
Item or Contractor Pay
Items
• Progress by Qtys Installed
• Track Qtys & Hours
• Assess Productivity
• Physical % Complete
• (QURR)
Progress Progress ProgressProgress
Schedule Activities
• Progress Detailed
Activities
• Map & Weight
Copyright @ 2011. All rights reserved
Integrated Change Management
Board / Programme
Director
Delivery Director
Programme
Director
Finance Director
Business
Manager
Project
Director
Business
Manager
Project
Director
Project
Director
Business
Manager
Business
Manager
Project
Director
Business
Manager
Project
Director
Business
Manager
Project
Director
Business
Manager
Project
Director
Technical
Director
Project Manager
BoardDirectorsSeniorManagement
Project
Mgrs
CEs/
SMEs
Cost Engineers
Project
Director
Programme
Controls Director
Project
Director
Business
Manager
Initiate Change
APPROVAL
AUTHORITY
Review &
Approve
Copyright @ 2011. All rights reserved
PRISM Integration Engine
PRISM
Integrator
EDI messaging
protocols
web
services
all major
databases
email
file
management
in-memory
data-grid
communication
protocol
• By Bi-Directional Integration
• System Agnostic
Copyright @ 2011. All rights reserved
PRISM Integration Engine – Designer Interface
Flexibility to Add & Remove Connections
Define & Modify Field Mapping
Define & Customize Workflows
Copyright @ 2011. All rights reserved
PRISM Integration Engine – Workflow Logic
Copyright @ 2011. All rights reserved
Synchronized WBS, Integration & Automation
Lvl 1
Lvl 2 Lvl 2Lvl 2
Lvl 3 Lvl 3 Lvl 3 Lvl 3 Lvl 3
Cost Performance
CostOS
Estimator
Contracts
ERP
Schedule
Master WBS Asset Register
NEC
• PRISM Integrator synchronizes the WBS & Asset coding across
all applications
• Additions and Changes to the structure require approval from all
stake holders
NEC Contract Changes in
CEMAR are automatically
synchronized with budget &
forecast changes in PRISM
1
Payment request
in CEMAR are
automatically
submitted through
SAP for validation
and payment
2
3
Risk
PRISM Integrator
Copyright @ 2011. All rights reserved
Sub Contractor & Client Integration
• Review
• Amend
• Accept
• Or Reject
Client
Staging Area
• Actuals
• Progress &
Performance
• Review
• Amend
• Accept
• Or Reject
Client
Staging Area
• Actuals
• Progress &
Performance
Sub
Contractors
PRISM Web
Forms
Sub
Contractor
Instance
Client
Instance
Direct Feed
WEBFORMS
PRISMTO
PRISM
Client
Instance
Copyright @ 2011. All rights reserved
PRISM Data Warehouse
Data Warehouse & Snapshots
Custom Data Entry Forms
Copyright @ 2011. All rights reserved
Quickly Produce Integrated Dashboards
Copyright @ 2011. All rights reserved
Ensuring Data Integrity with Validation Checks
Cost Data Validation:
* Control Account ID , Control Account
Owner, Data Anomaly or Error
Automated Data Exception & Error Reporting Rules
Data Validation Checks:
Copyright @ 2011. All rights reserved
Standard Performance Reporting
Copyright @ 2011. All rights reserved
Productivity & Progress Gantt Charts
Copyright @ 2011. All rights reserved
Questions ??
Lateef Daly
Director, Europe & Middle East
Operations
ARES Software UK Ltd
25 Canada Square
Canary Wharf
London E14 5LQ
ldaly@aresprism.com
UK: +44 (0) 7800 66 5049
Get in Touch if you’d like to know more!
Copyright @ 2011. All rights reserved

More Related Content

What's hot

Project Management Professional (PMP)
Project Management Professional (PMP) Project Management Professional (PMP)
Project Management Professional (PMP) Ahmad Maharma, PMP,RMP
 
Project Control Practical Way by Herve Baron
Project Control Practical Way by Herve BaronProject Control Practical Way by Herve Baron
Project Control Practical Way by Herve Baronignitetribes
 
Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIChris Carson
 
5 phases of project management
5 phases of project management5 phases of project management
5 phases of project managementJared C. Powell
 
Lec 03 project life cycle
Lec 03 project life cycleLec 03 project life cycle
Lec 03 project life cycleSAJID ALI RUK
 
Introduction to Project Portfolio Management (PPM)
Introduction to Project Portfolio Management (PPM)Introduction to Project Portfolio Management (PPM)
Introduction to Project Portfolio Management (PPM)Kimmy Chen
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Fakhar-un -Nisa
 
Implementing a Project Office Management
Implementing a Project Office ManagementImplementing a Project Office Management
Implementing a Project Office ManagementRicardo Viana Vargas
 
Project Management Fundamentals | Project Management Simplified | PMP® Traini...
Project Management Fundamentals | Project Management Simplified | PMP® Traini...Project Management Fundamentals | Project Management Simplified | PMP® Traini...
Project Management Fundamentals | Project Management Simplified | PMP® Traini...Edureka!
 
EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...Fahad Ali
 
Session T2 - Best Practice Project Controls with EcoSys
Session T2 - Best Practice Project Controls with EcoSysSession T2 - Best Practice Project Controls with EcoSys
Session T2 - Best Practice Project Controls with EcoSysProject Controls Expo
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlM Maged Hegazy, LLM, MBA, CCP, P3O
 

What's hot (20)

PMO Mandate
PMO MandatePMO Mandate
PMO Mandate
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
 
Project Management Professional (PMP)
Project Management Professional (PMP) Project Management Professional (PMP)
Project Management Professional (PMP)
 
Project Control Practical Way by Herve Baron
Project Control Practical Way by Herve BaronProject Control Practical Way by Herve Baron
Project Control Practical Way by Herve Baron
 
Performing against the wall - SPI after completion
Performing against the wall - SPI after completionPerforming against the wall - SPI after completion
Performing against the wall - SPI after completion
 
Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEI
 
5 phases of project management
5 phases of project management5 phases of project management
5 phases of project management
 
Milestone checklist
Milestone checklist   Milestone checklist
Milestone checklist
 
Lec 03 project life cycle
Lec 03 project life cycleLec 03 project life cycle
Lec 03 project life cycle
 
Epc presentation robert foxpresentation
Epc presentation robert foxpresentationEpc presentation robert foxpresentation
Epc presentation robert foxpresentation
 
Project portfolio management
Project portfolio managementProject portfolio management
Project portfolio management
 
Introduction to Project Portfolio Management (PPM)
Introduction to Project Portfolio Management (PPM)Introduction to Project Portfolio Management (PPM)
Introduction to Project Portfolio Management (PPM)
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)
 
The PMO in practice
The PMO in practiceThe PMO in practice
The PMO in practice
 
Implementing a Project Office Management
Implementing a Project Office ManagementImplementing a Project Office Management
Implementing a Project Office Management
 
Project Management Fundamentals | Project Management Simplified | PMP® Traini...
Project Management Fundamentals | Project Management Simplified | PMP® Traini...Project Management Fundamentals | Project Management Simplified | PMP® Traini...
Project Management Fundamentals | Project Management Simplified | PMP® Traini...
 
EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...
 
Session T2 - Best Practice Project Controls with EcoSys
Session T2 - Best Practice Project Controls with EcoSysSession T2 - Best Practice Project Controls with EcoSys
Session T2 - Best Practice Project Controls with EcoSys
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project Control
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
 

Similar to ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Project Controls Expo 2017, Arsenal Stadium, London

CAD and BIM Outsourcing Services
CAD and BIM Outsourcing ServicesCAD and BIM Outsourcing Services
CAD and BIM Outsourcing Servicestheaecassociates1
 
Leveraging C3D® to Ensure Compliance of Site Execution Teams
Leveraging C3D® to Ensure Compliance of Site Execution TeamsLeveraging C3D® to Ensure Compliance of Site Execution Teams
Leveraging C3D® to Ensure Compliance of Site Execution TeamsCCT International
 
Automating Infrastructure as a Service Deployments and monitoring – TEC213
Automating Infrastructure as a Service Deployments and monitoring – TEC213Automating Infrastructure as a Service Deployments and monitoring – TEC213
Automating Infrastructure as a Service Deployments and monitoring – TEC213Chris Kernaghan
 
Project Controls Expo, 13th Nov 2013 - "Loading Cost and Activity data into P...
Project Controls Expo, 13th Nov 2013 - "Loading Cost and Activity data into P...Project Controls Expo, 13th Nov 2013 - "Loading Cost and Activity data into P...
Project Controls Expo, 13th Nov 2013 - "Loading Cost and Activity data into P...Project Controls Expo
 
Project Controls Expo, 18th Nov 2014 - "The Computer Age and Estimating – Don...
Project Controls Expo, 18th Nov 2014 - "The Computer Age and Estimating – Don...Project Controls Expo, 18th Nov 2014 - "The Computer Age and Estimating – Don...
Project Controls Expo, 18th Nov 2014 - "The Computer Age and Estimating – Don...Project Controls Expo
 
Oracle projects integration
Oracle projects integrationOracle projects integration
Oracle projects integrationLawson James
 
Asites Appbuilder Breakfast Seminar
Asites Appbuilder Breakfast SeminarAsites Appbuilder Breakfast Seminar
Asites Appbuilder Breakfast SeminarTracey Saunders
 
Resume - Senior Projects Planner / Schedule
Resume - Senior Projects Planner / ScheduleResume - Senior Projects Planner / Schedule
Resume - Senior Projects Planner / Schedulesaieq
 
Leading practices in Project Planning
Leading practices in Project PlanningLeading practices in Project Planning
Leading practices in Project PlanningAlithya
 
Oracle PPM Cloud Deployment, Made Easy
Oracle PPM Cloud Deployment, Made EasyOracle PPM Cloud Deployment, Made Easy
Oracle PPM Cloud Deployment, Made EasyMatthew Bezuidenhout
 
Session T7 - Total Cost Management - The synergy between Cost Estimating and ...
Session T7 - Total Cost Management - The synergy between Cost Estimating and ...Session T7 - Total Cost Management - The synergy between Cost Estimating and ...
Session T7 - Total Cost Management - The synergy between Cost Estimating and ...Project Controls Expo
 
Integrated Engineering Deployment in a New Engineering Office
Integrated Engineering Deployment in a New Engineering OfficeIntegrated Engineering Deployment in a New Engineering Office
Integrated Engineering Deployment in a New Engineering OfficeAVEVA Group plc
 
Resume - Imtiaz Ahamed (1)
Resume - Imtiaz Ahamed (1)Resume - Imtiaz Ahamed (1)
Resume - Imtiaz Ahamed (1)imtiaz9292
 
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo
 
Cloud Economics, from TCO to ROI
Cloud Economics, from TCO to ROICloud Economics, from TCO to ROI
Cloud Economics, from TCO to ROIAmazon Web Services
 
Project Controls Expo - 31st Oct 2012 - Extending Earned Value Methodology To...
Project Controls Expo - 31st Oct 2012 - Extending Earned Value Methodology To...Project Controls Expo - 31st Oct 2012 - Extending Earned Value Methodology To...
Project Controls Expo - 31st Oct 2012 - Extending Earned Value Methodology To...Project Controls Expo
 
Complexity - Advanced Engineering Project Management
Complexity - Advanced Engineering Project ManagementComplexity - Advanced Engineering Project Management
Complexity - Advanced Engineering Project ManagementMDCSystems
 
Accurate BI &MDM Lead to successful Project Execution!
Accurate BI &MDM Lead to successful Project Execution!Accurate BI &MDM Lead to successful Project Execution!
Accurate BI &MDM Lead to successful Project Execution!Orchestra Networks
 

Similar to ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Project Controls Expo 2017, Arsenal Stadium, London (20)

CAD and BIM Outsourcing Services
CAD and BIM Outsourcing ServicesCAD and BIM Outsourcing Services
CAD and BIM Outsourcing Services
 
Leveraging C3D® to Ensure Compliance of Site Execution Teams
Leveraging C3D® to Ensure Compliance of Site Execution TeamsLeveraging C3D® to Ensure Compliance of Site Execution Teams
Leveraging C3D® to Ensure Compliance of Site Execution Teams
 
Automating Infrastructure as a Service Deployments and monitoring – TEC213
Automating Infrastructure as a Service Deployments and monitoring – TEC213Automating Infrastructure as a Service Deployments and monitoring – TEC213
Automating Infrastructure as a Service Deployments and monitoring – TEC213
 
Project Controls Expo, 13th Nov 2013 - "Loading Cost and Activity data into P...
Project Controls Expo, 13th Nov 2013 - "Loading Cost and Activity data into P...Project Controls Expo, 13th Nov 2013 - "Loading Cost and Activity data into P...
Project Controls Expo, 13th Nov 2013 - "Loading Cost and Activity data into P...
 
Project Controls Expo, 18th Nov 2014 - "The Computer Age and Estimating – Don...
Project Controls Expo, 18th Nov 2014 - "The Computer Age and Estimating – Don...Project Controls Expo, 18th Nov 2014 - "The Computer Age and Estimating – Don...
Project Controls Expo, 18th Nov 2014 - "The Computer Age and Estimating – Don...
 
Oracle projects integration
Oracle projects integrationOracle projects integration
Oracle projects integration
 
Asites Appbuilder Breakfast Seminar
Asites Appbuilder Breakfast SeminarAsites Appbuilder Breakfast Seminar
Asites Appbuilder Breakfast Seminar
 
Resume - Senior Projects Planner / Schedule
Resume - Senior Projects Planner / ScheduleResume - Senior Projects Planner / Schedule
Resume - Senior Projects Planner / Schedule
 
Leading practices in Project Planning
Leading practices in Project PlanningLeading practices in Project Planning
Leading practices in Project Planning
 
Oracle PPM Cloud Deployment, Made Easy
Oracle PPM Cloud Deployment, Made EasyOracle PPM Cloud Deployment, Made Easy
Oracle PPM Cloud Deployment, Made Easy
 
Session T7 - Total Cost Management - The synergy between Cost Estimating and ...
Session T7 - Total Cost Management - The synergy between Cost Estimating and ...Session T7 - Total Cost Management - The synergy between Cost Estimating and ...
Session T7 - Total Cost Management - The synergy between Cost Estimating and ...
 
Integrated Engineering Deployment in a New Engineering Office
Integrated Engineering Deployment in a New Engineering OfficeIntegrated Engineering Deployment in a New Engineering Office
Integrated Engineering Deployment in a New Engineering Office
 
Resume - Imtiaz Ahamed (1)
Resume - Imtiaz Ahamed (1)Resume - Imtiaz Ahamed (1)
Resume - Imtiaz Ahamed (1)
 
Harish Srivastava -Resume
Harish Srivastava -ResumeHarish Srivastava -Resume
Harish Srivastava -Resume
 
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
 
Cloud Economics, from TCO to ROI
Cloud Economics, from TCO to ROICloud Economics, from TCO to ROI
Cloud Economics, from TCO to ROI
 
Project Controls Expo - 31st Oct 2012 - Extending Earned Value Methodology To...
Project Controls Expo - 31st Oct 2012 - Extending Earned Value Methodology To...Project Controls Expo - 31st Oct 2012 - Extending Earned Value Methodology To...
Project Controls Expo - 31st Oct 2012 - Extending Earned Value Methodology To...
 
Pes profile
Pes profilePes profile
Pes profile
 
Complexity - Advanced Engineering Project Management
Complexity - Advanced Engineering Project ManagementComplexity - Advanced Engineering Project Management
Complexity - Advanced Engineering Project Management
 
Accurate BI &MDM Lead to successful Project Execution!
Accurate BI &MDM Lead to successful Project Execution!Accurate BI &MDM Lead to successful Project Execution!
Accurate BI &MDM Lead to successful Project Execution!
 

More from Project Controls Expo

National Grids Project Controls Journey – past, present and future
National Grids Project Controls Journey – past, present and futureNational Grids Project Controls Journey – past, present and future
National Grids Project Controls Journey – past, present and futureProject Controls Expo
 
Case study in Company Project Controls Transformation By Rod Whiting - Region...
Case study in Company Project Controls Transformation By Rod Whiting - Region...Case study in Company Project Controls Transformation By Rod Whiting - Region...
Case study in Company Project Controls Transformation By Rod Whiting - Region...Project Controls Expo
 
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...Project Controls Expo
 
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...Project Controls Expo
 
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...Project Controls Expo
 
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...Project Controls Expo
 
Managing the risk of change by "Simon White - Risk Management Consultant for ...
Managing the risk of change by "Simon White - Risk Management Consultant for ...Managing the risk of change by "Simon White - Risk Management Consultant for ...
Managing the risk of change by "Simon White - Risk Management Consultant for ...Project Controls Expo
 
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...Project Controls Expo
 
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...Project Controls Expo
 
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...Project Controls Expo
 
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...Project Controls Expo
 
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...
Governance: An Enabler? by "	 Ian Beaumont - Delivery Partner Programme Direc...Governance: An Enabler? by "	 Ian Beaumont - Delivery Partner Programme Direc...
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...Project Controls Expo
 
Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Governance and the art of decision making on Crossrail by "Walter Macharg - H...Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Governance and the art of decision making on Crossrail by "Walter Macharg - H...Project Controls Expo
 
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...Project Controls Expo
 
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...Project Controls Expo
 
Governance and Assurance for Nationally Significant Infrastructure Projects b...
Governance and Assurance for Nationally Significant Infrastructure Projects b...Governance and Assurance for Nationally Significant Infrastructure Projects b...
Governance and Assurance for Nationally Significant Infrastructure Projects b...Project Controls Expo
 
A review of whether interdependency exists in effective Project Control Metho...
A review of whether interdependency exists in effective Project Control Metho...A review of whether interdependency exists in effective Project Control Metho...
A review of whether interdependency exists in effective Project Control Metho...Project Controls Expo
 
A Source of Project Cost Integration by "David Hurren - Technical Director fo...
A Source of Project Cost Integration by "David Hurren - Technical Director fo...A Source of Project Cost Integration by "David Hurren - Technical Director fo...
A Source of Project Cost Integration by "David Hurren - Technical Director fo...Project Controls Expo
 
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...Project Controls Expo
 
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...Project Controls Expo
 

More from Project Controls Expo (20)

National Grids Project Controls Journey – past, present and future
National Grids Project Controls Journey – past, present and futureNational Grids Project Controls Journey – past, present and future
National Grids Project Controls Journey – past, present and future
 
Case study in Company Project Controls Transformation By Rod Whiting - Region...
Case study in Company Project Controls Transformation By Rod Whiting - Region...Case study in Company Project Controls Transformation By Rod Whiting - Region...
Case study in Company Project Controls Transformation By Rod Whiting - Region...
 
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
 
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
 
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
 
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
 
Managing the risk of change by "Simon White - Risk Management Consultant for ...
Managing the risk of change by "Simon White - Risk Management Consultant for ...Managing the risk of change by "Simon White - Risk Management Consultant for ...
Managing the risk of change by "Simon White - Risk Management Consultant for ...
 
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
 
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
 
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
 
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
 
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...
Governance: An Enabler? by "	 Ian Beaumont - Delivery Partner Programme Direc...Governance: An Enabler? by "	 Ian Beaumont - Delivery Partner Programme Direc...
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...
 
Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Governance and the art of decision making on Crossrail by "Walter Macharg - H...Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Governance and the art of decision making on Crossrail by "Walter Macharg - H...
 
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
 
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
 
Governance and Assurance for Nationally Significant Infrastructure Projects b...
Governance and Assurance for Nationally Significant Infrastructure Projects b...Governance and Assurance for Nationally Significant Infrastructure Projects b...
Governance and Assurance for Nationally Significant Infrastructure Projects b...
 
A review of whether interdependency exists in effective Project Control Metho...
A review of whether interdependency exists in effective Project Control Metho...A review of whether interdependency exists in effective Project Control Metho...
A review of whether interdependency exists in effective Project Control Metho...
 
A Source of Project Cost Integration by "David Hurren - Technical Director fo...
A Source of Project Cost Integration by "David Hurren - Technical Director fo...A Source of Project Cost Integration by "David Hurren - Technical Director fo...
A Source of Project Cost Integration by "David Hurren - Technical Director fo...
 
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
 
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
 

Recently uploaded

Russian Call Girls in Kolkata Vaishnavi 🤌 8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Vaishnavi 🤌  8250192130 🚀 Vip Call Girls KolkataRussian Call Girls in Kolkata Vaishnavi 🤌  8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Vaishnavi 🤌 8250192130 🚀 Vip Call Girls Kolkataanamikaraghav4
 
The 3rd Intl. Workshop on NL-based Software Engineering
The 3rd Intl. Workshop on NL-based Software EngineeringThe 3rd Intl. Workshop on NL-based Software Engineering
The 3rd Intl. Workshop on NL-based Software EngineeringSebastiano Panichella
 
Simulation-based Testing of Unmanned Aerial Vehicles with Aerialist
Simulation-based Testing of Unmanned Aerial Vehicles with AerialistSimulation-based Testing of Unmanned Aerial Vehicles with Aerialist
Simulation-based Testing of Unmanned Aerial Vehicles with AerialistSebastiano Panichella
 
Genesis part 2 Isaiah Scudder 04-24-2024.pptx
Genesis part 2 Isaiah Scudder 04-24-2024.pptxGenesis part 2 Isaiah Scudder 04-24-2024.pptx
Genesis part 2 Isaiah Scudder 04-24-2024.pptxFamilyWorshipCenterD
 
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...Krijn Poppe
 
Philippine History cavite Mutiny Report.ppt
Philippine History cavite Mutiny Report.pptPhilippine History cavite Mutiny Report.ppt
Philippine History cavite Mutiny Report.pptssuser319dad
 
LANDMARKS AND MONUMENTS IN NIGERIA.pptx
LANDMARKS  AND MONUMENTS IN NIGERIA.pptxLANDMARKS  AND MONUMENTS IN NIGERIA.pptx
LANDMARKS AND MONUMENTS IN NIGERIA.pptxBasil Achie
 
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...henrik385807
 
call girls in delhi malviya nagar @9811711561@
call girls in delhi malviya nagar @9811711561@call girls in delhi malviya nagar @9811711561@
call girls in delhi malviya nagar @9811711561@vikas rana
 
Microsoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AIMicrosoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AITatiana Gurgel
 
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...NETWAYS
 
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝soniya singh
 
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdfCTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdfhenrik385807
 
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...NETWAYS
 
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...Pooja Nehwal
 
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...NETWAYS
 
Work Remotely with Confluence ACE 2.pptx
Work Remotely with Confluence ACE 2.pptxWork Remotely with Confluence ACE 2.pptx
Work Remotely with Confluence ACE 2.pptxmavinoikein
 
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝soniya singh
 
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )Pooja Nehwal
 
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...Salam Al-Karadaghi
 

Recently uploaded (20)

Russian Call Girls in Kolkata Vaishnavi 🤌 8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Vaishnavi 🤌  8250192130 🚀 Vip Call Girls KolkataRussian Call Girls in Kolkata Vaishnavi 🤌  8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Vaishnavi 🤌 8250192130 🚀 Vip Call Girls Kolkata
 
The 3rd Intl. Workshop on NL-based Software Engineering
The 3rd Intl. Workshop on NL-based Software EngineeringThe 3rd Intl. Workshop on NL-based Software Engineering
The 3rd Intl. Workshop on NL-based Software Engineering
 
Simulation-based Testing of Unmanned Aerial Vehicles with Aerialist
Simulation-based Testing of Unmanned Aerial Vehicles with AerialistSimulation-based Testing of Unmanned Aerial Vehicles with Aerialist
Simulation-based Testing of Unmanned Aerial Vehicles with Aerialist
 
Genesis part 2 Isaiah Scudder 04-24-2024.pptx
Genesis part 2 Isaiah Scudder 04-24-2024.pptxGenesis part 2 Isaiah Scudder 04-24-2024.pptx
Genesis part 2 Isaiah Scudder 04-24-2024.pptx
 
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
 
Philippine History cavite Mutiny Report.ppt
Philippine History cavite Mutiny Report.pptPhilippine History cavite Mutiny Report.ppt
Philippine History cavite Mutiny Report.ppt
 
LANDMARKS AND MONUMENTS IN NIGERIA.pptx
LANDMARKS  AND MONUMENTS IN NIGERIA.pptxLANDMARKS  AND MONUMENTS IN NIGERIA.pptx
LANDMARKS AND MONUMENTS IN NIGERIA.pptx
 
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
 
call girls in delhi malviya nagar @9811711561@
call girls in delhi malviya nagar @9811711561@call girls in delhi malviya nagar @9811711561@
call girls in delhi malviya nagar @9811711561@
 
Microsoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AIMicrosoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AI
 
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
 
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
 
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdfCTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
 
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
 
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
 
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
 
Work Remotely with Confluence ACE 2.pptx
Work Remotely with Confluence ACE 2.pptxWork Remotely with Confluence ACE 2.pptx
Work Remotely with Confluence ACE 2.pptx
 
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
 
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )
 
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
 

ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Project Controls Expo 2017, Arsenal Stadium, London

  • 1. Copyright @ 2011. All rights reserved Integrating Project & Portfolio Management Project Controls Expo – 17th Nov 2017 Emirates Stadium, London
  • 2. Copyright @ 2011. All rights reserved About the Speaker Name: Lateef Daly Position: Director of Europe & Middle East Operations Organization: ARES PRISM  20+ Year of Project Controls & Earned Value Expertise  Finance, Estimating, Cost Engineering, Change Mgmt, System Integration  Industries:  Pharmaceuticals, Defence, Infrastructure, Rail, Nuclear, O&G  Major Project Experience:  Crossrail, TFL, High Speed 2, Horizon Nuclear, Expo 2020, Ronald Reagan Ballistic Missile Défense Test Site
  • 3. Copyright @ 2011. All rights reserved About the Topic Outline: • Common Coding • Cost Schedule Integration • Enterprise Portfolio Management • Utilizing Various Progress Methods • ARES PRISM Background • Project Lifecyle Management • Integration Engine – Client Customizable Integrations • Benefits of a Data Warehouse • Data Integrity & Validation • Reporting
  • 4. Copyright @ 2011. All rights reserved ARES PRISM Background ARES is a full-service project controls solution provider  ARES formed in 1992  First PRISM US Client in 1995  First UK client in 2009 (Sellafield)  UK Entity opened in 2010 to support Crossrail  Multiple EMEA clients today with strong Repeat Business  Local Support Capability backed by the Central PRISM Team  Local Services for Project Controls, Estimating, Scheduling and Contract Administration
  • 5. Copyright @ 2011. All rights reserved Global Clients - Common Best Practices EPC Nuclear / EnergyInfrastructure Mining & MetalsOil & Gas Government
  • 6. Copyright @ 2011. All rights reserved PRISM Integrated Lifecyle Management
  • 7. Copyright @ 2011. All rights reserved Integrator PRISM Integrator Provides: • Connection for IT/ ERP/ Risk/ Financial Systems • Workflow Modeling • Code-Free Data Mapping PRISM Integrated Lifecyle Management
  • 8. Copyright @ 2011. All rights reserved Estimating PRISM Estimating Provides: • 2D/3D/GIS/BIM Takeoff • Centralized Cost Estimates • Quantity Survey • Historical Data PRISM Integrated Lifecyle Management
  • 9. Copyright @ 2011. All rights reserved Cost Management PRISM G2 Cost Management Provides: • Time-Phased Budgeting • Resource Planning • Schedule • Commitments • Risk • Performance Measurement • Variance Analysis • Forecasting • Earned Value PRISM Integrated Lifecyle Management
  • 10. Copyright @ 2011. All rights reserved Change PRISM G2 Change Management Provides: • Defined Approvers and Reviewers • Tracks Change Requests • Manages Change Workflows PRISM Integrated Lifecyle Management
  • 11. Copyright @ 2011. All rights reserved Engineering PRISM G2 Engineering Provides: • Deliverable Status and Tracking • Time-Phased Engineering Packages • Progress Measurement • Engineering Performance • Forecasting PRISM Integrated Lifecyle Management
  • 12. Copyright @ 2011. All rights reserved Equipment & Materials PRISM G2 Equipment & Materials: • Develops Requisitions • Tracks Equipment and Attributes • Tracks Materials PRISM Integrated Lifecyle Management
  • 13. Copyright @ 2011. All rights reserved Contracts PRISM G2 Contracts Administration Provides: • Contract Bids • Bid Analysis • Award Contracts • Vendor Evaluations • Contract Scheduling • Punch List Tracking • Contract Changes PRISM Integrated Lifecyle Management
  • 14. Copyright @ 2011. All rights reserved Invoice PRISM G2 Invoice Management: • Tracks Invoices From Suppliers • Tracks Payments • Traces Back to Purchase Orders and Contracts PRISM Integrated Lifecyle Management
  • 15. Copyright @ 2011. All rights reserved Procurement PRISM G2 Procurement Provides: • Requisitions & Purchase Orders • Procurement Scheduling • Shipment Expediting, • Supplier Evaluations PRISM Integrated Lifecyle Management
  • 16. Copyright @ 2011. All rights reserved Field Progress PRISM G2 Field Progress Provides: • Construction Progress & Performance • Installed Quantities • Unit Rates Analysis • Rules of Credit • Mobile Access • Construction Changes PRISM Integrated Lifecyle Management
  • 17. Copyright @ 2011. All rights reserved Docs PRISM Docs Provides: • Document Access and Control • Automated Processes • Team Collaboration PRISM Integrated Lifecyle Management
  • 18. Copyright @ 2011. All rights reserved Dashboard, Reporting and Data Warehouse PRISM Dashboard, Reporting & Data Warehouse Provides: • Executive Insight • Visualized Data • Project Performance • Forecasts • Embedded KPIs PRISM Integrated Lifecyle Management
  • 19. Copyright @ 2011. All rights reserved Enterprise Portfolio Management PRISM Enterprise Portfolio Reporting PRISMProjectSpecific Configuration Calendars CurrenciesWBS/OBS/Asset Cost Elements Lbr Mtl Eqp Central Team Report Formats PRISMEnterprise Configuration • Define and promote a Common Enterprise Structure that is clearly defined and shared across all projects • Still have flexibility to define project by project specific configurations that rollup to the Enterprise Level • Single point of truth for portfolio reporting Project A Calendars Currencies WBS/OBS/Asset Cost Elements Lbr Mtl Eqp Project Teams Report Formats Can Be Setup Same or Unique Project B Calendars Currencies WBS/OBS/Asset Cost Elements Lbr Mtl Eqp Project Teams Report Formats Can Be Setup Same or Unique Project C Calendars Currencies WBS/OBS/Asset Cost Elements Lbr Mtl Eqp Project Teams Report Formats Can Be Setup Same or Unique
  • 20. Copyright @ 2011. All rights reserved Integrated Coding Structure Cost & Progress Schedule Contracts Estimate DEFINE SINGLE INTEGRATED STRUCTURE * Provides integration & traceability from Original Baseline Estimate and our operating Budget /Cost data, which is then time phased with the Schedule start & finish dates
  • 21. Copyright @ 2011. All rights reserved Creation of Integrated Coding Structure Estimate Level 1 Estimate Level 2 Estimate Etc… Estimate Etc… Estimate Etc… Estimate Estimate Level 2 Estimate Level 2 Activity Level 1 Plan Level 2 Plan Etc… Plan Etc… Plan Etc… Schedule Plan Level 2 Plan Level 2 Cost Level 1 Cost Level 2 Cost Etc… Cost Etc… Cost Etc… Cost & Reporting Cost Level 2 Cost Level 2 PRISM Control Accounts PRISM Level 1 PRISM Level 2 PRISM Level 2 PRISM Level 2 PRISM Etc… PRISM Etc… PRISM Etc… Identify Common Integration Point Items Level 1 Items Level 2 Items Etc… Items Etc… Items Etc… Contracts Items Level 2 Items Level 2 * Backbone of a Projects
  • 22. Copyright @ 2011. All rights reserved Promote Common Coding at Projects & Portfolio Level F A B CD E Estimating Packages Issue RFP / Compare Bids Award Contract Pay items .Measure Progress & Performance Track Invoices & Actuals . Monitor & Make Payments .
  • 23. Copyright @ 2011. All rights reserved Eliminate Pain Of Cost Loaded Schedules • Time consuming to setup & difficult to maintain • Dates changes in duration can skew historical & to date performance • Level of granularity between estimate & plan not always clear & mappable • Difficult to manage multiple budgets • Difficult to manage cost changes
  • 24. Copyright @ 2011. All rights reserved PRISM Cost Schedule Integration CA Work Pkg CBS Cost & Project Management Module CA CA CA CA WBS Bar Charts Scheduling Software Resource Histograms Schedule Reports Activity Data: • Durations • Resources • Progress Progress Data 25 Estimating Data: • Costs • Hours • Quantities Estimate Reports Original Baseline Estimating Time Phased Profiles Cost Progress & Perf Reports • Use the right tool for the right job • True Integration of disciplines • Single point of Truth • Clear Traceability between systems • Eliminates Need to Cost Load Schedule PRISM Estimator CostOS
  • 25. Copyright @ 2011. All rights reserved Integrated Performance MeasurementIn$1,000’s Budget at Completion (BAC) 1 2 3 4 5 6 7 8 9 10 Months TargetCompletionDate CurrentCompletionDate 200 400 600 800 1000 1200 11 1300 Planned = $500K : Data Date 20 40 60 80 100 120 140 Probable Schedule Delay = 4 weeks Probable Cost Overrun = $300K Estimate at Completion (EAC) Cost Variance -$100K Schedule Variance (Time) - 4 wks Schedule Variance ($) -$200K Earned = $300K Actual = $400K • Project Time Phased Cost Plan • To Date Actuals Cost of Work • To Date Earned Value • To Date Schedule Variance • To Date Cost Variance • Estimate At Complete • Variance At Complete All generated from PRISM
  • 26. Copyright @ 2011. All rights reserved Utilize Variety of Progressing MethodsCOST MODULE Engineering Deliverables Procurement & Contracts Construction Qtys Installed • Progress by Defined Rules • Track Qty & Hours • Assess Productivity • Physical % Complete • (EPPR) CONTROL ACCOUNTS SAMPLESOF PROGRESSINGMETHODS • Progress by Delivered Item or Contractor Pay Items • Progress by Qtys Installed • Track Qtys & Hours • Assess Productivity • Physical % Complete • (QURR) Progress Progress ProgressProgress Schedule Activities • Progress Detailed Activities • Map & Weight
  • 27. Copyright @ 2011. All rights reserved Integrated Change Management Board / Programme Director Delivery Director Programme Director Finance Director Business Manager Project Director Business Manager Project Director Project Director Business Manager Business Manager Project Director Business Manager Project Director Business Manager Project Director Business Manager Project Director Technical Director Project Manager BoardDirectorsSeniorManagement Project Mgrs CEs/ SMEs Cost Engineers Project Director Programme Controls Director Project Director Business Manager Initiate Change APPROVAL AUTHORITY Review & Approve
  • 28. Copyright @ 2011. All rights reserved PRISM Integration Engine PRISM Integrator EDI messaging protocols web services all major databases email file management in-memory data-grid communication protocol • By Bi-Directional Integration • System Agnostic
  • 29. Copyright @ 2011. All rights reserved PRISM Integration Engine – Designer Interface Flexibility to Add & Remove Connections Define & Modify Field Mapping Define & Customize Workflows
  • 30. Copyright @ 2011. All rights reserved PRISM Integration Engine – Workflow Logic
  • 31. Copyright @ 2011. All rights reserved Synchronized WBS, Integration & Automation Lvl 1 Lvl 2 Lvl 2Lvl 2 Lvl 3 Lvl 3 Lvl 3 Lvl 3 Lvl 3 Cost Performance CostOS Estimator Contracts ERP Schedule Master WBS Asset Register NEC • PRISM Integrator synchronizes the WBS & Asset coding across all applications • Additions and Changes to the structure require approval from all stake holders NEC Contract Changes in CEMAR are automatically synchronized with budget & forecast changes in PRISM 1 Payment request in CEMAR are automatically submitted through SAP for validation and payment 2 3 Risk PRISM Integrator
  • 32. Copyright @ 2011. All rights reserved Sub Contractor & Client Integration • Review • Amend • Accept • Or Reject Client Staging Area • Actuals • Progress & Performance • Review • Amend • Accept • Or Reject Client Staging Area • Actuals • Progress & Performance Sub Contractors PRISM Web Forms Sub Contractor Instance Client Instance Direct Feed WEBFORMS PRISMTO PRISM Client Instance
  • 33. Copyright @ 2011. All rights reserved PRISM Data Warehouse Data Warehouse & Snapshots Custom Data Entry Forms
  • 34. Copyright @ 2011. All rights reserved Quickly Produce Integrated Dashboards
  • 35. Copyright @ 2011. All rights reserved Ensuring Data Integrity with Validation Checks Cost Data Validation: * Control Account ID , Control Account Owner, Data Anomaly or Error Automated Data Exception & Error Reporting Rules Data Validation Checks:
  • 36. Copyright @ 2011. All rights reserved Standard Performance Reporting
  • 37. Copyright @ 2011. All rights reserved Productivity & Progress Gantt Charts
  • 38. Copyright @ 2011. All rights reserved Questions ?? Lateef Daly Director, Europe & Middle East Operations ARES Software UK Ltd 25 Canada Square Canary Wharf London E14 5LQ ldaly@aresprism.com UK: +44 (0) 7800 66 5049 Get in Touch if you’d like to know more!